Report (22) GeoP _ \1---1--4 v C ", .-
Engin+eering.inc.
Real-World Geotechnical Solutions 14835 SW 72nd Avenue Tel (503) 598-8445
Investigation • Design •Construction Support Portland, Oregon 97224 Fax(503) 941-9281
DAILY FIELD REPORT
PROJECT DATE
72nd Avenue Apartments 9/17/2018
PROJECT NUMBER WEATHER
17-4626 Clear,70°F
CLIENT CONTRACTOR
Hill Architects DBEC
PERMIT NUMBER PAGE#
1 of 2
Inspection Notes: (Include location,testing data,substitutions/deviations,materials,and methods of construction,conformance statement,etc.)
TYPE OF OBSERVATION:
Stripping Inspection, Basement Demo, Heating Oil Tank Removal, Septic Tank Removal
GeoPacific geologist Ben Cook onsite to observe site demolition, stripping, and preparation for structural fill materials.Currently
the contractor has removed the existing homes, and in the process a septic tank was encountered for each. In addition, the
north home contained a buried heating oil tank. The contractor is working with an environmental firm regarding proper removal
of the septic and heating oil tank. It is my understanding that they were given the ok to backfill both septics, however the heating
oil tank is only approved to backfill the lower half. The excavation areas and depths of each is approximately as follows:
• Heating Oil Tank Removal, south side of northern house. Digout following removal of contaminated soil = 17'x17x16'.
Exposed soils consist of stiff, moist, apparent native, brown SILT(ML). Some bluish remnant left, environmental firm
conducting testing of sidewalls currently.
• Septic at northern house, southwest corner of the house. Digout following removal =7'x6'x6'. Exposed soils consist of
stiff, moist, apparent native, brown SILT(ML).
• Septic at southern house, northwest corner of the house. Digout following removal =approximately 7'x6'x6'. Exposed
soils consist of stiff, moist, apparent native, brown SILT(ML).
The noted areas were cleaned of loose soil exposing competent apparent native soils, and appeared adequate for placement of
backfill material. The contractor indicated that they can import either%"-0 or 1.5"-0 crushed aggregate to backfill, and I
suggested either is fine, as long as there is no more than approximately 10% by weight passing the U.S. No. 200 sieve.
While onsite the contractor was also preparing the rear parking lot subgrade for fill placement. Approximately two feet of
engineered fill is needed to reach design subgrade elevation. The area was heavily vegetated and terraced, and had consisted
of garden and back yard areas. The elevation was uneven at the time I arrived, but the contractor worked to scarify, aerate,
moisture condition, level, and recompact the subgrade. A wet area was encountered on the northeastern corner of the parking
lot where irrigation systems had been. Several French drain pipes, a 4 inch metal culvert, and haphazardly constructed
drainage network of rounded gravel was encountered across the area. The contractor is removing the drains as encountered.
Following bulk removal of organics and yard debris,the exposed soils consisted of apparent native, damp, medium stiff to stiff,
SILT. I observed a dozer with a large rake ripping the existing subgrade on the order of 24 inches deep, and the contractor
using a hose attached to a hydrant to spray down dry dirt, and blend to optimum moisture. The contractor needs the rest of the
day to finish preparing and compacting the subgrade soils.
In general site demolition and preparation is well under way. Debris has been stockpiled in the center of the site and is being
loaded into trucks and removed.
DISTRIBUTION LIST: OBSERVED BY: B.Cook
Anders Otterlei,Anders.Otterlei u@hillarchitects.com
Robert Leger, rlegeredci-engineers.com
Geff Halle, GeffH(u�keywaycorp.com
Ken Dykes, ken c(�.digdbec.com REVIEWED BY: J. Imbrie
Doug Weeks, dougwa.digdbec.com
GeoPacific Engineering, Inc. Signature
Information contained herein pertains to materials tested/inspected only. The fact that any particular work has been observed or tested does not waive
the contractor's responsibility for the means and methods of construction,job site safety,or to comply with the contract documents. This information
contained herein should be considered preliminary until review by the project engineer.
GeoPacific
Engtneering,tnc.
Real-World Geotechnical Solutions 14835 SW 72nd Avenue Tel (503) 598-8445
Investigation • Design •Construction Support Portland,Oregon 97224 Fax(503)941-9281
DAILY FIELD REPORT
PROJECT DATE
72nd Avenue Apartments 9/19/2018
PROJECT NUMBER WEATHER
17-4626 Clear,70°F
CLIENT CONTRACTOR
Hill Architects DBEC
PERMIT NUMBER PAGE#
1 of 2
Inspection Notes: (Include location,testing data,substitutions/deviations,materials,and methods of construction,conformance statement,etc.)
TYPE OF OBSERVATION:
Site Stripping, Engineered Fill Placement
GeoPacific geologist Ben Cook onsite to observe continued removal of debris from the site, and placement of engineered fill in
the eastern side parking area, as well as the southern portion of the building envelope.
Upon arrival to the site the contractor had essentially removed the building and landscaping debris from the site and the central
stockpile continued to be hauled off. It appeared that the areas surrounding the stockpile were adequately stripped. As
mentioned yesterday, existing subgrade soils for the parking area were adequately prepared and the contractor began
engineered fill placement. In addition,the contractor prepared subgrade where the site steps and terraces to the west, along the
southeastern to south-central portion of the site which includes the driveway along the southern portion of the site, as well as the
southern portion of the building. Exposed subgrade soils consisted of stiff, moist, SILT. The contractor scarified and
recompacted the soils using a Dynapac front drum, vibratory, sheeps-foot compactor. Following recompaction of the existing
subgrade a 12 inch lift of onsite SILT soil was placed across the eastern parking lot, and the southern portion of the building
envelope. Following compaction of the initial lift nuclear density testing was conducted relative to 90%AASHTO T-180.
Passing moisture and density test results were achieved at the locations tested and are reported on the Density Test Data Sheet
dated 9/19/2018.
DISTRIBUTION LIST: OBSERVED BY: B. Cook
Anders Otterlei, Anders.Otterlei@hillarchitects.com
Robert Leger, rleger(adci-engineers.com
Geff Halle, GeffH(a�kevwaycorp.com REVIEWED BY: J. Imbrie
Ken Dykes, ken(a�digdbec.com
Doug Weeks, dougwa(�digdbec.com
GeoPacific Engineering, Inc. Signature
Information contained herein pertains to materials tested/inspected only. The fact that any particular work has been observed or tested does not waive
the contractor's responsibility for the means and methods of construction,job site safety,or to comply with the contract documents. This information
contained herein should be considered preliminary until review by the project engineer.
GeoPacific
Engineering,inc.
Real-World Geotechnical Solutions • 14835 SW 72"d Avenue Tel (503) 598-8445
Investigation •Design •Construction Support Portland, Oregon 97224 Fax(503) 941-9281
AILY FIELD REPORT
PROJECT DATE
72"d Avenue Apartments 9/18/2018
PROJECT NUMBER WEATHER
17-4626 Clear,70°F
CLIENT CONTRACTOR
Hill Architects DBEC
PERMIT NUMBER PAGE#
1 of 2
Inspection Notes:(Include location,testing data,substitutions/deviations,materials,and methods of construction,conformance statement,etc.)
TYPE OF OBSERVATION:
Structural Backfill, Parking Area Subgrade Preparation
GeoPacific geologist Ben Cook onsite to observe compaction of structural backfill in the septic and heating oil tank removal
excavations, compaction and preparation of parking area subgrade in the eastern portion of the site, and general site demolition
and preparation.
The contractor is importing 1.5"-0 crushed aggregate from Tigard Sand and Gravel to backfill the septic and heating oil tank
excavations. I collected a sample for a proctor and sieve tests. The sample will be submitted for AASHTO T-180. The
contractor was filling the holes in 12-inch lifts, adding water with a hose, and using a diesel sled plate compactor attached to the
end of an excavator to lower it in the hole and compact the aggregate. Because the heating oil and septic tank excavations
were too deep to safely enter to conduct nuclear density testing, visual observations of compaction were conducted until the fill
reached an elevation where I could safely enter, near approximately+4 feet on each septic. I observed 4 feet of aggregate
visually compacted to a dense non-yielding condition which appeared adequate. Upon achieving testable elevations passing
nuclear density test results were achieved relative to 95%AASHTO T-180. Both septic tanks were filled with 6 feet of crushed
aggregate and brought to finish grade for those locations. The heating oil tank area was filled with approximately 6 feet of
crushed aggregate, but the contractor needs to stop and wait for more environmental testing before continuing backfilling. There
is approximately 6 more feet of fill to place for the heating oil tank excavation.
While onsite the contractor completed moisture conditioning and recompacting the subgrade soils for the east side parking lot
subgrade. The scarified and recompacted grade appeared to contain near optimum moisture and was compacted to a dense,
non-yielding condition. Nuclear density testing was conducted relative to 90%AASHTO T-180 on the recompacted subgrade,
and passing test results were achieved. The eastern parking lot area subgrade appears to have been adequately reworked and
compacted, and is suitable for placement of engineered fill. Approximately two feet of onsite native engineered fill soil will be
placed.
The debris pile is continued to be hauled off but is currently occupying the central portion of the site. Following final removal of
the pile is needed to open up the central portion of the site for continued grading.
DISTRIBUTION LIST: OBSERVED BY: B. Cook
Anders Otterlei, Anders.Otterlei(a.hillarchitects.com
Robert Leger, rleoeraa..dci-engineers.corn
Geff Halle, GeffH(a�kevwavcorp.com
Ken Dykes, ken( .digdbec.com REVIEWED BY: J. Imbrie
Doug Weeks, dougwCa.digdbec.com
GeoPacific Engineering, Inc. Signature
Information contained herein pertains to materials tested/inspected only. The fact that any particular work has been observed or tested does not waive
the contractor's responsibility for the means and methods of construction,job site safety,or to comply with the contract documents. This information
contained herein should be considered preliminary until review by the project engineer.