Permit (24) CITY OF TIGARD BUILDING PERMIT
2±:. COMMUNITY DEVELOPMENT a , i Permit#: BUP2019-00047
13125 SW Hall Blvd.,Tigard OR 97223 503.718.2439
TIGARD •��� Date Issued: 05/23/2019Parcel: 151260000300
Jurisdiction: Tigard
Site address: 9753 SW WASHINGTON SQUARE RD D02
Project: 85C Bakery Subdivision: None Lot: None
Project Description: Tenant improvement for new bakery. 9/17/19: REPRINTED permit to reduce scope of work to interior only.
Contractor: PHILCO Owner: PPR WASHINGTON SQUARE LLC
16037 SW KELLY ST PO BOX 847
PORTLAND, OR 97236 CARLSBAD, CA 92018
PHONE: 503-427-2988 PHONE:
FAX:
FEES
Specifics:
Description Date Amount
Type of Use: COM
Class of Work: ALT Type of Const: IIA Permit Fee-Additions,Alterations, 05/21/2019 $2,615.95
Demolition
Occupancy Grp: M Occupancy Load: 117 12%State Surcharge-Building 05/21/2019 $313.91
Dwelling Units: Plan Review 03/01/2019 $1,700.37
Stories: Height: ft DC Provision Review, COM TI-Ping 05/21/2019 $388.00
Bedrooms: Bathrooms: Plan Review-Fire Life Safety 05/21/2019 $1,046.38
Value: $350,000 Info Process/Archiving-Lg$2.00(over 05/21/2019 $100.00
11x17)
Info Process/Archiving-Sm$0.50(up to 05/21/2019 $100.50
Floor Areas: 11x17)
Metro Const. Excise Tax 05/21/2019 $420.00
Total Area:
Accessory Struct:
Basement:
Carport:
Covered Porch:
Deck:
Garage:
Mezzanine:
Total $6,685.11
Required: Required Items and Reports(Conditions)
Fire Sprinkler: Parapet:
Fire Alarm: Protected Corridors:
Smoke Detectors: Manual Pull Stations:
Accessible Parking:
This permit is issued subject to the regulations contained TigardMunicipal the Munici al Code, State of OR. Specialty Codes and all other applicable law. All work will
be done in accordance with approved plans. This permit will expire if work is not started within 180 days of issuance, or if work is suspended for more the 180
days. ATTENTION: Oregon law requires you to follow the rules adopted by the Oregon Utility Notification Center. Those rules are set forth in OAR
952-001-0010 through OAR/ 952-001-0090. You may obtain a copy of the rules or direct questions to OUNC by calling 503.232.1987 or 1.800.332.2344.
11111.
Issued By: Permittee Signature: • 7.4.44."(----("?/4-1
f„„,,
all 503.639.4175 by 7:00 a.m.for the next available inspection date.
This permit card shall be kept in a conspicuous place on the job site until completion of the project.
Approved plans are required on the job site at the time of each inspection.
Branden Taggart
From: ksmith@smithco.org
Sent: Tuesday, September 17, 2019 1:32 PM
To: Branden Taggart
Cc: Tom McGuire;#Building Permit Technicians; Samuel Copelan
Subject: RE: 85c bakery WASHINGTON square - 9753 SW Washington Square Rd.
Caution! This message was sent from outside your organization.
Brandon, per our conversation, we are removing the patio and landscaping out of the scope for the permit BUP2019-
00047, 9753 SW Washington Square, 85C Bakery
We will put the existing landscaping back in its original condition.
I will have the GC go in with approved site permit drawings for you to mark-up.
Thanks for your help
keith 1. smith
principal
aii ..
603 stewart street
suite 610
wattle, washingtort 98101
206.713, 076 m
k'tnith etssrni hco.car e
WWW:$,M0419-rZ w
1 hh tomer ortgmatea from smith co,Ile tt contacts intaracn ttknn that ntay be czaralldented end is eatcnded only for the individual or entaty named
above Unless you are the sddro.ee.(or autheoa`zed to receive leer the addreasc4 you may not duclose copy,use,or thstrthute this hriarmattota
A0 p€rsors.al moss?excess v:ewe solely of the sender,wtheh are net to be attr but ta,I ith,tcr,,ft,and may not bcr.corer,or distr(bee
ed
without this t mit a.inacr. It you rook-mod this vmt.t att in error,l trate notary us insrttrdieeeIy et 1,intttlattimtttoestrz or call t2061 713..5076,
76,
ti and-or.
From:. Branden Taggart<brandent@ ov>g g
Sent: Monday, September 16, 2019 5:32 PM
To: ksmith@smithco.org
Cc:Tom McGuire<TomM@tigard-or.gov>; #Building Permit Technicians<TigardBuildingPermits@tigard-or.gov>; Samuel
Copelan <samuelc@tigard-or.gov>
Subject: RE: 85c bakery WASHINGTON square -9753 SW Washington Square Rd.
1
CITY OF TIGARD BUILDING PERMIT
COMMUNITY DEVELOPMENT Permit#: BUP2019-00047
T[GARD 13125 SW Hall Blvd.,Tigard OR 97223 503.718.2439 Date Issued: 05/23/2019
Parcel: 1S1260000300
Jurisdiction: Tigard
Site address: 9753 SW WASHINGTON SQUARE RD D02
Project: 85C Bakery Subdivision: None Lot: None
Project Description: Tenant improvement for new bakery.
Contractor: PHILCO Owner: PPR WASHINGTON SQUARE LLC
16037 SW KELLY ST PO BOX 847
PORTLAND, OR 97236 CARLSBAD, CA 92018
PHONE: 503-427-2988 PHONE:
FAX:
Specifics: FEES
Description Date Amount
Type of Use: COM
Class of Work: ALT Type of Const: IIA Permit Fee-Additions,Alterations, 05/21/2019 $2,615.95
Demolition
Occupancy Grp: M Occupancy Load: 117 12%State Surcharge-Building 05/21/2019 $313.91
Dwelling Units: Plan Review 03/01/2019 $1,700.37
Stories: Height: ft DC Provision Review,COM TI-Ping 05/21/2019 $388.00
Bedrooms: Bathrooms: Plan Review-Fire Life Safety 05/21/2019 $1,046.38
Value: $350,000 Info Process/Archiving-Lg$2.00(over 05/21/2019 $100.00
11x17)
Info Process/Archiving-Sm$0.50(up to 05/21/2019 $100.50
Floor Areas: 11x17)
Metro Const.Excise Tax 05/21/2019 $420.00
Total Area:
Accessory Struct:
Basement:
Carport:
Covered Porch:
Deck:
Garage:
Mezzanine:
Total $6,685.11
Required: Required Items and Reports(Conditions)
Fire Sprinkler: Parapet:
Fire Alarm: Protected Corridors:
Smoke Detectors: Manual Pull Stations:
Accessible Parking:
This permit is issued subject to the regulations contained in the Tigard Municipal Code, State of OR. Specialty Codes and all other applicable law. All work will
be done in accordance with approved plans. This permit will expire if work is not started within 180 days of issuance, or if work is suspended for more the 180
days. ATTENTION: Oregon law requires you to follow the rules adopted by the Oregon Utility Notification Center. Those rules are set forth in OAR
952-001-0010 through OAR 2-001-0090. You may obtain a copy of the rules or direct questions to OUNC by calling 503.232.1987 or 1.800.332.2344.
Issued By: Permittee Signature:
Call 503.639.4175 by 7:00 a.m.for the next available inspection date.
This permit card shall be kept in a conspicuous place on the job site until completion of the project.
Approved plans are required on the Job site at the time of each inspection.
City of Tigard
■ 11
COMMUNITY DEVELOPMENT DEPARTMENT
T 1 G A R D Building Permit Review — Commercial - With Land Use
Building Permit #: /3 Z1/0,2.6/9 -- 90i91 7
Site Address: 9-75:sSid L/t3f1� /c•/5.5 62. Suite/Bldg#:
Project Name: .3.5 e d;-- --X--X
(Name of commercial business occupying the space. If vacant,enter Spec Space.)
Planning Review
Proposal: '�
t :
1.. r in&Jvvi 1p4,elrlri
js,Verify site address/suite# exists and active in permit system.
j:SOZ.iver Terrace Neighborhood: ❑ Yes X No
,Land Use Case#: /7/- 2D/9 eo o O:j
g-Plans Match Approved Land Use:
Site Plan ❑ Landscape Plan ❑ Other:
❑ Urban Forestry Plan ❑ Elevation Plan
Building Height: Maximum Height Actual Height
Conditions Met: ❑ Prior to Submittal ❑ Prior to Permit Issuance
,Business License:
Exists: ❑ Yes No,applicant notified to obtain business license
Public Facilities Improvement (PFI) Permit:
Required: ❑ Yes,applicant was notified No Applied For: ❑ Yes ❑ No,stop intake
Notes:
Approved by Planning: ro
,. „ Date: 311i 11�
Revisions (after Building Submitta only) Reviewer Date
Revision 1: ❑ Approved ❑ Not Approved
Revision 2: ❑ Approved ❑ Not Approved
Revision 3: ❑ Approved ❑ Not Approved
Building Permit Submittal
Original Submittal Date: o?,a2,��/y
Site Plans: # 3
Building Plans: # -=5
Building Permit#: D--Enter building permit#above.
Workflow Routing: Planning Q.igineering I ermit Coordinator ®wilding
Workflow Sign-off: Si -off for Planning(include notes from planning review)
Route Application Documents: Wig: original permit application, site plans,building plans, engineer and
beam calculations and trust details,if applicable, etc.
Notes: -1
By Permit Technician: .., /Z�t{, Date: �/�,
I:\Building\Forms\BldgPermitRvw_COM_W ithLandUse_070915.docx
Engineering Review
❑ Slope at building pad:
❑ PFI Permit#:
❑ Conditions "Met"prior to issuance of building permit
❑ Easements (encroachments) per engineering conditions of approval and plat (not typical on SDR/CUP)
❑ Water Quality/Quantity Facility:
Assess Water Quality Fee in-lieu: ❑ Yes ❑ No
Assess Water Quantity Fee in-lieu: ❑ Yes ❑ No
LIDA Facility on lot: ❑ Yes ❑ No
❑ NOT Approved by Engineering: Date
Notes:
Approved by Engineering: ✓� Date: 3ls-7i�
Revisions (after Building Submittal only) Reviewer Date
Revision 1: ❑ Approved ❑ Not Approved
Revision 2: ❑ Approved ❑ Not Approved
Revision 3: ❑ Approved ❑ Not Approved
Permit Coordinator Review
❑ Conditions "Met"prior to issuance of building permit
❑ Approved,NOT Released: Date:
Notes:
Revisions (after Building Submittal only)
Revision Notice 1: Date Sent to Applicant:
Revision Notice 2: Date Sent to Applicant:
Revision Notice 3: Date Sent to Applicant:
q C Fees Entered: Wash Co Trans Dev Tax: ❑ Yes 42 (1/A
Tigard Trans SDC: ❑ Yes
Parks SDC: CI Yes VeA
A
OK to Issue Permit
Approved by Permit Coordinator: Al;ate: J 2
ler
1:\Building\Fonns\BldgPennitRvw_COM_W ithLandUse_0709 1 5.docx