MMD1998-00006 MMD98 00006 TIGARD CENTRAL INDUSTRIAL PARK September 8, 1998 Katie G. Twombly CITY OF TIGARD Tigard Central Industrial Park PO Box 230414 OREGON Tigard, OR 97281-0414 Dear Ms. Twombly: This letter is in response to your request for Minor Modification approval to place a second modular office building on the Tigard Central Industrial Park site located on SW Hall Boulevard. This property is zoned Light Industrial (L-I) in which the present manufacturing, storage and distribution uses of the site are permitted uses. The site received Minor Modification approval for the existing modular unit in December 1993. The Tigard Community Development Code Chapter 18.120, Site Development Review, provides that a modification ' to an approved site plan or existing use may be a major or a minor modification. Major modifications are processed as a new Site Development Review application. Section 18.120.070.B states that the Director shall determine that a major modification will result if one (1) or more of the following changes are proposed: 1. An increase in dwelling unit density, or lot coverage for residential development. The proposal does not include residential development; therefore, this criterion does not apply. 2. A change in the ratio or number of different types of dwelling units. The proposal does not include residential development; therefore, this criterion does not apply. 3. A change that requires additional on-site parking in accordance with Chapter 18.106. Section 18.106.030.D identifies required parking for industrial uses. Based on the applicant's information regarding the mix of industrial uses and associated office space on the site, the current required off-street parking is 198 spaces (57 manufacturing employees @ 1 space per employee = 57 spaces; 125,344 square feet of storage and distribution area @ 1 space per 1,000 square feet = 125 spaces; and 3,212 square feet of office area @ 1 space per 200 square feet = 16 spaces). Placement of the additional 1,056 square foot modular office building would require five (5) parking spaces (1 space required per 200 square feet) for a total of 203 spaces. The site plan indicates that the site currently has a total of 177 striped parking spaces, 26 spaces short of what the code would require for the modified site. The applicant has submitted a parking plan, prepared as part of an on-going parking lot re-sealing and striping project. The plan shows that the existing paved area can accommodate 204 spaces, including five (5) accessible spaces as required by ADA standards. Staff finds that this Minor Modification criterion is satisfied in that additional 13125 SW Hall Blvd., Tigard, OR 97223 (503) 639-4171 TDD (503)684-2772 Page 1 of 3 parking lot area will not be required as a result of the proposed modification and because the applicant has demonstrated how development code standards for off-street parking provision will be met on completion of the re-sealing and striping work. A condition of approval shall be that, prior to release of a final Certificate of Occupancy for the new modular structure, the City shall perform a site inspection and verify completion of the parking lot re-striping in conformance with the applicant's parking plan. 4. A change in the type of commercial or industrial structures as defined by the Uniform Building Code. The proposal will add one additional modular office structure adjacent to the existing modular unit approved in 1993. The proposal will not alter any of the existing structures in any way; therefore, this criterion does not apply. 5. An increase in the height of the building by more than 20 percent. As noted above, the proposal will not alter any of the existing buildings in any way; therefore, this criterion does not apply. 6. A change in the type and location of accessways and parking areas where off-site traffic would be affected. No changes are proposed to the location and type of existing parking areas or accessways that would affect off-site traffic. Therefore, this criterion does not apply. 7. An increase in vehicular traffic to and from the site and the increase can be expected to exceed 20 vehicles per day. The applicant has stated that an increase in the number of vehicles is expected as a result of the expansion. The expansion is to house additional office-based employees of Sauder Industries Ltd. No increase in customer or vendor visits to the site is anticipated. The increase in traffic is expected to be approximately ten (10) vehicles, less than the 20 vehicle threshold. Therefore, this criterion is not triggered. 8. An increase in the floor area proposed for a non-residential use by more than 10 percent excluding expansions under 5,000 square feet. The proposed modular building would add 1,056 square feet of office space. This is less than the 5,000 square foot threshold; therefore, this criterion is not triggered. 9. A reduction in the area reserved for common open space and/or usable open space that reduces the open space area below the minimum required by this code or reduces the open space by more than 10 percent. There is no common open space provided on the site and none is required in the underlying I-L zoning district. Therefore, this criterion does not apply. 10. A reduction of project amenities (recreational facilities, screening, and/or landscaping provisions) below the minimum established by this code or by more than 10 percent where specified in the site plan. Landscaping is the only existing on-site amenity. This proposal will not impact the existing landscaping as the modular unit will be placed on existing hard surface. 9/9/98 Katie Twombly, Ltr. Page 2 of 3 RE: Tigard Central Industrial Park Minor Mod. Approval to Add one Modular Building 11. A modification to the conditions imposed at the time of Site Development Review approval that are not the subject of criteria (B) 1 through 10 above. The proposal would not require a modification to any conditions imposed at the time of Site Development Review approval. This request is determined to be a minor modification to approved site plans. Pursuant to Section 18.120.080.C, the Director's designee has determined, based on the above findings, that the proposed modification is not a major modification and does not violate any code provisions. The proposed minor modification is, therefore, approved. THIS REQUEST HAS BEEN APPROVED SUBJECT TO THE FOLLOWING CONDITIONS: 1. Prior to issuance of final Certificate of Occupancy, the City shall inspect the completed parking lot sealing and re-striping project and certify the number and layout of spaces conforms with City standards and the applicant's approved parking plan. Please provide a copy of this letter when applying for permits. There is a fee for the required permits. Please contact the Development Services Division for information on the current fees. If you need additional information or have any questions, feel free to call me at (503) 639-4171 ext. 315. Sincerely, tiM ' 1(742j4)/..4 i(-1Z) M. 174 ierts ( Associate Planner is\curpin\mjr\minmod\ind-pa rk.doc c: 1998 Planning correspondence file 9/9/98 Katie Twombly, Ltr. Page 3 of 3 RE: Tigard Central Industrial Park Minor Mod. Approval to Add one Modular Building APPLICANT MATERIALS RECEIVED H. WILLIAM GAZELEY - KATIE G. TWOMBLY AUG - ! 1998 TIGARD CENTRAL INDUSTRIAL PARK COMMUNITY DEVELOP SENT P.O. BOX 230414 TIGARD, OR 97281-0414 OFFICE: (503) 245-4856 FAX: (503) 768-4508 August 4, 1998 M.J. Roberts, Associate Planner City of Tigard 13125 S.W. Hall Boulevard Tigard, OR 97223 Dear Mr. Roberts: According to our conversation this morning, I have submitted three (3) copies of the following letter, a site plan drawing, diagram of the GE Modular Office unit, First American Title plat map of the property. The property is across Hall Boulevard and the railroad tracks from the City of Tigard offices, I would be happy to meet you over at the site at your convenience to discuss the proposed project. REQUEST: Approval of a "Minor Modification of Existing Development". We would like to install an additional GE Modular office structure 24'x44' (1,056 square feet) to be installed next to the current GE Modular office unit on the property. The additional office space is needed by the tenant, Sauder Industries, Ltd. CRITERIA: Tigard Municipal Code 18.120.080 "Minor Modification(s)to Approved Plans or Existing Development. A) The proposed modification is not within the description of a Major Modification and therefore is considered a Minor Modification. B1) I am submitting three (3) copies of the proposed modified site plan. I have color coded parking (blue), landscaping (green) and the proposed location of the new GE Modular Office unit (red), as well as the other buildings in the park and their square footage as you requested when we talked this morning. B2) Narrative: In October, 1997 the lumber company Columbia Hardwood & Moulding who leases Buildings D,E,F and Modular#1 was sold to Sauder Industries, Ltd. Sauder is consolidating some of their operations in Vancouver, Washington with the manufacturing plant in Tigard. Sauder has entered into lease agreements to lease Building G in addition to D,E, and F which they currently lease. To accommodate the staff who will be working in Tigard instead of Vancouver, they need additional office space. The proposed office is the same as the GE Modular Office that was approved by the City of Tigard and installed in 1995. I am to address the criteria listed in the Tigard Municipal Code 18.120.070 Major Modification to Approved Plans or Existing Development, to establish that this falls under the Minor Modification, not a Major Modification. B1) Does not apply. This is an industrial area. B2) Does not apply. This is an industrial area. B3) Sauder Mouldings anticipates 10 additional vehicles, existing parking is ample to meet their needs. B4) We propose to add a second office identical to the one approved by the City of Tigard in 1995. B5) The height of the buildings will not be increased. B6) The accessways and parking areas are not affected by the location of the new office. B7) Sauder Mouldings anticipates 10 additional vehicles, existing parking is ample to meet their needs. B8) The additional footage is 1,056 and less than 10% increase in floor area. B9) The percentage of common open space is not reduced by more than 10%. B10) The project amenities will not be affected. B11) I do not understand what you are asking me to address here. The tenant, Sauder Mouldings, Inc. would like to make their transition to the new location on or before October 1, 1998, if possible. Please keep me informed of where we are in the process, and if there is anything that I can do to expedite the time frame, let me know. Thank you for your time this morning, you were very helpful. I look forward to hearing from you soon. Sincerely, Katie G. Twombly Fax: Ron Erdahl - Sauder, Tigard Maurice Paquette - Sauder, Corporate CS rskA tke tvetrig)) 0300,0 TIGARD CENTRAL INDUSTRIAL PARK - SITE PLAN BUILDING INFORMATION: 12670: 12700: ■ OFFICE A: 3,000 SF MAIN OFC: 2,100 SF OFFICE B: 1,500 SF BLDG#A: 17,520 SF -••• I BLDG#1: 19,680 SF BLDG#B: 13,400 SF CM TW.I EVEL ACCESS BLDG#2: 19,320 SF BLDG#C: 8,544 SF BLDG#3: 20,000 SF BLDG#D: 33,100 SF BLDG#1 BLDG#2 BLDG#3 OUTSIDE STORAGE BLDG#G: 28,500 SF AVAILABLE Ofc Proposed New Modular Office #A 12670 5.W. HALL BOULEVARD Landscaped Areas Ofc PROPOSED: MODUE1#2 (Lovirtivok_ VilsurtiLLA6 Ili00-14) #B II I 1 E Parking Areas(165 painted parking spaces,additional paved space available if necessary) MOD #1 - DOCK LEVEL ACCESS • ■ Driveway access and turning areas ""••, .........._ ..... .... .... I V ... ..... , . . 1... t A .. • MAIN OFFICE BLDG#A BLDG#B BLDG#C BLDG#F BLDG#0 11•11MIMIL al••••■■ BLDG#D BLDG#E 12700 S.W.HALL BOULEVARD KAILKUAI) 1KACKALTE KR UK NNORTH 1.{r. 'fin` �4,u �, !�0. -'i'�', l',. ' ip �L 1 ;. FEB 16 ' 95 17: 04 A(iE gC ' F. .I oAPMODSPACE 00 - 23' 6" 7 4' 9" 7' 0" / 3' 0" X —8' 9" A0117 CI ig ,1~1 g ... ., -I- --\ , . Pi 1. )0111 ...., Al° II 4 L -..f2,,p____.) 141- 34 - L. iii nil il 1 ---1 I * >1 .< 1\ e I y cb 11$ I 1: 1..... - a, >8( . . in, -;` • 0 i rd X Li 1�_ ‘"--0 St 4 [1 '(---1111 \M )7• 1 / fi 1• i N. 1 ">e< 00 f Xi H fl I X ' 4 s 0 9 _I / i X X ) / 1 \ r/' I I� w< :t 1 /11 r`\ `�4 1 I , i p Y )2I° . Z •1 .. 2*X 1 — I r% t4)11■1• I 1 v I s I C I X Hr ., 1 >v<X 1 , ' I ■ 0 1 C i i N> .. ['Ai �� yi y 10.. y 0' h .....)##.. THIS MAP IS FURNISHED AS A CONVENIENCE IN LOCATING PROPERTv AND THE COMPANY ASSUMES NO LIAB' FOR ANY VARIATIONS AS MAY BE DISCLO: 3Y ACTUAL SURVEY 0/S A N t ,C .: First American Title Insurance Company of Oregon _ _ -y • an a saum, business name of TITLE INSURANCE COMPANY OF OREGON `���` y 310 S.W. FOURTH AVENUE, PORTLAND, OR 97204 Ti._ (,(i (.9,.. .-1 Pit,- (503) 222-3651 , Pi COR4ER '•7.---. 2 S WWGRAHAM D.LC 99 \ SEE MAP 4 2S1 ZAA *TC •r. A lik. w - 4400. • F9Lf ' I //i \, �,A / o • SEE MAP 'f,, N• 2S I IBC 0 o"° SEE - MAP 9-Q s '. 1 18 D 4 Ni a•: \ 0 • O 7 11ii4. • • ° t .moo \:;\\;„\\\\\ b0 ~'. • 0 ~♦�• �) . /? PO 46, M[ GOP MUKZIR[R SI • "r k°v 800 ?o p.b o • 4 •AI ti Ilp N • •P`j6.5•38,4, fo SEE MAP `,f 1,f h 2S I 2 DA k w � � X tJ 41) .e. , . .s. . V7 t._ .,- 120000. 24.e• 19x4..... ....03..so.t.23...74 \ ,. ,,. Poi' 6 r 1 100 \T O s r 1 60,164A 60vec,) 0,800E4 TIGARD CENTRAL INDUSTRIAL PARK - SITE PLAN BUILDING INFORMATION: 12670: 12700: OFFICE A: 3,000 SF MAIN OFC: 2,100 SF Pilki"X er !BLDG#A: 17,520 SF fASA ... 5 BLDG : 19,680 SS FF 51BLDG#B: 13,400 SF ''.. CM Anp I:PATEL ACCFSS * ( s a-t BLDG#2: 19,320 SF , c BLDG#3: 20,000 SF BLDG#C: 8 544 SF cv , (A BLDG#D: 33,100 SF di BLDG#1#1 BLDG#2 BLDG#3 OUTSIDE STORAGE C$031 e 'BUZ#G: 28,500 SF i AVAILABLE Ofc Proposed New Modular Offle '(-1- 6 4 Fiet,itcp #A 12670 ;.W.HALL BOULEVARD , Landscaped Areas (tic(_ weArA cetkix3cui Ofc PROPOSED: MOD #2 Actaha fiB 1 _ 4 , E Parking Areas(165 painted parking spaces, additional paved space available if necessary) MOD #1 \ ■i 1 DOCK LEVEL ACCESS 1 Driveway access and turning areas . ......_..._ ., -- ••••••• •••' ..... • .4 . a'-----&"----111110111111111111111111111111' • .. . ' k. / •: , . '...-........-•-'''' - MAIN OFFICE , BLDG#A BLDG#B BLDG#C BLDG#F BLDG#G 11•11111111111■ - BLDG OD BLDG#E 12700 S.W.HALL BOULEVARD s KAILKCJAITTRACKALlt, k(K UK 1 ( ---\'-' -- / 'NORTH 0-, " jilt_ ' ' a 4 ix o> ' ..111$16:9" , :‘‘' ''' ..'f' '41**,,, ''.*ilt4-nZI*14,:°r':;;i5'1'';;;-:,:::.ti`; tt,...:'1,,, ,,,, : ,..,,. • ilLIII wpi "`M- ,1:4c.:4 ''''''' '''4'-, ' s.,\ % . 110 t %r 4 e �', x, a ° '"� i his y ' ., t' ; { t •Ii.:‘,."' - .;-,i •Sli • 'A AP,;(.. ' � � � � �^ k� l". � a ar ae te x� , ,w, fk e -�." a , a ,t, *\,,,‘''''''',.4.:;I*"k„i .1,-`1(N:5 i' t • : r 4& " s - " I - / , , *,,f,„-A,,.,.. ,I 1,..„ .„,- •, , .% .i.,,„0- - pqr:-7-.. lc""4-.--7 0,1* A& I. ' s.4*,N4:fi.:-*71---ri:t, 1r1 41t. Alit 411 '' '' V.t• , ': '''''.:14#7 4 '"14"..'" ft $ 4;4'; •} 4X � {-...,,r 40.6 � :� � .fit�-F- ,'"�`"3..„,_4.. Y �� d . •.11 f i. '� .'1°' • ",x ,a , '' s 09/11/98 16: 17 $503 684 7297 CITY OF TIGARD a001 ****************$:F:********* *** ACTIVITY REPORT *** i $*:t:************************ TRANSMISSION OK TX/RX NO. 7336 CONNECTION TEL 5032454856 CONNECTION ID START TIME 09/11 16:15 USAGE TIME 02'16 PAGES 3 RESULT OK September 8, 1998 Katie G_ Twombly CITY OF TIGARD Tigard Central Industrial Park OREGON PO Box 230414 Tigard, OR 97281-0414 Dear Ms. Twombly: This letter is in response to your request for Minor Modification approval to place a second modular office building on the Tigard Central Industrial Park site located on SW Hall Boulevard. This property is zoned Light Industrial (L-I) in which the present manufacturing, storage and distribution uses of the site are permitted uses_ The site received Minor Modification approval for the existing modular iUnit in December 1993. The Tigard Community Development Code Chapter 18.120, Site Development Review, provides that a modification to an approved site plan or existing se may be a major or a minor modification. Major modifications are processed as a new Site Development Review application. Section 18.120.070.B states that the DI irector shall determine that a major modification will result if one (1) or more of the followieg changes are proposed: 1. An increase in dwelling unit densiy, or lot coverage for residential development. The proposal does not include residential development; therefore, this criterion does not apply. 2. A change in the ratio or number of different types of dwelling units. The proposal does not include residential development; therefore, this criterion does not apply. 3. A change that requires additional on-site parking in accordance with Chapter 18.106. September 8, 1998 itigoopici d Katie G. Twombly CITY OF TIGARD Tigard Central Industrial Park PO Box 230414 OREGON Tigard, OR 97281-0414 Dear Ms. Twombly: This letter is in response to your request for Minor Modification approval to place a second modular office building on the Tigard Central Industrial Park site located on SW Hall Boulevard. This property is zoned Light Industrial (L-I) in which the present manufacturing, storage and distribution uses of the site are permitted uses. The site received Minor Modification approval for the existing modular unit in December 1993. The Tigard Community Development Code Chapter 18.120, Site Development Review, provides that a modification to an approved site plan or existing use may be a major or a minor modification. Major modifications are processed as a new Site Development Review application. Section 18.120.070.B states that the Director shall determine that a major modification will result if one (1) or more of the following changes are proposed: 1. An increase in dwelling unit density, or lot coverage for residential development. The proposal does not include residential development; therefore, this criterion does not apply. 2. A change in the ratio or number of different types of dwelling units. The proposal does not include residential development; therefore, this criterion does not apply. 3. A change that requires additional on-site parking in accordance with Chapter 18.106. Section 18.106.030.D identifies required parking for industrial uses. Based on the applicant's information regarding the mix of industrial uses and associated office space on the site, the current required off-street parking is 198 spaces (57 manufacturing employees @ 1 space per employee = 57 spaces; 125,344 square feet of storage and distribution area @ 1 space per 1,000 square feet = 125 spaces; and 3,212 square feet of office area @ 1 space per 200 square feet = 16 spaces). Placement of the additional 1,056 square foot modular office building would require five (5) parking spaces (1 space required per 200 square feet) for a total of 203 spaces. The site plan indicates that the site currently has a total of 177 striped parking spaces, 26 spaces short of what the code would require for the modified site. The applicant has submitted a parking plan, prepared as part of an on-going parking lot re-sealing and striping project. The plan shows that the existing paved area can accommodate 204 spaces, including five (5) accessible spaces as required by ADA standards. Staff finds that this Minor Modification criterion is satisfied in that additional 13125 SW Hall Blvd., Tigard, OR 97223 (503) 639-4171 TDD (503)684-2772 Page 1 of 3 parking lot area will not be required as a result of the proposed modification and because the applicant has demonstrated how development code standards for off-street parking provision will be met on completion of the re-sealing and striping work. A condition of approval shall be that, prior to release of a final Certificate of Occupancy for the new modular structure, the City shall perform a site inspection and verify completion of the parking lot re-striping in conformance with the applicant's parking plan. 4. A change in the type of commercial or industrial structures as defined by the Uniform Building Code. The proposal will add one additional modular office structure adjacent to the existing modular unit approved in 1993. The proposal will not alter any of the existing structures in any way; therefore, this criterion does not apply. 5. An increase in the height of the building by more than 20 percent. As noted above, the proposal will not alter any of the existing buildings in any way; therefore, this criterion does not apply. 6. A change in the type and location of accessways and parking areas where off-site traffic would be affected. No changes are proposed to the location and type of existing parking areas or accessways that would affect off-site traffic. Therefore, this criterion does not apply. 7. An increase in vehicular traffic to and from the site and the increase can be expected to exceed 20 vehicles per day. The applicant has stated that an increase in the number of vehicles is expected as a result of the expansion. The expansion is to house additional office-based employees of Sauder Industries Ltd. No increase in customer or vendor visits to the site is anticipated. The increase in traffic is expected to be approximately ten (10) vehicles, less than the 20 vehicle threshold. Therefore, this criterion is not triggered. 8. An increase in the floor area proposed for a non-residential use by more than 10 percent excluding expansions under 5,000 square feet. The proposed modular building would add 1,056 square feet of office space. This is less than the 5,000 square foot threshold; therefore, this criterion is not triggered. 9. A reduction in the area reserved for common open space and/or usable open space that reduces the open space area below the minimum required by this code or reduces the open space by more than 10 percent. There is no common open space provided on the site and none is required in the underlying I-L zoning district. Therefore, this criterion does not apply. 10. A reduction of project amenities (recreational facilities, screening, and/or landscaping provisions) below the minimum established by this code or by more than 10 percent where specified in the site plan. Landscaping is the only existing on-site amenity. This proposal will not impact the existing landscaping as the modular unit will be placed on existing hard surface. 9/9/98 Katie Twombly, Ltr. Page 2 of 3 RE: Tigard Central Industrial Park Minor Mod. Approval to Add one Modular Building 11. A modification to the conditions imposed at the time of Site Development Review approval that are not the subject of criteria (B) 1 through 10 above. The proposal would not require a modification to any conditions imposed at the time of Site Development Review approval. This request is determined to be a minor modification to approved site plans. Pursuant to Section 18.120.080.C, the Director's designee has determined, based on the above findings, that the proposed modification is not a major modification and does not violate any code provisions. The proposed minor modification is, therefore, approved. THIS REQUEST HAS BEEN APPROVED SUBJECT TO THE FOLLOWING CONDITIONS: 1. Prior to issuance of final Certificate of Occupancy, the City shall inspect the completed parking lot sealing and re-striping project and certify the number and layout of spaces conforms with City standards and the applicant's approved parking plan. Please provide a copy of this letter when applying for permits. There is a fee for the required permits. Please contact the Development Services Division for information on the current fees. If you need additional information or have any questions, feel free to call me at (503) 639-4171 ext. 315. Sincerely, it,/41/4) dffd Zr M. II'r:erts ( Associate Planner i:\curpin\mjr\minmod\ind-park.doc C: 1998 Planning correspondence file 9/9/98 Katie Twombly, Ltr. Page 3 of 3 RE: Tigard Central Industrial Park Minor Mod. Approval to Add one Modular Building (- ) "" U n°) AtiA� TIGARD CENTRAL INDUSTRIAL PARK - SITE PLAN BUILDING INFORMATION: 12670: 12700: ■ OFFICE A: 3,000 SF MAIN OFC: 2,100 SF OFFICE B: 1,500 SF BLDG#A: 17,520 SF BLDG#1: 19,680 SF BLDG#B: 13,400 SF CM ADF I RVF.I.ACC1,SS BLDG#2: 19,320 SF BLDG#C: 8,544 SF BLDG#3: 20,000 SF BLDG#D: 33,100 SF BLDG#1 BLDG#2 BLDG#3 OUTSIDE STORAGE BLDG#G: 28,500 SF AVAILABLE Ofc Proposed New Modular Office #A 12670 .i.W.HALL BOULEVARD Landscaped Areas (k4 ( 0 � L�-1 Ofc PROPOSED: MOD #2 #B _ Parking Areas(165 painted parking spaces,additional paved space available if necessary) - ' MO #1 DOCK LEVEL ACCESS I Driveway access and turning areas I MAIN OFFICE BLDG#A BLDG#B BLDG#C BLDG#F BLDG#G BLDG HD BLDG#E 12700 S.W.-HALL BOULEVARD RAILROAD I KACKAUI RK UK '1101 NNORTH ype Unit 00 MAP • 4320 ° uaa° 12670 SW HALL BLVD BLD 1 °M PNL # . . . : ° ° S ° 12670 SW HALL BLVD BLD 2 °OD ZON ° ° Z° 12670 SW HALL BLVD BLD 3 °ER SERVICE:TIG: ° ° C° 12700 SW HALL BLVD BLD A °ER SERVICE:SWR: ° uaP° 12700 SW HALL BLVD BLD B ° ISDICTION :TIG: ° ° : ° 12700 SW HALL BLVD BLD C ° •E • ° ° D° 12700 SW HALL BLVD BLD D °ATED • 05/11/98 : : BRE: ° ° 12700 SW HALL BLVD BLD E ° ° uaa° 12700 SW HALL BLVD BLD F ° ° 12700 SW HALL BLVD BLD G ° ° 12700 SW HALL BLVD OFFIC ° ° a * = Project address aaaaaaaaaaaaaaaaaaaaaai ° aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaeaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaai STREET ADDRESSES: Add Change Project-address Delete Esc Add address for this parcel OaPARCELaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaoaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaG ° : 2S10100 00500 ° CREATION DATE: / / ° adPROPERTY OWNERaaaaaaaaaaaaaaaaaaaaaaaaaaac LEGAL LOT-7 • • ° ° :GAZELEY, H WILLIAM ° LAND VALUE. . $ : 893500: ° :PO BOX 230414 ° BLDG VALUE. . $ : 773960: ° ° :OaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaL VALUE. . $ : 1667460: ° ° STREET ADDRESS °CEL USE. . . : ° ° : ° No. -- -- Street name Type Unit 00 MAP • 4320 ° uaa° 12670 SW HALL BLVD BLD 1 °M PNL # . . . : ° ° S° 12670 SW HALL BLVD BLD 2 °OD ZON ° ° Z ° 12670 SW HALL BLVD BLD 3 °ER SERVICE:TIG: ° ° C° 12700 SW HALL BLVD BLD A °ER SERVICE:SWR: ° uaP° 12700 SW HALL BLVD BLD B ° ISDICTION :TIG: ° ° 12700 SW HALL BLVD BLD C ° •E : ° ° D° 12700 SW HALL BLVD BLD D °ATED • 05/11/98 : :BRE: ° ° 12700 SW HALL BLVD BLD E ° uaa° 12700 SW HALL BLVD BLD F ° ° ° 12700 SW HALL BLVD BLD G ° ° ° 12700 SW HALL BLVD OFFIC ° ° a * = Project address aaaaaaaaaaaaaaaaaaaaaai ° aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaeaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaai . ° BLDG VALUE. . $: 1585170 : ° ° : 7034 SW 83RD ° TOTL VALUE. . $: 2371760: ° ° : ° PARCEL USE. . . : IND : 0 : PORTLAND OR 97223 ° TOPO MAP • 4321 ° uaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaac COMM PNL # . . . : 0 ° SIZE • 6. 27 :acres ° FLOOD ZON *NON: ° ° ZONING • I-L ° WATER SERVICE:TIG: ° ° COMPLAN • IL : ° SEWER SERVICE:SWR: ° uaPLAT NAMEaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaac JURISDICTION :TIG: 0 ° ° CIT • E : 0 ° DIV: : BLOCK: LOT: ° UPDATED • 05/11/98 : : BRE: ° uaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaac ° aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaeaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaai STREET ADDRESSES : Add Change Delete Esc Add address for this parcel OaPARCELaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaoaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaC o : 2S10100 00600 ° CREATION DATE: / / ° uaPROPERTY OWNERaaaaaaaaaaaaaaaaaaaaaaaaaaac LEGAL LOT, • • ° o :GAZELEY, HARRY M/THELMA T & ° LAND VALUE. . $ : 786590 : ° 0 :GAZELEY, H W ° BLDG VALUE. . $ : 1585170 : ° o :OaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaL VALUE. . $ : 2371760: ° o : ° STREET ADDRESS °CEL USE. . . : IND : ° o : ° No. -- -- Street name Type Unit 00 MAP • 4321 ° uaa° 12700 SW HALL BLVD BDG C °M PNL # . . . : ° o S° °OD ZON 'NON: ° o Z ° °ER SERVICE:TIG: ° o C° °ER SERVICE: SWR: ° uaP° °ISDICTION :TIG: ° ° • E : ° o D° °ATED ' 05/11/98 : : BRE: ° o ° ° ° uaa° ° o a * = Project address aaaaaaaaaaaaaaaaaaaaaai 0 aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaeaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaai AAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAXXAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAXAAAX WA�AAAAAAAAAAAAAAAAAAAAAAAWAAAAAWAAAAAAAAAAAAAA AAAAAAAAAA. AAAAAAAAAAAAAAX AATPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPP PAA SS3HQQY ON MS TOL00-00TOTSZ <M> ,AA AA, AA, AA. AA. AA. AA. AA. AA. AA. AA. AA, AA. AA. AA. IS H3IIZNfH MS 00280 00L00-00TOTSZ <M> D Dag# GAZE{ TIVH MS OOLZT 00900-00TOTSZ OI3304 GAZE{ TIVH MS OOLZT 00500-00TOTSZ O UZE{# GAZE{ TIVH MS OOLZT 00500-00TOTSZ 3 GZE{# GAZE{ TIVH MS OOLZT 00500-00TOTSZ 3 QZg# GAZE{ TIVH MS OOLZT 00500-00TOTSZ G QZg# QAZg TIVH MS OOLZT 00500-00TOTSZ O QZg# GAZE{ TIVH MS OOLZT 00500-00TOTSZ g aZg# QAgg TIVH MS OOLZT 00500-00TOTSZ • a1g4 GAZE TIVH MS OOLZT 00500-00TOTSZ £ 012# GAZE{ ZZVH MS OL9ZT 00500-00TOTSZ Z a72# GAZE{ TIVH MS OL9ZT 00500-00TOTSZ I GZg# GAZE{ TIVH MS OL9ZT 00500-00TOTSZ ATpgng ssaappy TaoaPd <M> .AA .AA ,AA .AA ,AA .AA ,AA .AA .AA .AA .AA .AA 0XA * ,AA AA, 73OHVd Ag ONILSIZ .AA AAPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPOAA AAAAAAAXAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAXAXXXAXXXXXXXXXX paooaa goaTaS osg osTW asPO-puTd 0400 goaTaS :ONIZSIZ ZTOUVd AAAAAAAAAAAAAAAAAAAAAAAAAAAAAAXAAAAAAAAAAAXXXAAAXAXAAAAAAAAAAXXXAAAAAAAAXXXXXXXX AAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAXXAAAAAAAAAAAAAAX AAIPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPUAA AA. AA. AA. AA. AA. AA, AA. AA. AA. AA. AA, AA. AA, AA, AA, AA. SS3HGUV ON MS TOL00-00TOTSZ <M> .AA .AA TIVH MS OOLZT 00900-00TOTSZ .AA TIVH MS OOLZT 00500-00TOTSZ .AA =II MS OOLZT 00500-00TOTSZ .AA TIVH MS OOLZT 00500-00TOTSZ .AA TIVH MS OOLZT 00500-00TOTSZ .AA ZZVH MS OOLZT 00500-00TOTSZ .AA TIVH MS OOLZT 00500-00TOTSZ .AA TIVH MS OOLZT 00500-00TOTSZ .AA TIVH MS OOLZT 00500-00TOTSZ .AA TIVH MS OL9ZT 00500-00TOTSZ .AA TIVH MS OL9ZT 00500-00TOTSZ .AA TIVH MS OL9ZT 00500-00TOTSZ .AA ssaappV TaoaPd <M> * .AA IS H3)IZNfH MS 00280 00L00-00TOTSZ <M> D oag# QAZg OI330# GAGE{ D UZg# GAZE{ • GZg# GAZE{ 3 GZg# GAZE{ G GZE{# GAZE( O GZg# GAZE{ g GZg# GAZE{ • QZg# GAZE{ E GZg# GAZE{ Z a7g# GAZE{ T GZg# GAZE{ ATpgnS 73OHVd AE{ ONIZSII .AA AAPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPOAA AXXXAAXXXXXXAAXXXAAAXAAXAAXXAAXAAAXAXXAXAAAAXXAAXAAXXXXXAXXXAAAXXXXXXXXXXXXAXXXX paooaa goaTeS osg osTW asuo-puT3 ogo0 goaTaS :ONIZSIZ 73OHvd AAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAARAAAAAAAAAAAAAAA AAAAAAXAXXXXXXXAAAAAAAAAAAAAAAAAAAAAAAAAAAAARAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAAA AATPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPPAA AA. SSJHGGV ON MS TOL00-00TOTSZ <M> .AA AA. LS H3>IZNfH MS 00280 2I jL___I_._._._\ ?SI IBB S.W. GARDEN Pl.ACe ( F O N p • SEE MAP N.W.CORNER 2 S I IBA , W.W GRAHAM O.L.C. 39 �' SEE MAP G A ' 2S I 2AA STO:: J g W /(4,04 I r" - - - << / �% �� H RMaSO 9j _ WAY /� C� N.E. COR. / c, ` GRAHAM DLC 39 SEE MAP ?.' sW • �/ SEVELANO vn ° 2S I IBC c SEE MAP 9,A • 2S I IBD O N135°59.20",W 985.88' \J is ,, \ ,,c,„.9 14,..10....0 e SEE h 11■,4,;/ \ Li c°�A - � NE CO ap,wILEY I � a ., y�i 9 6 m O Q y�0 fn .7 : ? EwZ.On lb- c O� S. 6 9 J� yS. '0.qo < \ ' h , N.:..4. o a s x ■ ''• s ' ti0 i ° /'' :1%. °' °' SEE MAP y k vF_O ,� 2S 1 I D B .- °... ,'5 1 �NOo,v,` M SEE MAP oq !• SW VARNS ST. 2S 1 2 D A '� Z w i \ X40°4 _ �"S- ADDITIONAL DOCUMENTS 12/3/99 Tag(s) for Parcel #: 2S10100-00600 • 10:26:10 AM Use Update Code Value Value Hold Description Notes Updated h PLN N Warning Minor Modification Tigard Central Industrial Park. Minor Modification to place a second 12/3/99 ST modular office building on site approved on September 8, 1999. See file in records. Page 1 of 1