GEODESIC FIELD PORT
Page 1 of 1
GDI Project: Polygon-1 13-05 Prepared By: Ken Buckingham
Project Name: Roshak Ridge 07/08/2019
Location: SW Bull Mountain Road and SW Roy Rogers Report#: I 1 52
Road,Tigard
Arrival: 1000 Departure: 1030
Weather: Partly Cloudy, 70's Permit#: TBA
Site Visit Requested By: I Tony w/Polygon Met With (on site): Tony(Phone)
Purpose: Evaluate lots 41 and 32 subgrade
Outstanding Issues: FR-146 (06/05/2019) Soft wall subgrade
I observed crew had excavated to approx. planned subgrade elevation on lots 41 and 42. I observed the subgrade to
consist of brown silt. Using a W diameter steel foundation probe, I evaluated the relative consistency of lot the
subgrade. Probe resistance indicated generally stiff to very stiff conditions.
Lot 41 address - 14179 SW River Terrace Blvd
Lot 42 address - 14157 SW River Terrace Blvd
Based on our observations and probing, it is our opinion that subgrade observed today has been prepared in general
accordance with our geotechnical recommendations.
Distribution:
Attachments: Site Plan (1)
Reviewed by:
This report presents opinions formed as a result of our observation of activities relating to geotechnical engineering or environmental services. We rely on the contractor to comply with the plans and
specifications throughout the duration of the project irrespective of the presence of our representative. Our work does not include supervision or direction of the contractor,the contractor's employees
or agents. Our firm is not responsible for site safety. This field report is a DRAFT representation of our field observations,testing,and preliminary recommendations. The report can only be
considered final upon review of the GeoDesign project m:.nager,as indicated by initials in the"Reviewed By"section.
Signature: