GDI Project: Polygon-130-05 Prepared By: John Hook
Project Name: River Terrace NW Date: 9"October, 2017
Location: 17492 SW Forest Hollow St Report#: 184
Arrival: 1330 Departure: 1350
Weather: 1 Sunny, 60s Permit#: TBD
Site Visit Requested By: Toby(Polygon) ............................................................................................._Met With (on site): Toby(Polygon)
Purpose: Observe footing subgrade for lots73, 74 and 75
Outstanding Issues: None
Upon my arrival,Toby indicated that the subgrade for the footings of the structures located in lots 73, 74 and 75
had not yet been observed.At the time of my visit, a skiff(<1/2")of crushed rock had been placed over all footing
surfaces Using a Yz"steel foundation probe, I probed the footing areas within the above mentioned lots, and found
the subgrade to be stiff to very stiff where probed. Subgrade consisted of native light brown silts.
Based on our observations,the footing subgrade observed today was prepared in general accordance with site
plans, and our geotechnical recommendations.
Distribution:
Attachments: Site Plan (1)
Reviewed by:
This report presents opinions formed as a result of our observation of activities relating to geotechnical engineering or environmental services.We rely on the contractor to comply with the plans and
specifications throughout the duration of the project irrespective of the presence of our representative.Our work does not indude supervision or direction of the contractor,the contractor's employees
or agents.Our firm is not responsible for site safety.This field report is a DRAFT representation of our field observations,testing, commendations.The report can only be
considered final upon review of the GeoDesign project manager,as indicated by initials in the"Reviewed By"section.
Signature:
15575 SW Sequoia Parkway,Suite 100 I Portland,OR 97224 1503.968.8787 I www.geodesigninc.com