Report (2) Bend Office (541)330-9155
Geotechnical Office (503)601-8250
Carlson Testing, Inc. Eugene Office (541)345-0289
Salem Office (503)589-1252
Tigard Office (503)684-3460
Special Inspection �t ' 0\Q —CSO 104-0
FINAL SUMMARY LETTER
November 27, 2018 aq .
Job#: T1805169
City of Tigard fit
13125 SW Hall Blvd
Tigard,OR 97223-8199
Attn: Building Division
Re: Project Nam • Din Tai Fung Washington Square
Address 9585 SW Washington Rd—Tigard, OR
Permit#: BUP2018-00140
Per Chapter 17,Section 1704.1.2 of the International Building Code (IBC),we have performed special inspection of the following
item(s)per our inspection reports only:
Reinforced Concrete
Structural Steel
All requested inspections and tests were performed and reported according to the requirements of project documents and to the best of
our knowledge, the work was in conformance with the approved plans and specifications, approved change orders and applicable
workmanship, provisions of the State Building Code and Standards,as well as the structural engineer's design changes,approvals and
verbal instructions.
Our construction inspection and testing services were provided and intended to help reduce the risk of construction defects,
deficiencies or omissions that arose during and after construction_ Our services do not constitute a warranty or guarantee of any type.
Even with diligent construction monitoring and testing, construction defects, deficiencies or omissions in the contractor's work may
exist. It is the contractor's responsibility to perform their work in accordance with the approved construction documents.
CTI has provided its professional services with the degree of care and skill currently exercised under similar circumstances by members
of its profession in the same locale. Statements made in our reports are based on technical judgments and should not be construed to
be conclusive representations of fact. Our reports pertain to the material tested/inspected only.
CTI's services did not include responsibilities related to determining, supervising, implementing or controlling the means, methods,
techniques,sequences or procedures of the construction or evaluating or reporting job conditions related to health,safety or welfare.
Information contained herein is not to be reproduced, except in full, without prior authorization from this office. If there are further
questions regarding this matter please do not hesitate to contact this office.
Respectfully submitted,
CARLSON TESTING INC.
Doug Loftesness
Project Manager
DUks
cc: Din Tai Fung—David Wasielewski
KPFF—Travis Smith
Chin-Ley Reche Associates—Sergio Chin-Ley
Emerick Construction Co—Paul Miller
Paragon Construction Consulting—Mike Kimmi
P:\Projects\General\Final Letter Forms\New Final Letter Templates\City of Tigard.doc Updated 11/30/11