Hall Boulevard-Tualatin Road Corridor Multimodal Connection - June 1995 Draft Technical Report
HALL BOULEVARD - TUALATIN ROAD CORRIDOR
MULTIMODAL CONNECTION
TIGARD, OREGON
D� June 1995
Prepared for:
City of Tigard, Oregon
TABLE OF CONTENTS
LIST OF TABLES iii
LIST OF FIGURES iv
INTRODUCTION 1
CORRIDOR VICINITY 2
CORRIDOR ALIGNMENT OPTIONS 3
TRANSPORTATION IMPACTS AND BENEFITS 4
CURRENT TRAFFIC CONDITIONS 4
FORECAST 2015 TRAFFIC CONDITIONS 6
Without Hall Boulevard- Tualatin Road Connector Roadway 6
With Bicycle/Pedestrian/Transit Connection 7
With 25-Mph Hall Boulevard-Tualatin Road Collector Roadway 8
With 40-Mph Hall Boulevard- Tualatin Road Arterial Roadway 9
BUILD-OUT TRAFFIC CONDITIONS 10
Without Hall Boulevard- Tualatin Road Connector Roadway 11
With 40-Mph Hall Boulevard-Tualatin Road Arterial Roadway 12
STRUCTURAL ANALYSIS OF EXISTING RAILROAD TRESTLE 13
COST ESTIMATES OF IMPROVEMENTS 14
PEDESTRIANBICYCLE FACILITY ALONG THE EXISTING RAIL LINE 14
PEDESTRIANBICYCLE FACILITY PARALLEL TO THE RAIL LINE 14
TWO-LANE ARTERIAL ROADWAY 15
FOUR-LANE ARTERIAL ROADWAY 15
NATURAL RESOURCES 17
INVENTORY 17
POTENTIAL IMPACTS 18
NEED FOR FURTHER ANALYSIS 18
REGULATORY AND REQUIREMENTS IMPLICATIONS 19
REVIEW OF COMPREHENSIVE PLANS OF AFFECTED JURISDICTIONS 20
APPROVAL PROCESS 20
Pedestrian/Bicycle Facility Along the Existing Railroad Corridor 20
Pedestrian/Bicycle Facility Parallel to the Railroad Corridor 21
Arterial Roadway Accommodating Pedestrian,Bicycle,And Vehicular Traffic 21
COMPREHENSIVE PLAN REVIEW 22
City of Durham 22
City of Tigard 24
r ;
City of Tualatin 24
Washington County ' 25
APPROVAL PROCESS SUMMARY 26
.,' CONCLUSIONS AND RECOMMENDATIONS 27
APPENDIX—LEVEL OF SERVICE DEFINITIONS
This project is partially funded by a grant from the Transportation and Growth
Management(TGM) Program, a joint program of the Oregon Department of Transportation
and the Oregon Department of Land Conservation and Development. TGM grants rely on
federal Intermodal Surface Transportation Efficiency Act and Oregon Lottery funds. The
contents of this document do not necessarily reflect views or policies of the State of Oregon.
ii
LIST OF TABLES
No. Title Page
1. CURRENT LEVELS OF SERVICE 5
2. FORECAST 2015 PM PEAK HOUR LEVELS OF SERVICE 7
111
LIST OF FIGURES
No. Title Follows Page
1. CURRENT PEAK HOUR TRAFFIC VOLUMES 4
2. FORECAST 2015 WITHOUT HALL-TUALATIN CONNECTOR 6
3. FORECAST 2015 WITH 25 MPH HALL-TUALATIN CONNECTOR 6
4. FORECAST 2015 WITH 40 MPH HALL-TUALATIN CONNECTOR 6
5. REQUIRED LANE CONFIGURATION 7
JUJU
iv
f, l
•
JJ _
t INTRODUCTION
LTJ `
/1 This report documents the results of our examination of developing the Hall Boulevard -
Tualatin Road Corridor as a multimodal regional connection between the cities of Tigard
and Tualatin.
The southern portion of the corridor is currently occupied by tracks belonging to the Oregon
Electric Railway. The northern portion of the corridor is SW 85th Avenue, which is the
southerly extension of SW Hall Boulevard south of SW Durham Road. The corridor
a� traverses the Tualatin River which is a natural barrier to north-south traffic circulation in the
area. Besides the existing railroad trestle along the corridor, the river is crossed by Highway
99W at 1.7 miles to the west and by SW Upper Boones Ferry Road at 0.4 miles to the east of
the corridor.
The existing railroad trestle and right-of-way have long served as a north-south corridor for
travel between Tigard and Tualatin. The railroad right-of-way provides the City an
opportunity to convert it for use by other transportation modes. The existing trestle may be
suitable for use as a bicycle/pedestrian path, or even potentially for transit use. Alternatively, a
new two-lane bridge over the river could serve as a collector or an arterial street for use by
general vehicular traffic.
The development of the corridor as a multimodal regional connection between Tigard and
Tualatin was evaluated based on the following five criteria:
1. an analysis of the transportation impacts and benefits,
2. a structural analysis of the existing railroad trestle,
3. reconnaissance-level cost estimates,
4. an environmental reconnaissance of impacts to natural resources, and
5. a review of potential conflicts between the corridor improvements and the
comprehensive plans of the affected jurisdictions.
A brief discussion of the evaluation of the multimodal corridor based on the above five
criteria is provided in the discussion below.
1
1
CORRIDOR VICINITY
South of the Tualatin River crossing, the corridor is bordered by the Tualatin Community
Park on the east and the Tualatin County Club on the west. North of the Tualatin River,
Durham City Park and the Unified Sewer Agency's Durham Sanitary Sewer Plant border the
corridor on the east, and the Thomas Jersey Dairy and Tigard High School border the
corridor on the west side. All along the east side of the tracks is an approximately 12 foot
wide gravel pathway.
(6U U
2
ti
CORRIDOR ALIGNMENT OPTIONS
Three basic alignment options were considered for a potential connection between Hall
Boulevard and Tualatin Road. The first option assumed that the rail line would be removed.
The second and third alignment options considered establishing a new transportation
corridor parallel with the rail bridge to either the west or the east.
The two alignment options which are parallel with the existing rail bridge have the obvious
advantage that they do not require discontinuation of rail service or the acquisition of a
substantial section of rail road right-of-way. Disadvantages common to both of these
alignment options are greater right-of-way acquisition costs from
adjacent potentially, property owners
and
p y, greater environmental impacts to wetlands and other natural resource areas.
The alignment option to the east side of the rail line would require substantial acquisition of
land from Tualatin's Community Park and from Durham City Park.
Both alignment options which seek to preserve the rail line would also have more
complicated traffic operations. The parallel option which places a road to the west of the rail
line would cause a substantial increase in traffic which would cross the rail line at-grade on
Tualatin Road. For example, all of the traffic from downtown Tualatin would have to cross
the rail line to get to the new connector leading to Tigard. The parallel option which places
a new road to the east of the rail line would avoid some of the traffic-railroad complications
at the south end of the corridor, but would trade those for difficulties on the north side of the
Tualatin River. A roadway which started on the east side of the rail line in Tualatin
Community Park would have to transition to the west side of the line to connect to Hall
Boulevard at Durham Road. A grade-crossing on the Tigard side of the Tualatin River
would be undesirable and a grade separation would be expensive. In either case, the
alignment of the road would need to be adjusted so the crossing occurred at an angle
approaching 90 degrees. Adjusting the road alignment to make a right-angle crossing would
cause further intrusion into Durham City Park. _
The land acquisition, environmental, wetlands, and traffic impacts would all be difficult and
potentially expensive to resolve, but none appears to be an absolute prohibition to the
development of the corridor. However, it would be substantially easier, less expensive, and
less disruptive if the corridor could be developed following abandonment of the rail line.
This report focuses on an alignment option which assumes abandonment of the rail line at
some future date.
3
TRANSPORTATION IMPACTS AND BENEFITS
Development of the corridor could potentially provide significant transportation benefits,
whether it is opened to general vehicular traffic or limited to buses, bicycles, and/or
pedestrians.
Transportation impacts and benefits were analyzed for two future development scenarios and
compared with current traffic conditions. The first of the future scenarios was a 2015
development scenario based on Metro's year 2010 traffic projections. The second future
( ^ scenario was based on build-out of lands in the vicinity of the corridor. The build-out
scenario was based on assumptions of dwelling units and employment provided by staff
from the Cities of Tigard and Tualatin.
Traffic conditions were analyzed at the following major signalized intersections in the study
area that would experience a significant change in traffic demand as a result of the Hall
Boulevard - Tualatin Road connection:
• SW Boones Ferry Road and SW Nyberg Street
• SW Tualatin Road and SW Boones Ferry Road
• SW Upper Boones Ferry Road and SW Lower Boones Ferry Road
• SW Upper Boones Ferry Road and SW Bridgeport Road
• SW Upper Boones Ferry Road and SW Durham Road
• SW Hall Boulevard and SW Durham Road
• SW Tualatin Road and Proposed Hall-Tualatin Connector
CURRENT- TRAFFIC CONDITIONS
Current traffic volumes at major signalized intersections in the study area during the
weekday morning peak period (7:00 AM to 9:00 AM) and during the afternoon peak period
(4:00 to 6:00 PM) were obtained from the City of Tigard. These are illustrated in Figure 1.
As illustrated in Figure 1, traffic volumes in the study area are generally heavier during the
weekday PM peak hour than in the AM peak hour. Between SW Tualatin Road and SW
Durham Road, traffic volumes along SW Boones Ferry Road vary between 750 and 1,100
vehicles during the AM peak hour and the traffic volumes vary between 925 and 1,900
vehicles during the PM peak hour.
Traffic conditions were analyzed at the major signalized intersections in the study area based
on procedures established in the 1985 Highway Capacity Manual (see Table 1).
4
ti
LEGEND
00 = AM PEAK HOUR TRAFFIC VOLUME 4
(00) = PM PEAK HOUR TRAFFIC VOLUME
aA NTS
x � CICO
� O
DAVID EVANS AND ASSOCIATES, INC.
N�N 4�
125 (230) -k
CO a5 N X250 (650) i.¢,�.S*-
SW DURHAM RD 4 j P 60 (15) tO 4454
.411
}
(165) 265 -itt1 1 °'�0`<VC°�\ �J� 0�
(400) 640 —+ ' '° g ��.5, ��1q0 6� .b,0
O�T60 O /��0
bb b
Q:.5
00\ Sw g D ORT RD
10
(5) 15 ..." NI r/.
(5) 20 --ow w,a kA
(10) 5- ^c OO� S
`6- IL17451 Ss 1'-1 R0
SW TUALATIN RD i .-- 6) FERg
las
N`,,
um} r .-
N co 360 (435) (151 `'A
1 L r 145 (200)
r
cc
N
t•-•-:S ONOcN .i
co
l
O O 10 (25)
ooi�+:° .--925 (790)
SW TUALATIN- ) 175 (315) NYBERG RD
SHERWOOD RD(110) 110 -I '61 t r
(770) 835—► m o al FIGURE 1
(110) 105 `'' "
1 '"0 N CURRENT PEAK HOUR
� N .,
Ci-• c..1
co ` ' TRAFFIC VOLUMES
z
°ow
c
•
Intersection operation is expressed as level of service (LOS), a graduating scale of A through
F, with A describing'free flow travel conditions and F describing extreme congestion (see
Appendix for more detailed LOS definitions). LOS D is generally considered an acceptable
condition in urban areas. The LOS for non-signalized intersection operation is a function of
the reserve capacity or amount of capacity not used by the traffic demand crossing or
entering the main street from a stop-sign-controlled street.
TABLE 1
CURRENT LEVELS OF SERVICE
Current Traffic Operations
INTERSECTION AM Peak PM Peak
:D Hour Hour
SW Boones Ferry Rd and SW Nyberg Street 1.06 E_ 0.97 E'
SW Tualatin Rd and SW Boones Ferry Rd 0.764B 0.57 B
SW Upper Boones Ferry Rd and SW Lower Boones Ferry Rd_ N/A _ 0.72 B _
SW Upper Boones Ferry Rd and SW Bridgeport Rd 0.30 A 0.43 A
SW Upper Boones Ferry Rd and SW Durham Rd 0.79 C 0.93 D
SW Hall Boulevard and SW Durham Rd 0.71 B 0.80B
LEGEND:
1. 0.76 B Intersection volume to capacity ratio(v/c)of 76 percent and at LOS B
The LOS for signalized intersections is typically defined in terms of delay. According to the
1985 Highway Capacity Manual, delay is a measure of driver comfort, frustration, fuel
consumption, and lost travel time'. (See Appendix for more detailed LOS definitions). An
additional measure of signalized intersection performance is its capacity. Intersection
approach capacity is the maximum rate of flow for the subject approach which may pass
through the intersection under prevailing traffic, roadway, and signalization conditions.
The amount of capacity utilized by the traffic for the intersection, as a whole, is based upon
the lane groups or approaches that have the highest volume to capacity (v/c) ratio. An
overall ratio of less than 1.00 indicates that the design, cycle length, and phasing are able to
accommodate all critical flows without exceeding capacity. However, a-v/c ratio at or
approaching 1.00 is not considered an acceptable condition and is an indication that some
roadway improvements may be necessary.
The intersection of SW Boones Ferry Rd and SW Nyberg Street is estimated to operate at
close to capacity conditions during both the weekday AM and PM peak hours. All other major
signalized intersections in the study area are estimated to operate at acceptable levels of service
during the AM and PM peak hours; i.e. at less than 95 percent saturation and at LOS D or
better during the peak 15-minutes of the peak hour.
'Transportation Research Board,Highway Capacity Manual, Special Report 209(Washington, D.C.: National
Research Council, 1985).
5
_
FORECAST 2015 TRAFFIC CONDITIONS
Metro's year 2010 traffic model served as the basis for the year 2015 development scenario.
Year 2015 was selected to provide a twenty-year planning horizon for evaluation of the
corridor. The difference between current (1995) counts and Metro's 2010 traffic volume
forecasts were extrapolated to a twenty-year period using an exponential function to account
for the annual compounding of traffic growth. Thus, the growth increment predicted in the
Metro model was increased by somewhat more than one-third and added to the observed
1995 traffic volumes.
Since the weekday PM peak hour carries higher traffic volumes than the AM peak hour, the
year 2015 traffic conditions were analyzed for the weekday PM peak hour. Four scenarios
were analyzed for the corridor:
• Without the Hall Boulevard - Tualatin Road connector roadway (see Figure 2).
• With a bicycle/pedestrian/transit connection.
• With a 25-mph Hall Boulevard - Tualatin Road collector roadway (see Figure 3).
• With a 40-mph Hall Boulevard - Tualatin Road arterial roadway (see Figure 4).
The results of traffic operations analysis at major signalized intersections in the study area for
the above scenarios are summarized in Table 2.
Without Hall Boulevard -Tualatin Road Connector Roadway
Without the Hall Boulevard - Tualatin Road connector roadway, traffic service levels will
deteriorate at all major signalized intersections in the study area. At the intersection of SW
Boones Ferry Rd and SW Nyberg Street, traffic demand during the peak 15-minutes is forecast
to be more than 60 percent higher than the ability of the intersection to service that demand.
Also, the intersection of SW Upper Boones Ferry Rd and SW Durham Rd and the intersection
of SW Hall Boulevard and SW Durham Rd are forecast to operate at close to capacity
conditions during the peak 15-minutes of the weekday PM peak hour.
Acceptable traffic operations (i.e. v/c ratio less than 0.95 and LOS D or better) can be
maintained at the intersection of SW Boones Ferry Rd and SW Nyberg Street by providing an
additional through lane and a right-turn lane at the eastbound (EB) and southbound (SB)
approaches, a right-turn lane at the northbound (NB) approach, and a second left-turn lane at
the westbound (WB) approach. The intersection of SW Hall Boulevard and SW Durham Rd
can be maintained at acceptable traffic operation levels by providing an additional through lane
at the EB and WB approaches. The intersection of SW Upper Boones Ferry Rd and SW
Durham Rd can be maintained at acceptable traffic operation levels by providing an additional
WB through lane. It is calculated that without the Hall Boulevard - Tualatin Road connector
roadway, these additional lanes will provide for acceptable traffic operations through year
6
A AARAARGD/1F CI'f I AI p d' PUL.CTO ATT./`r,Tc n r.4/lc n 1 r rcrs nr��. r.r.r� .+.................. �. _..__._..,�..
•
1 ,
4A NTS
x0:1 §)g=_Di&
DAVID EVANS AND ASSOCIATES, INC.
O
.co0 400 4
795 '‘/?0'
SW DURHAM RD J 1 R�' 15 �t
190-1 1 t r 69po ��O
4000--0- 'o co o ry,6
cpoV
t1p/f
c ��8y0 S
D ORT RD
cozip: .� c).-0
r
1 '
30� �� OAES
1,0\0'
PC
44
SW TUALATIN RD
20 . � r10
�►
N 4 485 30 or 520 �*
tr
,co
25
o •
�� +- 1120
SW TUALATIN— )
675 NYBERG RD
SHERWOOD RD 120 "\ t r FIGURE 2
1270--► N o 0
130, ~ N N FORECAST 2015 PM
PEAK HOUR TRAFFIC VOLUMES
WITHOUT HALL-TUALATIN
z CONNECTOR ROADWAY
ox
ow
.4r-k6-
a A NTS
.4y
, xccl g0 0
DAVID EVANS AND ASSOCIATES, INC.
CO
b'300 '0
0 Lo 11.5
m M 2 -•--795 i,40"
1 0"
SW DURHAM RD i r 20 NS4
400 -0 9 �O
190 J 1 r 6 5 O
35 1 "ate v�'cv
rcr
O
x., \ .Airs\cpo
?DO 9 "S•''FI $ob,
4
4
F 3
a
p B D ORT RD
<12
o �
6 S
4O J (i
4..e3,
x:
FFIU r
z1W 10 .E !
FZ
A.220—.. II S
0 O 30, `��co $OOZE
.Io V45g,
tsul
11I I (44
SW TUALATIN RD 1 t
70, 000 20J ) 1E►
�� �c 10' to to
685--N. b 510 30
x 435 "'
fr
o Ln
1 rn
155
�
to,. +-1120
SW TUALATIN 1 r 600 NYBERG RD
SHERWOOD RD 120 J 1 t r FIGURE 3
1270--► N s s
130.E ~ m N FORECAST 2015 PM PEAK
A HOUR TRAFFIC VOLUMES WITH
1C4 25 MPH HALL-TUALATIN
z CONNECTOR ROADWAY
oow
caw
Arii.
I A NTS
, xO C ..00 O
O
DAVID EVANS AND ASSOCIATES, INC.
CO
4'0
u)w,o L 226 $�
csi N +-795 4444
SW DURHAM RD 1 r 25 �'� i,��
130 J ' I i .P 5 (5
400--.- N c.4 v bet:\ 4
130 'm it
0
foo � ~� 'ea
o
if
Eye �66...
Q
QI<.
hIA
a ¢O ID ORT RD
0
xl�x coon �A� o
Flo .1
/ r
z
zW ioJ � rr"
W I 220�
ao o 30- 4 �N^ R BOD ES
o 44o S\14
gR`� 119
SW TUALATIN RDk
120 °o"o" 20 ) � r�
o� u,eo lo—� �
650'N ' `540 30 �^,
1 x385
CIr
ego O
CD
225
Nr iTi +- 1120
570 NYBERG RD
SW TUALATIN
SHERWOOD RD 120 .J ' N t r FIGURE 4
1270— - a g ig
130� - - FORECAST 2015 PM PEAK
A HOUR TRAFFIC VOLUMES WITH
x 40 MPH HALL—TUALATIN
cn
w CONNECTION ROADWAY
o x
o w
MI r..,
2015. The lane modification required to maintain acceptable traffic operations without the
Hall Boulevard- Tualatin Road connector roadway are illustrated in Figure 5.
TABLE 2
FORECAST 2015 PM PEAK HOUR LEVELS OF SERVICE
Without With 25 mph With 40 mph
INTERSECTION Hall-Tualatin Hall-Tualatin Hall-Tualatin
Connection Connection Connection
SW Boones Ferry Rd and SW Nyberg Street 1.63-F 0.97 D 0.97 D
SW Tualatin Rd and SW Boones Ferry Rd 0.841 0.90 D 0.91 Cs
SW Upper Boones Fey Rd and SW Lower Boones Fey Rd _ 0.93 C 0.89 C _ 0.85 C
SW Upper Boones Ferry Rd and SW Bridgeport Rd 0.80 B 0.75 B 0.70 B
JUJU SW Upper Boones Ferry Rd and SW Durham Rd 1.00 0.94 D 0.89 D
SW Hall Boulevard and SW Durham Rd 0.99p 0.92 D _ 0.96 D
SW Tualatin Rd and Proposed Hall-Tualatin Connector N/A 0.81 B 0.81 B
LEGEND:
1.0.84 B.=Intersection volume to capacity ratio(v/c)of 84 percent and at LOS B without capacity improvements
2.0.91 C�=Intersection volume to capacity ratio(v/c)of 91 percent and at LOS C with capacity improvements
With Bicycle/Pedestrian/Transit Connection
As a bicycle/pedestrian pathway, the corridor would serve short-distance non-commuter travel,
for example, as a recreation route for bicyclists and joggers in the area. The trestle has long
g
been used by students from Tualatin attending schools in Tigard, but with the opening of
Tualatin High School,this activity appears to have decreased.
A bicycle and pedestrian pathway with either exclusive or shared use of the existing railroad
trestle would contribute towards meeting Oregon's Transportation Planning Rule (TPR)
requirements by providing a more balanced transportation system by reducing the need to
use automobiles for short, intra-city trips. The Oregon TPR requires that all four
metropolitan areas (including the Portland metropolitan area) reduce the regional per capita
vehicle miles traveled (VMT) by 10 percent over the next 20 years. —
The traffic volumes in the study area with a new bicycle/pedestrian connection along the
corridor were estimated by modeling a 15-mph roadway link along the corridor based on
Metro's regional travel demand model. Modeling the link with an assumed speed of 15-mph,
which approximates the operating speed of bicyclists, helps evaluate the reduction of travel
distance provided the new connection. Based on results from Metro's model, it is estimated
that a new bicycle/pedestrian connection along the corridor would have no measurable impact
on vehicular travel patterns and traffic congestion in the area. The use of the corridor for bus
travel would also have no measurable impact on traffic congestion in the area. Thereby, it is
estimated that all of the intersection improvements required without the Hall - Tualatin
LEGEND
CURRENT LANE CONFIGURATION
i a A .e .•ADDITIONAL LANE REQUIRMENTS BY 2015
WITHOUT HALL-TUALATIN CONNECTION
x ADDITIONAL LANE REQUIRMENTS BY 2015
WITH 25 MPH HALL-TUALATIN CONNECTION
-' ADDITIONAL LANE REQUIRMENTS BY 2015
WITH 40 MPH HALL-TUALATIN CONNECTION
IL 49
SW DURHAM RD IN r 44#1
} Nita115
� ly \ ' nit reGre8 W,ULL Vta\.ToacSn
) �4v
zl
F
P". 1>
E A
-f 4IQ ORT RD
• xP9
N
i 1,01.°
$`14 gg, II IL ?
fR
TUALATIN RD
SW 1 '0- `)it,.
<\1/4-•
1Lr
t
e
r
r
SW TUALATIN- 1 NYBERG RD
SHERWOOD RD t FIGURE 5
451' REQUIRED LANE
CONFIGURATION
w
z
ox
ow
CZ 40
(vehicular) connection would also be required with a new bicycle/pedestrian/transit connection
along the corridor.
With 25-Mph Hall Boulevard - Tualatin Road Collector Roadway
Based on Metro's regional travel demand model, it is estimated that 915 vehicles would be
diverted to a new 25-mph Hall Boulevard - Tualatin Road collector roadway during the
weekday PM peak hour. With the Hal_l - Tualatin collector, it is estimated that traffic
operation service levels will improve along SW Upper Boones Ferry Road at its
intersections with SW Lower Boones Ferry Road, SW Bridgeport Road, and SW Durham
7c)-V- )- Road. Thereby, the additional WB through lane (required in the case without the Hall -
Tualatin connector) would no longer be required at the intersection of SW Upper Boones
Ferry Road and SW Durham Road.
The new Hall Boulevard - Tualatin Road collector would result in higher traffic volumes, and
thereby deteriorate traffic operation service levels, at the remaining three existing major
signalized intersections included in the study area. Thus, the higher travel demand at the
intersection of SW Boones Ferry Rd and SW Nyberg Street with the provision of the Hall -
Tualatin collector would require an additional NB through lane, in addition to all of the
improvements that would be required without the Hall-Tualatin connector roadway.
At the intersection of SW Hall Boulevard and SW Durham Rd, the higher traffic volumes from
the Hall - Tualatin collector NB approach would require a left-turn lane at the NB approach
and a right-turn lane at the SB approach. These improvements are in addition to the through
lanes required at the EB and WB approaches without the Hall - Tualatin connector roadway.
Also, the new intersection of SW Tualatin Road and the Hall-Tualatin collector would have to
be modified so as to provide additional turning lanes at the SW Tualatin Road approaches to
the intersection.
These additional lane requirements by the year 2015, with a 25-mph Hall Boulevard - Tualatin
Road collector, for maintaining acceptable traffic operations at signalized intersections in the
study area are illustrated in Figure 5.
The abandonment of the railroad, with the construction of a new 25-mph Hall - Tualatin
collector, would simplify traffic operations at the intersection of SW Boones Ferry Rd and SW
Nyberg Street as it would remove railroad traffic interruptions at the west approach to that
intersection. Also, the abandonment of the railroad would offer an opportunity to realign and
correct the 90 degree turns along SW Tualatin Road, north of its intersection with SW Boones
Ferry Road.
8
1
With 40-Mph Hall Boulevard - Tualatin Road Arterial Roadway
Based on Metro's regional travel demand model, it is estimated that 1,615 vehicles would be
diverted to a new 40-mph Hall Boulevard - Tualatin Road arterial roadway during the
weekday PM peak hour. With the Hall - Tualatin arterial, it is estimated that traffic
operation service levels will improve along SW Upper Boones Ferry Road at its
intersections with SW Lower Boones Ferry Road, SW Bridgeport Road, and SW Durham
Road. Thereby, the additional WB through lane (required in the case without the Hall -
Tualatin connector) would no longer be required at the intersection of SW Upper Boones
Ferry Road and SW Durham Road.
The new Hall Boulevard - Tualatin Road arterial would result in higher traffic volumes, and
thereby deteriorate traffic operation service levels, at the remaining three existing major
signalized intersections included in the study area. Thus, the higher travel demand at the
intersection of SW Boones Ferry Rd and SW Nyberg Street with the provision of the Hall -
Tualatin collector would require an additional NB through lane and an additional WB right-
turn lane, in addition to all of the improvements that would be required without the Hall -
Tualatin connector roadway. Also, traffic operations at this intersection would be simplified
due to abandonment of the railroad at the east approach.
At the intersection of SW Hall Boulevard and SW Durham Rd, the higher traffic volumes from
the Hall - Tualatin collector NB approach would require a left-turn lane at the NB approach
and a right-turn lane at the SB approach. These improvements are in addition to the through
lanes required at the EB and WB approaches,without the Hall-Tualatin connector roadway.
At the intersection of SW Tualatin Rd and SW Boones Ferry Rd, additional through capacity
needed in the NB direction will require that the existing right-turn lane be modified to permit
both through and right-turn movements. Also, the new intersection of SW Tualatin Road and
the Hall-Tualatin collector would have to modified so as to provide additional turning lanes at
the SW Tualatin Road approaches to the intersection.
These additional lane requirements by the year 2015, with a 40-mph Hall Boulevard - Tualatin
Road arterial, for maintaining acceptable traffic operations at signalized intersections in the
study area are illustrated in Figure 5.
The abandonment of the railroad, with the construction of a new 40-mph Hall - Tualatin
arterial, would simplify traffic operations at the intersection of SW Boones Ferry Rd and SW
Nyberg Street as it would remove railroad traffic interruptions at the west approach to that
intersection. Also, the abandonment of the railroad would offer an opportunity to realign and
correct the 90 degree turns along SW Tualatin Road, north of its intersection with SW Boones
Ferry Road.
9
BUILD-OUT TRAFFIC CONDITIONS
Because of concerns expressed by staff from Tigard and Tualatin about Metro's assumptions
for future development, another calculation of future traffic was prepared. This was based
on build-out of land in parts of Tigard and Tualatin.
The population and employment were estimated at build-out for zones in the vicinity of the
Hall-Tualatin multimodal corridor. Traffic analysis zones (TAZ's) 333, 334, 347, 363, and
365 in Metro's regional transportation model were considered for this purpose.
TAZ's 333 and 334 are within the City of Tigard. They include an area roughly bounded by
the Tualatin River to the south, the Southern Pacific Railroad to the east, McDonald Street to
the north, and 108th Avenue to the west. The City of Tigard staff estimated the number of
households and employment at build-out for TAZ's 333 and 334 based on the adopted City
of Tigard Comprehensive Plan.
TAZ's 347, 363, and 365 are within the City of Tualatin. They include an area roughly
bounded by the Tualatin River to the north, I-5 to the east, Sagert/Avery Street to the south,
and 108th Avenue to the west. The City of Tualatin staff estimated the number of
households and employment at build-out for TAZ's 347, 363, and 365 based on the adopted
City of Tualatin Comprehensive Plan.
The estimated build-out population and employment for TAZ's 333, 334, 347, 363, and 365
were then compared with the population and employment assumed for those TAZ's in
Metro's 2010 regional transportation planning model. As shown in Table 3, the significant
differences between Metro and city projections are in the Tualatin zones rather than the
Tigard zones.
Based on an average rate of 10 trips per household, 20 trips per employee for retail
developments (not including pass-by trips), and 5 trips per employee for industrial
development, it is estimated that build-out of the lands in the vicinity of the corridor will add
another 73,000 daily trips to the surrounding street system. Assuming that approximately 10
percent of the weekday daily traffic occurs during the PM peak hour, it is estimated 7000
trips will be added to the surrounding street system during the weekday PM peak hour.
The distribution of the 7000 additional PM peak hour trips on to the surrounding street
system was estimated based on a select zone assignment for TAZ 347 in Metro's regional
model. The distribution of traffic from TAZ 363 and TAZ 365 is expected to be similar to
that for TAZ 347, especially for the northbound traffic. The distribution of trips from TAZ
347 was estimated for the following two cases: (a) without the Hall-Tualatin Connector
Roadway, and (b) with a 40 mph Hall-Tualatin Connector Roadway.
10
TABLE 3
COMPARISON OF DWELLING UNITS AND EMPLOYMENT
ESTIMATED DWELLING UNITS AND EMPLOYMENT
Traffic Analysis Metro 2010 Projections City of Tigard and City of Tualatin
Zone(TAZ) Build-out Projections
Number Households Retail Other Households Retail Other
Employees Employees Employees Employees
333 1,020 50 670 960 70 1,510
334 2,360 175 220 2,375 14 405
��� 347 465 345 1,740 425 0 1240
363 850 805 1,840 1,925 4,400 840
365 _ 70 455 _ 2,525 — 0 0 — 5,100 _
Total Households/ 4,765 1,830 6,995 5,685 4,484 9,095
Employees
Trip Rate 10 trips per 20 trips per 5 trips per 10 trips per 20 trips per 5 trips per
household employee employee household employee employee
Number of Daily 47,650 36,600 34,975 56,850 89,680 45,475
Trips
TOTAL DAILY 119,225 192,005
TRIPS
Without Hall Boulevard - Tualatin Road Connector Roadway
The select zone assignment revealed that the traffic generated during the weekday PM peak
hour from the area adjoining the Hall-Tualatin Corridor would distribute as follows to the
surrounding street system:
• 35 percent would travel north/east on Lower Boones Ferry Road to the I-5
interchange,
• 10 percent would travel north on Upper Boones Ferry Road,
• 18 percent would travel east on Nyberg Road to the I-5 interchange,
• 20 percent would travel west on Tualatin Road,
• 10 percent would travel west on Herman Road,
• 5 percent would travel south on Boones Ferry Road, and
• 2 percent would travel west on Tualatin-Sherwood Road.
As shown, in the Forecast 2015 Traffic Conditions section of this report, Upper Boones
Ferry Road is the critical link in the comparison with the Hall-Tualatin Connector Roadway.
With the addition of 700 trips (10 percent of 7,000 PM peak hour trips) to Metro's 2010
traffic volume forecasts, Upper Boones Ferry Road would have to be widened to five lanes
to accommodate the projected travel demand. To accommodate this build-out development
scenario, extensive improvements (beyond those identified in the Forecast 2015 Traffic
11
•
Conditions) would also be required along Tualatin-Sherwood Road, Nyberg Road, and
Tualatin Road in the project study area.
With 40-Mph Hall Boulevard -Tualatin RoadLArterialRoadway
With a 40 mph Hall-Tualatin Arterial Roadway, it is estimated based on a select zone
assignment that the traffic generated during the weekday PM peak hour from the area
adjoining the Hall-Tualatin Corridor would distribute as follows to the surrounding street
system:
• 15 percent would travel north on the new connector roadway,
�VJV • 30 percent would travel north/east on Lower Boones Ferry Road to the I-5
interchange,
• 18 percent would travel east on Nyberg Road to the I-5 interchange,
• 20 percent would travel west on Tualatin Road,
• 10 percent would travel west on Herman Road,
• 5 percent would travel south on Boones Ferry Road, and
• 2 percent would travel west on Tualatin-Sherwood Road.
Thus, of the 15 percent of the weekday PM peak hour traffic using a new 40 mph Hall-
Tualatin Arterial Roadway, ten percent is estimated to be diverted from Upper Boones Ferry
Road and the remaining 5 percent is estimated to be diverted from Lower Boones Ferry
Road.
With build-out of the lands in the vicinity of the corridor, the Hall-Tualatin Arterial
Roadway is estimated to carry approximately 1,000 more vehiclesdu_rin_g_the weekday PM
peak hour than indicated by Metro's 2010 traffic volume forecast. A four-lane connector
road would_be required to handle the estimated 2,650 vehicular trips forecast on the
connector roadway during the weekday PM peak hour.
The new four-lane arterial roadway would eliminate the need for widening Upper Boones
Ferry Road to five lanes to accommodate the increased traff c from the build-out scenario.
12
•
STRUCTURAL ANALYSIS OF EXISTING RAILROAD TRESTLE
The bridge is approximately 975 foot long and is composed of 55 timber pile trestle
approach spans and a 150 foot steel through truss main river span. The trestle spans have a
15 foot wide gravel ballast deck and the truss span is 16 foot clear horizontally between
trusses. The bridge and approach fills are approximately 10 feet above the adjacent ground
level.
There is an overhead power and utility line paralleling the bridge approximately 10 feet to
�� the east. Two utility lines (1 - 6 in. diameter and 1 - 3 in. diameter) are attached to the west
o side of the bridge.
The structure appears to be in good condition with no obvious signs of rot or deterioration of
the timber and no indication of damage or corrosion in the steel. Also, the river banks
appear to be stable and there are no indication of scour near the bridge. A review of the
latest inspection reports or a re-inspection of the bridge should be made prior to making
decisions on its future use or life expectancy.
13
COST ESTIMATES OF IMPROVEMENTS
The costs were estimated for the following four improvement alternatives:
• a pedestrian/bicycle facility along the railroad corridor, using the existing trestle;
• a pedestrian/bicycle facility parallel to the railroad corridor;
• a two-lane roadway accommodating pedestrian, bicycle, and vehicular traffic,
and
• a four-lane roadway accommodating pedestrian, bicycle, and vehicular traffic.
- PEDESTRIANBICYCLE FACILITY ALONG THE EXISTING RAIL LINE
The existing railroad trestle can be converted to either transit or bicycle/pedestrian use by
removing the trackway rails and ties, paving over the gravel ballast, installing decking and
paving on the truss, and installing either pedestrian railing. It is estimated that this
improvement would cost $250,000.
PEDESTRIANBICYCLE FACILITY PARALLEL TO THE RAIL LINE
A new 16 foot wide pedestrian/bicycle facility parallel to the railroad corridor would require
a new bridge crossing over the Tualatin River. It is estimated that the new
pedestrian/bicycle bridge would cost approximately $1,300,000. The estimated cost for the
new bridge was calculated assuming two 360 foot approach spans at $80 per square foot, and
a 250 foot river span at $100 per square foot. The estimated cost of the bridge might decrease
if the length of the bridge spans were reduced. However, this may not be possible due to
hydraulic requirements in the flood plain.
Sections of independent path totaling about 0.7 miles would be required on_both ends of the
bridge to tie it to nearby roadways or paths. These sections of the new 16 foot wide
pedestrian/bicycle facility would cost an additional $400,000, based on a unit construction of
$580,000 per mile. The unit cost of pathway construction is based on an estimate prepared by
Tualatin engineering staff in 1992 based on recent project costs. This estimate is somewhat
higher than costs listed by the Oregon Department of Transportation for many of its separate
bike paths. ODOT's costs range from $273,000 to $923,000 per mile with an average cost of
$470,000 per mile.
The total cost for providing a new 16 foot wide pedestrian/bicycle facility, parallel to the
railroad corridor, is estimated to be approximately $1,700,000. This does not include costs
due to any wetland mitigation which might be necessary, and they do not include right-of-
way acquisition, engineering and contingency_ costs.
14
TWO-LANE ARTERIAL ROADWAY
Alternatively, the corridor can accommodate a two-lane collector or arterial street open to
general vehicular traffic. It is estimated that replacing the existing railroad trestle with a new
two-lane bridge would cost $4 150,000. The remaining one mile length of the new two-lane s
roadway would cost an additional $2,000,000, assuming it could be built at-grade or on an
earthen berm. Should hydrologic or environmental factors require a longer bridge or longer
approach spans, costs would considerably greater. The cost estimates for the two-lane
roadway and bridge structure are based on a 30-foot pavement section with 7-foot sidewalks
and a 5-foot clearance on either side. The above cost estimates do not assume any wetland
mitigation which might be necessary, and they do not include rght loL w y.-costs.
A new two-lane roadway along the corridor would also require modifications to the existing
railroad trestle supporting Southern Pacific (SP) rail line running east-west near Tualatin
Road. A clear span of at least 54 feet in width would be required to accommodate a two-
lane roadway with bike lanes and sidewalks. It is estimated that the improvement to the SP
trestle would cost $100,000, if sufficient vertical clearance is available without altering the
existing road or railroad grades.
A new Hall - Tualatin collector or arterial street open to general vehicular traffic would also
require capacity improvements to other intersections in the study area, as discussed in the
section of the report on transportation impacts and benefits. The cost estimates were based
on a unit cost of$75,000 for every additional through or turning lane at the intersections and
a unit cost of$150,000 for each new signal.
Based on the above unit cost assumptions, intersection improvements with the new two lane
collector or arterial street are estimated to cost an additional $600,000, over and above the
cost of intersection improvements without the Hall - Tualatin connector roadway. Thereby,
the total incremental cost of providing a two-lane multimodal roadway connection along the
Hall - Tualatin corridor is estimated to be $7,200,000, exclusive of right-of-way and,
potential wetland..mitigation.
FOUR-LANE ARTERIAL ROADWAY
As indicated in the section discussing the build-out scenario, a four lane arterial roadway is
the appropriate facility if widening of the northern portion of SW Upper Boones Ferry Road
is to be avoided.
Building a four-lane roadway increases the costs considerably. The cost estimates for the
four-lane roadway and bridge structure are based on a 54-foot pavement section with 7-foot
sidewalks and a 5-foot clearance on either side. The cost of the bridge would rise to
15
.._...___ ...._ IFz.
I
$6,150,000. Four-lane approaches to the bridge are estimated to cost at least $1,000,000
more than would two-lane approach roadways. These cost estimates do not assume any
wetland mitigation which might be necessary, or right-of-way costs.
A new four lane roadway along the corridor would also require modifications to the existing
railroad trestle supporting Southern Pacific (SP) rail line running east-west near Tualatin
Road. To accommodate a four lane road beneath it, the railroad bridge would need a clear
horizontal span of at least 78 feet. Alternatively, multiple spans could be used if the arterial
were divided with a median. It is estimated that the improvement to the SP trestle would
exceed $150,000. With a four-lane arterial roadway, it becomes increasingly unlikely that
)U U sufficient vertical clearance is available without altering the existing road or railroad grades.
U U Any change in railroad tracks becomes increasingly expensive due to railroads' low
tolerance for grades.
LThe cost differential between a two-lane roadway and bridge and a facility with four lanes
ceeds $3,000,000. As indicated in the section on the build-out traffic conditions, the four
lane section for the connector is an alternative to widening of Upper Boones Ferry Road.
Costs associated with that option and for other street improvement needs associated with the
build-out scenario were beyond the scope of this study and were not calculated.
16
n cecneoco nn ci•�i.An a. ruc caro nrcr..- .....-..n.-o.....,... -.... _____ ....-.__..._.
NATURAL RESOURCES
A site reconnaissance was performed on January 24, 1995, to determine if wetlands or other
significant natural features occur along an approximately 1.2 mile long north-south corridor.
The study area for the environmental reconnaissance of impacts. to natural resources
included the segment of the Oregon Electric Railway tracks that runs between Tualatin Rd
on the south and SW 85th Street on the north and crosses over the Tualatin River. The
corridor is located in Township 2 South, Range 1 West, sections 13, 14, 23, and 24.
The reconnaissance involved reviewing existing in-house resource materials, and conducting
an on-site visit to determine if wetland indicators discussed in the Corps of Engineers
Wetland Delineation Manual (Environmental Laboratory, 1987) were present. According to
the manual, an area is determined to be a wetland if there is simultaneous occurrence of
hydric soils, a dominance of hydrophytic vegetation, and hydrology specific to wetlands.
Wetlands determined on the basis of the Corps of Engineers Wetland Delineation Manual
(Environmental Laboratory, 1987) are subject to regulatory jurisdiction by the Oregon
Division of State Lands (DSL) and the US Army Corps of Engineers (COE).
INVENTORY
The National Wetlands Inventory (NWI) map that covers the project area (Beaverton 7.5
minute quad) and the Washington County Soil Survey were examined to assist with the
wetland presence determination. The NWI map identified the Tualatin River as a lower
perennial riverine, permanent, open water wetland (R2OWZ) and Fanno Creek as a
palustrine broad-leaved deciduous forested wetland that is intermittently flooded (PFO 1 W).
No other wetlands were identified within the project corridor. The Washington County Soil
Survey indicates that six soil series occur on the site: Chehalis, McBee, Quatama, Wapato,
Xerochrepts and Haploxerolls, and urban land. The Wapato soil series is classified as hydric
by the National Technical Committee for Hydric Soils. The Wapato soil series is mapped as
a pocket north of the Tualatin River that is located on both sides of the tracks and a smaller
pocket located on the west side of the tracks just north of Tualatin Rd.
The City of Tualatin's Goal 5 inventory of significant natural areas and wetlands has located
a small wetland west of the railroad tracks and north of the condominiums. The City is in
the process of identifying areas that would qualify as"significant"under Goal 5.
The database at the Natural Heritage Program was queried for locations of sensitive,
threatened, and endangered species and habitats that may be located in the project. There are
no records in the project area.
17
Habitat types within 50 feet of either side of the tracks consisted mainly of herbaceous
ground cover, with the exception of blackberries (Rubus spp.) and scotch broom (Cytis
scoparius) growing along the slopes of the berm south of the Tualatin River.
The confluence of Fanno Creek and the Tualatin River is on the east side of the tracks at the
bridge crossing.
On the east side of the corridor, the riparian areas of both Fanno Creek and the Tualatin
River are forested with a mixed deciduous-coniferous forest vegetation. This forested
vegetation is at least 50 feet from the tracks. The only forested area adjacent to the tracks is
a small pocket of forested vegetation is located on the southwest bank of the Tualatin. This
UJU forested area is upland riparian habitat and is part of the Tualatin Country Club. All of the
understory has been cleared, and the area appears to be used as a park or picnic area.
Wetlands may be present in both pastures located on the west side of the corridor based on
the area being mapped as hydric soil and visual observation of ponding. The vegetation was
not identifiable given the dormant stage of the vegetation and grazing by cattle. Detailed
data plots were not conducted because DEA did not have permission to access private
properties adjacent to the tracks.
POTENTIAL IMPACTS
There are no wetlands within the current railroad right-of-way. If the proposed corridor
would be widen outside of the existing railroad right-of-way, wetlands may be present on the
west side of the tracks.
Both the Tualatin River and Fanno Creek are regulated water bodies by both the Division of
State Lands (DSL) and the US Army Corps of Engineers (COE). Any fill placed within the
top-of-the bank of the Tualatin River would require coordination with DSL and the COE.
The City of Tualatin has designated the Tualatin River and 40 feet on either side of the River
as a greenway. Widening of the corridor in this area would require coordination with the
City.
There are no sensitive species within the existing corridor.
NEED FOR FURTHER ANALYSIS
If construction activity were proposed which would result in widening of the existing
corridor, removal of forest vegetation and riparian vegetation along the Tualatin River and
Fanno Creek should be avoided.
18
Prior to preliminary design, a wetland delineation should be performed to determine the
extent and location of jurisdictional wetlands and water courses. Wetland delineations are
more accurate when performed when the ground water is recharged. This is typically in
March through early May. After that period, hydrology must be assumed to be present
based on hydrologic indicators. This often, but not always, results in more area delineated
as wetland. The wetland delineation process defines precise wetland boundaries that may be
legally described and utilized during design and site development.
REGULATORY AND REQUIREMENTS IMPLICATIONS
cUUU The COE administers Section 404 of the Clean Water Act, which regulates the discharge of
dredge or fill materials into waters of the United States, including wetlands. Nationwide
Permit 26 under Section 404 allows filling up to one acre of isolated wetland or adjacent
wetlands located above the headwaters. However, filling of wetlands is not permitted in
documented habitat for federally or state listed endangered, threatened, or sensitive plant or
animal species. Water quality certification must be obtained from the Oregon Department of
Environmental Quality before the COE will issue a letter of compliance under a Nationwide
Permit 26.
The COE also authorizes an Individual Permit for more than one acre of fill for these types
of wetlands, or for any amount of fill in adjacent wetlands below headwaters. This type of
permit is both time consuming and costly, requiring multiple agency review, and an
alternative analysis.
Any activity that proposes removal, filling, or alteration of more than 50 cubic yards of
material within the banks or beds of waters of the State of Oregon (including wetlands)
requires a Removal-Fill Permit from DSL. In addition, DSL also requires a mitigation plan
that will compensate for the wetland loss.
19
REVIEW,OF COMPREHENSIVE PLANS OF AFFECTED
JURISDICTIONS
Comprehensive plans of the following affected jurisdictions were reviewed to identify areas
where the plans may conflict with corridor improvements: City of Tigard, City of Tualatin,
City of Durham, and Washington County. Based on the review, it was determined that
although the Comprehensive Plans with the exception of the City of Tigard, do not include a
multi-modal facility within the Hall Boulevard - Tualatin Road corridor area, the
development of such a multi-modal facility would not be_precluded by Plans. The Tigard
Plan contains a notation about a future crossing of the Tualatin River generally within the
U JU identified corridor, however, the plan amendment process would be necessary in order to
permit a specific facility.
The development review and approval processes for a multi-modal facility are generally
similar within all of the potentially impacted jurisdictions, and they would not be an obstacle
in and of themselves. Three key land use issues would however, be difficult to mitigate.
These issues include wetlands and environmentally sensitive areas; floodplain areas on the {'
Tualatin River and Fanno Creek; and compatibility with developed public and private
recreational uses and linkages.
APPROVAL PROCESS
The process for gaining approval to develop the multi-modal facility would require a
Comprehensive Plan Amendment in each jurisdiction. The process to accomplish the
necessary plan amendment is virtually similar in all the affected jurisdictions. Coordination
and timing of the amendment process in the individual jurisdictions is critical. An example
of the need for coordination is the fact that Tualatin will consider Legislative Plan
Amendments on a timely basis as submitted; Washington County .considers Plan
Amendments only between March 1 and October 1; and Tigard only twice a year. The
following three alternatives are currently being considered:
• a pedestrian/bicycle facility along the railroad corridor, using the existing trestle;
• a pedestrian/bicycle facility parallel to the railroad corridor; and
• an arterial roadway accommodating pedestrian, bicycle, and vehicular traffic.
Pedestrian/Bicycle Facility Along the Existing Railroad Corridor
A pedestrian/bicycle facility along the existing railroad corridor, using the existing railroad
trestle, may require an intergovernmental agreement between the City of Tigard, City of
Tualatin, CitY—of Durham, and Washington County. The intergovernmental agreement
20
would identify the ownership and maintenance responsibilities of the bicycle/pedestrian
corridor. Alternatively, Washington County could assume responsibility for the entire
facility.
Pedestrian/Bicycle Facility Parallel to the Railroad Corridor
A pedestrian/bicycle facility parallel to the railroad corridor would require an Administrative
Type II development permit from Washington County, and it may require "M ni'or'Plan
Amendments from the City of Tigard, City of Tualatin, and City of Durham.
Any construction activities within the wetlands and floodplain associated with the Tualatin
River and Fanno Creek would require a joint application to the U.S. Army Corps _of
Engineers and the Division of State Lands (DSL). The Oregon Department of Fish and
Wildlife and the U.S, Fish and Wildlife Service would also be involved in the review and
approval process due to potential impact on the aquatic and riparian habitats. The joint
application would seek to determine that the proposed facility would not have an adverse
environmental impact with respect to the following key land use issues:
• Significant wetlands and environmentally sensitive areas.
• Floodplain areas on the Tualatin River and Fanno Creek.
• Compatibility with developed public and private recreational uses and linkages.
Development of the pedestrian/bicycle facility may also require an intergovernmental
agreement that will identify the ownership and maintenance responsibilities of the
bicycle/pedestrian corridor. Alternatively, Washington County could assume responsibility
for the entire facility.
Arterial Roadway Accommodating Pedestrian, Bicycle,And Vehicular Traffic
The development of a roadway facility accommodating pedestrian, bicycle, and vehicular
traffic would require a "Major" Plan Amendment from the City of Tigard, City of Tualatin,
City of Durham, and Washington Count' Plan Amendment processes within all of the
potentially impacted jurisdictions are generally similar to each other, with the exception that
Washington County has the most rigorous process for review and approval of a major multi-
modal transportation facility.
There is no clear procedure in any of the ordinances for the review and approval of a facility
being developed jointly within multiple jurisdictions. If this is the case, then each pan
amendment would have to be processed independents in each j.urisdicti_on. The process
would require extensive coordination and public involvement among the jurisdictions in
developing, evaluating, and selecting a preferred alternative.
21
Any construction activities within the wetlands and floodplain associated with the Tualatin
River and Fanno Creek would require a joint application to the U.S. Army Corps of
Engineers and the Division of State Lands (DSL). The Oregon Department of Fish and
Wildlife and the U.S. Fish and Wildlife Service would also be involved in the review and
approval process due to potential impact on the aquatic and riparian habitat. The joint
application would seek to determine that the proposed facility would not have an adverse
environmental impact with respect to the following key land use issues:
• Significant wetlands and environmentally sensitive areas.
• Floodplain areas on the Tualatin River and Fanno Creek.
• Compatibility with developed public and private recreational uses and linkages.
3 C Development of the multi-modal facility may also require an intergovernmental agreement
that will identify the ownership and maintenance responsibilities of the bicycle/pedestrian
corridor. Alternatively, Washington County could assume responsibility for the entire
facility.
COMPREHENSIVE PLAN REVIEW
City of Durham
A portion of the potential corridor is located along the west edge of the City of Durham.
The area consists of floodplain and low land areas at the confluence of Fanno Creek with the
Tualatin River. Within the City, the area including the potential corridor is designated on
the Comprehensive Plan (November, 1987) as Greenway. The following is a listing of those
sections of the Plan/Zoning Code which would apply to any "hard" development within the
corridor in Durham.
Chapter II,Article 3, Section 5- Greenway District(G)
A. Purpose and Intent - The purpose of this District is to protect and preserve
natural water storage areas, floodplains and drainage way areas and other
Greenway areas by discouraging or prohibiting incompatible uses except in
those instances where findings may properly be made by the Planning
Commission or City Council allowing limited use of such area.
B. Uses - Permitted uses, prohibited uses and activities, non-conforming uses,
special permits or exceptions, and standards for permitted structures within
this District shall be regulated through the procedures described in Chapter V
- Greenways.
22
r, `
1
Chapter V,Article 1, Section 2-Definitions
G. "Obstruction" means any dam, wall, embankment, levee, dike, pile,
abutment, projection, excavation, channel modification, bridge, conduit,
culvert, building, gravel, refuse, fill, structure or matter in, along, or across or
projecting into any channel, water course, or floodplain drainage ways areas
which may impede, retard, or change the direction of the flow of water, either
in itself or by catching or collecting debris carried by such water, or that is
placed where the flow of water might carry the same downstream to the
damage of health or property.
�UvU
K. "Greenways" are defined as unbuildable lands and other lands that establish a
greenway system that will (a) tie together recreation areas, schools and their
service areas; (b) provide protective buffers between incompatible land uses;
(c) reduce flood hazard by restricting development along natural drainage
ways; (d) provide opportunities for passive recreation activities; (e) afford
alternative pedestrian and bicycle circulation routes separated from the street
system and motorized vehicles; and (f) preserve the amenity of the area.
Chapter V,Article 2, Section 1 -Permitted Uses
C. Roadways, bridges or utility structures designed to not significantly impede
the flow of floodwaters.
Chapter V,Article 2, Section 2-Prohibited Uses and Activities
A. Filling.
D. Excavating.
H. Any change in the topography or terrain which would have a substantial
tendency to change the flow of waters during flooding periods or which
would increase flood hazard or alter the direction or velocity of the
floodwater flow.
Chapter V,Article 2, Section 4-Special Permits or Exceptions
NOTE: Section 4 establishes the requirements and process for review of those uses
requiring permits. Development of a roadway link would be governed by this
Section as a minimum.
23
City of Tigard
The potential corridor alignment in the City of Tigard consists of developed public (U.S.A.
Treatment Plant), public institutional (Tigard High School), and light industrial uses along
S.W. 85th Avenue south of the Durham Road intersection. These areas should not present
significant obstacles to development of a multi-modal facility. Further south beyond the
developed portion of S.W. 85th Avenue, the area within the City of Tigard is designated as
Open Space on the Comprehensive Plan. Much of that area is within the floodplain and
wetlands associated with Fanno Creek and the Tualatin River. A substantial portion of the
Open Space area is overlain with a floodplain designation. This area presents a number of
Copotential obstacles to the development of a multi-modal facility.
U��J The Tigard Area Comprehensive Pedestrian - Bicycle Pathway Plan identified four priority
phases for developing a city-wide pathway system. The link along 85th Avenue from
Durham Road over the Tualatin River was classed as a Phase 4 priority. Although the plan
does not state why this link was given such a low priority, it was most likely due to the costs
and potential problems associated with a crossing of the Tualatin River.
There is no specific mention of a multi-modal facility as a permitted use in the residential or
light industrial zoning district listings. Section 18.70.030 which lists the permitted uses for
the I-L, Light Industrial District cites "Civic use types" as a permitted use but, there is no
definition in the Code for "Civic use types". There are four sub-categories listed under
"civic use types", a. Public support facilities; b. Parking facilities; c. Postal services; and d.
Public safety services. None of these sub-categories specifically fit a multi-modal facility.
A notation on the Comprehensive Plan indicates a crossing of the Tualatin River but, does
not identify a specific location. This notation has the effect of giving "conceptual" support
to a crossing subject to a Plan Amendment identifying and further refinement of a specific
location and type of facility. A multi-modal facility would be processed as a special project
since it "bridges" both land use and land division issues. Issues such as land use
compatibility; access and circulation; project design; environmental impact; and visual
appearance would be best handled through a process of public information workshops
preceding the Plan Amendment public hearings.
City of Tualatin
The proposed corridor corresponds generally with the alignment of Tualatin Road north of
Boones Ferry Road along the boundary between Neighborhood Planning Areas (NPA) 1 and
6. The area within NPA 1 is designated Park/Greenway and is developed as Tualatin
Community Park. This park is the site of the annual Crawfish Festival and experiences
extensive use at all times of the year due to its location on the Tualatin River.
24
4 ." •
1
On the west side of the potential alignment is an area in NPA 6 which is designated RL-Low
Density Residential(1-5 dwelling units per acre). Approximately 134.08 acres of this area is
developed as the Tualatin Country Club golf course. Development of a golf course is
permitted as a conditional use on land zoned for low density residential land uses. At the
north end of the corridor is the Tualatin River.
The Transportation Plan shows only two crossings of the Tualatin Ricer within the city. One
is the Highway 99W crossing located at the northwest edge of the city, and the other is the
Boones Ferry Road crossing north of the downtown. Although there is some general
wording in the plan addressing continuity, crossing of the river, and pedestrian/bicycle links,
F)>U
n_ there is no specific mention of any type of crossing in the vicinity of this corridor.
Due to the existing passive and active recreation resources, and the wetlands-and..floodplain
associated with the Tualatin River, it would be extremely difficult to develop a multi-modal
facility within the proposed corridor alignment. A Comprehensive Plan Amendment would
be necessary to include a crossing of the Tualatin River as a major component of the
transportation element. Although building a facility is not prohibited by the plan, zoning, or
the overlying special zones, the recreational, environmental, and floodplain issues as well as
the lack of specific identification of such a facility in the plan would need to be addressed
when evaluating the cost/benefit of the facility. Such an evaluation would probably render
serious consideration of the corridor impractical. However, a much lower intensity non-
motorized vehicle connection serving pedestrians and bicyclists would provide for a crossing
of the Tualatin River. --
Washington County
The portion of the corridor area within unincorporated Washington County is designated on
the county plan for industrial uses, however, the majority of the area is within the floodplain
and wetland area on the west bank of the Tualatin River. Since a multi-modal facility is a
major transportation facility Washington County requires a complex review to provide the
broadest possible community input. In addition, the County Transportation Plan does not
identify an arterial facility within the corridor area.
Approval for the development of a multi-modal facility and, in essence, an amendment to
the Transportation Plan would be subject to the standards, process, and procedures identified
in Article VII,Public Transportation Facilities, for Category B Uses. This process requires a
rigorous alternative alignment analysis including a description of citizen involvement,
criteria used to select the alternative alignments, a description of anticipated impacts of
alternative alignments, and a description of the rationale for the proposed alignment with
potential mitigation measures. The process and requirements are virtually identical to those
required for federal highway projects.
25
D ACh.fDCD!lC CI'fl AID '�' TLYC CTD STC!`•/"Tr...rr r.r^�nrn�..n,' ,' ^'-
•
APPROVAL PROCESS SUMMARY
Development of any one of the three alternatives will require legitimization through the
Comprehensive Plan Amendment process in each affected jurisdiction. The following is a
summary of how the process would be handled in each of the jurisdictions.
• Legislative and quasi-judicial Comprehensive Plan Amendments in Tualatin are
processed at any time of the year on a timely basis as applications are received.
• Legislative Comprehensive Plan Amendments in Tigard are processed twice a year in
April and October. Quasi-judicial Plan Amendments are processed at any time of the
UOU year on a timely basis.
• Legislative Comprehensive Plan Amendments in Washington County are processed
between March 1 and October 1. Quasi-judicial Plan Amendments are processed at any
time of the year on a timely basis.
26
A MFAARCDnG CI'f1AlP 41,_TI4T CTD AT[:(:1/`Tc k• ..rrrr[n.rnarc ............. ...... ....�. _..-_ -'-
CONCLUSIONS AND RECOMMENDATIONS
The Hall Boulevard-Tualatin Road corridor has some obvious complications ranging from
environmental, wetlands, land acquisition, park impacts to traffic operations, construction,
and financing. Abandonment of the rail line, should that ever occur, would make it easier to •
resolve some of the complications. That would make traffic operations and roadway design
issues easier at both ends of the corridor and might reduce land acquisition costs, as well as
potentially reducing the impact on parks and wetlands. A bicycle and pedestrian connection
might even be developed using the existing trestle and bridge if the rail line were removed.
P)) 'cULU Based upon the modeling performed by Metro, it appears that the Hall Boulevard-Tualatin
Road corridor would be used if a facility were provided. The amount of use would depend
both on the type of facility and upon the amount of development which occurs in the area.
A low-speed facility, such as a local or collector street would attract relatively modest
amounts of traffic because it would offer slight time savings relative to existing alternative
routes, such as Boones Ferry Road, the nearest river crossing. Based on the Metro
modeling, a higher-speed arterial crossing which would provide a more direct connection
between Tualatin Road and Hall Boulevard would attract considerably more traffic due to its
shorter travel path and the time savings it would offer.
The key factor in determining the value of the potential Hall Boulevard-Tualatin Road
connector is the amount of development which will occur. The assumptions related to future
development in Tualatin have a significant impact on future traffic volumes. The year 2010
assumptions used by Metro in its modeling vary significantly from those of the City of
Tualatin.
Year 2015 traffic forecasts derived from Metro's traffic modeling for year 2010 showed that
a two-lane roadway in the Hall Boulevard-Tualatin Road corridor would provide adequate
capacity. Based on Metro's modeling, several intersections in the study area would require
improvements to maintain an acceptable peak hour level of service. The Hall Boulevard-
Tualatin Road connection would have mixed impacts. In some locations, such as
intersections on Tualatin Road, the facility creates a need for additional turn lanes. At
others, such as the intersection of Durham Road and Upper Boones Ferry Road, the
connector eliminates the need for a turn lane on one approach. The potential Hall
Boulevard-Tualatin Road connector does not eliminate the need for any major, expensive
improvement. When evaluated in the context of etro's jnodeling, Upper Boones Ferry
Road is not expected to be overloaded. Thus, the4Hall Boulevard-Tualatin Road facility
would provide added capacity in the area rather than serving as an alternative to a needed
improvement.
1.
27
Future traffic volume forecasts based on a build-out of lands in the vicinity of the Hall
Boulevard-Tualatin Road corridor present a very different picture. Particularly on the
Tualatin side of the river, a build-out scenario produces much higher traffic volumes than
does one based on Metro's_assumptions. Many existing roadways and intersections in the
area will likely experience considerable peak hour congestion. Extensive improvements to
many roads in the area would likely be necessary to maintain an acceptable peak hour level
of service. Upper Boones Ferry Road, the key facility which serves as the present day
alternative to the Hall Boulevard-Tualatin Road connector, is expected to be overloaded. Its
existing three lane cross-section would not be expected to provide adequate capacity to
accommodate a build-out land use scenario. A four lane Hall Boulevard-Tualatin Road
�E)U U connection would serve as a substitute for at least one potential project -- the widening of
Upper Boones Ferry Road to a five-lane cross-section.
Thus, future land use and development in the northern part of Tualatin is the key factor when
seeking to determine whether a road would be a useful facility in the Hall Boulevard-
Tualatin Road corridor. Capacity improvements in the Hall Boulevard-Tualatin Road
corridor or the Upper Boones Ferry Road corridor may or may not be necessary, depending
upon the amount of development in the area. Those corridors are not, however, the only
facilities in the area which will require extensive improvements if a build-out development
scenario occurs. Should additional capacity be needed due to development, the Hall
Boulevard-Tualatin Road connector, including a bridge over the Tualatin River, may be a
viable alternative to widening of Upper Boones Ferry Road.
The Cities of Tigard and Tualatin need to carefully analyze the development potential of the
vacant land which could have significant traffic impact on the corridor and resolve the issue
of differences between their assumptions and those of Metro.
Whether proposed as a two-lane or four-lane facility, construction of a bridge and roadway
would require a formal environmental analysis, most likely an Environmental Impact
Statement. It would also require plan amendments on the part of several jurisdictions. Both
would be lengthy and expensive processes, but would help ensure that a broad range of
alternatives were clearly and carefully evaluated. A bicycle-pedestrian bridge would also
require an environmental assessment and planning actions on the part of local agencies. The
actions would likely be both less expensive and less time-consuming than would be those for
a road.
(---
Many of the impacts, including environmental, land acquisition, impacts on parks, and
traffic operations, would likely be easier to resolve or mitigate if the rail line were to be
abandoned at some future date. Construction of a road is estimated to have a greater impact
than would construction of a bridge for bicyclists and pedestrians.
1
28
•
Because of the lack of a demonstrated, short-term need for a road, Tigard and Tualatin need I
not actively pursue funding for or an environmental analysis for a road connection or
acquisition of the railroad right-of-way. However, because of a long-term potential need for
additional street capacity due to a build-out land use scenario, the cities should probably not
abandon all plans for public use of the corridor. The cities should seek to resolve land use
and development issues, continue to monitor possible changes in use of the rail line, and
retain easements, setbacks or other mechanisms to protect the corridor.
Because a connector for exclusive use of bicyclists or pedestrians is judged to have lesser
environmental, land acquisition, and traffic operations impacts, there are fewer reasons for
delay action on a facility to serve these modes. Consideration of a bicycle-pedestrian facility
CJ�U 3 can proceed if sufficient justification exists independent of other needs. —�
1.
29
• , 4.,
TABLE A-1
SIGNALIZED LEVEL OF SERVICE
LEVEL DESCRIPTION
OF
SERVICE
A Operations with very low delay - less than 5 seconds per vehicle; occurs when most
< >� vehicles arrive during green phase, with most vehicles not stopping at all; short cycle
lengths may contribute to low delay.
B Operations with delay from 5.1 to 15 seconds per vehicle; occurs with good progression
and/or short cycle lengths;more vehicles stop than with LOS A.
C Operations with delay from 15.1 to 25 seconds per vehicle; occurs with fair progression
and/or longer cycle lengths; individual cycle failures may begin to appear at this level; the
number of vehicles stopping is significant at this level, although many vehicles still pass
through the intersection without stopping.
D Operations with delay from 25.1 to 40 seconds per vehicle; at this LOS, the influence of
congestion becomes more noticeable; longer delays result from a combination of
unfavorable progression, long cycle lengths, or high volume/capacity (v/c) ratios; many
vehicles stop,and the proportion of vehicles not stopping declines; individual cycle failures
are noticeable.
E Operations with a delay of 40.1 to 60 seconds per vehicle; upper limit reflects capacity of
intersection; high delay indicates poor progression, long cycle lengths, and high v/c ratios;
individual cycle failures are frequent.
F Operations with delay in excess of 60 seconds per vehicle; condition occurs from over-
saturation,when arrival flow rates exceed capacity of the intersection; may also occur with
high v/c ratios less than 1.0 with many individual cycle failures;poor progression and long
cycle lengths may also contribute to high delay.
Source: Transportation Research Board, Highway Capacity Manual, Special Report 209, National Research
Council,Washington,D.C., 1985.
A-1