Report (38) Bend Office (541)330-9155
Carlson Testin Inc. Geotechnical Office (503)601-8250
Eugene Office (541)345-0289
g, Salem Office (503)589-1252
Tigard Office (503)684=3460
Special Inspection
FINAL SUMMARY LETTER
Date: August 1, 2017
Job#: T1607865
City of Tigard
13125 SW Hall Blvd
Tigard, OR 97223-8199
Attn: Building Division
Re: Project Name: Pacific Rim Martial Arts
Address: 8970 SW Burnham St. —Tigard, OR
Permit#: BUP2016-00235
Per Chapter 17, Section 1704.1.2 of the International Building Code(IBC), we have performed special inspection of the
following item(s) per our inspection reports only:
Reinforced Concrete
Cast-In-Place Anchors, Adhesive Anchors &Screw Anchors
Structural Steel
Wood Construction
The non-compliance (NC) items recorded for each of the above inspection categories, as listed on the non-compliance
report, have been either repaired and re-inspected by CTI for compliance or reviewed and accepted by the engineer of
record for the project in the "As-Built Condition" or through an RFI.
The issuance of this final report is based on the engineer's acceptance of the NC items not specifically re-inspected by
CTI. CTI did not provide any additional review or re-inspection of those items beyond the inspections that initially
generated each of these individual items on the non-compliance list. The engineer of record has provided the acceptance
of the non-compliance items and as-built conditions.
All requested inspections and tests were performed and reported according to the requirements of project documents and
to the best of our knowledge, the work was in conformance with the approved plans and specifications, approved change
orders and applicable workmanship, provisions of the State Building Code and Standards, as well as the structural
engineer's design changes, approvals and verbal instructions.
Our construction inspection and testing services were provided and intended to help reduce the risk of construction
defects, deficiencies or omissions that arose during and after construction. Our services do not constitute a warranty or
guarantee of any type. Even with diligent construction monitoring and testing, construction defects, deficiencies or
omissions in the contractor's work may exist. It is the contractor's responsibility to perform their work in accordance with
the approved construction documents.
CTI has provided its professional services with the degree of care and skill currently exercised under similar
circumstances by members of its profession in the same locale. Statements made in our reports are based on technical
judgments and should not be construed to be conclusive representations of fact. Our reports pertain to the material
tested/inspected only.
P:\Projects\General\2016\T1607865\08-01-17 Final Letter.doc Updated 11/30/11
Date: August 1, 2017
Job#: T1607865
Page 2 of 2
CTI's services did notinclude responsibilities related to determining, supervising, implementing or controlling the means,
methods, techniques, sequences or procedures of the construction or evaluating or reporting job conditions related to
health, safety or welfare.
Information contained herein is not to be reproduced, except in full, without prior authorization from this office. If there are
further questions regarding this matter please do not hesitate to contact this office.
Respectfully submitted,
CARLSON TESTING INC.
4144
Neil S. Shannon
Project Manager
NS/jng
cc: Pacific Rim Martial Arts—Mike Martyn'' mike.martyn@gmail.com
City of Tigard Building Division—Walter"Chip" Barnett v EMAILED
Eleven Engineering & Design LLC— Nate Carter Nate.carter@11-ed.com
Radian Construction —Dave Whitney dave@radianconstruction.com
Carlson Testing, Inc.
Incompleted Items List (NCL)
Aug 01,2017
T1607865.
Project Name: PACIFIC RIM MARTIAL ARTS
Project Address: 8970 SW BURNHAM ST TIGARD OR
Permit No: BUP2016-00235
P.O.No: Project Manager: NEIL S. SHANNON
Item# Insp. Date Item Description Compliance CTI Sign-Off Date
Corrected
1 KEJ 12/12/2016 NO APPROVED MIX DESIGN ON SITE. MIX USED WAS WCP RECEIVED AND REVIEWED. STEVEN W. LEACH 05/12/2017
#355501WH. SLUMP WAS 3.5" AND AIR WAS 1.6%.
12/22/16: REMAINS OUTSTANDING.
2 TR 12/22/2016 NO APPROVED MIX DESIGN ON SITE. MIX USED WAS WCP RECEIVED AND REVIEWED. STEVEN W. LEACH 05/12/2017
406001W - SLUMP: 4", AIR: 1.6%. ENGINEER OF
RECORD TO REVIEW.
3 KG 01/10/2017 NO APPROVED MIX DESIGN ON SITE. MIX USED WAS RECEIVED AND REVIEWED. STEVEN W. LEACH 05/12/2017
597FS. SLUMP WAS 4"±1" AND AIR WAS 1.5%
4 BP 02/01/2017 5/8" ANCHORS EMBEDDED AT 17" FOR HOLDOWNS WITH NO DETAILS CONFIRMED IN RFI NEIL S. SHANNON 08/01/2017
APPROVED DETAIL. #01.
CC:PACIFIC RIM MARTIAL ARTS - MIKE MARTYN
CITY OF TIGARD BUILDING DIVISION - WALTER 'CHIP' BARNETT
ELEVEN ENGINEERING & DESIGN LLC - NATE CARTER
RADIAN CONSTRUCTION - DAVE WHITNEY
Page: 1
Bend Office (541)330-9155
Geotechnical Office (503)601-8250
Carlson Testing, Inc. Eugene Office
Salem Office (541)345-0289
(503)589-1252
Tigard Office (503)684-3460
Special Inspection
FINAL SUMMARY LETTER
Date: July 27, 2017
Job#: T1701331
City of Tigard
13125 SW Hall Blvd
Tigard, OR 97223-8199
Attn: Building Division
Re: Project Name: Landmark Ford Lincoln—Service Department Renovation
Address: 12300 SW 68th Ave.—Tigard, OR
Permit#: BUP2016-00285
Per Chapter 17, Section 1704.1.2 of the International Building Code(IBC),we have performed special inspection of the following
item(s)per our inspection reports only:
Reinforced Concrete
Screw Anchors
Structural Steel
All requested inspections and tests were performed and reported according to the requirements of project documents and to the
best of our knowledge, the work was in conformance with the approved plans and specifications, approved change orders and
applicable workmanship, provisions of the State Building Code and Standards, as well as the structural engineer's design
changes, approvals and verbal instructions.
Our construction inspection and testing services were provided and intended to help reduce the risk of construction defects,
deficiencies or omissions that arose during and after construction. Our services do not constitute a warranty or guarantee of any
type. Even with diligent construction monitoring and testing, construction defects, deficiencies or omissions in the contractor's
work may exist. It is the contractor's responsibility to perform their work in accordance with the approved construction
documents.
CTI has provided its professional services with the degree of care and skill currently exercised under similar circumstances by
members of its profession in the same locale. Statements made in our reports are based on technical judgments and should not
be construed to be conclusive representations of fact. Our reports pertain to the material tested/inspected only.
CTI's services did not include responsibilities related to determining, supervising, implementing or controlling the means,
methods, techniques, sequences or procedures of the construction or evaluating or reporting job conditions related to health,
safety or welfare.
Information contained herein is not to be reproduced, except in full,without prior authorization from this office. If there are further
questions regarding this matter please do not hesitate to contact this office.
Respectfully submitted,
CARLSON TEST NG INC.
Neil S. Shannon
Project Manager
NS/jng
cc: Landmark Ford—Jim Corliss JCORLISS@LANDMARKFORD.COM
City of Tigard Building Division—Walter'Chip' Barnett WALTER@TIGARD-OR.GOV
BK Engineers Inc— Bill Berry BILL@BKENGINEERS.COM
LRS Architects Inc—Byron Balogh BBALOGH@LRSARCHITECTS.COM
R& H Construction—Dave Fuerstenberg DFUERST@RHCONST.COM
P:\Projects\General\2017\T1701331\07-27-17 Final Letter.doc Updated 11/30/11