Report (18) Plans reference page/section:
✓ 5. Heat pump supplementary heat.Heat pumps having supplementary electric resistance heat have controls that,except during defrost,
prevent supplementary heat operation when the heat pump can meet the heating load.
Plans reference page/section:
✓ 6. Set point overlap restriction.Where used to control both heating and cooling,zone thermostatic controls provide a temperature range
or deadband of at least 5°F(2.8°C)within which the supply of heating and cooling energy to the zone is capable of being shut off or
reduced to a minimum.
• Plans reference page/section:
✓ 7. Optimum Start Controls.Each HVAC system has controls that vary the start-up time of the system to just meet the temperature set
point at time of occupancy.
Plans reference page/section:
✓ 8. Off-hour controls.Each zone is provided with thermostatic setback controls that are controlled by either an automatic time clock or
programmable control system.
Plans reference page/section:
✓ 9. Shutoff damper controls.Both outdoor air supply and exhaust are equipped with not less than Class I motorized dampers.
Plans reference page/section:
✓ 10.Freeze Protection and Snow melt system controls.Freeze protection systems,such as heat tracing of outdoor piping and heat
exchangers,including self-regulating heat tracing,include automatic controls capable of shutting off the systems when outdoor air
temperatures meet code criteria.
Plans reference page/section: NA
✓ 11.Humidity control. If a system is equipped with a means to add or remove moisture to maintain specific humidity levels in a zone or
zones,a humidity control device is provided.
Plans reference page/section: NA
✓ 12.Humidity control.Where a humidity control device exists it is set to maintain a deadband of at least 10%relative humidity where no
active humidification or dehumidification takes place.
Plans reference page/section: NA
✓ 13.Ventilation.Ventilation,either natural or mechanical,is provided in accordance with Chapter 4 of the International Mechanical Code.
Where mechanical ventilation is provided,the system has the capability to reduce the outdoor air supply to the minimum required by
Chapter 4 of the International Mechanical Code.
Plans reference page/section:
✓ 14.Demand controlled ventilation(DCV).DCV is required for spaces larger than 500 ft2 for simple systems and spaces larger than 150 ft2
for multiple zone systems.
Plans reference page/section:
✓ 15.Kitchen hoods.Kitchen makeup is provided as required by the Oregon Mechanical Specialty Code.
Plans reference page/section:
✓ 16.Enclosed parking garage ventilation controls.In Group S-2,enclosed parking garages used for storing or handling automobiles employs
automatic carbon monoxide sensing devices.
Plans reference page/section: NA
✓ 17Air system balancing.Each supply air outlet and zone terminal device is equipped with means for air balancing in accordance with the
requirements of IMC 603.17.Discharge dampers intended to modulate airflow are prohibited on constant volume fans and variable
volume fans with motors 10 horsepower.
Plans reference page/section: NA
18.Manuals.The construction documents require that an operating and maintenance manual be provided to the building owner by the
mechanical contractor.See long description for specifications.
Plans reference page/section:
✓ 19.Allowable fan floor horsepower.Each HVAC system at fan system design conditions does not exceed the allowable fan system motor
nameplate hp(Option 1)or fan system bhp(Option 2)as shown and calulated in requirement details.
Plans reference page/section:
Project Title: Tigard APTS Report date: 09/08/16
Data filename:\\Projects.jetheating.local\Projects\2016\16-0219-TIGARD APTS\1 ENGR\11 SPPT\1 HVAC\Comcheck-Bldg
A3.cck Page 2 of 3
! 1 20AII air-conditioning equipment and air-handling units with direct expansion cooling and a cooling capacity at ARI conditions greater than
or equal to 110,000 Btu/h that serve single zones have their supply fan operation controlled according to code specific requirements.
f Plans reference page/section:NA
Section 5: Compliance Statement
Compliance Statement: The proposed mechanical design represented in this document is consistent with the building plans,specifications
and other calculations submitted with this permit application.The proposed mechanical systems have been deigned to meet the 2014
Oregon Energy Efficiency Specialty Code requirements in COMcheck Version 4.0.4.1 and to c. 'y wit n: andatory requirements in the
Requirements Checklist. / /
Jeff Stauffer, PE �y 7 i,I�l
Nam - � . r/ 8 Sept 2016
e Title
Sign.. re� 1 / I r Date
Section 6: Post Construction Complianc- Statement
0 HVAC record drawings of the actual installation,system capacities,calibration information,and performance data for each equipment
provided to the owner.
HVAC O&M documents for all mechanical equipment and system provided to the owner by the mechanical contractor.
u Written HVAC balancing and operations report provided to the owner.
The above post construction requirements have been completed.
Principal Mechanical Designer-Name Signature Date
Project Notes:
Building A3
Project Title:Tigard APTS
Data filename:\\Projects.jetheating.local\Projects\2016\16-0219-TIGARD APTS\1 ENGR\11 SPPT11 HVAC\Comcheck-Bldg Report date: 09/08/16
A3.cck
Page 3 of 3