Loading...
Report (62) .C\S5- 2 cP-- Uc\c Sova ,• -\ St, perlo � CONSTRUCTION 6955 SW Sandburg NOV `ff ?018 Preliminary Budget .! ' , 1,7/10/2018 . .1 .1 ,� , t , Vrs`,1, DESCRIPTION QUANTITY UNIT PRICE TOTAL PRICE BUILDING AND SITE MODIFICATIONS ON SITE SUPERVISION 5 WK $ 3,600.00 $ 18,000 SITE MODIFICATIONS SAWCUT EXISTING AC 80 LF $ 7.00 $ 560 REMOVE AND HAUL OFF BRUSH AND PLANTINGS 565 SF $ 10.00 $ 5,650 STRIP SITE SOIL 565 SF $ 3.50 $ 1,978 HAUL OFF STRIPPINGS 14 CY $ 100.00 $ 1,400 CUT AND FILL 57 CY $ 25.00 $ 1,425 FINISH GRADING 565 SF $ 3.00 $ 1,695 CAST IN PLACE CURBS 38 LF $ 30.00 $ 1,140 4"AC PAVING PATCH 565 SF $ 6.00 $ 3,390 8"PAVING BASE ROCK 19 CY $ 75.00 $ 1,425 NEW DRIVE THROUGH DOOR $ - SAWCUT FOR DOOR OPENING 168 SF $ 22.50 $ 3,780 STRONGBACKS AT DOOR OPENING 34 SF $ 95.00 $ 3,230 NEW 12'x 14'DOOR 1 EA $ 3,500.00 $ 3,500 MOTOR OPERATOR WITH POWER CONNECTION 0 EA $ 3,500.00 $ - TOUCH UP PAINT AT DOOR 168 SF $ 4.50 $ 756 PAINT OH DOOR 1 EA $ 350.00 $ 350 INTERIOR DEMOLITION DEMO EXISTING STAIRS 1 EA $ 1,250.00 $ 1,250 DEMO SHOP AREA 8,050 SF $ 4.00 $ 32,200 DEMO FIRST FLOOR OFFICES 7,650 SF $ 3.50 $ 26,775 DEMO SECOND FLOOR OFFICES 1,125 SF $ 4.00 $ 4,500 DEMO MEZZANINE STRUCTURE 6,850 SF $ 5.00 $ 34,250 STAIR MODIFICATIONS MODIFY ENTRY STAIR ALLOWANCE 1 EA $ 20,000.00 $ 20,000 NEW GUARDRAIL AT EXISTING STAIRS 1 EA $ 2,500.00 $ 2,500 NEW BUILD OUT MODIFY EXISTING RESTROOM ALLOWANCE 300 SF $ 85.00 $ 25,500 NEW FULL HEIGHT WALL 1,000 SF $ 10.00 $ 10,000 MEP SAFE OFF 24,775 SF $ 0.75 $ 18,581 MODIFY FIRE SPRINKLER DROPS 2,250 SF $ 1.75 $ 3,938 NEW LIGHTING AT OLD MEZZANINE LOCATION 6,850 SF $ 3.00 $ 20,550 LOW VOLTAGE CABLING 0 SF $ 1.50 $ - $ - CONTINGENCY NOT INCLUDED 0 LS $ - $ - ARCH AND ENGINEERING NOT INCLUDED 0 LS $ - $ - PERMITS NOT INCLUDED 0 LS $ - $ - GENERAL CONDITIONS 1.50 MO $ 12,478.33 $ 18,718 SUBTOTAL $ 267,040 CONTRACTORS FEE 6.5% $ 17,358 GENERAL LIABILITY INSURANCE 1.15% $ 3,271 TOTAL $ 287,668 CLARIFICATIONS AND EXCLUSIONS •We have not included architecture and engineering. ��'� •We have not included permits and jurisdictional fees. 5%of the project cost is typical. °e C' •We have not included low voltage systems or equipment. OW 071018 Pape New Building Modifications 1 7/11/2018