August 20, 2013
Project No.03-8449 /4 7771/ 6
Stonebridge Homes Job No. 1426
Attention: Andy Thomas �5 T 2, 13 - a o l 3 7'
Stonebridge Homes .»..�t,ti,2✓
4230 SW Galewood St., Ste. 100 / S/ �� S`" S',,
Lake Oswego, OR 97035
Fax 503-387-7615
SEWER CONNECTION BACKFILL
LOT 55—ARLINGTON HEIGHTS NO.3
15154 SW SUMMERVIEW DRIVE
CITY OF TIGARD,OREGON
This brief report presents the results of our density testing for the sewer connection that was too
close to the porch pad footing. Density testing achieved 95 percent of the standard Proctor
maximum dry density. The porch pad is not adequately laterally supported.
Our work scope pertains to a.geotechnical engineer's foundation excavation review only and the
conditions existing and exposed at the time of our site visit. Within the limitations of scope, schedule
and budget, GeoPacific attempted to execute these services in accordance with generally accepted
professional principles and practices in. the fields of geotechnical engineering and engineering
geology at the time the report was prepared. No warranty, expressed or implied, is made. If you
have any questions, please call.
Sincerely,
GeoPacific Engineering, Inc.
���co PRoppso
c`J =GIN S ' .
47•
OREGON
ZS DA
EXPIRES:06/30/M/i
•
James D. Imbrie, G.E.
Geotechnical Engineer