October 11, 1988
Sarah M. Tentau
Westwood Corporation
3030 S.W. Moody
Portland, Oregon 97201
RE: It's Country
Tigard Towne Square - Suite 0
16200 S.W. Pacific Hwy.
Tigard, Oregon 97224
Dear Sarah:
A fire and life safety plan review was conducted on the above captioned
project for compliance with the 1985 editions of the Uniform Building Code
(UBC), Uniform Mechanical Code (UMC), and Uniform Fire Code (UFC) as amended
by Tualatin Rural Fire Protection District's Ordinance 86 -5.
Plans are approved conditional to the following items:
1. Exit Door Hardware: All doors shown on the drawings must be openable
from the inside for immediate exit at all times without the use of a
key, special knowledge, or effort. (UBC Sec. 3304)
2. Firestopping: In all wood framed walls and partitions, firestopping
consisting of 2 -inch nominally -sized lumber or other approved
materials must be installed at all floor and ceiling levels.
Penetrations in this prescribed firestopping to accommodate wiring,
plumbing. and .other similar utility runs must be packed with
noncombustible materials in an approved manner so as to prevent the
passage of flame. (UBC Sec. 2516)
3. Fire Extinguisher Required: A fire extinguisher having a minimum
rating of 2A10B:C must be placed in an accessible location within
plain view. (UFC Sec. 10.301(a))
4. Approved Plans on Job Site: One set of approved plans bearing the
stamps of the Tigard Building Department and this office must be
maintained on the project site throughout all phases of construction
and must be made available to building and fire inspectors for
reference during required construction inspections. (UBC Sec. 303)
4755 S.W. Griffith Drive • P.O. Box 4755 • Beaverton, Oregon 97076 • (503) 526 -2469
Sarah M. Tentau
October 11. 1988
Page 2
5. Inspections Required: Inspection and approval of construction by a
representative of this office is required: (a) prior to the cover of
any new framing elements following the installation of all utility
runs which will be concealed within wall and partition cavities; (b)
upon completion of construction and prior to occupancy of the tenant
space. (UBC Sec. 305)
6. Certificate of Occupancy Required: Prior to the use and occupancy of
the project (space), a certificate of occupancy or other written
instrument of approval must be obtained from the City of Tigard
Building Department. (UBC Sec. 307)
SPECIAL NOTICE:
DEVIATIONS FROM THE SUBMITTED AND HEREBY CONDITIONALLY APPROVED PLANS
DURING THE COURSE OF CONSTRUCTION, EXCLUSIVE OF THOSE NECESSARY TO
COMPLY WITH FIRE SAFETY REQUIREMENTS AS LISTED HEREIN, ARE PROHIBITED
WITHOUT THE WRITTEN AUTHORIZATION OF THE WASHINGTON COUNTY BUILDING
DEPARTMENT AND THIS OFFICE.
APPROVAL OF SUBMITTED PLANS IS NOT AN APPROVAL OF OMISSIONS OR
OVERSIGHTS BY THIS OFFICE OR OF NON- COMPLIANCE WITH ANY APPLICABLE
REGULATIONS OF LOCAL GOVERNMENT.
If I can be of any further assistance to you, please feel free to contact me
at 526 -2502.
Sincerely, III
Gene Birchill
Deputy Fire Marshal
GB:kw /
cc: Tigard Building Department l/
CITY OF TIGA RD
OREGON
October 10, 1988 \\\„..<
Linda Jones
Westwood Corporation
PROJECT: Tigard Town Square Shops A
It's Country, BP882001
Cianci's Videoland, BB 881983
Dear Ms. Jones:
Plans for this project have been reviewed for conformity with applicable codes
and are approved. We note that the mechanical and plumbing plans will be
separately submitted.
If we may be of assistance, or if you have any questions, contact us at any
time.
Sincerely,
Jim Jaqu.
Plans Examiner
cs/7476D