Resolution No. 19-38 CITY OF TIGARD, OREGON
TIGARD CITY COUNCIL
RESOLUTION NO. 19- 98
A RESOLUTION ADOPTING A WORKPLAN TO IMPLEMENT THE STRATEGIES AND
RECOMMENDATIONS OF THE TIGARD SOUTHWEST CORRIDOR AFFORDABLE HOUSING
PREDEVELOPMENT PROJECT
WHEREAS, the City of Tigard was awarded a Metro Equitable Housing Planning and Development Grant to
perform the Tigard Southwest Corridor Affordable Housing Predevelopment Project;and
WHEREAS,the Tigard Southwest Corridor Affordable Housing Predevelopment Project included a Feasibility
Assessment Report that analyzed the feasibility of building affordable senior housing on the Tigard Senior
Center site;and
WHEREAS,the City,acting on the report recommendations released a Request for Information for developers
interested in building on the site;and
WHEREAS, the City selected Northwest Housing Alternatives with which to negotiate a development
agreement;and
WHEREAS, the City has developed a work plan to guide the implementation of the project, the adoption of
which is a milestone of the grant.
NOW,THEREFORE,BE IT RESOLVED by the Tigard City Council that:
SECTION 1: The Tigard City Council hereby adopts the work plan (Exhibit A) to guide and inform the
development of affordable senior housing on the Tigard Senior Center site, which was the
result of the Tigard Southwest Corridor Affordable Housing Predevelopment Project.
SECTION 2: This resolution is effective immediately upon passage.
PASSED: This 154-A day of_Odd �e►r 2019.
ity of Tigard
ATTEST: --c ^�:•' j7%� -
City Recorder-City of Tigar
RESOLUTION NO 19-
Page 1
EXHIBIT A
Senior Center Affordable Senior Housing Work Plan
This is an estimate of timelines and milestones as the parties understand them as of September 23,
2019.
Action Anticipated Lead City
Timeline involvement
Formation of Advisory Committee September 2019 NHA
Advisory Committee meetings October 2019- NHA Participant
March 2020
Exclusive Negotiating Agreement October 2019 City Council
consideration
Negotiation of Development October 2019- City and Staff/Attorneys
Agreement and Lease January 2020 NHA negotiate
Design Charette November 2019 NHA Participant
Development Agreement/Lease January 2020 City Council
Execution consideration
Monitor Development Agreement January 2020- City and Review
May 2022 NHA Agreement
Milestones
Construction Begins April 2021 NHA
Construction Concludes May 2022 NHA