Correspondence City of Tigard, Oregon • 13125 SW Hall Blvd. • Tigard, OR 97223
October 21, 2008 67653 s-1 , I II
RE: FIRE SPRINKLER SYSTEM cot
Information
Building Permit: BUP2008 -00350 Construction Type: 2 -B
Tenant Name: Sanrio Occupancy Type: M
Address: 9585 SW Washington Sq. Occupant Load: 27
Area: NA Stories: 2
The plan review was performed under the State of Oregon Structural Specialty Code
(OSSC) 2007 edition; National Fire Protection Association, Standard 13 (NFPA 13)
2002 edition and the State of Oregon Fire Code (OFC) 2007edition.
GENERAL
1. The clearance between the deflector and the top of storage shall be 18 inches or
greater. Section 8.6.6.1 NFPA 13. The distance shall be increased to 36 inches
for Large Drop sprinkler heads. Section 8.11.6 NFPA 13
2. Sprinklers shall be located a minimum of 4 inches from walls and spaced not less
than 6 feet on center. Sections 8.6.3.3 & 8.6.3.4.1 NFPA 13.
3. Clearances shall be provided around all piping extending through platforms,
foundations, walls and floors. The diameter of the hole shall be 2 inches larger
than the penetrating pipe for pipe sizes 1 inch through 3'/ inches. The diameter
of the hole shall be 4 inches larger than the penetrating pipe for pipe sizes 4
inches and larger 2 inches is required. Sections 9.3.4.1 & 9.3.4.2 NFPA 13.
4. The system piping shall be braced to resist both lateral and longitudinal
horizontal seismic loads to prevent vertical motion resulting from seismic loads.
The structural components to which bracing is attached shall be determined to be
capable of carrying the added applied seismic loads. Sway braces shall be
designed to withstand forces in tension and compression. Bracing shall be
attached directly to feed and cross mains.
5. The end sprinkler on a line shall be restrained against excessive vertical and
lateral movement.
6. All concealed spaces enclosed wholly or partly by exposed combustible
construction shall be protected by sprinklers.
7. Sprinkler heads must have 1 inch free movement in any direction at head
penetration in ceiling tile or a flexible head design.
Phone: 503.639.4171 • Fax: 503.684.7297 • www.tigard or.gov • TTY Relay: 503.684.2772
Approved Plans: 1 set of approved plans, bearing the City of Tigard approval stamp,
shall be maintained on the jobsite. The plans shall be available to the Building Division
inspectors throughout all phases of construction. 106.4.2 OSSC
When submitting revised drawings or additional information, please attach a copy of the
enclosed City of Tigard, Letter of Transmittal. The letter of transmittal assists the City
of Tigard in tracking and processing the documents.
Respectfully,
de r
igo
Dan Nelson,
Senior Plans Examiner
(503) 718 -2436
dann @ tgard- or.gov