Carlson Testing Inc. Eugene Office
Salem Office (541)345-0289
(503)589-1252
Tigard Office (503)684-3460
Special Inspection
FINAL SUMMARY LETTER
Date: April 17, 2019
Job#: T1905963
City of Tigard
13125 SW Hall Blvd
Tigard, OR 97223-8199
Attn: Building Division
Re: Project Name: Compass Oncology—Tigard Westside Cancer Center
Address: 12123 SW 69th Ave.—Tigard, OR
Permit#: BUP2018-00242
Per Chapter 17, Section 1704.1.2 of the International Building Code(IBC),we have performed special inspection of the
following item(s)per our inspection reports only:
Reinforced Concrete
Adhesive Anchors& Expansion Anchors
Structural Steel
Fireproofing
Pile Grout
Any non-compliance (NC) items recorded for each of the above inspection categories, as listed on the non-compliance
report, have been either repaired and re-inspected by CTI for compliance or reviewed and accepted by the engineer of
record for the project in the"As-Built Condition"or through an RFI.
The issuance of this final report is based on the engineer's acceptance of the NC items not specifically re-inspected by
CTI. If CTI did not provide additional review or re-inspection of those items beyond the inspections that initially generated
each of the non-compliance items, then the engineer of record has provided acceptance of the non-compliance items and
as-built conditions.
All requested inspections and tests were performed and reported according to the requirements of project documents and
to the best of our knowledge, the work was in conformance with the approved plans and specifications, approved change
orders and applicable workmanship, provisions of the State Building Code and Standards, as well as the structural
engineer's design changes, approvals and verbal instructions.
Our construction inspection and testing services were provided and intended to help reduce the risk of construction
defects, deficiencies or omissions that arose during and after construction. Our services do not constitute a warranty or
guarantee of any type. Even with diligent construction monitoring and testing, construction defects, deficiencies or
omissions in the contractor's work may exist. It is the contractor's responsibility to perform their work in accordance with
the approved construction documents.
CTI has provided its professional services with the degree of care and skill currently exercised under similar
circumstances by members of its profession in the same locale. Statements made in our reports are based on technical
judgments and should not be construed to be conclusive representations of fact. Our reports pertain to the material
tested/inspected only.
P:1Projects\Genera1120191T1905963104-17-19 Final Letter.doc Updated 11/30/11
Date: April 17, 2019
Job#: T1905963
Page 2 of 2
CTI's services did not include responsibilities related to determining, supervising, implementing or controlling the means,
methods, techniques, sequences or procedures of the construction or evaluating or reporting job conditions related to
health, safety or welfare.
Information contained herein is not to be reproduced, except in full, without prior authorization from this office. If there are
further questions regarding this matter please do not hesitate to contact this office.
Respectfully submitted,
CARLSON TESTING INC,
Steven W. Leach
Project Manager
SWL/jng
cc: McKesson Specialty Health—Rodney Villafranca RODNEY.VILLAFRANCA@MCKESSON.COM
City of Tigard Building Division—Walter'Chip' Barnett EMAILED
Corgan Associates—Steven Castaneda STEVEN.CASTANEDA@CORGAN.COM
Turner Construction Co—Bruce Reid BREID@TCCO.COM
Corgan Associates—Dennis Escobar DENNIS.ESCOBAR@CORGAN.COM
VLMK—Brian Dubai BRIAND@VLMK.COM
VLMK—Trent Nagele TRENT@VLMK.COM
Carlson Testing, Inc. •
Incompleted Items List (NCL)
Apr 17,20I9
T1905963.
Project Name: COMPASS ONCOLOGY - TIGARD WESTSIDE CANCER CENTER
Project Address: 12123 SW 69TH AVE TIGARD OR
Permit No: BUP2018-00242
P.O.No: 47722-0000000436 Project Manager: STEVEN W. LEACH
Item# Insp. Date Item Description Compliance CTI Sign-Off Date
Corrected
1 Al 01/24/2019 NO WELDING PROCEDURE RECEIVED AND REVIEWED KEITH R. GAUVIN 04/17/2019
DURING 01/30/19
INSPECTION BY CTI
REPRESENTATIVE C. DEPUY.
2 DEL 02/27/2019 APPROVED FIREPROOFING SUBMITTAL WAS NOT ON HAND APPROVED FIREPROOFING KEITH R. GAUVIN 04/17/2019
FOR REVIEW AND USE DURING INSPECTION. SUBMITTAL RECEIVED AND
REVIEWED.
3 DEL 02/27/2019 FP APPLIED W/O REQUIRED SUBSTRATE VERIFICATION ACCEPTABLE PER LOAD KEITH R. GAUVIN 04/17/2019
INSPECTION. REQUIRES ARCHITECT'S REVIEW. TESTING.
CC:MCKESSON SPECIALTY HEALTH - RODNEY VILLAFRANCA
CITY OF TIGARD BUILDING DIVISION - WALTER 'CHIP' BARNETT
CORGAN ASSOCIATES - STEVEN CASTANEDA
TURNER CONSTRUCTION CO - BRUCE REID
CORGAN ASSOCIATES - DENNIS ESCOBAR Page: 1