Shiels Obletz Johnsen ~ C200041
CITY OF TIGARD - CONTRACT SUMMARY & ROUTING FORM
Contract Overview
Contract/Amendment Number: C200041a4
Contract Start Date: 10/15/19 Contract End Date: 06/30/2024
Contract Title: Owner’s Representative/Project Management Services – Tigard Universal Plaza and Fanno
Creek Overlook
Contractor Name: Shiels Obletz Johnsen
Contract Manager: Sean Farrelly
Department: CD
Contract Costs
Original Contract Amount: $250,000.00
Total All Previous Amendments: $n/a
Total of this Amendment: n/a
Total Contract Amount: $312,500.00
Procurement Authority
Contract Type: Personal Services
Procurement Type: PCR 10.075 Contract Amendments
Solicitation Number: N/A
LCRB Date: N/A
Account String: Fund-Division-Account Work Order – Activity Type Amount
FY
Contracts & Purchasing Approval
Purchasing Signature:
Comments: Time extension
DocuSign Routing
Route for Signature Name Email Address
Contractor Francesca Gambetti francesca@sojpdx.com
City of Tigard Steve Rymer stever@tigard-or.gov
Final Distribution
Contractor Francesca Gambetti francesca@sojpdx.com
Contractor Kim Knox knox@sojpdx.com
Project Manager Sean Farrelly sean@tigard-or.gov
Buyer Toni Riccardi tonir@tigard-or.gov
CITY OF TIGARD - CONTRACT SUMMARY & ROUTING FORM
Contract Overview
Contract/Amendment Number: C200041a3
Contract Start Date: 10/15/19 Contract End Date: 12/31/23
Contract Title: Owner’s Representative/Project Management Services – Tigard Universal Plaza and Fanno
Creek Overlook
Contractor Name: Shiels Obletz Johnsen
Contract Manager: Sean Farrelly
Department: CD
Contract Costs
Original Contract Amount: $250,000.00
Total All Previous Amendments: $62,500.00
Total of this Amendment: n/a
Total Contract Amount: $312,500.00
Procurement Authority
Contract Type: Personal Services
Procurement Type: PCR 10.075 Contract Amendments
Solicitation Number: N/A
LCRB Date: N/A
Account String: Fund-Division-Account Work Order – Activity Type Amount
FY
Contracts & Purchasing Approval
Purchasing Signature:
Comments: Time extension, add Exhibit A.
DocuSign Routing
Route for Signature Name Email Address
Contractor Francesca Gambetti francesca@sojpdx.com
City of Tigard Steve Rymer stever@tigard-or.gov
Final Distribution
Contractor Francesca Gambetti francesca@sojpdx.com
Contractor Kim Knox knox@sojpdx.com
Project Manager Sean Farrelly sean@tigard-or.gov
Buyer Toni Riccardi tonir@tigard-or.gov
CITY OF TIGARD - CONTRACT SUMMARY & ROUTING FORM
Contract Overview
Contract/Amendment Number: C200041a2
Contract Start Date: 10/15/19 Contract End Date: 6/30/23
Contract Title: Owner’s Representative/Project Management Services – Tigard Universal Plaza and Fanno
Creek Overlook
Contractor Name: Shiels Obletz Johnsen
Contract Manager: Sean Farrelly
Department: CD
Contract Costs
Original Contract Amount: $250,000.00
Total All Previous Amendments: 0
Total of this Amendment: $62,500.00
Total Contract Amount: $312,500.00
Procurement Authority
Contract Type: Personal Services
Procurement Type: PCR 10.075 Contract Amendments
Solicitation Number: N/A
LCRB Date: N/A
Account String: Fund-Division-Account Work Order – Activity Type Amount
FY 23 940-8000-56005 92059-940-130 $62,500.00
Contracts & Purchasing Approval
Purchasing Signature:
Comments: Time extension, add Exhibit A.
DocuSign Routing
Route for Signature Name Email Address
Contractor Francesca Gambetti francesca@sojpdx.com
City of Tigard Steve Rymer stever@tigard-or.gov
Final Distribution
Contractor Francesca Gambetti francesca@sojpdx.com
Contractor Kim Knox knox@sojpdx.com
Project Manager Sean Farrelly sean@tigard-or.gov
Buyer Toni Riccardi tonir@tigard-or.gov
CITY OF TIGARD - CONTRACT SUMMARY & ROUTING FORM
Contract Overview
Contract/Amendment Number: C200041a2
Contract Start Date: 10/15/19 Contract End Date: 6/30/23
Contract Title: Owner’s Representative/Project Management Services – Tigard Universal Plaza and Fanno
Creek Overlook
Contractor Name: Shiels Obletz Johnsen
Contract Manager: Sean Farrelly
Department: CD
Contract Costs
Original Contract Amount: $250,000.00
Total All Previous Amendments: 0
Total of this Amendment: $62,500.00
Total Contract Amount: $312,500.00
Procurement Authority
Contract Type: Personal Services
Procurement Type: PCR 10.075 Contract Amendments
Solicitation Number: N/A
LCRB Date: N/A
Account String: Fund-Division-Account Work Order – Activity Type Amount
FY 23 940-8000-56005 92059-940-130 $62,500.00
Contracts & Purchasing Approval
Purchasing Signature:
Comments: Time extension, add Exhibit A.
DocuSign Routing
Route for Signature Name Email Address
Contractor Francesca Gambetti francesca@sojpdx.com
City of Tigard Steve Rymer stever@tigard-or.gov
Final Distribution
Contractor Francesca Gambetti francesca@sojpdx.com
Contractor Kim Knox knox@sojpdx.com
Project Manager Sean Farrelly sean@tigard-or.gov
Buyer Toni Riccardi tonir@tigard-or.gov
CITY OF TIGARD-CONTRACT SUMMARY&ROUTING FORM
Contract Overview
Contract/Amendment Number: C200041a1
Contract Start Date: 10/15/19 Contract End Date: 6 30 23
Contract Title: Owner's Representative/Project Management Services—Tigard Universal Plaza and Fanno
Creek Overlook
Contractor Name: Shiels Obletz Johnsen
Contract Manager: Sean Farrellv
Department: CD
Contract Costs
Original Contract Amount: $250.000.00
Total All Previous Amendments: 0
Total of this Amendment: 0
Total Contract Amount: $250,000.00
Procurement Authority
Contract Type: Personal Services
Procurement Type: PCR 10.075 Contract Amendments
Solicitation Number:
LCRB Date:
Account String: Fund-Division-Account Work Order—Activity Tyke Amount
FY N/A
FY
FY
FY
FY
m_
Contracts & Purchasing Approval
Mx4
Purchasing Signature:
Comments:Time extension.
DocuSign Routing
Route for Signature Name Email Address
Contractor Francesca Gambetti francesca&sojj2dx.com
City of Tigard Steve Rymer stever&tigard-or.gov
Final Distribution
Contractor Francesca Gambetti francesca so' dx.com
Contractor Kim Knox knox9sojj2dx.com
Project Manager Sean FarreHy sean ti and-or. ov
Buyer Christine Moody christine ti and-or. ov
DocuSign Envelope ID:C8BA2CEA-64EE-44CF-A412-AD8E2498D9BD
CITY OF TIGARD, OREGON
AMENDMENT TO CONTRACT NUMBER 0200041
FOR
OWNER'S REPRESENTATIVE/PROJECT MANAGEMENT SERVICES—
TIGARD UNIVERSAL PLAZA AND FANNO CREEK OVERLOOK
AMENDMENT #1
The Agreement between the City of Tigard,a municipal corporation of the State of Oregon,hereinafter called
City, and Shiels Obletz Johnsen, hereinafter referred to as Contractor,is hereby amended as follows:
1. EFFECTIVE DATE AND DURATION
This Agreement is extended for 21 months with a new expiration date of June 30, 2023.
IN WITNESS WHEREOF, City has caused this Amendment to be executed by its duly authorized
undersigned officer and Contractor has executed this Amendment upon signature and date listed below.
CITY OF TIGARD SHIELS OBLETZ JOHNSEN
Vwf'�wt^ �rata ce sca GaH bc{{i
5134FBF58 [HC9... ili EP,5EBPBi5_.
Signature Signature
Steve Rymer Francesca Gambetti
Printed Name Printed Name
10/14/2021 10/13/2021
Date Date
Rev. 8/21
CITY OF TIGARD OREGON-CONTRACT SUMMARY FORM
(THIS FORM MUSTACCOMPANYEVERYCONTRACT)
Contract Title: Owner's Representative/Project Management Services Number: l'JO'�UUV�
Tigard Universal Plaza and Fanno Creek Overlook
Contractor: Shiels Obletz Johnsen Contract Total: $250,000
Contract Overview: Provide project management and owner's representative services through design
enWneering.and construction of the Universal Plaza and Fanno Creek Overlook
projects _
Initial Risk Level: ❑ Extreme ❑ High ® Moderate ❑ Low
Risk Reduction Steps:
Risk Comments:
Risk Signature:
Contract Manager: Sean Farrell z Ext: 2420 Department: CD
Type: ® Personal Svc ❑ Professional Svc ❑ Architectural Agr ❑ Public Imp ❑ General Svc
❑ Engineering Svc ❑ Other: Start Date: 10/15/19_End Date: 9/30/21
Quotes/Bids/Proposal: FIRM AMouNT (SRR
Shiels Obletz Johnsen 1
Plan B 2
Mears CPM 3
Account String: Fund-Division-Account Work Order—Activilyl=e Am un
FY 19-20 940-8000-56005 92059-940-180 $70,000
FY 20-21 940-8000-56005 92059-940-180 $150,000
FY 21-22 940-8000-56005 92059-940-180 $30,000
Approvals - LCRB Date: 9Z24/2019
Department Comments:
Department Signature:
Purchasing Comments:
Purchasing Signature:
City Manager Comments:
City Manager Signature:
After securing all required approvals, forward original copy to the Contracting and Purchasing Office along with a
completed Contract Checklist.
City of Tigard
FINANCE AND INFORMATION SERVICES
Request for Proposal (RFP)
OWNER'S REPRESENTATIVE/PROJECT
MANAGEMENT SERVICES - TIGARD UNIVERSAL PLAZA AND
FANNO CREEK OVERLOOK
Proposals Due:_ August 28. 2019-2:00 p.m. local time
Submit Proposals To: City of Tigard—Contracts &Purchasing Office
Attn: Jamie Greenberg,Purchasing Specialist
13125 SW Hall Blvd.
Tigard, Oregon 97223
Direct Questions To: Sean Farrelly,Redevelopment Project Manager
Phone: (503) 718-2420
Email: sean e,tigar�d-oror.gov
Kenny Asher, Community Development Director
Phone: (503) 718-2443
Email: kennya@ igard-or.gov
Lori Faha,City Engineer
Phone: (503) 718-2759
Email: lorif@tigard-or.gov
City of Tigard 1 13125 SW Hall Blvd.,Tigard, OR 97223 1 (503) 639-41711 www.tigard-or.gov
PUBLIC NOTICE
REQUEST FOR PROPOSAL
OWNER'S REPRESENTATIVE/PROJECT MANAGEMENT SERVICES-
TIGARD UNIVERSAL PLAZA AND FANNO CREEK OVERLOOK
The City of Tigard is seeking sealed proposals from qualified firms to provide owner's representative/project
management services for the City's Universal Plaza and Fanno Creek Overlook projects. Proposals will be
received until 2:00 p.m.local time,Wednesday,August 28,2019,at Tigard City Hall's Municipal Court Counter
at 13125 SW Hall Blvd.,Tigard, Or 97223.
No proposal will be considered unless fully completed in a manner provided in the RFP packet. Facsimile and
electronic (email) proposals will not be accepted nor will any proposal be accepted after the stated due date and
time. Any proposal received after the closing time will be returned to the submitting firm unopened after a
contract has been awarded for the required services.
RFP packets may be downloaded from www.dgard-or.gov/bids or obtained in person at Tigard City Hall's
Municipal Court Counter located at 13125 SW Hall Blvd.,Tigard, Or 97223.
Proposers are required to certify non-discrimination in employment practices, and identify resident status as
defined in ORS 279A.120. Pre-qualification of proposers is not required. All proposers are required to
comply with the provisions of Oregon Revised Statutes and Local Contract Review Board (LCRB) Policy.
The City may reject any proposal not in compliance with all prescribed public bidding procedures and
requirements,and may reject for good cause any or all proposals upon a finding of the City if it is in the public
interest to do so.
PUBLISHED: Daily-I ournal of Commerce
DATE: Friday,August 8,2019
RFP—Universal Plaza Owner's Representative/Project Management Page 2
Close—August 28,2019
TABLE OF CONTENTS
TITLE PAGE
TitlePage------------------------------------------------------------------------------------------------ -------1
Public Notice --------------------------
------------------------------------------------------------------------
Tableof Contents----------------------------------------------------------------------------------------- 3
SECTIONS
Section 1 Introduction------------ ------------------------------------------------------------------------------------- 4
Section 2 Proposer's Special Instructions----------------------------------------------------------------------4
Section3 Background------------------------------- --------------------------------------------------------------- -----6
Section 4 Scope and Schedule of Work-------------------------------------------------------------------------8
Section 5 Proposal Content and Format---------------------------------------------------------------------11
Section 6 Proposal Evaluation Procedures......................................._------------_-------------12
Section 7 Proposal Certification-------------- --------- --------- ---------------------------------------------14
Section 8 Signature Page-------------------- -------------------------------------------------------------------------15
ATTACHMENTS
Attachment A Acknowledgement of Addendum________________________________________________________________16
Attachment B Statement of Proposal______________ _________ _________ _________ _________ _____________________17
Attachment C City of Tigard Personal Services Agreement-----------------------------------------------18
Attachment D Resolve Universal Plaza Concept.......................................Separate Document
Attachment E Tigard Universal Plaza Design Brief..................................Separate Document
Attachment F Fanno Creek Public Space Feasibility Study.....................Separate Document
RFP—Universal Plaza Owner's Representative/Project Management Page 3
Close—August 28,2019
SECTION 1
INTRODUCTION
The City of Tigard is seeking sealed proposals from qualified firms owner's representative/project
management services for the City's Universal Plaza and Fanno Creek Overlook projects. Proposals will be
received until 2:00 p.m.local time,Wednesday,August 28,2019,at Tigard City Hall's Municipal Court Counter
at 13125 SW Hall Blvd.,Tigard,Or 97223.
No proposal will be considered unless fully completed in a manner provided in the RFP packet. Facsimile and
electronic (email) proposals will not be accepted not will any proposal be accepted after the stated due date and
time. Any proposal received after the closing time will be returned to the submitting firm unopened after a
contract has been awarded for the required services.
Proposers are required to certify non-discrimination in employment practices, and identify resident status as
defined in ORS 279A.120. Pre-qualification of proposers is not required. All proposers are required to
comply with the provisions of Oregon Revised Statutes and Local Contract Review Board (LCRB) Policy.
The City may reject any proposal not in compliance with all prescribed public bidding procedures and
requirements,and may reject for good cause any or all proposals upon a finding of the City if it is in the public
interest to do so.
SECTION 2
PROPOSER'S SPECIAL INSTRUCTIONS
A. PROPOSED TIMELINES
Friday,August 9, 2019 Advertisement and Release of Proposals
Wednesday August 28 2019—2:00 p.m. Deadline for Submission of Proposals
Week of September 9,2019 Interviews (if necessary)
Tuesday,September 24. 2019 Award of Contract by LCRB
Monday.. September 30,2019 Commencement of Services
NOTE: The City reserves the right to modify this schedule at the City's discretion
B. GENERAL
By submitting a proposal, the Proposer certifies that the Proposal has been arrived at independently
and has been submitted without any collusion designed to limit competition.
C. PROPOSAL SUBMITTAL
The Proposal and all amendments must be signed and submitted no later than 2:00 p.m.,Wednesday,
August 28, 2019, to the address below. Each proposal must be submitted in a sealed envelope and
designated with proposal title. To assure that your proposal receives priority treatment, please mark
as follows.
RFP—Owner's Re resentadve Pro'ect Management—
Tigard Universal Plaza&Fanno Creek Overlook
City of Tigard—Municipal Court Counter
Attn: Jamie Greenberg,Purchasing Specialist
13125 SW Hall Blvd.
Tigard,Oregon 97223
Proposer shall put their name and address on the outside of the envelope. It is the Proposer's
responsibility to ensure that proposals are received prior to the stated closing time. The City shall not be
RFP—Universal Plaza Owner's Representative/Project Management Page 4
Close—August 28, 2019
responsible for the proper identification and handling of any proposals submitted incorrectly. Late
proposals, late modification or late withdrawals shall not be considered accepted after the stated bid
opening date and time and shall be returned unopened. Facsimile and electronic (email) proposals will
not be accepted.
D. PROTEST OF SCOPE OF WORK OR TERMS
A Proposer who believes any details in the scope of work or terms detailed in the proposal packet and
sample contract are unnecessarily restrictive or limit competition may submit a protest in writing, to
the Purchasing Office. A protest may be submitted via facsimile. Any such protest shall include the
reasons for the protest and shall detail any proposed changes to the scope of work or terms. The
Purchasing Office shall respond to any protest and,if necessary, shall issue any appropriate revisions,
substitutions, or clarification via addenda to all interested Proposers.
To be considered, protests must be received at least five (5) days before the proposal closing date.
The City shall not consider any protest against award due to the content of proposal scope of work
or contract terms submitted after the established protest deadline. All protests should be directed to
the attention of Jamie Greenberg,Purchasing Specialist,and be marked as follows:
RFP Specification/Term Protest
City of Tigard—Contracts and Purchasing Office
Attn: Jamie Greenberg,Purchasing Specialist
13125 SW Hall Blvd.
Tigard, Oregon 97223
If a protest is received in accordance with section above, the proposal opening date may be extended if
necessary to allow consideration of the protest and issuance of any necessary addenda to the proposal
documents.
E. PROPOSAL SUBMISSION AND SIGNING
All requested forms and attachments (Signature Page, Acknowledgment Addendum, Statement of
Proposal, etc.) must be submitted with the Proposal and in the required format. The submission and
signing of a proposal shall indicate the intention of the firm to adhere to the provisions described in
this RFP.
F. COST OF PREPARING A PROPOSAL
The RFP does not commit the City to paying any costs incurred by Proposer in the submission or
presentation of a proposal, or in making the necessary studies for the preparation thereof.
G. INTERPRETATIONS AND ADDENDA
All questions regarding this project proposal shall be directed to Jamie Greenberg, Purchasing
Specialist. If necessary,interpretations or clarifications in response to such questions will be made by
issuance of an "Addendum" to all prospective Proposers within a reasonable time prior to proposal
closing, but in no case less than 72 hours before the proposal closing. If an addendum is necessary
after that time,the City,at its discretion, can extend the closing date.
Any Addendum issued, as a result of any change in the RFP, must be acknowledged by submitting the
"Acknowledgment of Addendum"with proposal. Only questions answered by formal written addenda
will be binding. Oral and other interpretations or clarifications will be without legal effect.
RFP—Universal Plaza Owner's Representative/Project Management Page 5
Close—August 28,2019
H. BUSINESS LICENSEIFEDERAL TAX ID REQUIRED
The City of Tigard Business License is required. Chapter 5.4 of the Tigard Municipal Code states any
business doing business in the City of Tigard shall pay a City of Tigard Business License. Successful
Contract will be required to present a copy of their City of Tigard Business License at the time of
contract execution. Successful Contractor shall also complete a W-9 form for the City at the time of
contract execution.
I. CITY'S PROJECT MANAGER
The City's Project Manager for this work will be Sean Farrelly,Redevelopment Project Manager,who
can be reached by phone at (503) 718-2420 or by email at sean@tiggd-or.gov.
J. PROPOSAL VALIDITY PERIOD
Each proposal shall be irrevocable for a period of one hundred twenty (120) days from the Proposal
Opening Date.
K. FORM OF CONTRACT
A copy of the City's standard personal services agreement,which the City expects the successful firm
or individual to execute,is included as "Attachment C". The contract will incorporate the terms and
conditions from this RFP document and the successful proposer's response documents. Firms taking
exception to any of the contract terms shall submit a protest or request for change in accordance with
Section 2.1) "Protest of Scope of Work or Terms" or their exceptions will be deemed immaterial and
waived.
L. TERM OF CONTRACT
The term of the contract shall be a period of two (2) years with the mutual option to renew for up to
one (1) additional one-year period. The total term of the contract cannot exceed three (3) years.
M. TERMINATION
The contract may be terminated by mutual consent of both parries or by the City at its discretion with
a 30 days'written notice. If the agreement is so terminated, Contractor shall be paid in accordance
with the terms of the agreement.
N. NON-COLLUSION
Proposer certifies that this proposal had been arrived at independently and has been submitted without
collusion designed to limit independent bidding or competition.
P. PUBLIC RECORD
All bid material submitted by bidder shall become the property of the City and is public record unless
otherwise specified. A bid that contains any information that is considered trade secret under ORS
192.501(2) should be segregated and clearly identified as such. This information will be kept
confidential and shall not be disclosed except in accordance with the Oregon Public Records Law,
ORS 192. The above restrictions may not include cost or price information,which must be open to
the public.
SECTION 3
BACKGROUND
The City of Tigard and its urban renewal agency,the Town Center Development Agency(TCDA),have been
focusing on the growth and redevelopment of downtown Tigard. It adopted the City Center Urban Renewal
RFP—Universal Plaza Owner's Representative/Project Management Page 6
Close—August 28,2019
Plan to further this. One of the Plan goals is to "develop urban spaces that will provide active and passive
recreational opportunities for pedestrians and attract residents and visitors to downtown.
In 2017, the TCDA Board endorsed constructing a large plaza on the agency-owned 1.18 acre "Miller
property" on Burnham Street. The site will be vacated by its current tenant within the next 6-8 months.
ReSolve Architecture and Planning was hired to develop a concept for the site (Attachment D — Universal
Plaza Concept). The design considerations for the plaza included:
• Activation of the site
• Contours of the site
• Views from and of the site
• Connectivity to Fanno Creek Park and Trail and Burnham Street
• Budget to construct
• Maintenance considerations
• Versatility and Identity
The plaza concept is the Universal Plaza. "Universal"refers to the plaza design incorporating amenities that
are usable by people of all ages,abilities,ethnic and racial backgrounds,as well as its embodiment of elemental
features of our universe. The conceptual plaza features include interpretive artwork and installations on
natural ecosystems with data, art, history and stories that will make the plaza an educational destination for
school and summer camp field trips. A large splash pad (Tigard's first) would attract families with children.
The plaza could also accommodate musical or other events that seat up to 900 people and a farmer's market
or a fair with 80 booths. The design connects to Fanno Creek Park and the recent remeander of Fanno Creek
which restored the historical course of the creek and planted native vegetation on the banks.
In May,the City engaged Gehl Studios to do an intermediate pre-design process to refine and"ground-truth"
the plaza concept. They performed a Public Life/Public Space study in Downtown. The insights and
recommendations gained from this study will be used to generate design and programming guidelines(a design
brief- Attachment E) to inform the RFP for plaza design and engineering to be released in late
August/September 2019.
Advancing the design and engineering of Universal Plaza is a City Council Goal for 2019-2021.
A second project is on a more uncertain timeline: the Fanno Creek Overlook.This project would construct
public space a public space next to Fanno Creek that would build a provide better access to the natural and
recreational resources of creek and a new connection to the Fanno Creek Trail. The project will involve
widening a driveway to accommodate two-way traffic, since the land where the Overlook would be building
is presently a driveway. Fanno Creek Public Space Feasibility Study—Attachment F.
The City of Tigard is seeking an Owner's Representative/Project Manager to assist with project management
and coordination of design and construction of the Universal Plaza (Project 1) and Fanno Creek Overlook
(Project 2).
The phases of the projects include:
• Design/Engineering Procurement
• Design Concept Refinement
• Design
RFP—Universal Plaza Owner's Representative/Project Management Page 7
Close—August 28,2019
• Construction Drawings
• Permitting
• Construction
• Project Closeout
SECTION 4
SCOPE AND SCHEDULE OF WORK
The following overview describes tasks the City has identified as necessary for this Project 1 and Project 2.
This is not intended to be a complete list of services that the Consultant may deem necessary to complete this
project but is offered as a guideline in developing a scope for the project.
The Owner's Representative/Project Manager shall provide sufficient organization, personnel and
management to carry out the requirements of this Agreement in an expeditious and economical manner
consistent with the interests of the City. Support and staffing levels may vary significantly throughout the
project duration depending on project need. The Owner's Representative/Project Manager services budget
for these projects is an amount not to exceed$250,000 over the life of the contract.
Task 1— Project Management
1.1 Project Management and Coordination
A. The Owner's Representative shall be the point of contact for the City design team, coordinate
with A/E consultants and contractor for both the Universal Plaza (Project 1) and Fanno Creek
Overlook (Project 2).
B. In consultation with the City Project Manager(staff),manage the A/E and construction contractor
contracts and project budget. Review consultant/contractor invoicing and recommend approval
to City staff.
1.2 Master Schedule
A. The Owner's Representative shall prepare a master schedule detailing the design and construction
phases of the project,including potential phasing
B. Update the project schedule at each phase of design
C. Manage the master schedule.
1.3 Project Meetings and Communication
Provide project management support services for internal project team coordination including project
team and stakeholder meetings, and regular project updates.
A. The Owner's Representative shall prepare for and conduct a project kick-off meeting at the City
to discuss the project scope, schedule, and design team deliverables with city staff. Kick-off
meeting to last 2.5 hours.
B. Schedule and lead up design progress and project management meetings (likely monthly,but final
number to be negotiated) at the City and prepare meeting agendas and minutes. Meetings to last
up to 2 hours.
RFP—Universal Plaza Owner's Representative/Project Management Page 8
Close—August 28, 2019
C. Participate in weekly conference call with city project team. Weekly conference calls are
anticipated to last 15 minutes.
D. Participate in up to two public open-house meetings.
E. Participate in up to three TAC meetings
F. Act as primary point of contact for adjacent property owners and other stakeholders
G. Provide regular status reports to project team
1.4 Design and Engineering Procurement
Assist in review of responses to Design and Engineering RFP and interviews.
Task 2— Plans, Specifications, and Estimates
2.1 Predesign project planning
Assist with predesign project planning and organization documentation, including templates,
recommendations, and review of scope, schedule, budget, communications, risk management, and
other project document management.
2.2 Design Phase Document Reviews
Provide review and analysis of A/E refined concept, 30%, 60%, and 90% and final construction
documents
2.3 Review Preliminary Construction Cost Estimates
Review A/E preliminary construction cost estimates at 30%,60%,and 90%and final design
Task 3— Land Use and Permitting
3.1 Land Use Approvals
Assist city and A/E with documentation and facilitation of timely land use review and permitting
process,including Clean Water Services permits to minimize impacts on project scope, schedule and
budget.
3.2 Permitting
Assist city and A/E with documentation and facilitation of LUR,PFI, building permit and any other
permitting processes, as required. Project 2 may require coordination with the Army Corps of
Engineers and Department of State Lands
Task 4— Pre-Construction
4.1 Design Development Cost Estimate
Provide analysis of cost estimates and oversee reconciliation of project cost estimate
4.2 Construction Cost Estimate
Provide analysis of cost estimates and oversee reconciliation of project cost estimate
RFP—Universal Plaza Owner's Representative/Project Management Page 9
Close—August 28,2019
4.3 Construction Phasing and Constructability review
Provide analysis of construction phasing plans and constructability reviews
4.4 Contractor Bidding and Procurement
Assist City Project Manager with bidding and procurement of construction contractor
Task 5— Support During Construction
5.1 Weekly meetings with Contractor during construction
5.2 Change Orders
Analyze all Change Orders over designated amount, and forward to City Project Manager with
recommendations
5.3 Submittals
Analyze all submittals and approve or forward to City Project Manager with recommendations
5.4 Requests for Information
Analyze all RFI's and respond or forward to City Project Manager with recommendations
5.5 Substitution Requests
Analyze all Substitution Requests and respond or forward to City Project Manager with
recommendations
5.6 Site Observations
Perform periodic site observations,as requested by City project manager.
5.7 Notices of deficient work
Provides content and review of deficiency list (with Contractor)
5.8 Code and permit compliance
Review documents and site activities for compliance w/ applicable codes and permits and advise PM
and design team accordingly
5.9 Operations and Maintenance Manual
Oversee development and review of Operations and Maintenance Manual by A/E consultant
Task 6 — Project Closeout
6.1 As-built review and verifications
Provide additional review,verification and comment on as-built documentation
6.2 Project Close-out
Support project close-out, including but not necessarily limited to resolving any claims or disputes
resulting from the project and drafting required contractor report
RFP—Universal Plaza Owner's Representative/Project Management Page 10
Close—August 28,2019
Potential Schedule for Projects 1&2
Phase Time
Desigii/Engineering Procurement September/October 2019
Desinr/En=iueering,Contract November 2019
Design Concept Refinement December 2019-February-2020
Des Februar4.2020—September 2020
Construction Drawings September 2020-J anuary 2021
Permitting anuan^2021-April ril 2021
Construction Mai•2021-October 2021
Project Closeout November 2021-]anuary 2022
SECTION 5
PROPOSAL CONTENT AND FORMAT
A. FORMAT
To provide a degree of consistency in review of the written proposals, firms are requested to prepare
their proposals in the standard format specified below.
1. Title Page
Proposer should identify the RFP Tide, name and title of contact person,address, telephone
number, fax number, email address and date of submission.
2. Transmittal Letter
The transmittal letter should be not more than two (2) pages long and should include as a
minimum the following:
a. A brief statement of the Proposer's understanding of the project and services to be performed;
b. A positive commitment to perform the services within the time period specified, starting and
completing the project within the deadlines stated in this RFP; and the names of persons
authorized to represent the Proposer, their title, address and telephone number (if different
from the individual who signs the transmittal letter.)
3. Table of Contents
The table of contents should include a clear and complete identification by section and page
number of the materials submitted.
4. Firm and Team Qualifications
a. Background of the firm. This should include a brief history of the firm and types of services
the firm is qualified to perform.
b. Qualifications of the firm in performing this type of work. This should include examples of
related experience and references for similar studies and projects.
c. Proposers must identify the anticipated members of their firm that will be assigned to meet
the City's needs. Proposers should identify individuals and subcontractors who will provide
the services,their experience,and their individual qualifications. Pertinent resumes of assigned
personnel should be included.
5. Project Understandigg and Approach
Proposers should provide the City with information regarding their understanding of the City's
needs with regards to the Scope and Schedule of Work. Proposers should demonstrate a general
RFP—Universal Plaza Owner's Representative/Project Management Page 11
Close—August 28,2019
understanding of the needs of a municipality in the State of Oregon from a project management
firm. As part of their service understanding documentation, Proposer's should address their
availability to meet the City's needs.
6. Cost Structure
The proposed fee structure should include the complete breakout for the Contractor's costs to
provide all of the services under the subsequent contract.
B. ADDITIONAL SERVICES
Provide a brief description of any other services that your firm could provide the City and an
approximation of the hourly charge for each service of this type. Such services would be contracted
for on an"as needed"basis, to be provided and billed for separately.
C. ADDITIONAL INFORMATION
Please provide any other information you feel would help the Selection Committee evaluate your
firm for this project.
D. REFERENCES
Contractor must demonstrate successful past performance of the firm's ability to provide services as
set forth in this specification. Contractors must detail three (3) references to document experience.
References must be detailed in Attachment B "Statement of Proposal"
E. DISPUTES
Should anv doubt or difference of opinion arise between the City and a Proposer as to the items to be
furnished hereunder or the interpretation of the provisions of this RFP,the decision of the City shall
be final and binding upon all parties.
F. CITY PERSONNEL
No Officer,agent,consultant or employee of the City shall be permitted any interest in the contract.
SECTION 6
PROPOSAL EVALUATION PROCEDURES
A. SELECTION AND EVALUATION PROCESS
A Selection Committee assembled by the City will review the written proposals. Proposals will be
evaluated to determine which ones best meet the needs of the City. After meeting the mandatory
requirements, the proposals will be evaluated on both their technical and fee aspects. The Selection
Committee will select the Proposer which best meets the City's needs based upon its evaluation of a
firms proposal. Proposals will be evaluated in accordance with the following:
1. Completed Proposal submitted on time Pass Fail
2. An original plus one electronic copy on portable USB drive Pass Fail
3. Transmittal letter Pass Fail
4. Firm and team qualifications 40 Points
5. Project understanding and =roach 35 points
6. Cost structure 25�points
TOTAL EVALUATION POINTS 100 POINTS
RFP—Universal Plaza Owner's Representative/Project Management Page 12
Close—August 28,2019
S. PRESENTATION INTERVIEW
At the option of the City, the top scoring proposers (based on the criteria points) may be asked to
make a presentation of their proposal. This will provide an opportunity to clarify or elaborate on the
proposal, but will not, in any way provide an opportunity to change any fee amount originally
proposed. The City's Project Manager will schedule the time and location of these presentations and
notify the selected firms. If the City elects to conduct a presentation/interview process, 25 criteria
points will be assigned to the process and will be added to the participating Proposers' total points.
C. INVESTIGATION OF REFERENCES
The City reserves the right to investigate references and the past performance of any Proposer with
respect to its successful performance of similar projects,compliance with specifications and contractual
obligations,its completion or delivery of a project on schedule and its lawful payment of employees and
workers.
D. CLARIFICATION OF PROPOSALS
The City reserves the right to obtain clarification of any point in regards to a proposal or to obtain
additional information necessary to properly evaluate or particular proposal. Failure of a Proposer to
respond to such a request for additional information or clarification could result in rejection of their
proposal.
E. RESERVATION IN EVALUATION
The Selection Committee reserves the right to either: (a) request "Best and Final Offers" from the
two finalist firms and award to the lowest priced or (b) to reassess the proposals and award to the
vendor determined to best meet the overall needs of the City.
F. INTENT OF AWARD
Upon review of the proposals submitted,the City may negotiate a scope of work and a general services
agreement with one firm,or may select one or more firms for further consideration.
G. PROTEST OF AWARD
In accordance with Tigard Public Contracting Rule 30.135,any adversely affected Proposer has seven
(7) calendar days from the date of the written notice of award to file a written protest.
H. PROPOSAL REJECTION
The City reserves the right to:
1. Reject any or all proposals not in compliance with all public procedures and requirements;
2. Reject any proposal not meeting the specifications set forth herein;
3. Waive any or all irregularities in proposals submitted;
4. In the event two or more proposals shall be for the same amount for the same work,the City shall
follow the provisions of LCRB 30.095 and Section 137-095 of the Oregon Attorney General's
Model Public Contract Manual;
5. Reject all proposals;
6. Award any or all parts of any proposal; and
7. Request references and other data to determine responsiveness.
RFP—Universal Plaza Owner's Representative/Project Management Page 13
Close—August 28, 2019
SECTION 7
PROPOSAL CERTIFICATIONS
Non-discrimination Clause
The Contractor agrees not to discriminate against any client, employee or applicant for employment or for
services, because of race, color,religion, sex, national origin, handicap or age with regard to, but not limited
to,the following:employment upgrading,demotion or transfer;recruitment or recruitment advertising;layoffs
or termination;rates of pay or other forms of compensation; selection for training; rendition of services. It
is further understood that any contractor who is in violation of this clause shall be barred from receiving
awards of any purchase order from the City,unless a satisfactory showing is made that discriminatory practices
have terminated and that a recurrence of
II such acts is unlikely.
Agreed by: CU�' t' I �tGhpl
Firm Name: Shiels Obletz Johnsen
Address: 1140 SW 11th Avenue, Suite 500
Portland, OR 97205
Resident Certificate
Please Check One:
17 Resident Vendor: Vendor has paid unemployment taxes and income taxes in this state during the last
twelve calendar months immediately preceding the submission of this proposal.
Or
❑ Non-resident Vendor:Vendor does not qualify under requirement stated above.
(Please specify your state f residence: ]
Officer's signature:
r
Kcolc,Type or print officer's name: "L ► ��� `-""'r��� bl
RFP—Universal Plaza Owner's Representative/Project Management Page 14
Close—August 28,2019
SECTION 8
SIGNATURE PAGE
The undersigned proposes to perform all work as listed in the Specification section, for the price(s) stated;
and that all articles supplied under any resultant contract will conform to the specifications herein,
The undersigned agrees to be bound by all applicable laws and regulations, the accompanying specifications
and by City policies and regulations.
The undersigned,by submitting a proposal,represents that:
A) The Proposer has read and understands the specifications.
B) Failure to comply with the specifications or any terms of the Request for Proposal may disqualify
the Proposer as being non-responsive.
The undersigned certifies that the proposal has been arrived at independently and has been submitted without
any collusion designed to limit competition.
The undersigned certifies that all addenda to the specifications has been received and duly considered and
that all costs associated with all addenda have been included in this proposal:
Addenda: No. 1 through No. 1 inclusive.
We therefore offer and make this proposal to furnish services at the price(s)indicated herein in fulfillment of
the attached requirements and specifications of the City.
Name of firm: Shiels Obletz Johnsen
Address: 1140 SW 11 th Avenue, Suite 500
Portland, OR 97205
Telephone N m er:503-242-0084 Fax Number: 503-299-6769
11
By: Date:
(Signatu�
of Authnorized Official. If partnership, signature of one partner.)
Typed Name/Title: lit 1
If corporation,attest: -
-------------------- h(cot
Co or:to(. fficer)
Corporation ❑Partnership ❑ Individual
Federal Tax Identification Number(TIN): 93-1283321
RFP—Universal Plaza Owner's Representative/Project Management Page 15
Close—August 28,2019
ATTACHMENT A
CITY OF TIGARD, OREGON
ACKNOWLEDGMENT OF ADDENDA
Project Title: Owner's Representative/Project Management Services—
Tigard Universal Plaza and Fanno Creek Overlook
Close: Wednesday.August 28.2019--2:00 P.M.
I/WE HAVE RECEIVED THE FOLLOWING ADDENDA (U'none received, write `None Received):
1 Addendum # 1 rec. 8/22/19 3
2. 4.
t
Date UJ
Signature o 'Proposer
Title (9 J Issw.,
Corporate Name
RFP—Universal Plaza Owner's Representative/Project Management Page 16
Close—August 28,2019
ATTACHMENT B
CITY OF TIGARD, OREGON
STATEMENT OF PROPOSAL
Name of Consultant: Shiels ObletZ Johnsen
Mailing Address: 1140 SW 11 th Avenue, Suite 500
Portland, OR 97205
Contact Person: Kim Knox
Telephone: (503)242-0084 Fax:(503)299-6769 Email: knox@sojpdx.com
accepts all the terms and conditions contained in the City of Tigard's Request for Proposal for Owner's
Representative/Project Management Services —Tigard Universal Plaza and Fanno Creek Overlook and the
attached n al Cervices reem nt(A tachment C):
8/27/2019
Signature of authorized representative Date
CCK�c_ M1C � (503)242-0084
Type or print name of authorized representative Telephone Number
ca�6G Ivi (503)242-0084
Type or print name of person(s) authorized to negotiate contracts Telephone Number
REFERENCES
Portland Bureau of Transportation 503.823.7051
Reference#1 Telephone Number
10th & Yamhill Smartpark Garage Renovation Chris Armes
Project Title Contact Individual
Oregon Rail Heritage Foundation 503-863-4376
Reference #2 Telephone Number
Oregon Rail Heritage Center Turntable Project Roy Hemmingway
Project Title Contact Individual
City of Beaverton 503-526-2289
Reference #3 Telephone Number
Beaverton Public Safety Center Eric Oathes
Project Title Contact Individual
RFP—Universal Plaza Owner's Representative/Project Management Page 17
Close—August 28, 2019
ATTACHMENT C
CITY OF TIGARD,OREGON
PERSONAL SERVICES CONTRACT
OWNER'S REPRESENTATIVE PRO ECT MANAGEMENT SERVICES-
TIGARD UNIVERSAL PLAZA AND FANNO CREEK OVERLOOK
THIS AGREEMENT made and entered into this 156 day of October, 2019 by and between the City of
Tigard, a municipal corporation of the State of Oregon, hereinafter called City, and Shiels Obletz Johnsen,
hereinafter called Contractor.
RECITALS
WHEREAS, the City's 2019-2020 fiscal year budget provides for services related to Owners Representative
and Project Management;and
WHEREAS, City has need for the services of a company with a particular training, ability, knowledge, and
experience possessed by Contractor,and
WHEREAS, City has determined that Contractor is qualified and capable of performing the professional
services as City does hereinafter require,under those terms and conditions set forth,
THEREFORE, the Parties agree as follows:
1. SERVICES TO BE PROVIDED
Contractor will initiate services immediately upon receipt of City's notice to proceed together with an
executed copy of this Agreement. Contractor agrees to complete work that is detailed in Exhibit A,
incorporated herein by reference.
2. EFFECTIVE DATE AND DURATION
This Agreement is effective upon the date of execution and expires on September 30, 2021, unless
otherwise terminated or extended. The Parties may agree on one (1) additional year extension. The
total term of this contract cannot exceed three (3) years. All work under this Agreement must be
completed prior to the expiration of this Agreement.
3. COMPENSATION
The City agrees to pay Contractor in accordance with the fee schedule outlined in Exhibit A. The
total amount paid to the Contractor by the City may not exceed Two Hundred Fifty Thousand and
No/100 Dollars ($250,000.00). Payments made to Contractor will be based upon the following
applicable terms:
A. Payment by City to Contractor for performance of services under this Agreement includes all
expenses incurred by Contractor, with the exception of expenses, if any, identified in this
Agreement as separately reimbursable.
B. Payment will be made in installments based on Contractor's invoice, subject to the approval of
the City Manager, or designee, and not more frequently than monthly. Unless otherwise agreed,
payment will be made only for work actually completed as of the date of invoice.
C. Payment by City releases City from any further obligation for payment to Contractor for services
performed or expenses incurred as of the date of the invoice. Payment may not be considered
acceptance or approval of any work or waiver of any defects therein.
D. Contractor must make payments promptly,as due, to all persons supplying labor or materials for
the performance of the work provided for in this Agreement.
E. Contractor may not permit any lien or claim to be filed or prosecuted against the City on any
account of any labor or material furnished.
F. Contractor will pay to the Department of Revenue all sums withheld from employees pursuant to
ORS 316.167.
G. Contractor will pay all contributions or amounts due the Industrial Accident Fund from the
contractor or any subcontractor.
H. If Contractor fails,neglects,or refuses to make prompt payment of any claim for labor or services
furnished to Contractor or a subcontractor by any person as such claim becomes due, City's
Finance Director may pay such claim and charge the amount of the payment against funds due or
to become due the Contractor. The payment of the claim in this manner does not relieve
Contractor or their surety from obligation with respect to any unpaid claims.
I. Contractor will promptly, as due, make payment to any person, co-partnership, association, or
corporation, furnishing medical, surgical, and hospital care or other needed care and attention,
incident to sickness or injury, to the employees of Contractor, of all sums that Contractor agrees
to pay for the services and all moneys and sums that Contractor collected or deducted from the
wages of employees pursuant to any law, contract, or agreement for the purpose of providing or
paying for services.
J. Contractor and its employees, if any, are not active members of the Oregon Public Employees
Retirement System and are not employed for a total of 600 hours or more in the calendar year by
any public employer participating in the Retirement System.
K. Contractor must obtain, prior to the execution of any performance under this Agreement, a City
of Tigard Business License. The Tigard Business License is based on a calendar year with a
December 31 st expiration date. New businesses operating in Tigard after June 30th of the current
year will pay a pro-rated fee though the end of the calendar year.
L. The City certifies that sufficient funds are available and authorized for this Agreement during the
current fiscal year. Funding during future fiscal years is subject to budget approval by Tigard's
City Council.
4. OWNERSHIP OF WORK PRODUCT
City is the owner of and is entitled to possession of any and all work products of Contractor which
result from this Agreement,including any computations,plans,correspondence,or pertinent data and
information gathered by or computed by Contractor prior to termination of this Agreement by
Contractor or upon completion of the work pursuant to this Agreement.
5. ASSIGNMENT DELEGATION
Neither party may assign, sublet or transfer any interest in or duty under this Agreement without the
written consent of the other and no assignment has any force or effect unless and until the other party
has consented. If City agrees to assignment of tasks to a subcontract, Contractor is fully responsible
for the acts or omissions of any subcontractors and of all persons employed by them. Neither the
approval by City of any subcontractor nor anything contained herein creates any contractual relation
between the subcontractor and City. The provisions of this Agreement are binding upon and will
inure to the benefit of the parties to the Agreement and their respective successors and assigns.
6. STATUS OF CONTRACTOR AS INDEPENDENT CONTRACTOR
Contractor certifies that:
A. Contractor acknowledges that for all purposes related to this Agreement, Contractor is an
independent contractor as defined by ORS 670.600 and not an employee of City. Contractor is
not entitled to benefits of any kind to which an employee of City is entitled and is solely
responsible for all payments and taxes required by law. Furthermore,in the event that Contractor
is found by a court of law or any administrative agency to be an employee of City for any purpose,
City is entitled to offset compensation due, or to demand repayment of any amounts paid to
Contractor under the terms of this Agreement, to the full extent of any benefits or other
remuneration Contractor receives (from City or third party) as a result of said finding and to the
full extent of any payments that City is required to make (to Contractor or to a third party) as a
result of said finding.
B. Contractor is not an officer,employee,or agent of the City as those terms are used in ORS 30.265.
7. CONFLICT OF INTEREST
The undersigned Contractor hereby represents that no employee of the City, or any partnership or
corporation in which a City employee has an interest, has or will receive any remuneration of any
description from Contractor,either directly or indirectly,in connection with the letting or performance
of this Agreement, except as specifically declared in writing.
If this payment is to be charged against Federal funds,Contractor certifies that he/she is not currently
employed by the Federal Government and the amount charged does not exceed his or her normal
charge for the type of service provided.
8. INDEMNIFICATION
City has relied upon the professional ability and training of Contractor as a material inducement to
enter into this Agreement. Contractor represents that all of its work will be performed in accordance
with generally accepted professional practices and standards as well as the requirements of applicable
federal, state, and local laws, it being understood that acceptance of a Contractor's work by City will
not operate as a waiver or release.
Contractor agrees to indemnify and defend the City,its officers,employees,agents,and representatives
and hold them harmless from any and all liability,causes of action,claims,losses,damages,judgments,
or other costs or expenses,including attorney's fees and witness costs (at both trial and appeal level,
whether or not a trial or appeal ever takes place including any hearing before federal or state
administrative agencies), that may be asserted by any person or entity which in anyway arise from,
during, or in connection with the performance of the work described in this contract, except liability
arising out of the sole negligence of the City and its employees. Such indemnification will also cover
claims brought against the City under state or federal worker's compensation laws. If any aspect of
this indemnity is found to be illegal or invalid for any reason whatsoever, such illegality or invalidity
does not affect the validity of the remainder of this indemnification.
9. INSURANCE
Contractor and its subcontractors must maintain insurance acceptable to City in full force and effect
throughout the term of this contract. Such insurance must cover risks arising directly or indirectly out
of Contractor's activities or work hereunder,including the operations of its subcontractors of any tier.
The policy or policies of insurance maintained by the Contractor must provide at least the following
limits and coverages:
A. Commercial General Liability Insurance
Contractor will obtain,at Contractor's expense,and keep in effect during the term of this contract,
Comprehensive General Liability Insurance covering Bodily Injury and Property Damage on an
"occurrence" form (CG 2010 1185 or equivalent). This coverage must include Contractual
Liability insurance for the indemnity provided under this contract. The following insurance will
be carried:
Coverage Limit
General Aggregate $2,000,000
Products-Completed Operations Aggregate $2,000,000
Personal&Advertising Injury $1,000,000
Each Occurrence $1,000,000
Fire Damage (Any one fire) $50,000
B. Commercial Automobile Insurance
Contractor must also obtain, at Contractor's expense, and keep in effect during the term of the
contract, Commercial Automobile Liability coverage including coverage for all owned, hired, and
non-owned vehicles on an "occurrence" form. The Combined Single Limit per occurrence may
not be less than$2,000,000.
If Contractor uses a personally-owned vehicle for business use under this contract,the Contractor
will obtain, at Contractor's expense, and keep in effect during the term of the contract, business
automobile liability coverage for all owned vehicles on an "occurrence" form. The Combined
Single Limit per occurrence may not be less than $2,000,000.
C. Workers' Compensation Insurance
The Contractor, its subcontractors, if any, and all employers providing work, labor, or materials
under this Contract that are subject employers under the Oregon Workers' Compensation Law
must comply with ORS 656.017,which requires them to provide workers'compensation coverage
that satisfies Oregon law for all their subject workers. Out-of-state employers must provide
Oregon workers' compensation coverage for their workers who work at a single location within
Oregon for more than 30 days in a calendar year. Contractors who perform work without the
assistance or labor of any employee need not obtain workers' compensation coverage. All non-
exempt employers must provide Employer's Liability Insurance with coverage limits of not less
than$1,000,000 each accident.
D. Additional Insured Provision
All required insurance policies, other than Workers' Compensation and Professional Liability,
must name the City its officers,employees,agents,and representatives as additional insureds with
respect to this Agreement.
E. Insurance Carrier Rati
Coverages provided by the Contractor must be underwritten by an insurance company deemed
acceptable by the City. All policies of insurance must be written by companies having an A.M.
Best rating of"A-VII" or better, or equivalent. The City reserves the right to reject all or any
insurance carrier(s) with an unacceptable financial rating.
F. Self-Insurance
The City understands that some contractors may self-insure for business risks and the City will
consider whether such self-insurance is acceptable if it meets the minimum insurance requirements
for the type of coverage required. If Contractor is self-insured for commercial general liability or
automobile liability insurance, Contractor must provide evidence of such self-insurance.
Contractor must provide a Certificate of Insurance showing evidence of the coverage amounts on
a form acceptable to the City. The City reserves the right in its sole discretion to determine
whether self-insurance is adequate.
G. Certificates of Insurance
As evidence of the insurance coverage required by the contract, Contractor will furnish a
Certificate of Insurance to the City. No contract is effective until the required Certificates of
Insurance have been received and approved by the City. The certificate will specify and document
all provisions within this contract and include a copy of Additional Insured Endorsement. A
renewal certificate will be sent to the below address prior to coverage expiration.
H. Primary Coverage Clarification
The parties agree that Contractor's coverage is primary to the extent permitted by law. The parties
further agree that other insurance maintained by the City is excess and not contributory insurance
with the insurance required in this section.
I. Cross-Liability Clause
A cross-liability clause or separation of insureds clause will be included in all general liability,
professional liability,pollution,and errors and omissions policies required by this Agreement.
A certificate in form satisfactory to the City certifying to the issuance of such insurance will be
forwarded to:
City of Tigard
Attn: Contracts and Purchasing Office
13125 SW Hall Blvd.
Tigard,Oregon 97223
At the discretion of the City, a copy of each insurance policy, certified as a true copy by an
authorized representative of the issuing insurance company,may be required to be forwarded to
the above address.
Such policies or certificates must be delivered prior to commencement of the work. The procuring
of such required insurance will not be construed to limit Contractor's liability hereunder.
Notwithstanding said insurance, Contractor is obligated for the total amount of any damage,
injury,or loss caused by negligence or neglect connected with this Agreement.
10. METHOD & PLACE OF SUBMITTING NOTICE BILLS AND PAYMENTS
All notices,bills and payments will be made in writing and may be given by personal delivery,mail,or
by fax. Payments may be made by personal delivery, mail, or electronic transfer. The following
addresses will be used to transmit notices, bills,payments,and other information:
CITY OF TIGARD SHIELS BLETZ OHNSEN
Attn: Sean Farrel1v Attn: Kim Knox
Address: 13125 SW Hall Blvd Address: 1140 SW 1 Vh Ave Ste 500
Tigard,OR 97223 Portland OR 97205
Phone: 503 718-2420 Phone: 503 242-0084
Email: seang)tigard-orgov Email: knoxg,soindx.com
Notice will be deemed given upon deposit in the United States mail, postage prepaid, or when so
faxed,upon successful fax. In all other instances,notices,bills and payments will be deemed given at
the time of actual delivery. Changes may be made in the names and addresses of the person to who
notices,bills,and payments are to be given by giving written notice pursuant to this paragraph.
11. SURVIVAL
The terms, conditions, representations, and warranties contained in this Agreement survive the
termination or expiration of this Agreement.
12. MERGER
This writing is intended both as a final expression of the Agreement between the parties with respect
to the included terms and as a complete and exclusive statement of the terms of the Agreement. No
modification of this Agreement will be effective unless and until it is made in writing and signed by
both parties.
13. TERMINATION WITHOUT CAUSE
At any time and without cause,City has the right in its sole discretion to terminate this Agreement by
giving notice to Contractor. If City terminates this Agreement pursuant to this paragraph, City will
pay Contractor for services rendered to the date of termination.
14. TERMINATION WITH CAUSE
A. City may terminate this Agreement effective upon delivery of written notice to Contractor, or at
such later date as may be established by City,under any of the following conditions:
1) If City funding from federal, state, local, or other sources is not obtained and continued at
levels sufficient to allow for the purchase of the indicated quantity of services. This Agreement
may be modified to accommodate a reduction in funds.
2) If federal or state regulations or guidelines are modified,changed,or interpreted in such a way
that the services are no longer allowable or appropriate for purchase under this Agreement.
3) If any license or certificate required by law or regulation to be held by Contractor, its
subcontractors, agents, and employees to provide the services required by this Agreement is
for any reason denied,revoked, or not renewed.
4) If Contractor becomes insolvent,if voluntary or involuntary petition in bankruptcy is filed by
or against Contractor, if a receiver or trustee is appointed for Contractor, or if there is an
assignment for the benefit of creditors of Contractor.
Any such termination of this agreement under paragraph (A) will be without prejudice to any
obligations or liabilities of either party already accrued prior to such termination.
B. City, by written notice of default (including breach of contract) to Contractor,may terminate the
whole or any part of this Agreement:
1) If Contractor fails to provide services called for by this Agreement within the time specified,
or
2) If Contractor fails to perform any of the other provisions of this Agreement,or fails to pursue
the work as to endanger performance of this Agreement in accordance with its terms, and
after receipt of written notice from City, fails to correct such failures within ten (10) days or
such other period as City may authorize.
The rights and remedies of City provided above related to defaults (including breach of contract)
by Contractor are not exclusive and are in addition to any other rights and remedies provided by
law or under this Agreement.
If City terminates this Agreement under paragraph (B), Contractor will be entitled to receive as
full payment for all services satisfactorily rendered and expenses incurred,provided, that the City
may deduct the amount of damages, if any, sustained by City due to breach of contract by
Contractor. Damages for breach of contract include those allowed by Oregon law, reasonable
and necessary attorney fees, and other costs of litigation at trial and upon appeal.
15. ACCESS TO RECORDS
City will have access to such books, documents, papers and records of Contractor as are directly
pertinent to this Agreement for the purpose of making audit,examination,excerpts and transcripts.
16. HAZARDOUS MATERIALS
Contractor will comply with all federal Occupational Safety and Health Administration (OSHA)
requirements and all Oregon safety and health requirements. In accordance with OSHA and Oregon
OSHA Hazard Communication Rules,if any goods or services provided under this Agreement may
release, or otherwise result in an exposure to, a hazardous chemical under normal conditions of use
(for example, employees of a construction contractor working on-site), it is the responsibility of
Contractor to provide the City with the following information: all applicable Safety Data Sheets,the
identity of the chemical/s, how Contractor will inform employees about any precautions necessary,
an explanation of any labeling system, and the safe work practices to prevent exposure. In addition,
Contractor must label,tag, or mark such goods.
17. FORCE MAJEURE
Neither City nor Contractor will be considered in default because of any delays in completion and
responsibilities hereunder due to causes beyond the control and without fault or negligence on the
part of the parties so disenabled,including but not restricted to, an act of God or of a public enemy,
civil unrest,volcano,earthquake, fire, flood,epidemic,quarantine restriction,area-wide strike, freight
embargo,unusually severe weather or delay of subcontractor or supplies due to such cause;provided
that the parties so disenabled will within ten (10) days from the beginning of such delay, notify the
other party in writing of the cause of delay and its probable extent. Such notification will not be the
basis for a claim for additional compensation. Each party will, however, make all reasonable efforts
to remove or eliminate such a cause of delay or default and will,upon cessation of the cause,diligently
pursue performance of its obligation under the Agreement.
18. NON-WAIVER
The failure of City to insist upon or enforce strict performance by Contractor of any of the terms of
this Agreement or to exercise any rights hereunder should not be construed as a waiver or
relinquishment to any extent of its rights to assert or rely upon such terms or rights on any future
occasion.
19. HOURS OF LABOR, PAY E ,UITY
In accordance with ORS 279B.235, the following are hereby incorporated in full by this reference:
A. Contractor may not employ an individual for more than 10 hours in any one day, or 40 hours in
any one week,except as provided by law. For contracts for personal services,as defined in ORS
279A.055, Contractor must pay employees at least time and a half pay for all overtime the
employees work in excess of 40 hours in any one week, except for employees who are excluded
under ORS 653.010 to 653.261 or under 29 U.S.C. 201 to 209 from receiving overtime.
B. Contractor must give notice in writing to employees who work on a public contract, either at the
time of hire or before commencement of work on the contract,or by positing a notice in a location
frequented by employees, of the number of hours per day and days per week that the employees
may be required to work.
C. Contractor may not prohibit any of Contractor's employees from discussing the employee's rate
of wage,salary,benefits or other compensation with another employee or another person and may
not retaliate against an employee who discusses the employee's rate of wage, salary, benefits or
other compensation with another employee or another person.
D. Contractor must comply with the pay equity provisions in ORS 652.220. Compliance is a material
element of this Agreement and failure to comply will be deemed a breach that entitles City to
terminate this Agreement for cause.
20. NON-DISCRIMINATION
Contractor will comply with all federal, state, and local laws, codes, regulations, and ordinances
applicable to the provision of services under this Agreement,including,without limitation:
A. Title VI of the Civil Rights Act of 1964;
B. Section V of the Rehabilitation Act of 1973;
C. The Americans with Disabilities Act of 1990, as amended by the ADA Amendments Act
(ADA_AA) of 2008 (Pub L No 101-336);and
D. ORS 659A.142,including all amendments of and regulations and administrative rules,and all other
applicable requirements of federal and state civil rights and rehabilitation statutes, rules and
regulations.
21. ERRORS
Contractor will perform such additional work as may be necessary to correct errors in the work
required under this Agreement without undue delays and without additional cost.
22. EXTRA(CHANGES)WORK
Only the City's Project Manager for this Agreement may change or authorize additional work. Failure
of Contractor to secure authorization for extra work constitutes a waiver of all right to adjust the
contract price or contract time due to such unauthorized extra work and Contractor will not be entitled
to compensation for the performance of unauthorized work.
23. WARRANTIES
Contractor will guarantee work for a period of one year after the date of final acceptance of the work
by the owner. Contractor warrants that all practices and procedures,workmanship and materials are
the best available unless otherwise specified in the profession. Neither acceptance of the work nor
payment therefore relieves Contractor from liability under warranties contained in or implied by this
Agreement.
Any intellectual property rights delivered to the City under this Agreement and Contractor's services
rendered in the performance of Contractor's obligations under this Agreement, will be provided to
the City free and clear of any and all restrictions on or conditions of use, transfer, modification, or
assignment, and be free and clear of any and all liens, claims,mortgages, security interests,liabilities,
charges, and encumbrances of any kind.
24. ATTORNEY'S FEES
In the event an action, suit of proceeding, including appeal, is brought for failure to observe any of
the terms of this Agreement, each party is responsible for that party's own attorney fees, expenses,
costs and disbursements for the action, suit,proceeding, or appeal.
25. CHOICE OF LAW,VENUE
The provisions of this Agreement are governed by Oregon law. Venue will be the State of Oregon
Circuit Court in Washington County or the U.S.District Court for Oregon,Portland.
26. COMPLIANCE WITH STATE AND FEDERAL LAWS/RULES
Contractor will comply with all applicable federal,state and local laws,rules and regulations applicable
to the work in this Agreement.
27. CONFLICT BETWEEN TERMS
In the event of a conflict between the terms of this Agreement and Contractor's proposal, this
Agreement will control. In the event of conflict between a provision in the main body of the Agreement
and a provision in the Exhibits, the provision in the main body of the Agreement will control. In the
event of an inconsistency between Exhibit A and Exhibit B,Exhibit A will control.
28. AUDIT
Contractor will maintain records to assure conformance with the terms and conditions of this
Agreement and to assure adequate performance and accurate expenditures within the contract period.
Contractor agrees to permit City,the State of Oregon,the federal government,or their duly authorized
representatives to audit all records pertaining to this Agreement to assure the accurate expenditure of
funds.
29. SEVERABILITY
In the event any provision or portion of this Agreement is held to be unenforceable or invalid by any
court of competent jurisdiction,the validity of the remaining terms and provisions will not be impaired
unless the illegal or unenforceable provision affects a significant right or responsibility,in which case
the adversely affected party may request renegotiation of the Agreement and,if negotiations fail,may
terminate the Agreement.
30. COMPLIANCE WITH TAX LAWS
Contractor represents and warrants that Contractor is, to the best of the undersigned's knowledge,
not in violation of any Oregon tax laws including but not limited to ORS 305.620 and ORS Chapters
316, 317, and 318. Contractor's failure to comply with the tax laws of this state or a political
subdivision of this state before the Contractor executed this Agreement or during the term of this
Agreement is a default for which the City may terminate this Agreement and seek damages and other
relief available under the terms of this Agreement or applicable law.
[Signature Page to Follow]
IN WITNESS WHEREOF, City and Contractor have caused this Agreement to be executed by their duly
authorized officials. Awarded by Tigard's Local Contract Review Board at their September 24,2019 meeting.
CITY OF TIGARD SHIELS OBLETZ JOHNSEN
B BY: t GjIJ 'G 6b �-
Name: Name:
Tide: Title: -r-Ir
Date: Date: �� 7A
EXHIBIT A
SCOPE OF WORK
The Owner's Representative/Project Manager will provide sufficient organization, personnel and
management to carry out the requirements of this Agreement for both the Universal Plaza (Project 1) and
Fanno Creek Overlook (Project 2),in an expeditious and economical manner consistent with the interests of
the City. Support and staffing levels may vary significantly throughout the project duration depending on
project need.
Task 1— Project Management
1.1 Project Management and Coordination
A. The Owner's Representative shall be the point of contact for the City design team, coordinate
with A/E consultants and contractor for both the Universal Plaza (Project 1) and Fanno Creek
Overlook (Project 2).
B. In consultation with the City Project Manager(staff),manage the A/E and construction contractor
contracts and project budget. Review consultant/contractor invoicing and recommend approval
to City staff.
1.2 Master Schedule
A. The Owner's Representative shall prepare a master schedule detailing the design and construction
phases of the project,including potential phasing
B. Update the project schedule at each phase of design
C. Manage the master schedule.
1.3 Project Meetings and Communication
Provide project management support services for internal project team coordination including project
team and stakeholder meetings, and regular project updates.
A. The Owner's Representative shall prepare for and conduct a project kick-off meeting at the City
to discuss the project scope, schedule, and design team deliverables with city staff. Kick-off
meeting to last 2.5 hours.
B. Schedule and lead up design progress and project management meetings (likely monthly,but final
number to be negotiated) at the City and prepare meeting agendas and minutes. Meetings to last
up to 2 hours.
C. Participate in weekly conference call with city project team. Weekly conference calls are
anticipated to last 15 minutes.
D. Participate in up to two public open-house meetings.
E. Participate in up to three TAC meetings
F. Act as primary point of contact for adjacent property owners and other stakeholders
G. Provide regular status reports to project team
1.4 Design and Engineering Procurement
Assist in review of responses to Design and Engineering RFP and interviews.
Task 2—Plans, Specifications, and Estimates
2.1 Predesign project planning
Assist with predesign project planning and organization documentation, including templates,
recommendations, and review of scope, schedule, budget, communications, risk management, and
other project document management.
2.2 Design Phase Document Reviews
Provide review and analysis of A/E refined concept, 30%, 60%, and 90% and final construction
documents
2.3 Review Preliminary Construction Cost Estimates
Review A/E preliminary construction cost estimates at 30%, 60%, and 90% and final design
Task 3 —Land Use and Permitting
3.1 Land Use Approvals
Assist city and A/E with documentation and facilitation of timely land use review and permitting
process,including Clean Water Services permits to minimize impacts on project scope, schedule and
budget.
3.2 Permitting
Assist city and A/E with documentation and facilitation of LUR,PFI,building permit and any other
permitting processes, as required. Project 2 may require coordination with the Army Corps of
Engineers and Department of State Lands
Task 4— Pre-Construction
4.1 Design Development Cost Estimate
Provide analysis of cost estimates and oversee reconciliation of project cost estimate
4.2 Construction Cost Estimate
Provide analysis of cost estimates and oversee reconciliation of project cost estimate
4.3 Construction Phasing and Constructability review
Provide analysis of construction phasing plans and constructability reviews
4.4 Contractor Bidding and Procurement
Assist City Project Manager with bidding and procurement of construction contractor
Task 5 — Support During Construction
5.1 Weekly meetings with Contractor during construction
5.2 Change Orders
Analyze all Change Orders over designated amount, and forward to City Project Manager with
recommendations
5.3 Submittals
Facilitate a process for timely review and response to all Submittals by Architect/Engineer.
5.4 Requests for Proposals
Facilitate a process for timely review and response to all RFP's by Architect/Engineer. Monitor RFP
responses for budget and schedule implications and report to Project Manager.
5.5 Substitution Requests
Facilitate a process for timely review and response to all substitution requests submittals by
Architect/Engineer.With Architect/Engineer,make recommendations to City Project Manager.
5.6 Site Observations
Perform periodic site observations,as requested by City project manager.
5.7 Notices of deficient work
Ensure that Architect/Engineer is conducting appropriate site inspections and that Notices of
Deficiency are timely developed and delivered to Contractor and Project Team.
5.8 Code and permit compliance
Ensure that Architect/Engineer reviews,documents and site activities for compliance with applicable
codes and permits. Facilitate communication of issues to City Project Manager.
5.9 Operations and Maintenance Manual
Oversee development and review of Operations and Maintenance Manual by A/E consultant
Task 6— Project Closeout
6.1 As-built review and verifications
Provide additional review,verification and comment on as-built documentation
6.2 Project Close-out
Support project close-out, including but not necessarily limited to resolving any claims or disputes
resulting from the project and drafting required contractor report
Potential Schedule for Projects 1 & 2
Phase Time
Design/Eineerin Procurement November/December 2019
Des' /En ' ieeLiiN Contract Februar• 2020
Design Concept Refinement March 2020—April 2020
Design Aril 2020—September 2020
Construction Drawings September 2020-1 anua.l 2021
Permitting ]anuary 2021-April 2021
Construction Mav 2021-October 2021
Project Closeout November 2021- anu 2022