Report (14) File No.: 0
8
Project: Rose City Futsal Date: 1
2
Project: Warehouse .
Conversion 2
8
Project No . : 572
2
0
1
6
6-00/ 8¢I
Final Acceptance
In accordance with provisions of the contract documents, the construction work for Rose
City Futsal warehouse conversion at 10831 SW Cascade Avenue, Tigard, Oregon,
performed by JHKeIIy, LLC is ACCEPTED.
The work is found to be in general conformance with the design documents and no
exception is taken.
Eric Lanciault
Design Professional in Charge
Eric Lanciault, Architect
3200 se 164th avenue suite 302
vancouver,washington 98683 360.798.3801
D:\Dropbox(elaooa)\elaooa\572-futsal tigard\09-contract administration\10-closeout\161228_final acceptance_572.docx