Report (4) CE0DESIGN= FIELD REPORT Page 1 of 1 GDI Project: Polygon-129-03 Prepared By: Kyle Hanson Project Name: River Terrace East Date: May 25,2018 Location: SW Scholls Ferry&Roy Rogers,Bvrtn. Report#: 230 Arrival: 1100 Departure: 1130 Weather: Sunny,70's Permit#: TBD Site Visit Requested By: Ken w/Polygon Met With(on site): Earthwork crew on site Purpose: 6ubgrade observation,Lots 11:0412 Outstanding Issues: Proof roll road and curb base rock and repair as needed before paving FR-58(12/06)-Decommission temporary storm and sewer lines through Tract E FR-177-Soft fill from slope CUT in lots 153, 154 and 155 FR-223-Large roots/organic wooden debris within lot 165 subgrade FR-226-Wooden debris within lot 104 footing subgrade I observed subgrade for lots 107 through 112 where indicated on the attached site plan. Subgrade appeared to generally consist of moist brown silt that was firm/unyielding underfoot. Approximately 2"of crushed rock granular base had been placed over the observed subgrade area. I used a W diameter steel foundation probe to evaluate the consistency of the subgrade material and observed probe penetrations indicated stiff to very stiff subgrade conditions today. Based on observations and probing,it is our opinion that the subgrade observed today,where indicated-on the attached site plan,has been prepared in general accordance with our geotechnical recommendations. Distribution: Attachments:Site Plan(1) Reviewed by: r/ / spa report presents throughout hoour the fordoed a plt rof our obsratve the of proarro erf ngour toe reseed Live.Our gd ores mrirnudnwle supervision service,or rets on the contra to comply witne the ems and specifications duuughout tthe duration of the project irrespective of the presence of test represenptlue.Our vnric dors not include supervision direction theofcontractor,the contractor's employees or agents.Our firm b not responsible for site safety.The field report is a DRAFT representation of our field observations,testing.and preliminary recommendations.The report can only be considered final upon review of the Ceooesign project manager,as indicated by initials in Me'Aevowe-i ay'section ./ats I Signature: 0 0 9450 SW Commerce Circle,Suite 300 I Wilsonville,OR 97070 1503.968.8787 I www.geodeslgninc.com C - "RIVER TERRACE EAsr ‘t ii0,4 4 vi. ft c4,, •, ?-7ila..A st Larlw HUB AND TACK CERTIFICATION NE & SE 1/4 SEC. 6, T 2 S, R 1 W, VV.M. CITY OF 11GARD, WASHINGTON COUNTY, OREGON SURVEYED APRIL 26, 2018 PREPARED OR: POLYGON NORTHWEST COMPANY SW BIRDSONG STREET 703 BROADWAY ST., SUITE 510 VANCOUVER, WA. 98660 In N 6' PUBLIC UTILITY EASEMENT \ N89•58'43''W 53,00' - - ----- -- ---- - -- -- - -- - - - - -- - - -- - - - - - 0 0• 4:) .CY$ 0' SO, N (V ; i---" --- < -Nt 01 . o b 6- 0) tri 00,__....... ,._ cb LOT 5' 1,j LOT --.--11.00' LOT 109 *- 110 t.a. 171 I- a — I— h T-- , w 0 .. z 0. 0 vx . r;- 00 Z 0 13. z • „12 f..) REGISTERED '6) b 4) , PROFESSIONAL o . cNi LAND SURVEYOR 7 to —• I 1 \ ... .., OREGON S89`58'43'T 53.00' JULY 9,2002 ...- ›,. TRAVIS C.JANSEN (rii) 57751 = ..c, 0 RENEWS:6/30/2019 ,-- I TRAVIS C. JANSEN, A REGISTERED PROFESSIONAL LAND SCALE 0 10 20 ?at SURVEYOR ITHE STATE OF OREGON, HEREBY CERTIFY THAT 20 osa. I HAVE ACCURATELY SURVEYED AND STAKED THE OFFSETS TO THE FOUNDATION ENVELOPE FOR LOT 110 OF THE PLAT 1 INCH = 20 FEET OF "RIVER TERRACE EAST”, i," 2 f DRAWN BY: 12 DATE: 5/21/18 PACIFIC COMMUNITY DESIGN REVIEWED BY. TCJ DATE: 5/21/18 , z PLANNING - ENGINEERING - SURVEYING , k PROJECT NO.: 395-041 \,.. (503) 941-9484 1 L