From: Wolff, John F. <John.Wolff @tvfr.com>
Sent: Thursday, May 16, 2013 11:16 AM
To: Mike White; Dan Nelson
Cc: Mark VanDomelen
Subject: RE: Hunziker
Code requirements for the gpm, according to their fire flow calc report of 4875 GPM
would dictates 5 hydrants. I am not asking for a hydrant farm but I believe based on
the GPM number of hydrants required and hydrant spacing requirements according to
Table C105.1 we need to have a valid reason to not meet the requirements. I am of
the opinion that we will need additional hydrants. One located where they are
proposing and at least another along Wall St perhaps on the south corner of the
property near the South entrance. By distance requirements, we actually need another
between the hydrant located on Hunziker at the NE corner of the site approx. 300 feet
along the east side towards the South entrance and one along the west side. I am
willing to work with them but like I said we would need a valid reason why they don't
need to meet code. As you know the system will be much more efficient if it is a loop
vs a dead end run. One on each corner and loop it would be the best situation for us
and meet the intent of the code.
My thoughts,
John
From: Mike White [mailto:MikeW@tigard- or.gov]
Sent: Wednesday, May 15, 2013 11:20 AM
To: Dan Nelson
Cc: Wolff, John F.
Subject: FW: Hunziker
Dan, John,
Here is a concept plan for an additional hydrant for the Hunziker Building (formerly Coe Manufacturing). John, do you
see any problems with it?
Mike
From: Steve Entenman f mailto:SteveE@ hhpr.coml
Sent: Wednesday, May 15, 2013 8:50 AM
To: Mike White
Subject: Hunziker
Mike —
This is what we are thinking.
1
Please comment.
Thanks
SteveE
Steven 1 Entenman, PE, SE
Structural Manager /Associate
HARPER HOUF PETERSON RIGHELLIS INC.
205 SE Spokane Street I Suite 200 I Portland, OR 1 97202
p: 503.221.1131 I f: 503.221.11711 SteveECalhhpr.comI hhpr.com
CIVIL ENGINEERS :: STRUCTURAL ENGINEERS :: PLANNERS :: LANDSCAPE ARCHITECTS :: SURVEYORS
1
DISCLAIMER: E -mails sent or received by City of Tigard employees are subject to public record laws. If requested, e-mail
may be disclosed to another party unless exempt from disclosure under Oregon Public Records Law. E -mails are retained
by the City of Tigard in compliance with the Oregon Administrative Rules "City General Records Retention Schedule."
2
iF f ag i4
# 418 ii
-----li .„41-
• li ILW llll1 :::::::::::::::::::::::t:.:::::::::::::
:.:•::• a •.
o ^ £
i 411
— :, : :: ::•:;•:•::• a a
:::::::::::::::::' I .
tijo
' '•:•.•. •:•i:•:•:•::::::::: 41 1 1;11 i ....
=152'. : >::::: iP _ a
y
.' ;::: '• ga d
M% ' 10: C) # f
/ Soli i : :i . / " ❖: :•:::i e R 0
00 • .•.•.•...
q 9 1A . .•. S}'
1 Non
8 E 4 A 1•::::;•::;•:.; !•• __• b i..�__ E i O•��
! s f it 1:111. 441 ii
I ' r tf ' 6 � P
I vrr-.. -- : , I a- .:�e• A� YSa -- . rJ= i 1 ■ ' �:. :. : ! . a
o I I I , ,
I H 1 1
I Q
il I
I #
; .
i `..»a..c�"�= rn ®fcm..SES r;..:3ct� e2i c..:t:C.r..,A1 ,.i 4 t
114 -------- - !W._ _
Eat r-
LI Iii 7
b li ,= Harper SITE PLAN
P r a c.-'.. j ' . • HIP. Houf Peterson
1 C a,, is , : r � ; Righellis Inc. 7940 HUNZIKER BUILDING ADDITION
a e v i s p o N s Dm O.. 3 � ' .`ti',.r..i >. ':': �.°;�, TIGARD, OREGON