October 29, 2006 .
RECEIVED
Project: Elite Care Extended Family Residence NOV 1 ?r;
12345 SW Grant St.
Tigard, Oregon 97223 CITY N DIVLS
BUILDING DIVt�tON
Summary of Lateral Engineering Revisions:
The engineering for the project residence has been revised from the originally
submitted engineering to reflect some plan changes. After a phone conversation
with Miller Consulting Engineers, code sections 1620.4.1 and 1620.2.9 have
been reviewed for plan irregularities. After another conversation with Miller
Consulting Engineers, concern of a soft story in the Solarium and passage
between the Main buildings was identified.
To resolve the soft story issue, the seismic design loads have been increased by
a multiple of 2.5. Some of the shearwalls on the ground level have been
lengthened by six inches and are sheathed on both sides. This increased lateral
resistance has increased the size of the footings below. Increased horizontal
diaphragm nailing requirements have also been added to the engineering.
The drawings are currently being revised to reflect these changes. The revised
engineering described above will be shipped to Miller Consulting Engineers the
week of October 30, 2006.
Please contact me by phone if there are concerns with the engineering approach
described above.
Respectfully submitted,
741,( 77W
Todd Rowell P
Rowell Engineering and Design
503-254-6292
JOB NAME: Pacific Park Plaza CITY OF TIGARD
JOB ADDRESS: 9975 SW Frewing BUILDING DEPARTMENT
DATE: January 10, 2006 13125 HALL BOULEVARD
MCE Project No.: 051333 , 1,/ TIGARD, OR 97223
iZ
SHEET 1 OF 1 C Tigard Building Permit BUP-2004-00297
STRUCTURAL PLAN REVIEW#2
Engineering Dated 3/22/06
Corr. Item Page No. Comments Code Section
Made No.
1 General Submit calculation for loads to shear walls as Table 1616.5.1.1 #2
required for the seismic and wind controlled Section 1620.4 &
directions. The analysis still needs to comply with Section 1609.1.5
Section 1609.1.5 which under simplified analysis
1617.5 requires compliance with 1620.2 that further
requires compliance with 1620.2 through 1620.5.
Therefore, submit details for lateral load transfer and
connections at the reentrant corner.
Not 2 Submit details for lateral load transfer and Section 2211
Req'd connections including Omega.
Not 3 Submit details for shear walls including fasteners, Section 2211
Req'd spacing and method of proper installation.
Not 4 Submit details and calculations as required. Section 2211
Req'd
5 Pages 3 The overturning calculations at the shear walls do not Section 1609.1.3
thru 6 of properly account for the application of forces from the
revised diaphragms. Submit calculations to properly account
calculation for the application of forces from the diaphragms to
the shear walls.
6 Pages 3 Submit calculations for the shear walls so as to Section 2306.4
thru 6 of comply with Table 2306.4.1.
revised
calculation
7 Plans Submit plans and details for the revised shear walls Section 106.1
including fasteners, spacing and method of proper
installation.
8 General Submit one set of manufactured floor and roof joist Section 106.3.4.2
shop drawings, which have been reviewed and
initialed by the project engineer, to be filed with the
City of Tigard before placement.
9
JOB NAME: Pacific Park Plaza .;t' CITY OF TIGARD
JOB ADDRESS: 9975 SW Frewing q r 'BUILDING DEPARTMENT
DATE: April 18, 2006 ` l v 13125 HALL BOULEVARD
MCE Project No.: 051333 $ N '
T� TIGARD, OR 97223
r. IGi '
SHEET 1 OF 1
Acf�+ 4 Tigard Building Permit BUP-2004-00297
G v)
REVISED STRUCTURAL PLAN REVIEW#2
Engineering Dated 3/22/06 / 4177- o
Corr. Item Page No. Comments Code Section
Made No. /9 U 1,0e-
Calculations
0e-
Calculations Submit calculation for loads to shear walls as Table 16-M#2
required for the seismic and wind controlled Section 1612.1 &
directions. The analysis still needs to comply with Section 1633.2.9
Section 1612.1 which requires compliance with
Sections 1633.2.5 and 1633.2.6. Therefore, submit
details for lateral load transfer and connections at the
reentrant corner.
Not 2 Submit details for lateral load transfer and Section 2211
Req'd connections including Omega.
Not 3 Submit details for shear walls including fasteners, Section 2211
Req'd spacing and method of proper installation.
Not 4 Submit details and calculations as required. Section 2211
Req'd
5 Pages 3 thru The overturning calculations at the shear walls do not Section 1612.1
6 of revised properly account for the application of forces from
calculations the diaphragms. Submit calculations to properly
account for the application of forces from the
diaphragms to the shear walls.
6 Pages 3 thru Submit calculations for the shear walls so as to Section 2315.1
6 of revised comply with Table 2306.4.1.
calculations
7 Plans Submit plans and details for the revised shear walls Section 106.3.3.1
per the calculations dated 3/22/06 including
fasteners, spacing and method of proper installation.
8 General Submit one set of manufactured floor and roof joist Section 106.3.4.2
shop drawings, which have been reviewed and
initialed by the project engineer, to be filed with the
City of Tigard before placement.
9 General Submit one set of stairway shop drawings, which Section 106.3.4.2
have been reviewed and initialed by the project
engineer, to be filed with the City of Tigard before
placement.
10 General Submit one set of suspended ceiling shop drawings, Section 106.3.4.2
which have been reviewed and initialed by the
project engineer, to be filed with the City of Tigard
before placement.
B NAME: Pacific Park Plaza CITY OF TIGARD
OB ADDRESS: 9975 SW Frewing, Tigard, OR BUILDING DEPARTMENT
DATE: May 4, 2006 13125 HALL BOULEVARD
MCE Project No.: 051333 TIGARD, OR 97223
SHEET 1 OF 3 Tigard Building Permit BUP-2004-00297
STRUCTURAL PLAN REVIEW#3
Engineering Dated 5/28/05, 3/22/06 and 4/15/06
Corr. Item Page No. Comments Code Section
Made No.
1 Calculations Submit calculation for loads to shear walls as Table 16-M#2
required for the seismic and wind controlled Section 1612.1 &
directions. The analysis still needs to comply with Section 1633.2.9
Section 1612.1 which requires compliance with
Sections 1633.2.5 and 1633.2.6. Therefore, submit
details for lateral load transfer and connections at the
reentrant corner.
Provide engineering to account for the bending in the
strap from the exterior wall to the line of action. In
addition, provide details in how the strap is
connected to the walls and the other framing.
Not 2 Submit details for lateral load transfer and Section 2211
Req'd connections including Omega.
Not 3 Submit details for shear walls including fasteners, Section 2211
Req'd spacing and method of proper installation.
Not 4 Submit details and calculations as required. Section 2211
Req'd
5 Pages 3 thru The overturning calculations at the shear walls do not Section 1612.1
6 of revised properly account for the application of forces from the
calculations diaphragms. Submit calculations to properly account
for the application of forces from the diaphragms to
the shear walls.
Provide information concerning the development of
the spreadsheet used in the calculations, as the
output seems to not properly account for the loads as
previously stated.
6 Pages 3 thru Submit calculations for the shear walls so as to Section 2315.1
6 of revised comply with Table 2306.4.1.
calculations Clarify the use of 505 plf for the capacity of the shear
walls as indicated in the plans.
7 Plans Submit plans and details for the revised shear walls Section 106.3.3.1
per the calculations dated 3t22/06 including
fasteners, spacing and method of proper installation.
Provide information for the complete lateral load path
to the foundation including bottom plate nailing and
anchor bolting.
8 Calculations Submit calculations and details to comply with the Section 1606.2
partition loading requirement.
JOB NAME: Pacific Park Plaza CITY OF TIGARD
JOB ADDRESS: 9975 SW Frewing, Tigard, OR BUILDING DEPARTMENT
DATE: May 4, 2006 13125 HALL BOULEVARD
MCE Project No.: 051333 TIGARD, OR 97223
SHEET 3 OF 3 Tigard Building Permit BUP-2004-00297
STRUCTURAL PLAN REVIEW#3
Engineering Dated 5/28/05, 3/22/06 and 4/15/06
Corr. Item Page No. Comments Code Section
Made No.
21 Plans Submit calculations and details for the trash Section 106.3.3.1
enclosure per the code requirements.
22 Plans Section 11/2 indicates a floor throughout the section, Section 106.3.3.1
whereas Sheet 9 indicates a clearstory volume.
Clarify and ensure the drawings are consistent.
23 Sheet 9 Submit calculations and details for the in-plane and Section 106.3.3.1
out-of-plane load transfer at the joist transition
between TJW and TJI joists.
24 Sheet 10 and Submit calculations for the joist connections at the Section 106.3.3.1
Detail 12/1 beams to comply with the code requirements.
25 Sheet 17 Clarify the shear wall locations as compared to the Section 106.3.3.1
wall locations as indicated in the wall elevations. In
addition, wall elevations 18/3 and 19/8 do not exist.
Provide information for each wall as required.
26 Sheet 17 Submit calculations and details for the load transfer Section 1612.1
between the full height shear wall and the two story
shear walls as indicated in the plans.
27 General Submit one set of manufactured floor and roof joist Section 106.3.4.2
shop drawings, which have been reviewed and
initialed by the project engineer, to be filed with the
City of Tigard before placement.
28 General Submit one set of stairway shop drawings, which Section 106.3.4.2
have been reviewed and initialed by the project
engineer, to be filed with the City of Tigard before
placement.
29 General Submit one set of suspended ceiling shop drawings, Section 106.3.4.2
which have been reviewed and initialed by the
project engineer, to be filed with the City of Tigard
before placement.
4
JOB NAME: Pacific Park Plaza CITY OF TIGARD
JOB ADDRESS: 9975 SW Frewing, Tigard, OR BUILDING DEPARTMENT
DATE: May 4, 2006 13125 HALL BOULEVARD
MCE Project No.: 051333 TIGARD, OR 97223
SHEET 2 OF 3 Tigard Building Permit BUP-2004-00297
STRUCTURAL PLAN REVIEW#3
Engineering Dated 5/28/05, 3/22/06 and 4/15/06
Corr. Item Page No. Comments Code Section
Made No.
9 Calculations Submit calculations and details for the ponding on Section 1612.3.3
the roof or show that the beams are adequate to
resist the additional loading as a result of the
ponding.
10 Calculations Submit calculations and details for the framing of the Section 1612.1
two-story walls including headers, sill framing and
columns to resist out-of-plane loading requirements.
11 Calculations Submit calculations and details for the second floor Section 1612.1
exiting including floor framing, floor framing
connections and the out-of-plane loading
requirements at the two-story ballooned framed wall.
12 Calculations Submit calculations and details for the snow drifting Section 1614
at the parapet along the perimeter per the code
requirements.
13 Revised Clarify the wind loading requirements as the Section 106.3.3.1
Calculations calculations indicate the 100 mph exposure 'B'
whereas the drawings indicate 80 mph exposure 'A'.
14 Revised Clarify the elevations of the building as the Section 1621.3
Calculations calculations indicate the overall building height as
29', but the drawings indicate the height to be 31' tall.
15 Revised Submit calculations and details for the seismic Section 1612.1
Calculations calculations including partition loading and storage
loading per the code requirements. In addition, show
calculations comparing the wind load in comparison
to the seismic load of sections "A" and "B".
16 Revised Submit calculations and details for the floor to floor Section 1612.1
Calculations holdowns in line with the capacities as listed by
Simpson Manufacturing.
17 Calculations Submit calculations and details for the uplift capacity Section 1612.1
Detail 8/2 & 3 of typical anchor bolts used as holdowns and the
allowable tension on the top of the thickened footing.
18 Calculations Clarify the use of the holdowns spaced at 4' o.c. and Section 106.3.3.1
Detail 8/2, 3 why they are used for negative tension.
& 10/3
19 Calculations Submit calculations and details for the in-plane and Section 1612.1
Detail 9/2 & 3 out-of-plane load transfer at the roof and floor
11/3 &4 diaphragms per the code requirements.
20 Calculations Submit calculations and details for the guardrails so Section 509
Detail 12/3 & as to comply with the code requirements.
4
JOB 'NAME: Pacific Park Plaza CITY OF TIGARD
JQU ADDRESS: 9975 SW Frewing, Tigard, OR BUILDING DEPARTMENT
DATE: May 26, 2006 13125 HALL BOULEVARD
M CE Project No.: 051333 TIGARD, OR 97223 •
SHEET 1 OF 4 Tigard Building Permit BUP-2004-00297
STRUCTURAL PLAN REVIEW#4
Engineering Dated 5/22/05 and 5/23/06
Corr. Item Page No. Comments Code Section
Made No.
1 Calculations Submit calculation for loads to shear walls as Table 16-M #2
required for the seismic and wind controlled Section 1612.1 &
directions. The analysis still needs to comply with Section 1633.2.9
Section 1612.1 which requires compliance with
Sections 1633.2.5 and 1633.2.6. Therefore, submit
details for lateral load transfer and connections at the
reentrant corner.
Provide engineering to account for the bending in the
strap from the exterior wall to the line of action. In
addition, provide details in how the strap is
connected to the walls and the other framing.
The submittal addressed a portion of the item.
Submit calculations and details to address each of
the items.
Not 2 Submit details for lateral load transfer and Section 2211
Req'd connections including Omega.
Not 3 Submit details for shear walls including fasteners, Section 2211
Req'd spacing and method of proper installation.
Not 4 Submit details and calculations as required. Section 2211
Req'd
5 Pages 3 thru The overturning calculations at the shear walls do not Section 1612.1
6 of revised properly account for the application of forces from the
calculations diaphragms. Submit calculations to properly account
for the application of forces from the diaphragms to
the shear walls.
Provide information concerning the development of
the spreadsheet used in the calculations, as the
output seems to not properly account for the loads as
previously stated.
The submittal is incomplete. Submit calculations and
details to address the item.
6 Pages 3 thru Submit calculations for the shear walls so as to Section 2315.1
6 of revised comply with Table 2306.4.1.
calculations Clarify the use of 505 plf for the capacity of the shear
walls as indicated in the plans.
Clarify the discrepancy between the plans and
engineering, as the engineering is based on
Structural 1 (from Table 23-11-I-1) whereas the
drawings specify OSB.
JOB NAME: Pacific Park Plaza CITY OF TIGARD
JOB ADDRESS 9975 SW Frewing, Tigard, OR BUILDING DEPARTMENT
DATE: May 26,2006 13125 HALL BOULEVARD
MCE Project Nc.: 051333 TIGARD, OR 97223
SHEET 2 OF 4 Tigard Building Permit BUP-2004-00297
STRUCTURAL PLAN REVIEW#4
Engineering Dated 5/22/05 and 5/23/06 •
!G� o Item Page No. Comments Code Section
Made No.
7 Plans Submit plans and details for the revised shear walls Section 106.3.3.1
per the calculations dated 3/22/06 including •
fasteners, spacing and method of proper installation.
Provide information for the complete lateral load path
to the foundation including bottom plate nailing and
anchor bolting.
The submittal is incomplete. Submit calculations and
details to address the item.
5/26/06 8 Calculations Submit calculations and details to comply with the Section 1606.2
partition loading requirement.
9 Calculations Submit calculations and details for the ponding on Section 1612.3.3
the roof or show that the beams are adequate to
resist the additional loading as a result of the
ponding.
The submittal is incomplete. Submit calculations and
details to address the item.
10 Calculations Submit calculations and details for the framing of the Section 1612.1
two-story walls including headers, sill framing and
columns to resist out-of-plane loading requirements.
The submittal is incomplete. Submit calculations and
details to address the item.
11 Calculations Submit calculations and details for the second floor Section 1612.1
exiting including floor framing, floor framing
connections and the out-of-plane loading
requirements at the two-story ballooned framed wall.
The submittal is incomplete. Submit calculations and
details to address the item.
5/26/06 12 Calculations Submit calculations and details for the snow drifting Section 1614
at the parapet along the perimeter per the code
requirements.
5/26/06 13 Revised Clarify the wind loading requirements as the Section 106.3.3.1
Calculations calculations indicate the 100 mph exposure 'B'
whereas the drawings indicate 80 mph exposure 'A'.
5/26/06 14 Revised Clarify the elevations of the building as the Section 1621.3
Calculations calculations indicate the overall building height as
29', but the drawings indicate the height to be 31' tall.
15 Revised Submit calculations and details for the seismic Section 1612.1
Calculations calculations including partition loading and storage
loading per the code requirements. In addition, show
calculations comparing the wind load in comparison
4
JOB NAME: Pacific Park Plaza CITY OF TIGARD
JOB ADDRESS: 9975 SW Frewing, Tigard, OR BUILDING DEPARTMENT
DATE: May 26, 2006 13125 HALL BOULEVARD •
MCE Project No.: 051333 TIGARD, OR 97223
SHEET 3 OF 4 Tigard Building Permit BUP-2004-00297
STRUCTURAL PLAN REVIEW#4
Engineering Dated 5/22/05 and 5/23/06
Corr. Item Page No. Comments Code Section
Made No.
to the seismic load of sections 'A"and "B".
The submittal is incomplete. Submit calculations and
details to address the item.
5/26/06 16 Revised Submit calculations and details for the floor to floor Section 1612.1
Calculations holdowns in line with the capacities as listed by
Simpson Manufacturing.
5/26/06 17 Calculations Submit calculations and details for the uplift capacity Section 1612.1
Detail 8/2 & 3 of typical anchor bolts used as holdowns and the
allowable tension on the top of the thickened footing.
5/26/06 18 Calculations Clarify the use of the holdowns spaced at 4' o.c. and Section 106.3.3.1
Detail 8/2, 3 why they are used for negative tension.
& 10/3 •
19 Calculations Submit calculations and details for the in-plane and Section 1612.1
Detail 9/2 & 3 out-of-plane load transfer at the roof and floor
11/3 &4 diaphragms per the code requirements.
The submittal is incomplete. Submit calculations and
details to address the item.
20 Calculations Submit calculations and details for the guardrails so Section 509
Detail 12/3 & as to comply with the code requirements.
4 The submittal is incomplete. Submit calculations and
details to address the item.
21 Plans Submit calculations and details for the trash Section 106.3.3.1
enclosure per the code requirements.
Clarify whether the trash enclosure is a deferred
submittal or not to be constructed.
5/26/06 22 Plans Section 11/2 indicates a floor throughout the section, Section 106.3.3.1
whereas Sheet 9 indicates a clearstory volume.
Clarify and ensure the drawings are consistent.
5/26/06 23 Sheet 9 Submit calculations and details for the in-plane and Section 106.3.3.1
out-of-plane load transfer at the joist transition
between TJW and TJI joists.
24 Sheet 10 and Submit calculations for the joist connections at the Section 106.3.3.1
Detail 12/1 beams to comply with the code requirements.
If the item is a deferred submittal, remove the call-
outs from the plans to avoid conflicts.
25 Sheet 17 Clarify the shear wall locations as compared to the Section 106.3.3.1
wall locations as indicated in the wall elevations. In
addition, wall elevations 18/3 and 19/8 do not exist. •
Provide information for each wall as required.
The submittal is incomplete. Submit calculations and
details to address the item.
JOB NAME: Pacific Park Plaza CITY OF TIGARD
JOB ADDRESS: 9975 SW Frewing, Tigard, OR BUILDING DEPARTMENT
DATE: May 26, 2006 13125 HALL BOULEVARD
MCE Project No.: 051333 TIGARD, OR 97223
SHEET 4 OF 4 Tigard Building Permit BUP-2004-00297
STRUCTURAL PLAN REVIEW#4
Engineering Dated 5/22/05 and 5/23/06
Corr. Item Page No. Comments Code Section
Made No.
26 Sheet 17 Submit calculations and details for the load transfer Section 1612.1
between the full height shear wall and the two story
shear walls as indicated in the plans.
The submittal is incomplete. Submit calculations and
details to address the item.
27 General Submit one set of manufactured floor and roof joist Section 106.3.4.2 •
shop drawings, which have been reviewed and
initialed by the project engineer, to be filed with the
City of Tigard before placement.
28 General Submit one set of stairway shop drawings, which Section 106.3.4.2
have been reviewed and initialed by the project
engineer, to be filed with the City of Tigard before
placement.
29 General Submit one set of suspended ceiling shop drawings, Section 106.3.4.2
which have been reviewed and initialed by the
project engineer, to be filed with the City of Tigard
before placement.