Report Bend Office (541)330-9155
Geotechnical Office (503)601-8250
Carlson Testing, Inc. Eugene Office (541)345-0289
Salem Office (541)589-1252
Tigard Office (503)684-3460
Special Inspection
FINAL SUMMARY LETTER
Date: October 14, 2014
Job#: T1401170.A
City of Tigard
13125 SW Hall Blvd
Tigard, OR 97223-8199
Attn: Building Division
Re: Project Name: Computer Solutions Tech—Tenant Improvement
Address:, 11105 SW Greenburg Rd.—Tigard, OR
Permit : BUP2014-00201 :
Per Chapter 17, Section 1704.1.2 of the International Building Code(IBC),we have performed special inspection of the following
item(s) per our inspection reports only:
Reinforced Concrete
Adhesive Anchors
All requested inspections and tests were performed and reported according to the requirements of project documents and to the
best of our knowledge, the work was in conformance with the approved plans and specifications, approved change orders and
applicable workmanship, provisions of the State Building Code and Standards, as well as the structural engineer's design
changes, approvals and verbal instructions.
Our construction inspection and testing services were provided and intended to help reduce the risk of construction defects,
deficiencies or omissions that arose during and after construction. Our services do not constitute a warranty or guarantee of any
type. Even with diligent construction monitoring and testing, construction defects, deficiencies or omissions in the contractor's
work may exist. It is the contractor's responsibility to perform their work in accordance with the approved construction
documents.
CTI has provided its professional services with the degree of care and skill currently exercised under similar circumstances by
members of its profession in the same locale. Statements made in our reports are based on technical judgments and should not
be construed to be conclusive representations of fact. Our reports pertain to the material tested/inspected only.
CTI's services did not include responsibilities related to determining, supervising, implementing or controlling the means,
methods, techniques, sequences or procedures of the construction or evaluating or reporting job conditions related to health,
safety or welfare.
Information contained herein is not to be reproduced, except in full, without prior authorization from this office. If there are further
questions regarding this matter please do not hesitate to contact this office.
Respectfully submitted,
CARLSON TESTING INC.
Keit R. Gauvin
Project Manager
KG/jk
cc: Robinson Construction Co— Ryan Robinson ryanr@robcon.com
City of Tigard Building Division—Walter'Chip' Barnett walter@tigard-or.gov
P:1 Projects\General12014\T1401170A\10-14-14 Final Letterdoc Updated 11/30/11