Envelope Compliance Certificate
Section 1: Project Information
Energy Code:2014 Oregon Energy Efficiency Specialty Code
Project Title: Landlord Improvement
Project Type:Alteration
Envelope Compliance Method:Simplified Trade-Off
Construction Site: Owner/Agent: Designer/Contractor:
12286 SW Scholls Ferry Road Ryan Sexton Kevin Kincaid
Tigard,Oregon 97223 Regency Centers Western Construction Services,Inc
5335 SW Meadows,Suite 295 2300 E 3rd Loop,Suite 110
Lake Oswego,Oregon 97035 Vancouver,Washington 98661
503-603-4903 360-737-0990
ryansexton@regencycenters.com kkincaid@westernconstruction.com
Building Location(for weather data): Tigard,Oregon
Climate Zone: 4c
Vertical Glazing/Wall Area Pct.: 10%
Building Use:Area Type Floor Area
1-Retail:Nonresidential 4886
Section 2: Envelope Assemblies and Requirements Checklist
Envelope PASSES
Envelope Assemblies:
R-Value Proposed Max.Allowed
Post-Alteration Assembly Cavity Cont. U-Factor SHGC U-Factor SHGC
Door: ,Entrance Door,Entrance Door,[Bldg.Use 1 -Retail] -- --- 0.800 0.400 0.800 0.400
Window:,Clear,[Bldg.Use 1 -Retail] --- --- 0.450 0.400 0.450 0.400
(a)Fenestration product performance must be certified in accordance with NFRC and requires supporting documentation.
In the following requirements,blank checkboxes identify requirements that the applicant has not acknowledged as being met. Checkmarks
identify requirements that the applicant acknowledges are met or excepted from compliance. 'Plans reference page/section'identifies where in
the plans/specs the requirement can be verified as being satisfied.
Fenestration Product Rating:
• 1. U-factors of fenestration products(windows,doors and skylights)are determined in accordance with NFRC 100 by an accredited,
independent laboratory,and labeled and certified by the manufacturer or are determined using the commercial size category values
listed in Chapter 15 of the 2009 ASHRAE Handbook of Fundamentals,Table No.4 and shall include the effects of the window frame.
The temporary label afixed to the fenestration products must not be removed prior to inspection.
Plans reference page/section:A0.0
• 2. Solar heat gain coefficient(SHGC)of glazed fenestration products(windows,glazed doors and skylights)shall be determined in
accordance with NFRC 200 by an accredited,independent laboratory,and labeled and certified by the manufacturer or be determined
using the Solar Heat Gain Coefficients(SHGC)in Chapter 15 of the 2009 ASHRAE Handbook of Fundamentals,Table No.10.The
overall values must consider type of frame material and operator for the SHGC at normal incidence.
Plans reference page/section: A0.0
Air Leakage, Insulation, and Component Certification:
✓ 3. Sealing of the building envelope.Openings and penetrations in the building envelope are sealed with caulking materials or closed with
gasketing systems compatible with the construction materials and location.Joints and seams are sealed in the same manner or taped
or covered with a moisture vapor-permeable wrapping material.Sealing materials spanning joints between construction materials allow
for expansion and contraction of the construction materials.
• Project Title: Landlord Improvement Report date: 02/01/17
Data filename: Page 1 of 3
Plans reference page/section:A0.0
✓ 4. Window and door assemblies.The air leakage of window and sliding or swinging door assemblies that are part of the building envelope
are determined in accordance with AAMANVDMA/CSA 101/I.S.2/A440,or NFRC 400 by an accredited,independent laboratory,and
labeled and certified by the manufacturer.
Plans reference page/section: A0.0
✓ 5. Curtain wall,storefront glazing and commercial entrance doors.Curtain wall,storefront glazing and commercial-glazed swinging
entrance doors and revolving doors are tested for air leakage in accordance with ASTM E 283.For curtain walls and storefront glazing,
the maximum air leakage rate is 0.3 cubic foot per minute per square foot of fenestration area.For commercial glazed swinging
entrance doors and revolving doors,the maximum air leakage rate is 1.00 cfm/ft2 of door area.
,Plans reference page/section:A0.0
✓ 6. Building thermal envelope insulation.An R-value identification mark is applied(by manufacturer)to each piece of insulation 12
inches or greater in width.Alternately,the insulation installers have provided a signed,dated and posted certification listing the type,
manufacturer and R-value of insulation installed.Refer to code section for blown or sprayed insulation installation/settling depths and
marker requirements.
✓ 7. Insulation mark installation.Insulating materials are installed such that the manufacturer's R-value mark is readily observable upon
inspection.
✓ 8. Insulation product rating.The thermal resistance(R-value)of insulation has been determined in accordance with the U.S.FTC R-value
rule.
✓ 9. Installation.All material,systems and equipment are installed in accordance with the manufacturer's installation instructions and the
International Building Code.
✓ 10.Outdoor air intakes and exhaust openings.Stair and elevator shaft vents and other outdoor air intakes and exhaust openings integral
to the building envelope shall be equipped with not less than a Class I motorized,leakage-rated damper with a maximum leakage rate
of 4 cfm per square foot at 1.0 inch water gauge when tested in accordance with AMCA 500D.Stair and shaft vent dampers shall be
capable of being automatically closed during normal building operation and interlocked to open as required by fire and smoke detection
systems.
Requirement is not applicable.
Plans reference page/section:
✓ 11.Loading dock weatherseals.Cargo doors and loading dock doors are equipped with weather seals to restrict infiltration when vehicles
are parked in the doorway.
Requirement is not applicable.
Plans reference page/section:
✓ 12.Recessed lighting.Recessed luminaires installed in the building thermal envelope are sealed to limit air leakage between conditioned
and unconditioned spaces.All recessed luminaires are IC-rated and labeled as meeting ASTM E 283.All recessed luminaires are
sealed with a gasket or caulk between the housing and interior wall or ceiling covering.
Requirement is not applicable.
Plans reference page/section:
✓ 13.Vestibules.Doors that separate conditioned space from the exterior are protected with an enclosed vestibule,with all doors of the
vestibule equipped with self-closing devices.Vestibules are designed so interior and exterior doors to not operate simultaneously.
Requirement is not applicable.
Plans reference page/section:
✓ 14.'Other'components have supporting documentation for proposed U-Factors.
Requirement is not applicable.
Plans reference page/section:
Section 3: Compliance Statement
Compliance Statement: The proposed envelope alteration project represented in this document is consistent with the building plans,
specifications and other calculations submitted with this permit application.The proposed envelope alteration project has been designed to
meet the 2014 Oregon Energy Efficiency Specialty Code requirements in COMcheck-Web and to comply with the mandatory requirements in
the Requirements Checklist.
Name-Title Signature Date
Project Title: Landlord Improvement Report date: 02/01/17