Loading...
HomeMy WebLinkAboutTile Flat Analysis Technical Memo_6-10-25 Draft Page | 1 MEMORANDUM DATE: June 10, 2025 TO: River Terrace 2.0 Project Management Team FROM: Adrian Witte, Toole Design and Kevin Chewuk, DKS Associates SUBJECT: River Terrace 2.0 Community Plan Tile Flat Extension Scenarios Evaluation #24434-000 This memorandum summarizes the multimodal transportation analysis methodology and findings for the evaluation of Tile Flat extension scenarios as part of the River Terrace 2.0 Community Plan. Included are the objectives of the study, a summary of the primary street network and Tile Flat extension scenarios, the performance metrics used to compare scenarios, and the results of the analysis, which will be used by staff to identify a scenario to recommend to decision makers moving forward. STUDY OBJECTIVES The objective of the study is to compare holistic benefits, impacts, and costs of the different primary street network scenarios and to understand and quantify if there are additional benefits to extending Tile Flat Road or Mountainside Way beyond providing the base network identified in the River Terrace 2.0 Concept Plan. TILE FLAT EXTENSION SCENARIOS The team identified four primary street network scenarios to be evaluated within the River Terrace 2.0 Community Planning process – two of these extend Mountainside Way without a connection to Tile Flat Road and two include an extension of Tile Flat Road to meet Mountainside Way. All scenarios provide a primary north to south collector route along Mountainside Way connecting from Scholls Ferry Road and running west of and eventually connecting to Roy Rogers Road at the Bull Mountain Road intersection. This scenario is identified as Scenario 1. The conceptual alignments of the primary streets for each of the four scenarios are shown on Figure 1 through Figure 4, although the alignments could be shifted slightly to better serve the surrounding neighborhood or provide other system benefits (e.g., to reduce costs, lessen impacts to sensitive lands, provide better connectivity, etc.). The Tile Flat extension scenarios include: Evaluation of Tile Flat Extension Scenarios June 2025 Page | 2 • Scenario 1: Includes the Mountainside Way extension from Scholls Ferry Road to the Roy Rogers Road / Bull Mountain Road intersection (Segment A) and is shown in red on Figure 1. • Scenario 2: Includes Segment A, plus the Tile Flat Road extension from Scholls Ferry Road to the Mountainside Way extension (Segment B) and is shown in green on Figure 2. • Scenario 3: Includes Segment A, plus the extension of Mountainside Way from Bull Mountain Road to connect with Roy Rogers Road somewhere at or between the Perth Road or Woodhue Street intersections (Segment C) and shown in blue on Figure 3. • Scenario 4: Includes Segments A, B, and C and is shown in purple on Figure 4. Figure 5 shows the primary street scenarios and preliminary alignments for supporting streets (assumed to be primarily neighborhood street classifications) that react to site constraints such as existing and planned intersections along the primary street network, jurisdictional boundaries, stream crossings, significant trees, groves, and wetlands, fire, life, safety access requirements, and other factors. Future iterations of the street network will further refine these assumptions and consider other factors such as alignment with school district boundaries and parcel boundaries that could impact phasing. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 3 SW Lasich Ln SW Bull Mtn Rd SW Beef Bend Rd SW R o y R o g e r s R d SW Scholls Ferry Rd SW Jean Louise Rd SW Woodhue St SW R i v e r T e r r a c e B l v d SW V a n d e r m o s t R d SW Clementine St A A FIGURE 1 : TILE FLAT EXTENSION SCENARIO 1. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 4 FIGURE 2 : TILE FLAT EXTENSION SCENARIO 2 . SW Lasich Ln SW Bull Mtn Rd SW Beef Bend Rd SW R o y R o g e r s R d SW Scholls Ferry Rd SW Jean Louise Rd SW Woodhue St SW R i v e r T e r r a c e B l v d SW V a n d e r m o s t R d SW Clementine St A A SW Tile Flat Rd B B Evaluation of Tile Flat Extension Scenarios June 2025 Page | 5 FIGURE 3 : TILE FLAT EXTENSION SCENARIO 3 . SW Lasich Ln SW Bull Mtn Rd SW Beef Bend Rd SW R o y R o g e r s R d SW Scholls Ferry Rd SW Jean Louise Rd SW Woodhue St SW R i v e r T e r r a c e B l v d SW Va n d e r m o s t R d SW Clementine St A A SW M o u n t a i n s i d e W a y C Evaluation of Tile Flat Extension Scenarios June 2025 Page | 6 FIGURE 4 : TILE FLAT EXTENSION SCENARIO 4. SW Lasich Ln SW Bull Mtn Rd SW Beef Bend Rd SW R o y R o g e r s R d SW Scholls Ferry Rd SW Jean Louise Rd SW Woodhue St SW R i v e r T e r r a c e B l v d SW V a n d e r m o s t R d SW Clementine St A A SW M o u n t a i n s i d e W a y C SW Tile Flat Rd B B Evaluation of Tile Flat Extension Scenarios June 2025 Page | 7 FIGURE 5 : PRELIMINARY RIVER TERRACE 2.0 STREET NETWORK DIAGRAM. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 8 PERFORMANCE METRICS The Tile Flat extension scenarios were assessed and compared using the performance metrics shown below. These include a mix of quantitative and qualitative considerations. Wherever possible, findings were communicated in terms of resident and traveler experiences, with a focus on identifying meaningful differences between scenarios. 1. Vehicular Network A. Vehicle Miles Traveled (VMT) B. Quantity of Travel C. Intersection Capacity D. Travel Time 2. Multimodal Network A. Bicycle Level of Traffic Stress (BLTS) B. Pedestrian Level of Traffic Stress (PLTS) C. Connectivity D. Vulnerable Road User Safety E. Future Transit Service 3. Environmental / Livability A. GHG and Emissions B. Natural Resource Impacts C. Livability Impacts of Regional Vehicle Trips 4. Development Feasibility A. Support to Commercial Areas B. Land Use and Development Feasibility C. Order-of-Magnitude Infrastructure Costs D. Timing, Phasing, and Project Cost E. Fire, Life, Safety 5. Equity A. Equitable Benefits Evaluation of Tile Flat Extension Scenarios June 2025 Page | 9 1. VEHICULAR NETWORK The following are performance metrics that compare vehicular travel between the Tile Flat extension scenarios. A. Vehicle Miles Traveled (VMT) Description Analysis A1: Comparison of the vehicle miles travelled on the arterial and primary and secondary street networks. This includes the combined VMT on arterials (i.e., Scholls Ferry Road from Tile Flat Road to Roy Rogers Road and Roy Rogers Road from Scholls Ferry Road to Perth Road) and on primary and secondary Streets (i.e., Mountainside Way from Scholls Ferry Road to Roy Rogers Road, Mountainside Way from Sabrina Avenue (south) to Perth Road and Tile Flat Road from Scholls Ferry Road to Mountainside Way). Analysis A2: Comparison of the vehicle miles travelled on just the primary and secondary street network. This includes the combined VMT on Mountainside Way from Scholls Ferry Road to Roy Rogers Road, Mountainside Way from Sabrina Avenue (south) to Perth Road and Tile Flat Road from Scholls Ferry Road to Mountainside Way. Methodology VMT was estimated using the forecasted motor vehicle traffic volumes along roadway segments for 2040 using Washington County's version of the Metro Regional Transportation Demand Model. The volumes were based on the PM peak hour and were multiplied by the length of the segment to estimate the total VMT for each scenario. A1: A scenario performs best if the total VMT decreases more than 1% from no-build, is neutral if there is a change of less than 0.5% from no-build, and performs worst if there is an increase of more than 1% from no- build. A2: A scenario performs best if the share of total VMT for RT 2.0 trips on the primary and secondary street network is greater than 75%, is neutral if it is between 50% and 60%, and performs worst if it is less than 25%. Results and Evaluation A1: Table 1 shows that the overall forecasted VMT on the arterial street network is expected to be fairly similar for each of the scenarios. Scenarios 1 and 3 include a total estimated VMT of over 6,700 along the arterial roadways in the River Terrace 2.0 West area, which is similar to the forecasted VMT under no-build conditions, and that is expected to decrease between 5% and 7% with Scenarios 2 and 4. The estimated VMT on Roy Rogers Road is expected to decrease slightly under all scenarios when compared to Scenario 1, with traffic shifting to Mountainside Way, although some of that shift is negated by other regional traffic shifting to Roy Rogers Road from other nearby congested arterials. The estimated VMT on Scholls Ferry Road is expected to decrease with Scenarios 2 and 4 when compared to Scenario 1, with traffic shifting to Tile Flat Road. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 10 TABLE 1 : COMPARISON OF VMT ON THE STREET NETWORK Ideal Definition Total VMT on the Arterial network (PM Peak Hour) Total VMT on the Primary and Secondary Street network (PM Peak Hour) Total VMT (PM Peak Hour) Total VMT Change from no- build Total VMT decreases on the arterial and primary and secondary street network* as the RT 2.0 primary and secondary street network is constructed and accommodates more local trips. Scenario 1 6,761 382 7,143 -0.5% Scenario 2 6,397 855 7,252 1.0% Scenario 3 6,729 420 7,149 -0.4% Scenario 4 6,254 903 7,156 -0.3% Notes: * Includes combined VMT on arterials (i.e., Scholls Ferry Road from Tile Flat Road to Roy Rogers Road and Roy Rogers Road from Scholls Ferry Road to Perth Road), and on the primary and secondary street network (i.e., Mountainside Way from Scholls Ferry Road to Roy Rogers Road, Mountainside Way from Sabrina Avenue (south) to Perth Road and Tile Flat Road from Scholls Ferry Road to Mountainside Way). The scenarios were ranked with the following compared to the ideal condition: - >=1% from no-build - 0.5% - 1% from no- build + - 0.5% from no- build + 0.5% - 1% from no-build + >=1% from no-build A2: Table 2 shows that the overall forecasted VMT on the primary and secondary street network is expected to be mostly local trips under Scenario 1, at 92%, and the share of the total VMT for local trips decreases under Scenarios 2, 3, and 4. In Scenarios 2 and 4, regional trips account for more than 50% of the total VMT on the primary and secondary street network, with these trips utilizing Tile Flat Road and Mountainside Way, instead of the surrounding arterials. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 11 TABLE 2 : COMPARISON OF VMT ON THE PRIMARY AND SECONDARY STREET NETWORK Ideal Definition VMT of Regional Trips (PM Peak Hour) VMT of RT 2.0 Trips (PM Peak Hour) Share of Total VMT for RT 2.0 Trips The RT 2.0 primary and secondary street network* serves local trips and discourages regional cut- through traffic. Scenario 1 30 352 92% Scenario 2 449 406 47% Scenario 3 160 260 62% Scenario 4 465 438 48% Notes: * Includes combined VMT on Mountainside Way from Scholls Ferry Road to Roy Rogers Road, Mountainside Way from Sabrina Avenue (south) to Perth Road and Tile Flat Road from Scholls Ferry Road to Mountainside Way. The scenarios were ranked with the following compared to the ideal condition: >=75% local trips 60-75% local trips 50-60% local trips 25-50% local trips <=25% local trips B. Quantity of Travel This performance metric compares the change in the forecasted average daily traffic (ADT) volume along the primary and secondary street network including Mountainside Way and Tile Flat Road. Methodology Average daily motor vehicle volumes were forecasted along roadway segments for 2040 using Washington County's version of the Metro Regional Transportation Demand Model. These volumes were estimated using the PM peak hour volumes and multiplying them by a factor of 10 to represent ADT. A scenario performs best if the forecasted ADT volume along the segment is consistent with that of a collector street through a residential neighborhood, with the ideal condition being under 6,000 vehicles per day (vpd). A scenario with a forecasted ADT over 6,000 vpd along a segment performs worst. Results Table 3 shows the forecasted 2040 ADT volume for each scenario along the primary and secondary street network. Figure 6 through Figure 9 show the forecasted 2040 ADT volumes for the street network in the River Terrace 2.0 area. Scenario 1 is forecasted to have the lowest ADT volumes along the primary and secondary street network. Scenarios 2 and 4 were found to draw trips from Scholls Ferry Road and Roy Rogers Road and increase trips on Tile Flat Road and the segments of Mountainside Way south of where Tile Flat Road would connect, as well as on Bull Mountain Road where it connects to Roy Rogers Road. These are street segments internal to the RT 2.0 Evaluation of Tile Flat Extension Scenarios June 2025 Page | 12 West development and the forecasted 2040 ADT volumes along Mountainside Way for Scenarios 2 and 4 are forecasted to be higher than Scenarios 1 and 3. Scenario 3 does not include the Tile Flat Road extension but extends Mountainside Way to Perth Road. It would result in similar forecasted 2040 ADT volumes along Scholls Ferry Road and Roy Rogers Road compared to Scenario 1, slight increases along Mountainside Way, and a reduction along Bull Mountain Road compared to Scenario 1. TABLE 3 : QUANTITY OF TRAVEL ON THE PRIMARY AND SECONDARY STREET NETWORK Ideal Definition Roadway Segment Scenario 1: ADT Scenario 2: ADT Scenario 3: ADT Scenario 4: ADT Forecasted average daily traffic volumes on the primary and secondary street network are consistent with that of a collector through a residential neighborhood, with the ideal condition being under 6,000 ADT. SW Mountainside Way Scholls Ferry Road to Sabrina Avenue 4,700 3,700 5,200 3,800 Sabrina Avenue (north) to Jean Louise Road 4,000 7,000 4,500 7,600 Jean Louise Road to Sabrina Avenue (south) 2,900 5,900 3,600 6,600 Sabrina Avenue (south) to Perth Road n/a n/a 2,100 3,400 SW Bull Mountain Road Sabrina Avenue (south) to Roy Rogers Road 3,000 5,800 1,700 3,400 SW Tile Flat Road Roy Rogers Road to Mountainside Way n/a 4,000 n/a 4,500 Notes: The scenarios were ranked with the following compared to the ideal condition: ADT <= 3,000 ADT 3,000-6,000 ADT 5,001-6,500 ADT 6,501-7,000 ADT >= 7,000 Evaluation of Tile Flat Extension Scenarios June 2025 Page | 13 FIGURE 6 : FORECASTED 2040 AVERAGE DAILY TRAFFIC FOR SCENARIO 1. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 14 FIGURE 7 : FORECASTED 2040 AVERAGE DAILY TRAFFIC FOR SCENARIO 2 . Evaluation of Tile Flat Extension Scenarios June 2025 Page | 15 FIGURE 8 : FORECASTED 2040 AVERAGE DAILY TRAFFIC FOR SCENARIO 3 . Evaluation of Tile Flat Extension Scenarios June 2025 Page | 16 FIGURE 9 : FORECASTED 2040 AVERAGE DAILY TRAFFIC FOR SCENARIO 4 . Evaluation of Tile Flat Extension Scenarios June 2025 Page | 17 C. Intersection Capacity This metric compares the traffic operational performance at surrounding intersections along the arterial network on Scholls Ferry Road and Roy Rogers Road. Methodology The Highway Capacity Manual 6th Edition methodology was used to calculate volume-to-capacity (v/c) ratios at intersections for the weekday PM peak hour. A scenario performs best if the intersection is forecasted to operate with a v/c ratio that is at or below the current mobility target and performs worst if it operates higher than it. Results As shown in Table 4, the intersections are forecasted to operate with similar v/c ratios under each scenario. The Mountainside Way extension to Perth Road included in Scenario 3, and when both it and the Tile Flat Road extension are combined under Scenario 4 allows for a slight improvement in forecasted operations at intersections along Scholls Ferry Road and at the Roy Rogers Road & Jean Louise Drive intersection. TABLE 4 : INTERSECTION OPERATIONS (2040 PM PEAK) Ideal Definition Intersection Volume-to-Capacity (V/C) Ratio Scenario 1 Scenario 2 Scenario 3 Scenario 4 Intersections are forecasted to be less congested once the RT 2.0 Primary and Secondary Street network is constructed, with intersections forecasted to operate with a v/c ratio that is at or below the current 0.99 mobility target. SW Scholls Ferry Road/ SW Tile Flat Road 0.97 0.85 0.97 0.85 SW Scholls Ferry Road/ SW Mountainside Way 0.97 0.53 0.58 0.53 SW Scholls Ferry Road/ SW Roy Rogers Road/ SW 175th Avenue 1.16* 1.21* 1.16* 1.21* SW Roy Rogers Road/ SW Jean Louise Road 0.93 0.92 0.89 0.91 SW Roy Rogers Road/ SW Bull Mountain Road 0.96 1.01* 0.93 0.98 SW Roy Rogers Road/ SW Perth Road 0.86 0.88 0.97 0.99 Notes: * Indicates an intersection that is forecasted to operate above the current mobility target of 0.99 v/c. The scenarios were ranked with the following compared to the ideal condition: v/c <=0.99 v/c 1.00-1.05 v/c 1.06-1.10 v/c 1.11-1.15 v/c >= 1.16 Evaluation of Tile Flat Extension Scenarios June 2025 Page | 18 The scenarios also alter turning movement patterns at intersections along Roy Rogers Road. Scenarios 2 and 4, that extend Tile Flat Road to Mountainside Way, add traffic to Bull Mountain Road, which results in slight degradation of forecasted operations at the Roy Rogers Road intersection. Scenario 3 that extends Mountainside Way to Perth Road draws traffic away from Bull Mountain Road, which slightly improves operations at the Roy Rogers Road intersection but results in slight degradation at the Roy Rogers Road & Perth Road intersection. It was found that after assuming the Tile Flat Road extension to Mountainside Way was in place and some drivers use that route instead of remaining on Roy Rogers Road and Scholls Ferry Road, that any new capacity available in this segment was filled by other regional traffic. In other words, future congestion on parallel arterials routes (such as OR 99W) could potentially cause drivers to re-route from those roadways to Roy Rogers Road and Scholls Ferry Road through the River Terrace 2.0 West and South area, which has an influence on the traffic operational results shown in Table 4. The model assigns vehicles to the shortest travel time routes for these trips, however drivers may not be that efficient in determining this, at least initially. D. Travel Time This performance metric compares the travel time for regional trips on the primary collector streets and along Roy Rogers Road and Scholls Ferry Road. Methodology Average daily motor vehicle volumes were forecasted along roadway segments for 2040 using Washington County's version of the Metro Regional Transportation Demand Model. These volumes were estimated using the PM peak hour and include vehicle trips that start and end outside of the River Terrace 2.0 area but travel along the adjacent arterials (i.e., Roy Rogers Road and Scholls Ferry Road). The total average travel time for regional trips (i.e., trips that have an origin and destination outside of the River Terrace 2.0 area) between the Scholls Ferry Road intersection with Tile Flat Road and the Roy Rogers Road intersection with Perth Road was calculated for each scenario. The scenarios were ranked based on the following criteria: average travel time for regional trips is forecasted to be -61 seconds or more from no-build (or half an average cycle length at a signalized intersection), -30 to -60 seconds from no-build, within 30 seconds of no-build, +30 to +60 seconds from no-build, +61 seconds or more from no-build. Results Table 5 shows that the average travel time for regional trips (i.e., trips that have an origin and destination outside of the River Terrace 2.0 area) between the S Scholls Ferry Road intersection with Tile Flat Road and the Roy Rogers Road intersection with Perth Road is around 7 minutes in each scenario. The extension of Tile Flat Road to Mountainside Way (Scenario 2) is not expected to change the average travel time for these regional trips, while the extension of Mountainside Way to Perth Road (Scenario 3) slightly increases the average travel time for these regional trips. Although some traffic is shifting from Roy Rogers Road and Scholls Ferry Road to Tile Flat Road and Mountainside Way under Scenarios 2 and 3, the excess capacity from that shift is largely negated by other regional traffic shifting to Roy Rogers Road from other nearby congested arterials, therefore the average travel time along these corridors remains similar under these scenarios. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 19 However, there is a travel time benefit of roughly 0.3 minutes or 18 seconds for regional trips when both Tile Flat Road and Mountainside Way are extended (Scenario 4). This represents approximately a 4% reduction in trip time compared to Scenario 1. Since more trips are shifting to Tile Flat Road and Mountainside Way under this scenario, the excess capacity is not entirely taken up by other regional traffic, and therefore the average travel times along Roy Rogers Road and Scholls Ferry Road are slightly reduced when compared to Scenario 1 through the River Terrace 2.0 area. Ideal Definition Average Travel Time in the PM Peak Hour (Minutes)* Change from no- build (seconds) Forecasted travel times for regional trips decrease by more than one half of a traffic signal cycle (more than 30 seconds) once the RT 2.0 Primary and Secondary Street network is constructed. Scenario 1 6.91 -11 Scenario 2 6.88 -13 Scenario 3 7.07 -2 Scenario 4 6.63 -28 The scenarios were ranked with the following compared to the ideal condition: ->=60 secs from no-build -30-60 secs from no-build +- 30 secs from no- build + 30-60 secs from no-build + >=61 secs from no-build TABLE 5 : COMPARISON OF TRAVEL TIME FOR REGIONAL TRIPS Evaluation of Tile Flat Extension Scenarios June 2025 Page | 20 2. MULTIMODAL NETWORK The following are performance metrics that compare bicycling, pedestrian, and transit travel between the primary street network scenarios. A. Bicycle Level of Traffic Stress (BLTS) This performance metric compares the types and scale of facilities and crossings needed to maintain low-stress conditions for bicyclists along the primary collector streets based on expected traffic volumes and speeds. Methodology This analysis is based on the ODOT BLTS methodology outlined in the Analysis Procedures Manual Chapter 14 – Section 14.4 and incorporating best practice principles from the 2024 AASHTO Guide for the Development of Bicycle Facilities. • It is assumed that the bicycling network in RT 2.0 will be designed to BLTS 1 (i.e., the highest level of comfort) to encourage bicyclists of all ages and abilities to use this mode for short- and medium- distance trips. • BLTS 1 needs to be maintained on segments, at intersections, and at crossings for the network to achieve BLTS 1. • The Tile Flat Road extension and other primary streets are assumed to be collectors with a 2-lane cross- section and turn lanes at arterial and other key intersections and with a posted speed limit of 25 mph or less. • Note that all widths for bike lanes are “useable widths,” which is defined by the 2024 AASHTO Guide for the Development of Bicycle Facilities as “a smooth, rideable surface clear of surface defects, joints, and other potential obstructions to minimize crash risk.” The useable width should not include a gutter, unless the gutter is integrated into the full width of the bicycle facility. Results & Evaluation Below are the design requirements to maintain BLTS 1: • Segment BLTS: cross-sections should include a shared use path or separated bike lanes. If volumes and speeds are lower, buffered bike lanes may be appropriate. See Appendix A – Table A1 for more detailed descriptions of required design criteria. All scenarios will be designed similarly and meet BLTS 1 at the expected speeds and volumes. • Intersection and crossing BLTS: design treatments to meet BLTS 1 at unsignalized, signalized, and roundabout intersections as well as at midblock crossings are described in Appendix A – Table A2. Signalized and roundabout intersections will be designed similarly and meeting BLTS 1 for all scenarios. The type of unsignalized crossing required depends on traffic volumes. For a 2-lane street at 25 mph or less, a median crossing is required when traffic volumes exceed 3,000 vpd. Based on these criteria and the expected ADT (see metric 1B), the following unsignalized crossing infrastructure is needed: o Scenario 1: median crossings on Mountainside Way north of Jean Louise Drive. No median required elsewhere. This is a total of 4 median crossings. o Scenario 2: median crossings on all streets including Tile Flat Road, Mountainside Way, and Bull Mountain Road. This is a total of 9 median crossings. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 21 o Scenario 3: median crossings on Mountainside Way north of Bull Mountain Road. No median required elsewhere. This is a total of 7 median crossings. o Scenario 4: median crossings on all streets including Tile Flat Road, Mountainside Way, and Bull Mountain Road. This is a total of 10 median crossings. Scenario 1 represents the lowest investment needed to achieve BLTS 1. Other scenarios will have some additional cost and right-of-way dedication associated with the additional median crossing needs. These costs will have some impact but are not considered significant relative to the overall cost. Right-of-way dedication and the impact on development yield is considered in metric 4B. Table 6 summarizes the level of infrastructure needed to achieve BLTS 1 under each scenario. TABLE 6 : EVALUATION OF INFRASTRUCTURE NEEDED TO MEET BLTS 1 INFRASTRUCTURE NEEDS TO MEET BLTS 1 SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 Segments Shared use path or separated bike lanes meets BLTS 1 Shared use path or separated bike lanes meets BLTS 1 Shared use path or separated bike lanes meets BLTS 1 Shared use path or separated bike lanes meets BLTS 1 Ideal condition- minimal investment to create BLTS 1 Intersections BLTS 1 achieved with median crossings needed at 4 locations BLTS 1 achieved with median crossings needed at all (9) locations BLTS 1 achieved with median crossings needed at some additional (7) locations BLTS 1 achieved with median crossings needed at all (10) locations Ideal condition- minimal investment to create BLTS 1 Overall Performance – Relative Investment Needed to Meet BLTS 1 Lowest investment to achieve BLTS 1 Achieves BLTS 1 with some costs for median crossings at all locations Achieves BLTS 1 with some costs for additional median crossings Achieves BLTS 1 with some costs for median crossings at all locations Ideal condition- minimal investment to create BLTS 1 B. Pedestrian Level of Traffic Stress (PLTS) This performance metric compares the types and scale of facilities and crossings needed to maintain low-stress conditions for pedestrians along the primary collector streets based on typical crossing spacing standards, expected traffic volumes, and speeds. Methodology This analysis was conducted based on the ODOT PLTS methodology outlined in the Analysis Procedures Manual Chapter 14 – Section 14.5. • It is assumed that the pedestrian network in RT 2.0 will be designed to PLTS 1 (i.e., the highest level of comfort) to support accessibility goals and encourage people to use this mode for short-distance trips. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 22 • PLTS 1 needs to be maintained on segments, at intersections, and at crossings for the network to achieve PLTS 1. • The Tile Flat Road extension and other primary streets are assumed to be collectors with a 2-lane cross- section and turn lanes at arterial and other key intersections and with a posted speed limit of 25 mph or less. Results & Evaluation Below are the design requirements to maintain PLTS 1: • Segment PLTS: sidewalk widths should be ≥ 6’ in general and ≥ 8’ in higher traffic and commercial areas. Sidewalks need to be in good condition with a sufficient width landscape or hardened buffer between it and the roadway. See Appendix B – Table B1 for more detailed descriptions of required design criteria. All scenarios will be designed similarly and meet BLTS 1 at the expected speeds and volumes. • Intersection and crossing PLTS: design treatments to meet PLTS 1 at unsignalized, signalized, and roundabout intersections as well as at midblock crossings are described in Appendix B – Table B2. Signalized and roundabout intersections will be designed similarly and meeting BLTS 1 for all scenarios. The type of unsignalized crossing required depends on traffic volumes. For a 2-lane street at 25 mph or less, a median crossing is required when traffic volumes exceed 5,000 vpd. Based on these criteria and the expected ADT (see metric 1B), the following unsignalized crossing infrastructure is needed: o Scenario 1: no median crossings are required to accommodate pedestrian crossings. o Scenario 2: median crossings on Mountainside Way south of the Tile Flat Road extension. No median crossings are required elsewhere to accommodate pedestrian crossings. This is a total of 6 median crossings. o Scenario 3: median crossings on Mountainside Way north of Sabrina Avenue. No median crossings are required elsewhere to accommodate pedestrian crossings. This is a total of 2 median crossings. o Scenario 4: median crossings on Mountainside Way from the Tile Flat Road extension to Bull Mountain Road. No median crossings are required elsewhere to accommodate pedestrian crossings. This is a total of 6 median crossings. Scenario 1 represents the lowest investment needed to achieve PLTS 1. Other scenarios will have some additional cost and right-of-way dedication associated with the additional median crossing needs. These costs will have some impact but are not considered significant relative to the overall cost. Right-of-way dedication and the impact on development yield is considered in metric 4B. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 23 Table 7 summarizes the level of infrastructure needed to achieve PLTS 1 under each scenario. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 24 TABLE 7 : EVALUATION OF INFRASTRUCTURE NEED ED TO MEET PLTS 1 INFRASTRUCTURE NEEDS SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 Segments Sidewalk with landscaped buffer meets PLTS 1 Sidewalk with landscaped buffer meets PLTS 1 Sidewalk with landscaped buffer meets PLTS 1 Sidewalk with landscaped buffer meets PLTS 1 Ideal condition- minimal investment to create BLTS 1 Intersections No median crossings needed to meet PLTS 1 Median crossing needed in some (6) locations to meet PLTS 1 Median crossings needed in very few (2) locations to meet PLTS 1 Median crossings needed in some (6) locations to meet PLTS 1 Ideal condition- minimal investment to create BLTS 1 Overall Performance – Relative Investment Needed to Meet PLTS 1 Lowest investment to achieve PLTS 1 Achieves PLTS 1 with some costs for additional median crossings Achieves PLTS 1 with some costs for additional median crossings Achieves PLTS 1 with some costs for additional median crossings Ideal condition- minimal investment to create BLTS 1 C. Connectivity This metric compares the directness and convenience of the multimodal network and identifies any barriers resulting from the primary street network scenarios related to accessing regional destinations as well as local destinations including commercial districts, parks, trails, transit stops, etc. Methodology The analysis compares performance in three sub-metrics: • Arterial connections: this compares the number of connections to the arterial street network with a higher number increasing access for future residents to regional destinations. • Internal street connectivity: a qualitative review of how well the internal street network supports development and a comparison of local street permeability measured by intersection density – the number of intersections per mile of primary street network. • Walking catchment: this includes a GIS walkshed analysis to compare the percentage of residential development in RT 2.0 that is within a ½ and 1-mile (i.e., 10- or 20-minute) walk of key destinations including the two commercial areas in RT 2.0 West and the existing Mountainside High School. Note that the analysis only includes the primary street network. The local street network may increase the percentage of development within each walking catchment. However, it is expected that the relative increase would be the same across scenarios. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 25 Results Table 8 compares external street network connectivity between scenarios. Table 9 compares internal street network connectivity. TABLE 8 : COMPARISON OF EXTERNAL NETWORK CONNECTIVITY * Includes intersections with the external street network including Scholls Ferry Road, Roy Rogers Road, Perth Road, and Vandermost Road. SCENARIO ARTERIAL CONNECTIONS EXTERNAL CONNECTIVITY A 3 Provides connections to Scholls Ferry Road and Roy Rogers Road. B 4 Extending Tile Flat Road provides a more direct vehicular connection to regional destinations northwest of RT 2.0. C 4 Extending Mountainside Way provides an additional connection to RT 1.0 and RT 2.0 South without having to use the arterial network. D 5 Extending Tile Flat Road provides a more direct vehicular connection to regional destinations northwest of RT 2.0. Extending Mountainside Way provides an additional connection to RT 1.0 and RT 2.0 South without having to use the arterial network. TABLE 9 : COMPARISON OF INTERNAL NETWORK CONNECTIVITY SCENARIO CONNECTIVITY INTERSECTIONS* LENGTH (MILES) PRIMARY STREET INTERSECTION DENSITY (INTXNS/MILE) A Provides internal circulation for RT 2.0. Future development on Vandermost Road is disconnected from the rest of RT 2.0. Development potential is limited on Vandermost Road. 8 1.05 7.6 B Provides internal circulation for RT 2.0. Future development on Vandermost Road would be connected to the rest of RT 2.0. 10 1.69 5.9 C Provides internal circulation for RT 2.0. Future development on Vandermost Road is disconnected from the rest of RT 2.0. Development potential is limited on Vandermost Road. 10 1.68 6.0 D Provides internal circulation for RT 2.0. Future development on Vandermost Road would be connected to the rest of RT 2.0. 12 2.32 5.2 Evaluation of Tile Flat Extension Scenarios June 2025 Page | 26 Scenario 1 provides the internal circulation required to support development in RT 2.0 West and includes three connections to the arterial street network at Scholls Ferry Road & Mountainside Way, Roy Rogers Road & Jean Louise Drive, and Roy Rogers Road & Bull Mountain Road. Additional street segments are not required to support development. However, extending Tile Flat Road as part of Scenarios 2 or 4 would provide a fourth connection to the arterial street network and a more direct vehicular connection to regional destinations northwest of RT 2.0. Extending Mountainside Way south to connect to Roy Rogers Road at Perth Road as part of Scenarios 3 or 4 would increase connectivity to RT 1.0 and RT 2.0 South by providing another east-west access route that could distribute traffic and shorten travel between some destinations in these areas. Scenario 3 would provide four connections to the arterial street network and Scenario 4 would provide five connections. Extending Tile Flat Road as part of Scenarios 2 or 4 would provide a connection to any future development on Vandermost Road, which would otherwise rely on the arterial street network (i.e., Scholls Ferry Road) to connect to the rest of RT 2.0. Development potential along Vandermost Road is limited and may not justify the cost of providing an additional connection along the Tile Flat Road alignment solely for the purpose of additional connectivity. Table 9 shows that Scenario 1 has the highest intersection density because it has the lowest length of street, but all scenarios would provide good local connectivity to the developable areas of RT 2.0 West. The results of the walkshed analysis in Table 10 show that with the extension of Tile Flat Road (Scenario 2), Mountainside Way (Scenario 3), or both (Scenario 4), there is an incremental increase in the amount of residential development that can access the Scholls Ferry & Mountainside Way (SFMW) commercial area, the Mountainside High School, and the Roy Rogers & Bull Mountain (RRBM) commercial area within a ½ mile walkshed – approximately a 5% to 15% increase. Table 11 shows that these extensions increase the amount of residential development within a 1-mile walkshed by up to 10% to 30%. Maps of the walkshed analysis are included in Appendix C. TABLE 10 : PERCENTAGE OF RESIDENTIAL DEVELOPMENT WITHIN A HALF MILE WALKSHED (10 - MINUTE WALK) SCENARIO COMMERCIAL A (SFMW) COMMERCIAL B (RR BM) MOUNTAINSIDE HIGH SCHOOL A 45% 20% 30% B 55% 20% 35% C 45% 35% 30% D 55% 35% 35% Evaluation of Tile Flat Extension Scenarios June 2025 Page | 27 TABLE 11 : PERCENTAGE OF RESIDENTIAL DEVELOPMENT WITHIN A ONE MILE WALKSHED (20 - MINUTE WALK) Evaluation Table 12 compares multimodal connectivity between scenarios. Scenario 1 provides sufficient connectivity for development with three access points to the arterial road network, good connectivity to River Terrace 1.0 and South Cooper Mountain, and the highest density of intersections (meaning more opportunities for crossings, etc.). It does have a lower walkshed coverage for key destinations in the neighborhood than other scenarios. TABLE 12 : EVALUATION OF MULTIMODAL CONNECTIVITY SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 External Network Connectivity (# of arterial connections) 3 4 4 5 Ideal condition – highest number of connections Intersection Density (intersections per mile) 7.6 5.9 6.0 5.2 Ideal condition – highest density of intersections Internal Network Connectivity Good connectivity to RT 1.0/2.0 and South Cooper Mountain Additional connectivity to Vandermost Additional connectivity to RT 1.0/2.0 Additional connectivity to Vandermost and RT 1.0/2.0 Ideal condition – highest number of connections Walkshed Analysis 60%-70% coverage 5%-20% more coverage 5%-15% more coverage 10%-30% more coverage Ideal condition – highest coverage percentage Overall Performance for Connectivity Provides sufficient connectivity for development and good Provides additional local and regional connectivity Provides additional local connectivity and walkshed coverage* Provides the most local and regional connectivity Ideal condition – high performance in local and SCENARIO COMMERCIAL A (SFMW) COMMERCIAL B (RR BM) MOUNTAINSIDE HIGH SCHOOL A 70% 60% 65% B 80% 80% 70% C 80% 75% 70% D 85% 90% 75% Evaluation of Tile Flat Extension Scenarios June 2025 Page | 28 SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 regional connectivity and walkshed coverage walkshed coverage and walkshed coverage* and walkshed coverage* * Increased traffic volumes and lower intersection densities could increase vehicle speeds and may require traffic calming and additional midblock pedestrian crossings to meet desirable crossing spacing standards. Other scenarios were evaluated higher than Scenario 1. Scenario 2 provides an additional connection to the regional network via the Tile Flat Road extension. This also increases the percentage of development that can walk to commercial areas and the high school. It also provides a secondary connection for development on Vandermost Road. However, development potential in that area is limited, and this benefit is not considered significant. Scenario 3 provides an additional connection to RT 1.0 and RT 2.0 South and additional walkshed coverage. Scenario 4 provides both the local and regional connectivity benefits but would have the lowest intersection density. The increased regional connectivity will increase traffic volumes and lower intersection densities could increase vehicle speeds and may require traffic calming and additional midblock pedestrian crossings to meet desirable crossing spacing standards. D. Vulnerable Road User Safety This metric compares the traffic exposure and relative safety risk (i.e., number of lanes, crossing distance, increased conflict with turning movements, etc.) for vulnerable road users including pedestrians and bicyclists traveling along the primary collector streets and crossing at key intersections including at Roy Rogers Road and Scholls Ferry Road. Methodology Analysis conducted for the City of Tigard’s Transportation Safety Action Plan (TSAP) shows that the High Injury Network (HIN) is most correlated to ADT, functional class, speed, and demographics (e.g., Oregon social equity index, percentage of households with no vehicles, etc.). There is no material difference between scenarios with respect to the functional class, speed, and demographic factors, i.e., in all scenarios the Tile Flat extension will be a collector street designed at the same speed and serving the same demographics. However, there will be increased exposure – including for pedestrians and bicyclists – resulting from differences in traffic volumes and the length of the different scenarios. • Segment crash exposure is calculated as: o Sum of (segment ADT * segment miles of road * segment # of lanes) Different scenarios will also result in different turning movement patterns in the network. This can increase crash exposure for pedestrians and bicyclists at intersection crossings and affect the cost to mitigate these impacts. • Turning movement crash exposure is calculated as follows: o Sum of turning movements conflicting with pedestrian crossings at an intersection. o Qualitative analysis of turning movements that conflict with likely school and commercial area pedestrian routes. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 29 Results & Evaluation Segment crash exposure is shown in Table 13. Scenario 1 has the lowest internal traffic volumes and therefore results in the lowest vulnerable road user (VRU) crash exposure. If the total length of all scenarios is considered, the increase in street network length and traffic volumes results in all other scenarios having higher VRU crash exposure. Scenario 3 is somewhat (43%) higher than Scenario 1 whereas Scenarios 2 and 4 are significantly higher (124% and 191%) than Scenario 1. Segment exposure was evaluated as follows: • The scenario with the lowest segment exposure was rated as having a medium impact in that it contributes some level of crash risk. • Scenarios within a 50% increase of the best performing scenario were considered to have a significant impact. • Scenarios with a more than 50% increase from the best performing scenario were considered to have a very significant impact on crash risk. TABLE 13 : COMPARISON OF SEGMENT CRASH EXPOSURE SEGMENT CRASH EXPOSURE (VEHICLE LANE MILES) SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 All Segments 7,290 16,350 10,430 21,250 Ideal definition – VRUs crash exposure is minimized (zero vehicle-lane-miles) Lowest overall VRU crash exposure VRU crash exposure is considerably higher than Scenario 1 (+124%) VRU crash exposure is somewhat higher than Scenario 1 (+43%) VRU crash exposure is considerably higher than Scenario 1 (+191%) * This analysis compares exposure on Mountainside Way from Scholls Ferry Road to Bull Mountain Road and on Bull Mountain Road from Mountainside Way to Roy Rogers Road. The location of turning movement exposure will change based on the scenario. Turning movement crash exposure is shown in Table 14. For Scenario 1, major turning movements will occur to and from the arterial street network at Scholls Ferry Road & Mountainside Way (505 total turning movements during the 2040 PM peak hour) and at Roy Rogers Road & Bull Mountain Road (860 total turning movements during the 2040 PM peak hour). These are controlled, signalized locations where these conflicts are expected although the former will be along a primary walking route to access Mountainside High School. This scenario would see the lowest turning movement crash exposure internal to the development along the primary walking and bicycling routes on Mountainside Way and Bull Mountain Road. This scenario would see 80 total turning movements during the 2040 PM peak hour at the Tile Flat Road Extension & Mountainside Way intersection. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 30 Scenario 3 would increase turning movement crash exposure when compared to Scenario 1 at the Scholls Ferry Road & Mountainside Way intersection (i.e., 530 total turning movements during the 2040 PM peak hour) but would reduce turning movements at the Roy Rogers Road & Bull Mountain Road intersection (i.e., 755 total turning movements during the 2040 PM peak hour) and shift them further south to the Roy Rogers Road & Perth Road intersection where there may be fewer pedestrian crossings expected. Turning movement exposure internal to the development would increase somewhat under this scenario (i.e., +20 total turning movements during the 2040 PM peak hour at the Tile Flat Road Extension & Mountainside Way intersection). Scenarios 2 and 4 would reduce turning movements when compared to Scenario 1 at the Scholls Ferry Road & Mountainside Way intersection (i.e., -50 total turning movements during the 2040 PM peak hour) and increase turning movements when compared to Scenario 1 at the Roy Rogers & Bull Mountain Road intersection (i.e., +240 and +110 total turning movements during the 2040 PM peak hour respectively). These scenarios would also increase turning movement exposure internal to the RT 2.0 WEST development (i.e., +225 total turning movements during the 2040 PM peak hour at the Tile Flat Road Extension & Mountainside Way intersection), along what will likely be a primary walking route to access Mountainside High School and the Scholls Ferry & Mountainside Way commercial area. Larger or more intense intersection designs – such as a protected intersections, roundabouts, or signals – may be required to address left- and right-turning conflicts with active transportation users at this intersection. TABLE 14 : COMPARISON OF TURNING MOVEMENT CRASH EXPOSURE INTERSECTION TOTAL TURNING MOVEMENT CONFLICTS WITH PEDESTRIAN CROSSINGS (PM PEAK VEHICLES PER HOUR) SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 Scholls Ferry Road / Mountainside Way 505 (+11%) 455 (lowest) 530 (+16%) 455 (lowest) Tile Flat Road / Mountainside Way 80 (lowest) 170 (+112%) 100 (+25%) 190 (+138%) Roy Rogers Road / Bull Mountain Road 860 (+14%) 1,100 (+46%) 755 (lowest) 970 (+28%) Roy Rogers Road / Perth Road - - 225 (lowest) 255 (+13%) Total Turning Movement Conflicts 1,445 vph 1,725 vph 1,610 vph 1,870 vph Ideal definition – VRUs crash exposure is minimized (zero vph turning movement conflicts) Lowest overall VRU crash exposure VRU crash exposure somewhat higher than Scenario 1 (+19%) VRU crash exposure somewhat higher than Scenario 1 (+11%) VRU crash exposure considerably higher than Scenario 1 (+29%) Evaluation of Tile Flat Extension Scenarios June 2025 Page | 31 Turning movement exposure was evaluated as follows: • The scenario with the lowest exposure was rated as having a medium impact in that it contributes some level of crash risk. • Scenarios within a 25% increase of the best performing scenario were considered to have a significant impact. • Scenarios with a more than 25% increase from the best performing scenario were considered to have a very significant impact on crash risk. Table 15 summarizes the evaluation of vulnerable road user safety. Scenario 1 represents the lowest vulnerable road user crash exposure both in terms of segment and turning movement exposure. Scenarios 2 and 4 represent somewhat higher exposures from increased traffic movements on the internal street network. Scenario 4 considerably increases crash exposure because it has the highest internal street traffic volumes and changed turning movement patterns conflicting with pedestrian crossing routes. TABLE 15 : EVALUATION OF VULNERABLE ROAD USER SAFETY SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 Segment Crash Exposure 7,290 16,350 10,430 21,250 Ideal definition – VRUs crash exposure is minimized (zero vehicle-lane-miles) Lowest overall VRU crash exposure VRU crash exposure is considerably higher than Scenario 1 (+124%) VRU crash exposure is somewhat higher than Scenario 1 (+43%) VRU crash exposure is considerably higher than Scenario 1 (+191%) Total Turning Movement Conflicts 1,445 vph 1,725 vph 1,610 vph 1,870 vph Ideal definition – VRUs crash exposure is minimized (zero vph turning movement conflicts) Lowest overall VRU crash exposure VRU crash exposure somewhat higher than Scenario 1 (+19%) VRU crash exposure somewhat higher than Scenario 1 (+11%) VRU crash exposure considerably higher than Scenario 1 (+29%) Overall Performance for VRU Safety Lowest VRU crash exposure VRU crash exposure higher than Scenario 1 VRU crash exposure somewhat higher than Scenario 1 VRU crash exposure considerably higher than Scenario 1 Ideal definition – VRUs crash exposure is minimized (zero) Evaluation of Tile Flat Extension Scenarios June 2025 Page | 32 E. Future Transit Service This metric compares the connectivity, travel time, and coverage performance for potential future transit service along the primary street network. Methodology The project team understands that TriMet will be extending service to Mountainside High School by 2028 as part of its Forward Together service expansion plan. TriMet would need to show >10 predicted boarding rides per hour to consider future service in the new development areas. Areas of River Terrace 1.0 and 2.0, South Cooper Mountain, and Kingston Terrace may all at some point meet this metric. There are numerous ways to service these areas with transit including regional services reaching into all or parts of these areas or local services to circulate and collect passengers for transfer at a regional transit hub. Street design standards will consider transit vehicle needs to make sure that the primary street network can accommodate future transit service. The Tile Flat Extension scenarios were evaluated to assess whether any of the scenarios created barriers or additional opportunities for future transit service compared to other scenarios. This included considering the amount of flexibility each scenario provides for route planning and circulation, potential destinations along the service route, and the potential to create regional transit hubs. Results & Evaluation Table 16 shows that Scenarios 2, 3, and 4 provide additional route flexibility but the additional connections beyond Scenario 1 are likely redundant for transit as the most effective route through RT2.0 would be via Mountainside Way and Bull Mountain Road. This route covers a significant portion of development, provides better connections to adjacent neighborhoods, would serve the two proposed commercial districts in RT2.0, and could help create transit and mobility hubs at mixed-use commercial nodes. Increases in traffic on the internal street network (see Metric 1B) could increase transit travel times under Scenarios 2, 3, and 4. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 33 Table 17 summarizes the evaluation of future transit service for RT 2.0. The primary transit route along Mountainside Way and Bull Mountain Road provides good coverage to the RT 2.0 development. This route is the most likely to be used under all scenarios to ensure good access to commercial hubs. Scenario 1 does not provide any route flexibility but would minimize transit delays as the lowest traffic volume scenario. Scenario 2 provides a route option on Tile Flat Road although that route is unlikely given residential densities along this corridor compared to others (e.g., Mountainside Way through South Cooper Mountain). Scenarios 3 and 4 do provide additional route options via the Mountainside Way extension to Perth Road that could provide secondary service to RT 1.0 and RT 2.0 South. Scenarios 2, 3, and 4 see increased traffic volumes on the primary street network that could result in transit delays. TABLE 16 : COMPARISON OF FUTURE TRANSIT SERVICE SCENARIO TRANSIT CONSIDERATIONS A • This scenario would allow for an efficient extension of existing service along Scholls Ferry Road to circulate through RT 2.0 West via Mountainside Way and into RT 1.0 via Bull Mountain Road before returning to Scholls Ferry Road to connect to the Washington Square Transit Center. • It could also support local or microtransit service connecting RT 1.0 and 2.0, Kingston Terrace, and South Cooper Mountain. • The commercial node at Scholls Ferry Road & Mountainside Way could serve as a regional transit hub and mobility hub. B • This scenario may offer an additional route option for any services using Tile Flat Road though it is likely service would run through South Cooper Mountain and down Mountainside Way making this additional connection redundant for transit. • Routing transit along the extension of Tile Flat Road would deviate the route from the commercial district at Scholls Ferry Road & Mountainside Way. C • This scenario may offer an additional route option to serve RT 1.0, RT 2.0 South, and Kingston Terrace using the Mountainside Way extension to Perth Road (without having to use the arterial street network). Base service is likely to run along Mountainside Way and Bull Mountain Road through RT 2.0 West. • Routing transit along the extension of Mountainside Way would deviate the route from the commercial district at Roy Rogers Road & Bull Mountain Road. D • This scenario may offer an additional route option to serve RT 1.0, RT 2.0 South, and Kingston Terrace using the Mountainside Way extension to Perth Road (without having to use the arterial street network). Base service is likely to run along Mountainside Way and Bull Mountain Road through RT 2.0 West. • Routing transit along the extension of Mountainside Way would deviate the route from the commercial district at Roy Rogers Road & Bull Mountain Road. • This scenario may offer an additional route option using the Tile Flat Road extension though it is likely service would run through South Cooper Mountain and down Mountainside Way making this additional connection redundant for transit. • Routing transit along the extension of Tile Flat Road would deviate the route from the commercial district at Scholls Ferry Road & Mountainside Way. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 34 TABLE 17 : EVALUATION OF FUTURE TRANSIT SERVICE SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 Provides a Primary Service Route Through RT2.0 Yes Yes Yes Yes Ideal definition – provides a primary route option with good residential and commercial access Additional Route Options Primary route option only Additional route option with Tile Flat extension but does not serve significant development Additional route options with extension of Mountainside Way to serve RT 1.0 and 2.0 South Additional route options with extension of Mountainside Way to serve RT 1.0 and 2.0 South Ideal definition – options for alternative routes that provide additional coverage Commercial Areas Impacted by Alternative Routes Transit passes by both commercial areas Alternative routes would not pass by the SFMW commercial area Alternative routes would not pass by the RRBM commercial area Alternative routes would not pass by the SFMW or RRBM commercial areas Ideal definition – transit passes by both commercial areas Potential for Transit Delay due to Traffic Lowest traffic volumes will result in lowest transit delays Higher traffic volumes on Mountainside Way will increase transit delay compared to Scenario 1 Slightly higher traffic volumes on Mountainside Way but similar to Scenario 1 Highest traffic volumes on Mountainside Way will increase transit delay compared to Scenario 1 Ideal definition – no delay to transit from traffic Overall Performance for Future Transit Primary route provides good coverage and lowest traffic volumes minimize delays Alternative routes available but may reduce coverage. Traffic volumes may result in some transit delays Alternative routes could provide additional residential coverage but reduce commercial exposure. Alternative routes could reduce commercial exposure. Traffic volumes may result in transit delays Ideal definition – high performance in base coverage, route options, and minimal transit delay Evaluation of Tile Flat Extension Scenarios June 2025 Page | 35 3. ENVIRONMENTAL / LIVABILITY The following provides performance metrics that are proposed to compare environmental and livability characteristics between the primary street network scenarios. A. GHG and Emissions This metric compares the relative scale and location of occurrence of GHG and emissions along the primary collector streets. Methodology The amount of transportation-related greenhouse gas and other emissions produced by vehicle operations depends on: • The mix of vehicle types and their emitting characteristics. For example, the percentage of internal combustion engines, diesel engines, heavy vehicles, hybrid vehicles, and all electric vehicles. • Vehicle miles traveled: the number of miles traveled by each vehicle type. Where these emissions occur is also important in terms of whether there are disproportionate impacts to residents, school children, or other vulnerable populations. GHG and other emissions will generally follow VMT patterns (see Metric 1A) with some variation depending on the fleet mix of different traffic components. It is unknown whether the vehicle fleet mix of residents moving to RT 2.0 will be significantly different to the fleet mix of the surrounding street network. This may be influenced by development standards for RT 2.0 that could encourage the adoption of electric vehicles for those residents that will own vehicles. For example, development standards may require or incentivize on-site charging options for residences with garages and/or electric vehicle (EV) charging in multifamily parking facilities and publicly available parking lots. These requirements could result in traffic to and from the development producing fewer per mile emissions than external traffic that might cut through the neighborhood. In that case, impacts would follow similar patterns to Metric 1A1 – VMT on the primary and secondary street network with Scenario 1 having the lowest potential for emissions internal to the RT 2.0 West because it includes primarily trips related to the RT 2.0 West development and has the fewest regional trips passing through the neighborhood. VMT was calculated for the component of regional traffic expected to cut-through the neighborhood as part of Metric 1A1 and is included in Table 18. Results & Evaluation Scenarios 2, 3, and 4 will attract higher volumes of regional “cut-through” trips compared to Scenario 1 and will result in higher VMT (see Table 18). This could result in higher emissions internal to the RT 2.0 West development and increased exposure for local residents, school aged children walking to school, at parks and community gathering spaces, and near environmentally sensitive locations such as streams and wetlands. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 36 TABLE 18 : EVALUATION OF GHG AND EMISSIONS SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 Cut-through VMT (2040) 300 VMT per day 4,490 VMT per day 1,600 VMT per day 4,650 VMT per day Ideal definition – cut-through VMT is minimized (zero) Lowest potential for emissions in RT 2.0 Emissions potential is considerably higher than Scenario 1 (+1,396%) Emissions potential is somewhat higher than Scenario 1 (+433%) Emissions potential is considerably higher than Scenario 1 (+1,450%) * A cut-through trip is defined as one that starts and ends outside of the River Terrace 2.0 area, but travels along Tile Flat Road, Mountainside Way, or Sabrina Avenue and through the River Terrace 2.0 area. The total for all scenarios is based on the segment of Mountainside Way, south of the Tile Flat Road intersection. B. Natural Resource Impacts This metric compares the number of stream crossings and impacts to specimen trees and groves, wetlands, and impervious surface under each of the primary street network scenarios. Methodology The analysis compares scenarios for the following performance measures: • Stream crossings: o A comparison of the number of stream crossings required for each scenario. The primary street network for RT 2.0 West shown on Figure 5 was designed to minimize the number and extent of stream crossings. Crossing alignment and location could shift to further minimize impacts and costs but the assumptions in Figure 5 are sufficient for an order of magnitude comparison of potential impacts. o Scenarios were rated based on the number of crossings required. Given the significance of stream crossings, scenarios needing additional crossings were rated as having higher impacts to natural resources. • Specimen trees and groves: o A comparison of the potential impact of the primary street network scenarios on specimen trees and groves. The primary street network for RT 2.0 West shown on Figure 5 was designed to as much as possible avoid impacts on specimen trees and groves. o Scenarios were rated based on the number of specimen trees or groves they impacted. • Impervious surface: o Area of impervious surface = Sum (feet of impervious surface per cross-section segment x length of street segment). This is calculated for two different primary street cross-section options in Table D1 in Appendix D. o Scenarios were evaluated as follows: ▪ The scenario with the lowest impervious surface area was rated as the best scenario. ▪ Scenarios within 25% of the best performing scenario were considered to have similar impacts. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 37 ▪ Scenarios were considered to have a medium impact if their impervious surface area was 25% to 75% higher than the best performing scenario. ▪ Scenarios were considered to have a high impact if their impervious surface area was more than 75% higher than the best performing scenario. • Impacts to wetlands and areas with environmental designations: o The primary street network for RT 2.0 WEST shown on Figure 5 was designed to minimize impacts to wetlands identified as significant by the project team. Scenarios were evaluated based on a qualitative assessment of their potential impact. Results Table 19 shows that the least impact on natural resources would come from Scenario 1. The shorter length of this scenario results in less impervious surface and fewer (two) stream crossings. All scenarios are likely to have some impact to the tree grove located in the southeast corner of the Scholls Ferry Road & Mountainside Way intersection. Scenarios 2 and 3 have increased natural resource impacts related to an additional stream crossing and increased impervious surface (approximately 60% more impervious surface than Scenario 1). Scenario 4 has an even more significant impact with a fourth stream crossing and the most impervious surface (approximately 120% more impervious surface than Scenario 1). Infrastructure costs will be significantly more under these scenarios to construct additional stream crossings and treat runoff from increased impervious surface. All scenarios are likely to have some impact to the tree grove located in the southeast corner of the Scholls Ferry Road & Mountainside Way intersection. Scenarios 1 and 3 could have some additional impacts on this tree grove depending on the size of the required design to accommodate higher turning movements at this intersection. The crossing of the north-south creek parallel to Vandermost Road is near an existing known beaver dam (see Figure 10). While the habitat quality and value of this area is unknown, it is possible that a Tile Flat Road crossing at this location could impact riparian habitat, wetlands, and hydrology modified by the beaver dam. Visits to the site showed significant pond-like features around the creek bed, further south than the wetlands previously mapped in the concept plan. Depending on detailed wetland delineation during design, a street crossing at this location (included as part of Scenarios 2 and 4) could trigger time and cost-intensive state and federal permitting impacts. Additionally, the steep slopes in this area and the potential need to set back footings from the wetland could increase structural cost of a bridge at this location. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 38 FIGURE 10 : LOCATION AND PHOTOGRAPH OF EXISTING KNOWN BEAVER DAM. Evaluation Natural resource impacts were evaluated based on the results above and summarized in Table 19. Scenario 1 has the least impact on natural resources. Scenarios 2 and 4 have some impacts given the need for additional stream crossings, increased impervious surface, and potential wetlands impacts from the Tile Flat Road extension under Scenario 2. Scenario 4 was considered to have a significant impact to natural resources given the need for two additional stream crossings, a more than doubling of impervious surface, and potential wetlands impacts from the Tile Flat Road extension. TABLE 19 : EVALUATION OF NATURAL RESOURCE IMPACTS SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 Stream Crossings 2 3 3 4 Ideal condition – no stream crossings Fewest stream crossings One additional stream crossing compared to Scenario 1 One additional stream crossing compared to Scenario 1 Two additional stream crossings compared to Scenario 1 Specimen Trees and Groves 1* 1 1* 1 Ideal condition – no impact to specimen trees and groves Potentially greater impact to tree grove at Scholls Ferry & Mountainside Way depending on intxn design Potential impact to tree grove at Scholls Ferry & Mountainside Way Potentially greater impact to tree grove at Scholls Ferry & Mountainside Way depending on intxn design Potential impact to tree grove at Scholls Ferry & Mountainside Way Impervious Surface 332,600 sq.ft. 535,400 sq.ft. (+61%) 532,200 sq.ft. (+60%) 735,000 sq.ft. (+121%) Evaluation of Tile Flat Extension Scenarios June 2025 Page | 39 SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 Ideal condition – impervious surface limited to primary development needs Lowest impervious surface to meet development needs Increase in impervious surface to extend Tile Flat Road Increase in impervious surface to extend Mountainside Way Significant increase in impervious surface to extend Tile Flat Road Wetland Impacts No expected impact Potential impact depending on wetland designation near Vandermost No expected impact Potential impact depending on wetland designation near Vandermost Ideal condition – no impacts to wetlands Overall Performance for Natural Resource Impacts Fewest stream crossings, some impact to trees, lowest impervious surface Additional stream crossing, some impact to trees, potential wetlands impact, increased impervious surface Additional stream crossing, some impact to trees, increased impervious surface Two additional stream crossings, some impact to trees, potential wetlands impact, highest impervious surface Ideal condition – minimal impact to streams, trees, wetlands, and impervious surface ^ Based on pavement surface from unidirectional bike lanes option in Table D1 in Appendix D. * Potential for additional impact if an increased intersection footprint is required at Scholls Ferry Road & Mountainside Way. C. Livability Impacts of Regional Vehicle Trips This metric considers the type of trips (e.g., local versus regional) along the primary collector streets and compares the number of trips going through the River Terrace 2.0 development that are attributable to regional (cut-through) trips. Methodology The forecasted local and regional motor vehicle traffic volumes were estimated along roadway segments for 2040 using Washington County's version of the Metro Regional Transportation Demand Model. The volumes were based on the PM peak hour and factored up by 10 to represent 2040 ADT. The volumes include the vehicle trips that start and end outside of the River Terrace 2.0 area but travel along the primary collector street network in the River Terrace 2.0 West subarea (i.e., Tile Flat Road, Mountainside Road, or Sabrina Avenue). Results & Evaluation Table 20 shows the volume of expected cut-through traffic on Mountainside Way and the relative increase compared to the best performing scenario. Scenarios were evaluated as follows: • Scenario 1 has some cut-through traffic, but a relatively minor amount compared to typical collector volume ranges and was scored as having a small impact. • Given cut-through volumes for the best performing scenario (Scenario 1) are low, scenarios were considered to have a medium impact if their cut-through traffic was 2- to 5-times that of the best performing scenario. Scenario 3 will see an increase in cut-through traffic from the extension of Mountainside Way to Perth Road. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 40 • Scenarios were considered to have a significant impact if their cut-through traffic was 5- to 10-times that of the best performing scenario. Scenarios were considered to have a very significant impact if their cut- through traffic was more than 10-times that of the best performing scenario. Scenario 2 will see a considerable increase in cut-through traffic from extending Tile Flat Road. Scenario 4 will see an even higher increase from extending both Tile Flat Road and Mountainside Way. TABLE 20 : TYPE OF TRAVEL ON THE PRIMARY STREET NETWORK CUT -THROUGH VEHICLE TRIPS (2040 ADT)* SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 Mountainside Way, south of Tile Flat Road Extension 200 vpd 2,300 vpd (+1050%) 800 vpd (+300%) 3,300 vpd (+1550%) Ideal definition – cut- through traffic is minimized (zero vpd) Lowest cut- through traffic and a small proportion of street volume Cut-through traffic is considerably higher than Scenario 1 and high proportion of street volume Some increase in cut-through traffic compared to Scenario 1 and relatively small portion of street volume Cut-through traffic is considerably higher than Scenario 1 and high proportion of street volume * A cut-through trip is defined as one that starts and ends outside of the River Terrace 2.0 area, but travels along Tile Flat Road, Mountainside Way, or Sabrina Avenue and through the River Terrace 2.0 area. The total for all scenarios is based on the segment of Mountainside Way, south of the Tile Flat Road intersection. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 41 4. DEVELOPMENT FEASIBILITY The following section provides performance metrics that compare potential impacts on the development feasibility of River Terrace 2.0 between the primary street network scenarios. A. Support to Commercial Areas This metric compares how well the primary street network scenarios align travel by multiple modes to connect with the planned commercial areas shown on Figure 11. FIGURE 11 : PLANNED COMMERCIAL AREAS IN RIVER TERRACE 2.0 WEST RELATIVE TO KEY STREET SEGMENTS. SW Lasich Ln SW Bull Mtn Rd SW Beef Bend Rd SW R o y R o g e r s R d SW Scholls Ferry Rd SW Jean Louise Rd SW Woodhue St SW R i v e r T e r r a c e B l v d SW M o u n t a i n s i d e W ay SW V a n d e r m o s t Rd SW Tile Flat Rd SW Clementine St A A B B C Scholls Ferry Road & Mountainside Way (SFMW) Roy Rogers Road & Bull Mountain Road (RRBM) Evaluation of Tile Flat Extension Scenarios June 2025 Page | 42 Methodology The analysis considers two performance measures for each of the commercial areas: • The ADT passing the two commercial areas in RT 2.0 West (shown on Figure 6 through Figure 9) both on the arterial street network and the collector street network. • Walkshed analysis: o GIS analysis to calculate the percentage of residential development in RT 2.0 West that is within a ½-mile and 1-mile walk of the two commercial areas (i.e., a 10- and 20-minute walk). Note that the analysis only includes the primary street network. The local street network may increase the percentage of development within each walking catchment. However, it is expected that the relative increase would be the same across scenarios. The results of these analyses are summarized in Table 21. Results & Evaluation An analysis by Johnson Economics found that the Scholls Ferry & Mountainside Way (SFMW) commercial area is more likely to support major commerce, while the Roy Rogers & Bull Mountain (RRBM) commercial area is more appropriate for smaller scale walkable mixed-use development. This means that the SFMW area is more dependent on vehicle access and traffic exposure to succeed. Since the RRBM commercial area is intended as a smaller commercial node primarily serving the adjacent development, walk/bike access may be more important to its success. These priorities have been considered in the evaluation. Table 21 shows that for the SFMW commercial area, Scenario 3 provides the most traffic exposure closely followed by Scenario 1 (2% less than Scenario 3). Scenarios 2 and 4, because of the traffic drawn to the Tile Flat Road extension, see 17% and 20% less pass-by traffic at this commercial area compared to Scenario 3. The results of the walkshed analysis included in Table 11 (see metric 2C) show that with the extension of Tile Flat Road (Scenario 2), Mountainside Way (Scenario 3), or both (Scenario 4), there is an incremental increase in the amount of residential development that can access the SFMW commercial areas within a 1-mile walkshed of the SFMW commercial area – up to a 15% increase. It’s important to note that walkshed modeling is an inexact science at this scale and for transportation networks that do not yet exist, and so it’s likely that any differences between the scenarios are marginal at best. Therefore, while the impacts are somewhat off-setting between the accessibility and visibility by different modes, Scenario 3 best balances multimodal accessibility with focusing vehicle traffic through the planned SFWM commercial area. For the RRBM commercial area, Scenario 2 provides the most traffic exposure because of the additional traffic drawn to the Tile Flat Road extension that is then routed along Bull Mountain Road past this commercial area. Scenario 1 (which does not have the extension of Tile Flat Road) sees approximately 7% less pass-by traffic compared to Scenario 2. Scenarios 3 and 4 that extend Mountainside Way to Perth Road see 14% and 10% less pass-by traffic compared to Scenario 2. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 43 TABLE 21 : EVALUATION OF SUPPORT TO COMMERCIAL AREAS SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 SCHOLLS FERRY ROAD & MOUNTAINSIDE WAY COMMERCIAL AREA Pass-by traffic (ADT) 28,600 vpd (-2%) 24,300 vpd (-17%) 29,300 vpd (highest) 23,400 vpd (-20%) Ideal definition – maximize traffic passing by commercial areas Slightly less but negligible difference in pass-by traffic compared to Scenario 3 Significantly less pass- by traffic compared to Scenario 3 Highest pass-by traffic Significantly less pass-by traffic compared to Scenario 3 Walkshed Analysis 70% 80% 80% 85% Ideal condition – highest coverage percentage 15% less coverage compared to Scenario 4 5% less coverage compared to Scenario 4 5% less coverage compared to Scenario 4 Highest coverage Overall Performance High pass-by traffic but lower walkshed coverage Significantly less pass- by traffic and good walkshed coverage Highest pass-by traffic and good walkshed coverage Significantly less pass-by traffic and additional walkshed coverage Ideal condition – maximize pass-by traffic with good walkability ROY ROGERS ROAD & BULL MOUNTAIN ROAD COMMERCIAL AREA Pass-by traffic (ADT) 38,900 vpd (-7%) 42,000 vpd (highest) 36,300 vpd (-14%) 37,700 vpd (-10%) Ideal definition – maximize traffic passing by commercial areas Somewhat less pass-by traffic compared to Scenario 2 Highest pass-by traffic Significantly less pass-by traffic compared to Scenario 2 Significantly less pass-by traffic compared to Scenario 2 Walkshed Analysis 60% 80% 75% 90% Ideal condition – highest coverage percentage 30% less coverage compared to Scenario 4 10% less coverage compared to Scenario 4 15% less coverage compared to Scenario 4 Highest coverage Overall Performance High pass-by traffic but lower walkshed coverage Highest pass-by traffic and good walkshed coverage Significantly less pass-by traffic and reduced walkshed coverage Somewhat less pass-by traffic but highest walkshed coverage Ideal condition – maximize pass-by traffic with good walkability COMBINED IMPACT TO COMMERCIAL AREAS Ideal definition – maximize traffic passing by and walkshed coverage for commercial areas Provides highest overall pass-by traffic but lower walkshed coverage Provides highest pass- by traffic for RRBM and good walkshed coverage Provides best performance for SFMW but lower pass-by traffic for RRBM Provides best performance for RRBM but lower pass-by traffic for SFMW Evaluation of Tile Flat Extension Scenarios June 2025 Page | 44 The results of the walkshed analysis included in Table 11 (see metric 2C) show that with the extension of Tile Flat Road (Scenario 2), Mountainside Way (Scenario 3), or both (Scenario 4), there is an incremental increase in the amount of residential development that can access the RRBM commercial areas within a 1-mile walkshed of the RRBM commercial area – up to a 30% increase. Therefore, while the impacts are somewhat off-setting between the accessibility and visibility by different modes, Scenario 4 best balances multimodal accessibility increasing the walkshed coverage for the planned RRBM commercial area. It is noted that overall, Scenario 1 has the highest overall pass-by traffic exposure for the two commercial areas combined, but the lowest walkshed coverage. Scenario 4 has the lowest combined pass-by traffic exposure but the highest walkshed coverage. Scenarios 2 and 4 fall somewhere in between on both metrics. Regardless of the scenario, the active transportation network should be planned to access and support the commercial areas. A high level of design is needed to separate pedestrians, bicyclists, and motor vehicles and to create inviting pedestrian spaces and opportunities for outside activities, seating, and sidewalk cafes. Regardless of the scenario, the most likely future transit route through the neighborhood will be along Mountainside Way and Bull Mountain Road. This will maximize transit access to these commercial areas and increase their role as mobility hubs for the neighborhood. B. Land Use and Development Feasibility This metric compares the potential impacts to developable acreage, development intensity, or development form resulting from the different primary street network scenarios. Methodology The analysis includes a quantitative assessment of the potential development impacts between scenarios focusing on development yield, development form, cost, and feasibility. Results Evaluation of Tile Flat Extension Scenarios June 2025 Page | 45 Table 22 summarizes the potential impacts on development from the different primary street network scenarios. The primary street network identified in Scenario 1 is what is required for development to occur. It has the fewest stream crossings and the lowest traffic volumes meaning that the required design of roadways and intersections will minimize cost and development form impacts. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 46 TABLE 22 : POTENTIAL IMPACTS ON LAND USE AND DEVELOPMENT FEASIBILITY SCENARIO DEVELOPMENT POTENTIAL A • This is the basic primary street network needed for development. • The area on Vandermost Road would be disconnected from the rest of the network which may further limit its development potential. • This scenario has the fewest stream crossings and the lowest traffic volumes reducing the size of internal streets and intersections. This scenario minimizes impacts on development cost and form. B • Extending Tile Flat Road is not essential to developing RT 2.0 but would better connect development on Vandermost Road to the rest of RT 2.0 West. • Extending Tile Flat Road will require additional dedication for right-of-way and intersection design and may require dedication for additional property setbacks to account for increases in traffic volume. This could have a minor impact on potential development yield. • Development on Vandermost Road is expected to be low intensity and would not (alone) justify the cost to extend Tile Flat Road and construct an additional stream crossing. • Right-of-way will need to be reserved for the Tile Flat Road extension until it is constructed. Its form will need to be determined for interim phases of development. C • The area on Vandermost Road would be disconnected from the rest of the network which may limit its development potential. • Extending Mountainside Way is not essential to developing RT 2.0 and part of the extension is outside the urban growth boundary and is not currently developable. • Extending Mountainside Way and constructing an additional stream crossing will add significant cost to the development for little or no additional development yield. • Extending Mountainside Way will require additional dedication for right-of-way and intersection design and may require dedication for additional property setbacks to account for increases in traffic volume. This could have a minor impact on cost and potential development yield. • Right-of-way will need to be reserved for the Mountainside Way extension until it is constructed. Its form will need to be determined for interim phases of development. D • Extending Tile Flat Road is not essential to developing RT 2.0 but would better connect development on Vandermost Road to the rest of RT 2.0 West. • Development on Vandermost Road is expected to be low intensity and would not (alone) justify the cost to extend Tile Flat Road and construct an additional stream crossing. • Extending Mountainside Way is not essential to developing RT 2.0 and part of the extension is outside the urban growth boundary and is not currently developable. • Extending Tile Flat Road and Mountainside Way and constructing two additional stream crossings will add significant cost to the development for little or no additional development yield. • Extending Tile Flat Road and Mountainside Way will require additional dedication for right-of-way and intersection design and may require dedication for additional property setbacks to account for increases in traffic volume. This could have a moderate impact on potential development yield. • Right-of-way will need to be reserved for the Tile Flat Road and Mountainside Way extensions until they are constructed. Their form will need to be determined for interim phases of development. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 47 The area of RT 2.0 along Vandermost Road is constrained by existing natural resources and is only expected to support lower intensity residential and smaller development parcels. The land use approach proposed in the Housing Plan designates this land for the lowest density development, but the final zoning map and regulations could lower this density even further in response to the environmental constraints and to address volume concerns at the intersection of Scholls Ferry Road & Vandermost Road. Without an extension of Tile Flat Road, this area would depend on the use of the arterial street network to connect to the rest of RT 2.0 which may further limit its development potential and sense of connection to the rest of RT 2.0. The Tile Flat Road and Mountainside Way extensions are not required to make the RT 2.0 development feasible. The additional creek crossings needed for Scenarios 2, 3, and 4 in the portion within the River Terrace 2.0 area would add significant costs that would need to be factored into the SDC project list, potentially increasing housing costs. The portions of Scenarios 2, 3, and 4 outside the Urban Growth Boundary would not be built by development and would need to be funded through a Capital Improvement Project, likely from MSTIP or other regional sources. This would potentially have implications for the funding strategy and timing relative to development, but the greater impact is likely on the limited regional funds available for construction and maintenance of transportation infrastructure in an increasingly constrained fiscal environment. In Scenarios 2, 3, and 4, some amount of right-of-way would need to be reserved for the Tile Flat Road and Mountainside Way extensions. This will leave undeveloped corridors, and the development design will need to determine the form of these corridors in the interim (e.g., closed to the public, open as trail corridors, interim bike/ped bridges at stream crossing locations, etc.). Despite a potentially long-time horizon to complete the road extensions, having a long-term plan for a future road could inhibit construction of bike/ped connections that could better serve the area in the near-term. Evaluation Scenario 1 allows development to be phased until a critical mass of development triggers the need for internal stream crossings. It has the least amount of dedication required but some small impacts on the development potential on Vandermost Road. Scenarios 2, 3, and 4 bring forward infrastructure costs – particularly the bridge crossings – in order to meet regional traffic needs. These scenarios also require additional dedication and right- of-way to be preserved until these extensions can be constructed in the future. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 48 TABLE 23 : EVALUATION OF LAND USE AND DEVELOPMENT IMPACTS SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 Funding and Timing Lowest cost scenario needed for development Potential implications on funding strategy and timing Potential implications on funding strategy and timing Highest costs with implications on funding strategy and timing Ideal definition – costs contained to those supported by development Right-of-Way Needs Least amount of dedication for ROW and setbacks Additional dedication for ROW and setbacks Additional dedication for ROW and setbacks Additional dedication for ROW and setbacks Ideal definition – ROW and dedications limited to what is needed to support RT 2.0 development Impacts on Development Yield Least dedication may be offset by limited access impacting development scale on Vandermost Additional dedication would have some but not significant impact on yield Additional dedication and limited access could impact development scale on Vandermost Additional dedication would have some but not significant impact on yield Ideal definition – least impact to development yield Overall Performance for Land Use and Development Costs can be supported by development, potential minor impact on development yield on Vandermost Higher costs may have implications on funding strategy. Some additional dedication needs Higher costs may have implications on funding strategy. Some additional dedication needs and potential impacts on development yield on Vandermost Highest costs may have significant implications on funding strategy. Some additional dedication needs Ideal definition – least impact to development with costs contained to those supported by development C. Order-of-Magnitude Infrastructure Costs and Funding Implications This metric compares order-of-magnitude costs for full multimodal network buildout and the implications for project funding. Methodology The analysis applied unit costs to the anticipated cross-sections, stream crossings, and intersections forms to develop a cost estimate for each scenario. A qualitative assessment was also made on the potential funding implications for each scenario based on expected project delivery. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 49 Results Estimated infrastructure costs and cost considerations are included in Table 25. Scenario 1 includes less new roadway and only two stream crossings and is the lowest cost scenario. Scenarios 2, 3, and 4 increase the length of roadway, number of intersections and approaches, and require additional stream crossing(s) to extend Tile Flat Road and/or Mountainside Way respectively. Scenarios 2 and 3 are almost double the cost of Scenario 1. Scenario 4 requires the most new roadway, intersections, intersection approaches, and a total of four stream crossings and is approximately 180% more expensive than Scenario 1. In addition, the ability for private development to construct the roadways with cost-sharing through System Development Charge (SDC) and/or Transportation Development Tax (TDT) credits varies for segments within RT 2.0 compared to those that extend outside the UGB. Segments that cannot be built by private development must be built as a Capital Improvement Plan (CIP) project and funded in full through SDCs, TDT, and/or other public sources, increasing the need for constrained transportation system construction and maintenance funds. In addition, because these segments are serving a regional purpose, it is likely not appropriate to impose their cost on development in RT 2.0, meaning that their construction would require contributions from county- or city-wide sources. The city has limited funds available for the construction and maintenance of facilities already listed in its Transportation System Plan, and the new prioritization framework and constrained project list requirements of the Transportation Planning Rule in the Climate Friendly and Equitable Communities updates means that the city has less dollars available in total for vehicle-centered projects, further impacting the ability to maintain and improve existing facilities. TABLE 24 : STREET NETWORK QUANTITY ASSUMPTIONS CATEGORY ASSUMPTIONS Total Length of new Collector Roadways (includes the total length of Tile Flat Road and/or Mountainside Way under each scenario) Scenario 1: 1.06 miles Scenario 2: 1.69 miles Scenario 3: 1.59 miles Scenario 4: 2.22 miles # of Stream Crossings Scenario 1: 2 Scenario 2 and 3: 3 Scenario 4: 4 # of Roundabouts Scenario 1: 0 Scenario 2 and 3: 1 Scenario 4: 2 # of new Approaches at Signalized Intersection Scenario 1: 2 Scenario 2 and 3: 3 Scenario 4: 4 Evaluation of Tile Flat Extension Scenarios June 2025 Page | 50 TABLE 25 : ESTIMATED INFRASTRUCTURE COSTS Evaluation Table 26 summarizes the evaluation of cost and funding implications. Scenario 1 has the lowest transportation infrastructure cost. Scenarios 2, 3, and 4 have higher or much higher costs and may also require CIP projects and contributions from county- or city-wide funding sources. SCENARIO ROADWAY COSTS COST CONSIDERATIONS A $18,500,000 • All roadway segments are within RT 2.0 and may be able to be built by development (with cost-sharing through SDC and/or TDT credits). B $37,500,000 • Extending Tile Flat Road results in a 103% increase in cost for additional and enhanced right-of-way and design and an additional stream crossing. • Tile Flat Road extension outside the UGB would likely require a CIP project and contributions from county- or city-wide funding sources. C $33,000,000 • Extending Mountainside Way results in a 78% increase in cost for additional and enhanced right-of-way and design and an additional stream crossing. • Mountainside Way extension outside the UGB would likely require a CIP project and contributions from county- or city- wide funding sources. D $52,000,000 • Extending Tile Flat Road and Mountainside Way results in a 181% increase in cost for additional and enhanced right-of- way and design and two additional stream crossings. • Tile Flat Road and Mountainside Way extensions outside the UGB would likely require CIP projects and contributions from county- or city-wide funding sources. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 51 TABLE 26 : EVALUATION OF COST AND FUNDING IMP LICATIONS SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 Order-of-Magnitude Cost $18.5 million (lowest) $37.5 million (+103%) $33 million (+78%) $52 million (+181%) Ideal definition – lowest cost Need for CIP project and/or contributions from county- or city-wide funding sources No Yes Yes Yes Ideal definition – costs contained to those supported by development Overall Performance for Cost and Funding Lowest cost and no need for CIP, County, or City funding sources Approximately double the cost of Scenario 1 and may need CIP, County, or City funding sources Higher cost compared to Scenario 1 and may need CIP, County, or City funding sources Approaching triple the cost of Scenario 1 and may need CIP, County, or City funding sources Ideal definition – lower costs contained to those supported by development D. Timing, Phasing, and Project Cost This metric looks at the potential timing for constructing different street segments and stream crossings and the implications on development phasing and infrastructure project delivery (e.g., public vs. private). It also considers the implications of future proofing the construction of streets to a higher standard in advance of and with the unknown of a Tile Flat Road extension. Methodology The analysis considered: • Elements of the primary street network that may need to be accelerated to support a regional traffic function in advance of their development need. • Additional elements of the primary street network scenarios that are beyond the needs of the RT 2.0 development. Results Scenario 1 allows for development in RT 2.0 West to occur in four independent phases: • The area accessed by extending Bull Mountain Road west of Roy Rogers Road. • The area accessed by extending Jean Louise Drive west of Roy Rogers Road. • The area accessed by extending Mountainside Way south of Scholls Ferry Road. • The area accessed along Vandermost Road. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 52 These areas could develop independently with primary and secondary connections to the arterial street network and over time be connected internally with the construction of the stream crossings north and south of Jean Louise Drive once a critical mass of development triggers the need for internal circulation. Extending Tile Flat Road and/or Mountainside Way (Scenarios 2, 3, and 4) may bring forward the need to construct the primary street network and these two primary stream crossings before development can support them and will require one or two additional stream crossings that are not required for development of RT 2.0 West. This raises the question of who funds the accelerated need for this infrastructure and the additional stream crossing(s) outside of the RT 2.0 West development schedule. TABLE 27 : TIMING, PHASING, AND PROJECT COST IMPACTS SCENARIO IMPACTS A • Elements of the primary street network could be constructed in each sub-area to support development until a critical mass of development triggers the need for the 2 primary stream crossings to complete internal circulation. • Regional traffic need may accelerate construction costs for the primary street network and primary stream crossings. • No additional right-of-way needs to be preserved along the Tile Flat Road and Mountainside Way extensions beyond that needed for local street circulation. B • Regional traffic need may accelerate construction costs for the primary street network and primary stream crossings. • Extending Tile Flat Road may bring forward the need to construct the primary street network and the 2 primary stream crossings before development can support them. This scenario also requires an additional stream crossing that is not needed as part of the base development schedule included in Scenario 1. • Right-of-way will need to be preserved sufficient for a collector street to be built along the Tile Flat Road alignment. This will require an easement or road stub to be maintained until this connection is funded. C • Regional traffic need may accelerate construction costs for the primary street network and primary stream crossings. • Extending Mountainside Way may bring forward the need to construct the primary street network and the 2 primary stream crossings before development can support them. This scenario also requires an additional stream crossing that is not needed as part of the base development schedule included in Scenario 1. • Right-of-way will need to be preserved sufficient for a collector street to be built along the Mountainside Way Extension alignment. This will require an easement or road stub to be maintained until this connection is funded. D • Regional traffic need may accelerate construction costs for the primary street network and primary stream crossings. • Extending Tile Flat Road and Mountainside Way may bring forward the need to construct the primary street network and the 2 primary stream crossings before development can support them. This scenario also requires 2 additional stream crossings that are not needed as part of the based development schedule included in Scenario 1. • Right-of-way will need to be preserved sufficient for collector streets to be built along the Tile Flat Road and Mountainside Way Extension alignments. This will require easements or road stubs to be maintained until this connection is funded. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 53 Evaluation Scenario 1 allows development to be phased until a critical mass of development triggers the need for internal stream crossings. Scenarios 2, 3, and 4 bring forward the need for these costs to meet regional traffic needs. They will also require right-of-way to be preserved until these extensions can be constructed in the future. TABLE 28 : EVALUATION OF TIMING, PHASING, AND PROJECT COST IMPACTS SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 Timing, Phasing, and Project Cost Impacts Phasing can be structured to delay costs Additional stream crossing may bring forward costs Additional stream crossing may bring forward costs Two additional stream crossings may bring forward costs Ideal definition – development can be phased to delay infrastructure costs E. Fire, Life, and Safety This metric compares the fire, life, and safety needs for each scenario including access, connectivity, response time, and development impacts (e.g., turnaround and circulation, building needs, etc.). Methodology The analysis includes a qualitative assessment of: • Connectivity of the street network and if development areas have more than one access and can be served by emergency routes from multiple directions. • Design and development considerations, e.g., cross-section and turnaround needs for emergency vehicles, building needs, etc. • Potential impact to emergency response times due to increased internal traffic volumes. These considerations are summarized in Table 29. Results Table 29 shows that Scenario 1 provides multiple accesses to most of the RT 2.0 West development and emergency response from multiple directions. Without the extension of Tile Flat Road, development on Vandermost Road would have a single access. Street design in that area will need to consider circulation and/or turnaround needs for emergency vehicles. Scenario 3 would be similar. Development potential along Vandermost Road is limited and will likely be below the 30 one- and two-family dwelling units where a second access is required by the Oregon Fire Code. These dwellings will need to be equipped throughout with an approved automatic sprinkler system. Given the low development potential, this impact is not considered significant. However, it does provide an additional emergency access route to the rest of RT 2.0 West via the extension of Mountainside Way to Perth Road. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 54 TABLE 29 : FIRE, LIFE, SAFETY CONSIDERATIONS SCENAR IO ACCESS AND CONNECTIVITY DESIGN AND DEVELOPMENT A • Multiple accesses and emergency response is possible from multiple directions for the majority of RT 2.0 West. • Interim right-in/right-out access may be needed as secondary access to the arterial network to support phased development before internal connections / stream crossings are built. • Development on Vandermost Road will be served by a single access and limited to 30 one- or two-family dwellings fitted with an approved automatic sprinkler system. • This scenario has the lowest internal traffic volumes that may help reduce response time. • Street design will need to consider circulation or turnaround for emergency vehicles on Vandermost Road. • Street design features (e.g., medians, protected bikeways, etc.) to be coordinated with Tualatin Fire & Rescue. B • Multiple accesses and emergency response is possible from multiple directions for all of RT 2.0 West – including an additional emergency response route to the northwest with the extension of Tile Flat Road. • Interim right-in/right-out access may be needed as secondary access to the arterial network to support phased development before internal connections / stream crossings are built. • Development on Vandermost Road will be connected to the rest of RT 2.0 providing secondary access for emergency response. • Increased internal traffic volumes may increase response time. • Street design features (e.g., medians, protected bikeways, etc.) to be coordinated with Tualatin Fire & Rescue. C • Multiple accesses and emergency response is possible from multiple directions for the majority of RT 2.0 West – including an additional emergency response route to the south with the extension of Mountainside Way. • Interim right-in/right-out access may be needed as secondary access to the arterial network to support phased development before internal connections / stream crossings are built. • Development on Vandermost Road will be served by a single access and limited to 30 one- or two-family dwellings fitted with an approved automatic sprinkler system. • Some increase in internal traffic volumes may increase response time. • Street design will need to consider circulation or turnaround for emergency vehicles on Vandermost Road. • Street design features (e.g., medians, protected bikeways, etc.) to be coordinated with Tualatin Fire & Rescue. D • Multiple accesses and emergency response is possible from multiple directions for all of RT 2.0 West – including additional emergency response route to the northwest and south with the extensions of Tile Flat Road and Mountainside Way. • Interim right-in/right-out access may be needed as secondary access to the arterial network to support phased development before internal connections / stream crossings are built. • Development on Vandermost Road will be connected to the rest of RT 2.0 providing secondary access for emergency response. • Increased internal traffic volumes may increase response time. • Street design features (e.g., medians, protected bikeways, etc.) to be coordinated with Tualatin Fire & Rescue. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 55 Scenarios 2 and 4 would provide additional access via the Tile Flat Road extension and allow emergency response from the northwest. These scenarios also provide a second emergency access to any development on Vandermost Road. Scenarios 3 and 4 would provide an additional emergency response route from the south with the extension of Mountainside Way to the Roy Rogers Road & Perth Road intersection. All scenarios will need to consider fire and emergency access during the phased buildout of the development. If development occurs before the stream crossings are constructed, secondary access points will be needed with interim right-in/right-out access to the arterial network. As the number of access points increases so does traffic volume internal to the development, which could offset some response time savings. Street design features such as medians, protected bike lanes, and other features that reduce street widths will need to be considered in relation to the Fire Code and in consultation with Tualatin Valley Fire & Rescue. Evaluation Table 30 shows that all scenarios address fire, life, and safety needs. Although Scenarios 1 and 3 do not include the Tile Flat Road extension, the resulting single access to development on Vandermost Road is not considered significant given that development potential in that area is likely less than the threshold needed for a secondary access and can be addressed with emergency vehicle circulation or turnaround and automatic sprinkler systems. While having additional emergency access is always helpful, Scenarios 1 and 3 provide emergency response routes from multiple directions and via multiple access points and as such meet fire, life, and safety needs. There is some potential for increased response under Scenarios 2 and 4, however, these increases are not expected to be significant. TABLE 30 : EVALUATION OF FIRE, LIFE, AND SAFETY IMPACTS SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 Multiple Access Points Available Multiple access points for majority of RT 2.0 West but single access may limit development on Vandermost^ Multiple access points for all of RT 2.0 West Multiple access points for majority of RT 2.0 West but single access may limit development on Vandermost^ Multiple access points for all of RT 2.0 West Ideal definition – all areas of development have multiple access points Primary Directions for Emergency Response 3 4 3 4 Ideal definition – more directions may reduce response times Potential for Response Time Delay due to Traffic Lowest traffic volumes will result in lowest transit delays Higher traffic volumes on Mountainside Way will increase transit delay Slightly higher traffic volumes on Mountainside Way but similar to Scenario 1 Highest traffic volumes on Mountainside Way will increase transit delay Ideal definition – no delay to emergency response times Evaluation of Tile Flat Extension Scenarios June 2025 Page | 56 SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 compared to Scenario 1 compared to Scenario 1 Overall Performance Meets Fire, Life, and Safety Needs Meets fire, life, safety needs with some impacts on development on Vandermost Meets fire, life, safety needs with multiple accesses and response directions. Higher traffic volumes may impact emergency response time Meets fire, life, safety needs with some impacts on development on Vandermost Meets fire, life, safety needs with multiple accesses and response directions. Higher traffic volumes may impact emergency response time Ideal definition – meets fire, life, safety with minimal impact on development yield and response times * Does not consider potential development on Vandermost Road, which is considered separately. ^ This will limit development to under 30 one- and two-family dwellings that will need to be fitted with an approved automatic sprinkler system. It will also require circulation or turnaround area for emergency vehicles. These requirements meet the Fire Code and are not considered significant. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 57 5. EQUITY The following provides an analysis of potential equity impacts across the primary street network scenarios. A. Equitable Benefits This metric compares who benefits and who is impacted under each of the network scenarios. The analysis compares impacts to potential residents of RT 2.0. Methodology Qualitative analysis of potential impacts to equity communities as mapped on the Oregon Social Equity Web App. It is difficult to measure the equitable distribution of impacts given the demographics of people that might move to RT 2.0 are unknown. However, the development is intended to include a mix of housing types available to a variety of income levels that could attract populations that face disparity in their access to health, transportation, education, housing, and wealth. As a comparison, although not fully built out, RT 1.0 between Scholls Ferry Road and Bull Mountain Road is designated as “low-medium disparity” when compared to state averages with respect to age, ability, income, language, and race/ethnicity (which are identified as predictors of disparity). If similar demographics are attracted to RT 2.0, then it will be important to minimize negative impacts from emissions and noise exposure, increased crash risk, reduced access to convenient and low-cost transportation, reduced access to parks, open space, and local destinations, housing affordability, and climate resilience in order to reduce the potential for these factors to increase disparities in access to health, transportation, education, housing, and wealth. Results & Evaluation Overall, Scenario 1 would minimize potential impacts to more vulnerable future residents by minimizing the amount of traffic on the internal street network (reducing exposure to emissions, noise, and crash risk) and providing comfortable and low-cost transportation options that can access local parks, commercial areas, schools, etc. Scenario 1 also has the lowest infrastructure cost which would bring down overall development costs and may reduce the cost of housing for future residents. With the fewest stream crossings and roadway footprint of the scenarios, Scenario 1 would preserve the greatest amount of natural resources in the project area. This contributes to improved climate resilience outcomes for future residents of RT 2.0 West such as increased carbon sequestration and better adaptation to climate change impacts like drier summers, hotter temperatures, and more intense rainfall events. Scenario 3 that extends Mountainside Way to Perth Road would provide a benefit to residents in terms of increasing access to destinations in parts of RT 1.0, RT 2.0, and Kingston Terrace. However, it would result in higher traffic volumes on the internal street network, increasing exposure to crash risk, noise, and emissions for future residents of RT 2.0 West. This could also increase travel time for future transit service, a critical service for lower-income individuals, youth, and people with mobility limitations to reach key destinations within RT 2.0 and the surrounding region. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 58 TABLE 31 : EVALUATION OF POTENTIAL IMPACTS ON DISPARITY PM PEAK HOUR VMT SCENARIO 1 SCENARIO 2 SCENARIO 3 SCENARIO 4 Emissions and Noise Exposure Lowest internal traffic volumes Higher traffic volumes than Scenario 1 Slight increase in traffic volumes compared to Scenario 1 Highest traffic volumes compared to Scenario 1 Ideal definition – lowest exposure Crash Risk Lowest VRU crash exposure VRU crash exposure somewhat higher than Scenario 1 VRU crash exposure somewhat higher than Scenario 1 VRU crash exposure considerably higher than Scenario 1 Ideal definition – lowest crash exposure Access to Convenient and Low- Cost Transportation Good access to transit and a well-connected active transportation network. Lowest transit delays Good access to transit and a well-connected active transportation network. Increased transit delay Potential for increased transit routes and additional active transportation connections. Low transit delays Potential for increased transit routes and additional active transportation connections. Highest transit delays Ideal definition – access to transit and well-connected active transportation Access to Parks, Open Space, and Local Destinations Good access to parks, open space, and local destinations Good access to parks, open space, and local destinations Potential for increased access to these destinations via Perth Potential for increased access to these destinations via Perth Ideal definition – well- connected access to these destinations Housing Affordability Lowest infrastructure costs may increase housing affordability Higher infrastructure costs compared to Scenario 1 may decrease housing affordability Higher infrastructure costs compared to Scenario 1 may decrease housing affordability Highest infrastructure costs compared to Scenario 1 may decrease housing affordability Ideal definition – lowest infrastructure costs resulting in lower housing prices Natural Resource Impacts and Climate Resilience Fewest stream crossings, some impact to trees, lowest impervious surface Additional stream crossing, some impact to trees, potential wetlands impact, increased impervious surface Additional stream crossing, some impact to trees, increased impervious surface Two additional stream crossings, some impact to trees, potential wetlands impact, highest impervious surface Ideal definition – minimal impact to streams, trees, wetlands, and impervious surface Overall Impacts on Populations Facing Disparity Lowest exposure to emissions, noise, and crash risk but some impacts from climate resilience Higher exposure to emissions, noise, and crash risk, impacts to housing affordability and climate resilience Higher exposure to emissions, noise, and crash risk, impacts to housing affordability and climate resilience. Increased connectivity Highest exposure to emissions, noise, and crash risk; impacts to housing affordability and climate resilience. Increased connectivity Ideal definition – no impacts to vulnerable populations Evaluation of Tile Flat Extension Scenarios June 2025 Page | 59 Scenarios 2 and 4 that extend Tile Flat Road would increase vehicular access to the arterial street network, particularly to regional destinations northwest of RT 2.0. However, it would result in higher traffic volumes on the internal street network increasing exposure to crash risk, noise, and emissions for future residents of RT 2.0 West. This could also increase travel time for future transit service. Increased development costs associated with these two scenarios may have a negative impact on housing affordability in RT 2.0, and the significant added impact to natural resources is expected to lessen climate resilience outcomes for future residents. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 60 APPENDICES Appendix A – Bicycle Level of Traffic Stress (BLTS) Design Requirements TABLE A1. SEGMENT BLTS 1 DESIGN CRITERIA Based on the ODOT BLTS methodology outlined in the Analysis Procedures Manual Chapter 14 – Section 14.4 and incorporating best practice principles from the 2024 AASHTO Guide for the Development of Bicycle Facilities FACILITY DESIGN CRITERIA Shared Use Path Assuming minimum standards per 2024 AASHTO Guide for the Development of Bicycle Facilities (Table 6-3). Assuming a peak hour volume on the shared use path between 300 to 500 bph: • Practical minimum width: 11’ (constrained scenarios only). • Recommended lower limit: 12’. • Recommended upper limit: 15’. • Recommended practical maximum is 16’. Separated Bike Lanes Assuming minimum standards per 2024 AASHTO Guide for the Development of Bicycle Facilities. Facility type: One-Way Separated Bike Lanes Between Sloped Curb, at Sidewalk Level, or Adjacent to Curb with Gutter widths (bike lane only, excluding curb widths): • 5.5’-7.5’ width (< 150 peak hour directional bicyclist volume). • 7.5’-9’ width (150-750 peak hour directional bicyclist volume). • ≥ 9’ width (> 750 peak hour directional bicyclist volume). Bike Lane with Adjacent Parking Lane For segments of the primary street network with on-street parking: • ≥ 15’ bike lane + parking lane width. • Bike lane should include buffers to both the traffic and parking lanes. Bike Lane with No Adjacent Parking Lane* For segments of the primary street network without on-street parking: • ≥ 7’ buffered bike lane. • Note: while the ODOT methodology to achieve segment BLTS 1 (Exhibit 14-5) permits a 7’ minimum on-street buffered bike lane (inclusive of buffer) for a 2-lane, 25 mph roadway, per the 2024 AASHTO Guide for the Development of Bicycle Facilities, this facility would not achieve the highest level of comfort and be considered below the standard of separated bike lanes and shared use path alternatives. Neighborhood Greenways No centerline, 750 - ≤1,500 ADT, local streets Distance Between Crossing Opportunities ≤ 0.10 mi (~500 ft) Evaluation of Tile Flat Extension Scenarios June 2025 Page | 61 TABLE A2. INTERSECTION BLTS 1 DESIGN CRITERIA Based on the ODOT BLTS methodology outlined in the Analysis Procedures Manual Chapter 14 – Section 14.4 and incorporating best practice principles from the 2024 AASHTO Guide for the Development of Bicycle Facilities INTERSECTION FEATURE DESIGN CRITERIA Right Turn Lanes Bike lanes may not jog across or to the left of a dedicated right turn lane to be considered BLTS 1. There are two scenarios to achieve BLTS 1 at intersections with on-street bike lanes to the right of dedicated right turn lanes: • A bike signal to separate bike and vehicular right turn movements. • A protected intersection design where bikes shift right, away from the curbline, and cross the intersection adjacent to the pedestrian crossing, with a bike signal or with the pedestrian signal. Left Turn Lanes Two-stage left turn maneuver - either with a protected intersection or with bike box/left turn queue box markings. Unsignalized Crossings without a Median For segments with ≤ 3 total through and turning lanes, these crossings are appropriate when: • ≤ 1,200 ADT on local streets. • ≤3,000 ADT on collector streets. Unsignalized Crossing with a Median These crossings should be used for streets with higher volumes than above and should consist of: • 1 crossing lane per direction. • Median refuge ≥ 10’ width. Roundabout Crossings Bicyclists should be provided a shared (with pedestrians) or separate pathway around the roundabout outside the roadway. The following criteria should be met: • Single lane entry or exit with splitter island refuge ≥ 10’ width. • 1 circulating lane. • Non-tangential entry (to create vehicle deflection). • Separate bike and pedestrian facilities or shared use path width ≥ 10’ (2024 AASHTO Guide for the Development of Bicycle Facilities, 11.10.3). • Per the 2021 AASHTO Guide for the Development of Pedestrian Facilities (Figure 3-39) and ODOT BLTS (pg. 21), 20’-30’ setback required from edge of circulating roadway to crossing to allow for reaction time for exiting vehicles while minimizing out-of-direction travel. • To transition from on-street bike lanes to/from the sidewalk level pathway around the roundabout, separate bike ramps or shared bike/pedestrian ramp with > 10’ width are required. Signalized Crossings (at Arterials) To maintain BLTS 1, signalized intersections require: • Bike detection or activation or pre-timed signals. • No permissive left or right turns. • Bike signals and/or bike turn boxes to treat right- and left-turn conflicts. • Protected intersection treatments. Other Criteria No frequent bike lane blockages due to transit, loading, etc. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 62 Appendix B – Pedestrian Level of Traffic Stress (PLTS) Design Requirements TABLE B1. SEGMENT PLTS 1 DESIGN CRITERIA Based on the ODOT PLTS methodology outlined in the Analysis Procedures Manual Chapter 14 – Section 14.5. FACILITY DESIGN CRITERIA Sidewalk Condition Good (new construction) Sidewalk Width ≥ 6 typical, ≥ 8’ in higher foot-traffic and commercial areas Physical Buffer Type Landscaped (with or without street trees) or solid surface. Solid surface could include a sidewalk-level bike lane, hardscape with a surface material change such as pavers or stamped concrete, hardscape with planters, street furniture, etc. Total Buffering Width ≥ 10’ that includes the width of the landscaped or solid surface buffer plus the width of any parking, shoulder, or bike lane. Distance Between Crossing Opportunities ≤ 0.10 mi (~500 ft) Evaluation of Tile Flat Extension Scenarios June 2025 Page | 63 TABLE B2 . INTERSECTION PLTS 1 DESIGN CRITERIA Based on the ODOT PLTS methodology outlined in the Analysis Procedures Manual Chapter 14 – Section 14.5. INTERSECTION FEATURE DESIGN CRITERIA Unsignalized Crossings at Collectors or Local Streets All ramps to be designed as standard ramps. Crossing types: • 2 crossing lanes with no median refuge is acceptable for ≤ 30 mph and ≤ 5,000 vpd. • 1 crossing lane in each direction with median refuge is acceptable for ≤ 30 mph and ≥ 5,000 vpd. Requires ≥ 10’ median refuge width. The following items may improve the PLTS: • Enhanced markings and signage. • Illumination. • Pedestrian activated beacons (e.g., RRFB). • In-street signs. • Curb extensions. • Raised crosswalks. • Standard 12” flashing beacons. Roundabout Crossings Single lane entry or exit crossings with splitter island refuge ≥ 10’ width. Signalized Crossings (at Arterials) Signalized crossings will generally be PLTS 1. However, no permissive left or right turns are allowed. Pedestrian signal countdown features are required. Lighting Adequate illumination of the intersection. Other Criteria PLTS 1 is not achieved if any of the following conditions exist: • Crossing distance ≥ 72’ or more than 6 lanes (or equivalents such as a parking lane). • Non-standard geometry (such as more than 4 legs or highly skewed approaches). • Closed or limited crosswalk legs. • Free-flow or yield-controlled channelized right turns. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 64 Appendix C – Walkshed Analysis Maps FIGURE C1: HALF -MILE WALKSHED FOR SCENARIO 1 . Evaluation of Tile Flat Extension Scenarios June 2025 Page | 65 FIGURE C2: HALF -MILE WALKSHED FOR SCENARIO 2. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 66 FIGURE C3: HALF -MILE WALKSHED FOR SCENARIO 3. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 67 FIGURE C4: HALF -MILE WALKSHED FOR SCENARIO 4. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 68 FIGURE C5: ONE -MILE WALKSHED FOR SCENARIO 1. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 69 FIGURE C6: ONE -MILE WALKSHED FOR SCENARIO 2. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 70 FIGURE C7: ONE -MILE WALKSHED FOR SCENARIO 3. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 71 FIGURE C8: ONE -MILE WALKSHED FOR SCENARIO 4. Evaluation of Tile Flat Extension Scenarios June 2025 Page | 72 Appendix D – Primary Street Impervious Surface Area Calculations TABLE D 1. PRIMARY STREET IMPERVIOUS SURFACE CALCULATIONS SCENARIO CROSS -SECTION HARDSCAPE WIDTH ASSUMPTIONS LENGTH OF SEGMENT IMPERVIOUS SURFACE AREA A SUP one side (16’), sidewalk opposite side (8’), total asphalt paved roadway (24’), curb and gutter (2’ + 2’) = 52’ Assumes 12’ lanes for roadway, not inclusive of gutter. Does not account for any intersection widening for turn lanes. Does not account for curb ramp/corner hardscape. Assumes landscaped buffer between curb and SUP/ sidewalk. Does not account for hardscape, concrete pads on sidewalk for bus stop locations, potential parking/loading zones, or choice of hardscape buffer for a tactile warning strip or street furniture. 1.05 mi or 5,544 ft ~288,300 SQFT Unidirectional bike lanes both sides (sidewalk-level or intermediate level) both sides (8’ + 8’), sidewalks both sides (8’ + 8’), total asphalt paved roadway (24’), curb and gutter (2’ + 2’) = 60’ Assumes 12’ lanes for roadway, not inclusive of gutter. Does not account for any intersection widening for turn lanes. Does not account for curb ramp/corner hardscape. Assumes landscaped buffer between curb and sidewalk-level bike lanes and between sidewalk- level bike lanes and sidewalk. Does not account for hardscape, concrete pads on sidewalk for bus stop locations, potential parking/loading zones, or choice of hardscape buffer for a tactile warning strip or street furniture. Does not assume an intermediate-level bikeway. 1.05 mi or 5,544 ft ~332,600 SQFT B SUP one side (16’), sidewalk opposite side (8’), total asphalt paved roadway (24’), curb and gutter (2’ + 2’) = 52’ See previous. 1.69 mi or 8,923 ft ~464,000 SQFT Unidirectional bike lanes both sides (sidewalk-level or intermediate level) both sides (8’ + 8’), sidewalks both sides (8’ + 8’), total asphalt paved roadway (24’), curb and gutter (2’ + 2’) = 60’ See previous. 1.69 mi or 8,923 ft ~535,400 SQFT Evaluation of Tile Flat Extension Scenarios June 2025 Page | 73 SCENARIO CROSS -SECTION HARDSCAPE WIDTH ASSUMPTIONS LENGTH OF SEGMENT IMPERVIOUS SURFACE AREA C SUP one side (16’), sidewalk opposite side (8’), total asphalt paved roadway (24’), curb and gutter (2’ + 2’) = 52’ See previous. 1.68 mi or 8,870 ft ~461,200 SQFT Unidirectional bike lanes both sides (sidewalk-level or intermediate level) both sides (8’ + 8’), sidewalks both sides (8’ + 8’), total asphalt paved roadway (24’), curb and gutter (2’ + 2’) = 60’ See previous. 1.68 mi or 8,870 ft ~532,200 SQFT D SUP one side (16’), sidewalk opposite side (8’), total asphalt paved roadway (24’), curb and gutter (2’ + 2’) = 52’ See previous. 2.32 mi or 12,250 ft ~637,000 SQFT Unidirectional bike lanes both sides (sidewalk-level or intermediate level) both sides (8’ + 8’), sidewalks both sides (8’ + 8’), total asphalt paved roadway (24’), curb and gutter (2’ + 2’) = 60’ See previous. 2.32 mi or 12,250 ft ~735,000 SQFT