Report (5) [DESIGN= FIELD REPORT J Page 1 of 1 GDI Project: Polygon-129-03 Prepared By: Kyle Hanson iO Project Name: River Terrace East Date: May 25,2018 Location: SW Scholls Ferry&Roy Rogers,Bvrtn. Report#: 230 Arrival: 1100 Departure: 1130 ) Weather: Sunny,70's Permit#: , TBD Site Visit Requested By: Ken w/Polygon Met With(on siteEarthwork crew on site 6 Purpose: Subgrade observation,Lots 107-112' Outstanding Issues: Proof roll road and curb base rock and repair as needed before paving J FR-58(12/06)-Decommission temporary storm and sewer lines through Tract E FR-177-Soft fill from slope cut in lots 153, 154 and 155 . ' : FR-223-Large roots/organic wooden debris within lot 165 subgrade FR-226 Wooden debris within lot 104 footing subgrade I observed subgrade for lots 107 through 112 where indicated on the attached site plan. Subgrade appeared to generally consist of moist brown silt that was firm/unyielding underfoot. Approximately 2"of crushed rock granular base had been placed over the observed subgrade area. I used a W diameter steel foundation probe to evaluate the consistency of the subgrade material and observed probe penetrations indicated stiff to very stiff subgrade conditions today. Based on observations and probing,tt.is our opinion.tbwt tl.:e subgrade observed toclay,where.indicatedonthe attached site plan,has been prepared in general accordance with our geotechnical recommendations. Distribution: Attachments:Site Plan(1) Reviewed by: Tho report presents opinions formed as a result of aur observation of activities relating to geotnchni al engmeering or environmental services.We rely on the contractor to comply with the plans and specifications throughout the duration of the project irmpecmre of the presence of our reprenentutoe,.Our work does not Include supervision ordirection of the contractor,the contractor's employees or aunts.Our firm is not responsible for site safety.This field report is a DRAFT representation of.rot field observations,testing,and preeminent recommendations.The report can only be considered final upon review of the GeoDesign project manager,as indicated by Initials in We lievIcred ay'section Signature: /'1< 9450 SW Commerce Circle,Suite 300 I Wilsonville,OR 97070 1503.968.8787 I www.geodeslgninc.com vv-s \--ra-TArei- Dc=P 172—\ "RIVER TERRACE EAST' tli 'CU r:, ,N,3 LOT 111 HUB AND TACK CERTIFICATION NE & SE 1/4 SEC. 6, T 2 S. R 1 W, W.M. CITY OF TIGARD, WASHINGTON COUNTY, OREGON SURVEYED APRIL 26, 2018 PREPARED FOR: POLYGON NORTHWEST COMPANY SW BIRDSONG STREET 703 BROADWAY ST., SUITE 510 VANCOUVER, WA. 98660 — — * — 70) 04 N89'58'43"W 45.00' . 4k .....1 c.o.. S to ... t 6' PUBLIC UTILITY„../ P EASEMENT 1 I 4 A 0 0 b , . C4 6 o V) 0 0) 5.04*--6-: - 14.1 - LOT a LOT to LOT _ N 110 z— 111 r.. 112 m , , w p x 0 0 . , 0 0 Z 0 Z 0 4. ...= 0 tE f REGISTERED 1 . PROFESSIONAL v U N. ... LAND SURVEYOR , tn fr) C.4 (0, g5.. .4007* ,--. ..1 OREGON . ,--s; JULY 9,2002 S89*513`43*E 45.00' ...e TRAVIS C.JANSEN 57751 .9▪ .- RENEWS:6/30/2019 .0) , I, TRAVIS C. JANSEN, A REGIS ILRED PROFESSIONAL LAND SCALE "5 0 10 20 2 SURVEYOR IN THE STATE OF OREGON, HEREBY CERTIFY THAT 20 0 I HAVE ACCURATELY SURVEYED AND STAKED THE OFFSETS TO THE FOUNDATION ENVELOPE FOR LOT 111 OF THE PLAT 1 INCH = 20 FEET OF "RIVER TERRACE EAST”, 7) 8/21/ DRAWN BY: T2 DATE: 18 PACIFIC COMMUNITY DESIGN , REVIEWED BY: TCJ DATE. 8/21/18 PLANNING - ENGINEERING -SURVEYING ± PROJECT NO.: 395-041 (503) 941-9484