Dear Mr. Shields:
MST2017-00253 LIDA Revision
Here are the revisions to the LIDA for this project. I have included your last email
containing the Engineering comments for reference.
The specific changes are as follows (per guidelines noted in the Engineering
response):
1. Previous LIDA area was too small. New LIDA area is 159 square feet.
2. The LIDA facility will connect to a public storm sewer that outfalls to Fanno
Creek (SUB2018-00002). This is an acceptable storm drainage solution per
Mr. Khoi Le; his email response from 4/19/2018 included for reference.
Hopefully, this revision adequately meets the project's LIDA requirements.
Best regards,
Albert Shields<albert@tigard-or.gov> 4/9/2018 4:09 PM
MST2017-00253; LIDA Revision
To LVICustom@gmail.com <Ivicustom@gmail.com> •chingtai@comcast.net<chingtai@comcast.net> Copy
Jonny Gish <jonny@tigard-or.gov>
Dear Ms. Hsu and Vadim: Upon reviewing the modified LIDA plans that you submitted on March 29, 2018,
Engineering had the following comments:
"HSU SFR: MST2017-00253—The applicant will need to revise the LIDA to meet CWS standard. Specifically,the
LIDA is too small and will need to be at least 158 square feet(2640 X .06). Additionally, Branden will be putting a
parcel tag to ensure that when the full development project(6 lot Subdivision)is complete,this house will be
required to connect to public storm on SW 76th,which will be built by the subdivision (Per Mark). Therefore,the
LIDA will need to have drainage outlets on the east and west side of the LIDA. The east side will be operable,
while the west side needs to be capped until they can connect to public storm. "
Please revise and re-submit plans for the LIDA accordingly and please let me know if you have any questions.
Albert Shields
City of Tigard
Permit Coordinator
.,,rf
13125 SW Flail Blvd.
Tigard,Oregon 97217
www.tigard-or.gov
DISCLAIMER: E-mails sent or received by City of Tigard employees are subject to public record laws. If
requested, e-mail may be disclosed to another party unless exempt from disclosure under Oregon Public Records
Law. E-mails are retained by the City of Tigard in compliance with the Oregon Administrative Rules "City General
Records Retention Schedule."
• Albert Shields.vcf(2 KB)
• image001.jpg (12 KB)
Khoi Le<khoi@tigard-or.gov> 4/19/2018 3:27 PM
RE: Hsu Subdivision Completeness Review
To Chingtai Hsu <chingtai@comcast.net>•Gary Pagenstecher<garyp@tigard-or.gov> •
Albert Shields<albert@tigard-or.gov>
Please see my response below.
From:Chingtai Hsu<chingtai@comcast.net>
Sent: Monday,April 16, 2018 12:31 PM
To:Gary Pagenstecher<Garyp@tigard-or.gov>; Khoi Le<khoi@tigard-or.gov>;Albert Shields<albert@tigard-
or.gov>
Subject: Re: Hsu Subdivision Completeness Review
Hi Gary, Khoi, Jonny, Mark, and Al,
I met my engineer today to discuss your comments for my application.
On extending public sanitary sewer southwards on SW 76th.
• Existing sewer at manhole is 6 ft deep. Taking into account the north-south grade of 76th
and the requested sewer line angle, the extension would have a depth —4 ft in front of Lot
1. My engineer believes this is too shallow to be of practical use by any future
development south of that point. Is your assessment different? Sewer extension will be
required.
• Lot 1 sewer is already connected to the existing 8" east-west extension from the
manhole. The existing lateral will cross the newly recreated parcel and will need to be
relocated.
On storm water management.
• My engineer assesses natural flow is to Fanno Creek based on topography.
• If I obtained an easement from the property owner east of the subdivision to outfall to
Fanno Creek, is that an acceptable solution? This is an acceptable solution.
Thanks,
Diane Hsu.
On April 12,2018 at 1:43 PM Gary Pagenstecher<Garyp(avtigard-or.gov>wrote:
Diane,
Please find attached the city's completeness review for your proposed subdivision. A hard copy has
been placed in the mail today.
Let us know if you have any questions.
Thank you,
Gary