CITY OF TIGARD BUILDING PERMIT
` 11: . COMMUNITY DEVELOPMENT Permit#: BUP2020-00006
13125 SW Hall Blvd.,Ti and OR 97223 503.718.2439 Date Issued: 01/23/2020
T[to 1 R.,L7 9
5 Parcel: 2S101BA00400
Jurisdiction: Tigard
Site address: 12215 SW 72ND AVE
Project: Basecamp Subdivision: None Lot: None
Project Description: Demolition of a 1,860 sq.ft.house on septic. Septic tank to be pumped and filled. UPON FINAL INSPECTION,
DEMO CREDITS FOR PARKS AND TRANSPORATION FEES WILL APPLY.
Contractor: LEASE CRUTCHER LEWIS Owner: BASE CAMP I LLC
550 SW 12TH AVENUE PO BOX 10638
PORTLAND, OR 97205 EUGENE, OR 97440
PHONE: 503-223-0500 PHONE:
FAX: 503-223-2874
Specifics: FEES
Description Date Amount
Type of Use: SF
Class of Work: DEM Type of Const: Permit Fee-Additions,Alterations, 01/22/2020 $286.64
Demolition
Occupancy Grp: Occupancy Load: Info Process/Archiving-Lg$2.00(over 01/22/2020 $14.00
Dwelling Units: 0 11x17)
Stories: 0 Height: 0 ft Erosion Control w/Development 01/22/2020 $80.70
Bedrooms: 0 Bathrooms: 0
Value: $13,970
Floor Areas:
Total Area: 0
Accessory Struct: 0
Basement: 0
Carport: 0
Covered Porch: 0
Deck: 0
Garage: 0
Mezzanine: 0
Total $381.34
Required: Required Items and Reports(Conditions)
Fire Sprinkler: Parapet: 1 Ersn Cntrl 503-639-4175
Fire Alarm: Protected Corridors:
Smoke Detectors: Manual Pull Stations:
Accessible Parking: 0
This permit is issued subject to the regulations contained in the Tigard Municipal Code, State of OR. Specialty Codes and all other applicable law. All work will
be done in accordance with approved plans. This permit will expire if work is not started within 180 days of issuance, or If work is suspended for more the 180
days. ATTENTION: Oregon law requires you to follow the rules adopted by the Oregon Utility Notification Center. Those rules are set forth in OAR
952-001-0010 through OAR 952-001-0090. You may obtain a copy of the rules or direct questions to OUNC by calling 503.232.1987 or 1.800.332.2344.
Issued By: / PePmlttee Signature: //�_l cJ�/f �
3.639.4175 by 7:00 a.m.for the next available inspection date. v 4
This permit card shall be kept In a conspicuous place on the job site until completion of the project.
Approved plans are required on the job site at the time of each inspection.
CITY OF TIGARD BUILDING PERMIT
COMMUNITY DEVELOPMENT Permit#: BUP2020-00006
13125 SW Hall Blvd.,Tigard OR 97223 503.718.2439 Date Issued: 01/23/2020
TIGARD Parcel: 2S101 BA00400
Jurisdiction: Tigard
Site address: 12215 SW 72ND AVE
Project: Basecamp Subdivision: None Lot: None
Project Description: Demolition of a 1,860 sq.ft. house.
Contractor: LEASE CRUTCHER LEWIS Owner: BASE CAMP I LLC
550 SW 12TH AVENUE PO BOX 10638
PORTLAND, OR 97205 EUGENE, OR 97440
PHONE: 503-223-0500 PHONE:
FAX: 503-223-2874
Specifics: FEES
Description Date Amount
Type of Use: SF
Class of Work: DEM Type of Const: Permit Fee-Additions,Alterations, 01/22/2020 $286.64
Demolition
Occupancy Grp: Occupancy Load: Info Process/Archiving-Lg$2.00(over 01/22/2020 $14.00
Dwelling Units: 0 11x17)
Stories: 0 Height: 0 ft Erosion Control w/Development 01/22/2020 $80.70
Bedrooms: 0 Bathrooms: 0
Value: $13,970
Floor Areas:
Total Area: 0
Accessory Struct: 0
Basement: 0
Carport: 0
Covered Porch: 0
Deck: 0
Garage: 0
Mezzanine: 0
Total $381.34
Required: Required Items and Reports(Conditions)
1 Ersn Cntrl 503-639-4175
Fire Sprinkler: Parapet:
Fire Alarm: Protected Corridors:
Smoke Detectors: Manual Pull Stations:
Accessible Parking: 0
This permit is issued subject to the regulations contained in the Tigard Municipal Code, State of OR. Specialty Codes and all other applicable law. All work will
be done in accordance with approved plans. This permit will expire if work is not started within 180 days of issuance, or if work is suspended for more the 180
days. ATTENTION: Oregon law requires you to follow the rules adopted by the Oregon Utility Notification Center. Those rules are set forth in OAR
952-001-0010 through OAR 952-001-0090. You may obtain a co of the rules or direct questions to OUNC by calling 503.232.1987 or 1.800.332.2344.
Issued By: Permittee Signature:
c.. 503.639.4175 by 7:00 a.m.for the next available inspe n date.
This permit card shall be kept in a conspicuous place on the job site until completion of t a project.
Approved plans are required on the job site at the time of each inspection.
•
Building Permit Application
( Commercial �'� FOR OFFICE USE ONLY
City of Tigard �„>! NED Received '
1 Permit
,
Date/B _age No.: Ji.1 -
II ■ 13125 SW Hall Blvd.,Tigard,OR 97223 �y r� Plan Review r
s Phone: 503-718-2439 Fax: 503-598-19651AN 9 ZO2.0 Date/B : .4� 2 Related Permit:
it C;A K U Inspection Line: 503-639-4175 p g Date Ready/By: El See Page 2 for
Internet: www.tigard-or.gov 11!TY OF T '(.:i—w- Notified/Method: ,. I i 1 7Supplemental Information
a
TYPE OF WORK REQUIRED DATA:1-AND 2-FAMILY DWELLING
P New construction X Demolition Permit fees*are based on the value of the work performed.
�� Indicate the value(rounded to the nearest dollar)of all
_
P.Addition/alteration/replacement [_ Other: equipment,materials,labor,overhead,and the profit for the
CATEGORY OF CONSTRUCTION work indicated on this application.
L__; 1-and 2-family dwelling ❑Commercial/industrial Valuation: $
❑Accessory building ❑Multi-family Number of bedrooms:
P Master builder X Other: Construction Trailers Number of bathrooms:
JOB SITE INFORMATION AND LOCATION Total number of floors:
Job site address:72nd Avenue ---;x„,-, %r_" C New dwelling area: square feet
City/State/ZIP: Tigard/Oregon/97223 Garage/carport area: square feet
Suite/bldg./apt.#: Project name: Basecamp Construction Trailers Covered porch area: square feet
Cross street/directions to job site: SW Elmhurst Street Deck area: square feet
Other structure area: square feet
REQUIRED DATA:COMMERCIAL-USE CHECKLIST
Subdivision: Lot#:400 Permit fees*are based on the value of the work performed.
Tax map/parcel 4: 2S 1 01 BA/400 Indicate the value(rounded to the nearest dollar)of all
equipment,materials,labor,overhead,and the profit for the
DESCRIPTION OF WORK work indicated on this application.
Removal of existing structures to prepare an area for Valuation: $ 13,970
construction staging, trailers, parking, etc. Existing building area: 1,860square feet
New building area: N/A square feet
X PROPERTY OWNER ❑ TENANT Number of stories:
Name:Base Camp 1, LLC Type of construction:
Address: 4550 Kruse Way, Ste. 125 Occupancy groups:
City/State/ZIP: Lake Oswego/Oregon/97035 Existing:
Phone:( ) Fax:( ) New:
X APPLICANT X CONTACT PERSON BUILDING PERMIT FEES*
(Please refer to fee schedule)
Business name:AKS Engineering & Forestry, LLC Structural plan review fee(or deposit):
Contact name:Chuck Gregory FLS plan review fee(if applicable):
Address:12965 SW Herman Road, Suite 100
Total fees due upon application:
City/State/ZIP:Tualatin/Oregon/97062
Phone:(503) 653-6151
Fax: :(503) 653-6152 Amount received:
PHOTOVOLTAIC SOLAR PANEL SYSTEM FEES*
E-mailchuckg@aks-eng.com
Commercial and residential prescriptive installation of
CONTRACTOR roof-top mounted PhotoVoltaic Solar Panel System.
Business nameLease Crutcher Lewis Submit two(2)sets of roof plan with connection details
and fire department access,along with the 2010 Oregon
Address:550 SW 12th Avenue Solar Installation Specialty Code checklist.
City/State/ZIP:Portland/Oregon/97205 Permit fee(includes plan review $180.00
and administrative fees):
Phone:( ) Fax:( ) State surcharge(12%of permit fee): $21.60
CCB Lic.:9291 Q Total fee due upon application: $201.60
Authorized signature: This permit application expires if a permit is not obtained
Sit _ within 180 days after it has been accepted as complete.
Print name: Matt Ba r Date: 1/6/2020 * Fee methodology set by Tri-County Building Industry
Service Board.
I:\Building\Permits\BUP_COM_PermitApp.doc Rev.04/21/2014 440-46 13T(11/02/COM/WEB)
City of Tigard • COMMUNITY DEVELOPMENT DEPARTMENT
1114 a
p Accessibility: Barrier Removal Improvement Plan
Commercial & Multi-Family - Additions or Alterations
TIGARD 13125 SW Hall Blvd. • Tigard, Oregon 97223 • 503.718.2439 • www.tigard-or.gov
REQUIREMENT: OREGON REVISED STATUTE (ORS) 447.241.
(1) Every project for renovation,alteration or modification to affected buildings and related
facilities shall be made to insure that the path of travel to the altered area and the restroom,
telephones and drinking fountains are readily accessible to individuals with disabilities unless
such alterations are disproportionate to the overall alterations in terms of cost and scope.
(2) Alterations made to the path of travel to an altered area may be deemed disproportionate to
the overall alteration when the cost exceeds twenty-five percent(25%).
VALUATION: Total of all renovation,alteration or modification being done,
excluding painting and wallpapering: [1] $
MULTIPLIER(25%barrier removal requirement): x .25
TOTAL BUDGET FOR BARRIER REMOVAL: [2] $
ELEMENTS: In choosing which accessible elements to provide under this section,priority shall be given
to those elements that will provide the greatest access. Elements shall be provided in the
following order:
(a) Parking $
(b) An accessible entrance: $
(c) An accessible route to the altered area: $
(d) At least one accessible restroom for each sex or a single unisex
restroom: $
(e) Accessible telephones: $
(f) Accessible drinking fountains:and, $
(g) When possible,additional accessible elements such as storage and
alarms: $
TOTAL(shall equal line [2] of Valuation Computation): $
I:\Building\Permits\BUP_COM_PermitApp.doc Rev.03/05/2019
City of Tigard • COMMUNITY DEVELOPMENT DEPARTMENT
. " Plan Submittal Requirements
Commercial & Multi-Family - New, Additions or Alterations
TIGAItD 13125 SW Hall Blvd. • Tigard, Oregon 97223 • 503.718.2439 • www.tigard-or.gov
1. SITE PLAN (3) copies - fully dimensional, drawn to scale and labeled with:
A. ❑ map&tax lot# ❑ project name ❑ site address ❑ suite number
❑ zoning ❑ applicant name ❑ phone number
B. North arrow.
C. Scale (architectural or engineering only).
D. Street names.
E. Setbacks.
F. Parking,including disabled access.
G. Finished floor elevations.
2. EROSION CONTROL PLANS AND DETAILS.
3. BUILDING PLANS: See the "Plan Submittal Requirement Matrix" for the number of
plans required based on submittal type (no redlines or tape-ons accepted).
All details listed below shall be incorporated into the plans:
A. Scale (architectural or engineering only).
B. Foundation plan.
C. Floor plan(s).
D. Cross sections.
E. Reflective ceiling plan.
F. Seismic bracing detail for suspended ceiling.
G. Roof plan.
H. Exterior elevations.
I. Structural calculations,plans, details and specifications.
J. Accessibility barrier removal worksheet.
K. Deposit- based on valuation of project.
I:\Building\Permits\BUP_COM_PernvtApp.doc Rev.03/05/2019
City of Tigard • COMMUNITY DEVELOPMENT DEPARTMENT
" Plan Submittal Requirements Matrix
Commercial & Multi-Family - New, Additions or Alterations
TIGARD 13125 SW Hall Blvd. • Tigard, Oregon 97223 • 503.718.2439 • www.tigard-or.gov
Type of Submittal # of Plans
(Includes new, additions and alterations.) Required at
Submittal
Demolition Permit 2
(site plan is required showing location and square footage
of all buildings to be demolished,erosion control plan and
tree protection,if applicable)
Site Work 3
(must include location of all accessible parking)
Plumbing (site utilities) 2
Building 3
Fire Protection System 3
Mechanical 2
Plumbing (building fixtures) 2
Electrical 2
Solar Photovoltaic 2
(Requires check list for prescriptive installation. If not
prescriptive installation,engineering is required.)
Plan review is dependent upon submittal of a completed application and plans.
After plan review approval, the Plans Examiner will contact the applicant to request
additional sets of plans for distribution purposes (for contractor, City of Tigard,Washington
County, and Tualatin Valley Fire&Rescue),if applicable.
I:\Building\Permits\BUP_COM_PermitApp.doc Rev.03/05/2019
City of Tigard
II COMMUNITY DEVELOPMENT DEPARTMENT
■ .
T1cARD Building Permit Review — Commercial - No Land Use
Building Permit #: „&„712.2.60 Dedoo(r-
Site Address: /-2,',2/ ) .-- 3/4 -e_ Suite/Bldg#:
Project Name: --•LlYp
(Name of commercial business occupying the space. If vacant,enter Spec Space.)
Planning Review /
Proposal: 2 // g(Q 4Zd-S-Q
Existing Business Activity: A--%
Proposed Business Activity: /1
. Verify site address/suite# exists and active in permit system.
1" ver Terrace Neighborhood: ❑ Yes ❑ No
oning: /ti •
—
ermitted Use: YCI Yes ❑ No ❑ Spec Space
1a Confirm no land use required.
MUto :usiness License:
Exists: ❑ Yes ❑ No,applicant was provided a business license application
Notes:
Approved by Planning: 2:---- !'-' (-
_ Date: //17V.2_6)
Revisions (after Building Submittal only) Reviewer Date
Revision 1: ❑ Approved ❑ Not Approved
Revision 2: ❑ Approved ❑ Not Approved
Revision 3: ❑ Approved ❑ Not Approved
Building Permit Submittal /k)Original Submittal Date: /J�j
Site Plans: # ).
Building Plans: # ,,2..
Building Permit#: nter building pe above.
Workflow Routing: anningt Coordinator ❑ Building
Workflow Sign-off: S' -off for Planning(include notes from planning review)
Route Application Documents: ❑g ding: original permit application, site plans,building plans,engineer and
beam calculations and trust details,if applicable,etc.
Notes:
By Permit Technician: %' �,.. _ Date: / A)
I:\Building\Forms\BldgPermitRvw_COM_NoLandUse_l 11819.docx
Permit Coordinator Review
❑ Conditions "Met"prior to issuance of building permit
❑ Approved,NOT Released: Date:
Notes:
Revisions (after Building Submittal only)
Revision Notice 1: Date Sent to Applicant:
Revision Notice 2: Date Sent to Applicant:
Revision Notice 3: Date Sent to Applicant:
SDC Fee Entered: Wash Co Trans Dev Tax: ❑ Yes ,� I`I A
Tigard Trans SDC: ❑ Yes L��N�A
Parks SDC: ❑ Yes D4 /A
OK to Issue Permit
4(Approved byPermit Coordinator: Date:i/t/O AO
PP
1:\Building\Forms\BldgPermitRvw_COM_NoLandUse_111819.docx
A alcS
RECEIVED
Submittal
JAN 9 2020
Transmittal
CITY OF .fl(-`Air.l)
AKS Engineering &Forestry LLC 129gUtypttelatiltS10100 Tualatin, OR 97062
FROM: Chris Knight
AKS Engineering & Forestry LLC TO: Branden Taggart
12965 SW Herman Rd. City of Tigard Community Development
Suite 100 13125 SW Hall Blvd.
Tualatin, OR 97062 Tigard, OR 97223
KnightC@aks-eng.com brandent@tigard-or.gov
503-563-6151 503-718-2449
PROJECT: 72nd Avenue MOB DATE SENT: 1/9/2020
4762
SUBJECT: City of Tigard Demo Permit TL 400 ID: 00093
Submittal 1
PURPOSE: For Review and Comment VIA: Courier
REMARKS: Hello Branden,
•
Please see the attached demolition permits showing valuation for the demo
work including abatement. Per your instructions I have only filled out the
first page but have submitted one demo permit for each property.
Please feel free to contact me with any questions you may have.
Thank you,
Chris
Christopher Knight, EI
AKS ENGINEERING & FORESTRY, LLC
12965 SW Herman Road, Suite 100 I Tualatin, OR 97062
CONTENTS
QTY: DATED DESCRIPTION: ACTION:
1 1/9/2020 Demo Permit Application - TL400
QTY: DATED DESCRIPTION: ACTION:
2 1/9/2020 Construction Plans
Page 1 of 1
Stacey Morrill
From: Branden Taggart <brandent@tigard-or.gov>
Sent: Wednesday, December 18, 2019 4:16 PM
To: Chris Knight
Cc: Chuck Gregory; #Building Permit Technicians
Subject: RE: Basecamp contractor trailer farm - permits: 7350 SW Dartmouth St.
Attachments: Branden Taggart2.vcf; BUP_COM_PermitApp.pdf
Importance: High
Follow Up Flag: Follow up
Flag Status: Flagged
Hi Chris,
Regarding the Site Work grading permit for job trailers and parking that you submitted recently, I initially thought we
could combine this scope of work under the preliminary site grading permit to simplify the permitting. However, since
this work will take place on adjacent parcels, we will need to issue (1) new Site Work permit. Additionally, after
reviewed the permit history for these parcels, and I do not see demolition permits for the following Basecamp owned
properties with houses on them:
• 12215 SW 72nd Ave. (Parcel 2S101BA00400)
• 12235 SW 72nd Ave. (Parcel 2S101BA00402)
In order to begin the Site Work grading,you will also need to apply for(2) demolition permits at the above
addresses. The Demolition permits do not need to be finaled or closed prior to the Issuance of the Site Work permit, but
the demolition permits will need to be submitted before we can issue the Site Work permit. Once the job trailers have
been removed from these parcels, we will be able to close out the demolition permits. Furthermore, our Building
Official has determined that it will not be necessary to create new addresses after the demolition of these houses since a
new building will not be constructed on these parcels. To help you with the submittal of demolition permits, I have
attached a Building Permit Application above for you to reference, and I have also included information below:
Demolition permit requirements:
• Complete Page 1 only of the building permit application (see attached).
o Complete one application for each address.
o Provide project valuation on each application.
• Submit (2) copies of a site plan, drawn to scale, for each address showing:
o Footprint of all structures to be demolished, with square footages noted.
o Identify utilities, septic tanks, etc.
• Decommissioning of septic tanks will require a pump/fill or removal receipt prior to scheduling
final inspection.
o Erosion control plan.
o Tree protection measures, if applicable.
o Pedestrian protection, if applicable.
Permit applications and plans may be submitted in person between the hours of 8:00 a.m. to 4:00 p.m., Monday
through Thursday. We are closed on Fridays. Applications and plans can be mailed or submitted in person. Electronic
plan submittal is not possible at this time. All permit fees will be collected when these permits are ready to
issue. Please allow 1-2 weeks for plan review. We will notify you when these permits are ready to issue, and we will
give you the balance due at that time. Please let me know if you have questions.
Thank you,
INBranden Taggart
q City of Tigard
r.•.t Senior Permit Technician
TIGARI) Community Development
13125 SW Hall Blvd
Tigard, OR 97223
1503) 718-2449
brandent@tigard-or.gov
From: Branden Taggart
Sent:Tuesday, September 10, 2019 8:32 AM
To: Chris Knight<KnightC@aks-eng.com>
Cc: #Building Permit Technicians<TigardBuildingPermits@tigard-or.gov>
Subject: RE: Basecamp contractor trailer farm - permits: 7350 SW Dartmouth St.
Chris,
Since there will not be public access, a permit for the stairs or ramps will not be needed.
Thanks,
Branden Taggart
City of Tigard
s 0 Senior Permit Technician
Community Development
13125 SW Hall Blvd
Tigard, OR. 97223
(503)718-2449
brandent@tigard-or.gov
From: Chris Knight<KnightCPaks-eng.com>
Sent:Tuesday, September 10, 2019 8:24 AM
To: Branden Taggart<brandent@tigard-or.gov>
Cc:#Building Permit Technicians<TigardBuildingPermits@tigard-or.gov>
Subject: RE: Basecamp contractor trailer farm - permits: 7350 SW Dartmouth St.
.......................................
Hello Branden,
These trailers are just construction job trailers, no sales or public access but I do not know about the foundations yet.
Regardless of the foundation type we will need a building permit for the stairs/ramps correct?
Thanks for the link,
2
Chris
Christopher Knight, El
AKS ENGINEERING &FORESTRY, LLC
P:503.563.6151 Ext.252 I F:503.563.6152 I www.aks-eng.com I KnightCPaks-eng.com
From: Branden Taggart<brandent@tigard-or.gov>
Sent:Tuesday, September 10, 2019 8:14 AM
To: Chris Knight<KnightC@aks-eng.com>
Cc: #Building Permit Technicians<TigardBuildingPermits@tigard-or.gov>
Subject: RE: Basecamp contractor trailer farm - permits: 7350 SW Dartmouth St.
Hi Chris,
You are welcome. I am trying to recall the use of the trailers from our conversation. Will the use of the trailers be for
construction, like a job trailer, or will there be any sales trailers with public access? Also, will the trailers have wheels or
foundations?
For additional clarification, a typical job trailer on wheels will not require a permit. An electrical permit for temporary
power is all that is needed, and the electrical contractors can submit for these permits online through our website:
https://aca.accela.com/TIGARD/Welcome.aspx. If there will be public access to the trailer, like a sales trailer,then a
Commercial Manufactured Structure permit is required for the placement of the structure, and a building permit for the
ADA accessibility will also be required as we discussed. From our conversation, I may have made the assumption that
the public will have access. I have attached the CMS permit application above in the event that the public will have
access to the trailers. Please let me know if you have additional questions.
Thanks,
Branden Taggart
q City of Tigard
■ Senior Permit Technician
Community Development
TIC ARD
13125 SW Hall Blvd
Tigard, OR 97223
1503)718-2449
brandent@tigard-or.gov
From: Chris Knight<KnightC@aks-eng.com>
Sent: Monday, September 9, 2019 4:48 PM
To: Branden Taggart<brandent@tigard-or.gov>
Subject: Basecamp contractor trailer farm - permits
Hello Branden,
Thanks for talking with me earlier about the permits needed for the trailer farm. I was looking for the "commercial
manufactured structure permit" in the permit document webpage (https://www.tigard-or.gov/help me to/forms.php#)
and was not able to locate it. I assumed it was a separate permit, is it part of a more general from or have I missed it?
3
Thanks,
Chris
Christopher Knight, El
ALS(
AKS ENGINEERING & FORESTRY, LLC
12965 SW Herman Road,Suite 100 I Tualatin,OR 97062
P:503.563.6151 Ext.252 I F:503.563.6152 I www.aks-eng.com I KnightC@aks-eng.com
Offices in: Bend, OR I Keizer, OR I Tualatin, OR I Vancouver,WA
NOTICE: This communication may contain privileged or other confidential information.If you have received it in error,please advise the sender by
reply e-mail and immediately delete the message and any attachments without copying or disclosing the contents.AKS Engineering and Forestry
shall not be liable for any changes made to the electronic data transferred.Distribution of electronic data to others is prohibited without the express
written consent of AKS Engineering and Forestry.
DISCLAIMER: E-mails sent or received by City of Tigard employees are subject to public record laws. If requested, e-mail
may be disclosed to another party unless exempt from disclosure under Oregon Public Records Law. E-mails are retained
by the City of Tigard in compliance with the Oregon Administrative Rules "City General Records Retention Schedule."
4