August 1, 1990
MEMORANDUM
CITY OF TIGARD, OREGON
TO: Transportation Advisory Committee
FROM: Randy Wooley, City Enginee
DATE: August 1, 1990
SUBJECT: Project Update
1. BOND PROJECTS
There is a great deal of work happening currently on the bond projects. Here
is a brief status report:
Bonita Road: A contract has been signed with Kampe Engineering to provide
design for the completion of the Bonita project, scheduled for 1991
construction.
Durham Road: Currently under construction. The road is to be reopened to
through traffic by September 1st. Construction should be completed by
November.
Gaarde/99W Intersection: State funding of $180,000 has been approved for this
project, which will reduce the City costs. We will begin the detailed design
process soon, still targeting construction in 1991.
Greenbury Road: Bids have been opened for the first phase, the storm drainage
work near Center Street. This work has to be done before we can install a
storm drainage system along Greenburg. Bids were below engineer's estimate.
We expect the work to begin in late August or early September. This phase was
delayed by the railroads, who needed to give permission for us to install
piping across their rights of way.
We are currently advertising for bids for the second phase, installation of the
underground utilities along Greenburg Road. The utility work was rescheduled
for this fall to better coordinate with the utility companies and to allow time
for acquisition of nearly 70 utility easements.
Actual roadway construction will be bid as the final phase, with construction
to begin in the spring of 1991, after the other two phases are completed.
Locust Street: This project is completed.
Main Street: Selection of a design consultant for the bridge replacement will
occur this month. Construction will be scheduled for summer and fall of 1991.
McDonald Street: The intersection improvements at Hall Blvd. should be
completed this month. Work was delayed while utility companies relocated the
poles. The GTE strike contributed to the delay.
Following a June meeting with property owners, the design consultants are
completing construction plans and preparing right-of-way descriptions. We
expect to be ready to bid this project early in 1991.
Walnut Street: The project is under construction, scheduled for completion by
September 1st.
69th Avenue/99W Intersection: This project is scheduled for 1991.
121st Avenue: Construction is progressing and should be mostly completed
during August.
Budget: Overruns on some projects have been offset by underruns on other
projects. At this point, we still expect to finish all 10 projects within the
$8,500,000 budget. After the final project bids are opened next spring, we
will know if there is enough money left to fund an additional project.
2. C.I.P. PROJECTS
Design consultants are preparing plans for the Durham/92nd signal and the
Bonita/72nd signal. We expect to bid both this fall, with construction early
next year.
Construction of the Greenburg/Cascade signal will begin soon. The signal is to
be in operation before Thanksgiving.
3. COMPREHENSIVE PLANNING
At their workshop meeting on July 2nd, the Council provided additional
direction on several transportation issues. A number of potential plan changes
will be considered this fall and winter. We expect to be ready to provide an
update and schedule at the September meeting of the Transportation Committee.
rw/TTAC-Aug