Meeting Notes
SUBJECT: Jurisdictional Meeting / Project Overview
PROJECT: Dr. Sepp, Dentist Office Project
MTG. DATE: July 01, 2004
LOCATION: 16035 SW Pacific Highway
ATTENDEES: Gary Lampella, City of Tigard
Allan Clair, CLAIR
Deborah Martisak, CLAIR
Dr. Sepp, Property Owner
NOTES BY: Deborah Martisak, CLAIR
Meeting Summary 4:00 PM to 5:30 PM:
Meeting held on -site to discuss the status of the Project and to determine jurisdictional
responsibility.
Project Summary: Type V -N Building,
No Sprinklers,
No Fire Alarm
2,500 SF,
3- Stories,
B- Occupancy
The scope of this Project as defined by the City of Tigard is the conversion of a single -
family dwelling to business occupancy (R3 to B Occupancy), dentist office.
Permits issued from City of Tigard on December 15, 2003, include Building, Mechanical,
Site Plumbing & Plumbing. The Site Plumbing permit has been withdrawn.
Additional square footage that was not originally permitted by City of Tigard has been
designed and is in the process of being constructed.
The following is a summary of the discussions held and the action required by all parties in
attendance.
•
Jurisdictional Meeting / Project Overview
w c La i r July 1, 2004
E L Page: 2 of 4
AR # Subject Define Action Responsible Date Due
Party
07.01.04 - Exterior Decision by Dr. Sepp is pending on whether to Dr. Sepp N/A
#1 Siding remove or keep the existing siding. If siding is
removed a Building Permit is required to be
pulled. Permits for any new scope of work, not
already permitted by City of Tigard, will need to
be permitted by the City of King City. It appears
as indicated on the March '04 submitted plans
and calculations that, that the plans indicate the
removal of the siding and installation of new
lateral bracing / sheathing.
07.01.04 Engineering Use and design methodology has been altered, Dr. Sepp Submit with
#2 & Design examples provided below; Revised
1)Third floor (attic) will not be converted to an Plans
office space. The stairs will be removed and
the attic will be an unoccupied — unfinished
space.
2) Larger windows were installed in patient
lobby area.
3) Additional square footage to the permitted
floor plan as been added above the garage.
4) Steel beam shown on plans was constructed
with a wood glue -lam beam.
5) Removal of stair case (pending).
•
Based on the above noted design changes, Dr.
Sepp will need Engineer / Designer to revise
structural calculations and IFC drawings. Once
documents are completed, submit 4 -sets of
copies to the City of Tigard. City of Tigard will
determine what needs to be permitted by City of
King City and will forward accordingly. Once
the determination of what City of King City will
be reviewing and inspecting of the new scope of
work, CLAIR will contact Dr. Sepp and
coordinate the permits.
07.01.04 Patient Engineer of Record (current plans) indicate Dr. Sepp Submit with
#3 Lobby Area hold -downs directly under an existing window. Revised
— N.E Corner Please provide revised hold -down design for Plans
of Wall this area.
Shear Wall
Hold -Downs
•
Jurisdictional Meeting / Project Overview
c La i r July 1, 2004
Page: 3 of 4
AR # Subject Define Action Responsible Date Due
Party
07.01.04 Lateral Request Engineering for lateral support. Dr. Sepp Submit with
#4 Support Revised
Plans
07.01.04 West End of Provide engineering for support of bearing wall Dr. Sepp Submit with
#5 Glue -lam where glue -lam beam is currently installed. Revised
Support Plans
07.01.04 Rafters — S Provide ventilation for the rafters in the vaulted Dr. Sepp Prior to
#6 Wall — Side ceiling. Framing
Exit Door Inspection
Room
07.01.04 Use of Third Provide revised plans indicating that the Attic Dr. Sepp Submit with
#7 Floor - Attic will be an occupied — unfinished area. Revised
Plans
07.01.04 Shear Wall - The plans indicate that the plywood attached to Dr. Sepp Before
#8 Back of the shear wall is to be nailed not screwed. Framing
Space — Please construct per approved plans and Inspection
West Side, details or get approval from Engineer or
Adjacent to Record.
Side Exit
Door
07.01.04 Additional Once revised plans and calculations are Dr. Sepp After plans
#9 SF Above received by CLAIR from the City of Tigard, the have been
Garage following permits will need to be applied for revised and
from the City of King City; submitted
Building Permit (valuation of new SF only) to City of
Mechanical Permit & Electrical Permit Tigard
07.01.04 Additional Provide engineering for built -up beam header Dr. Sepp Submit with
#10 SF Above over garage and validate adequate footing Revised
Garage support. Contractor indicated that the built -up Plans
header would be in- filled with bearing wall
below, foundation footing and wall design
should be provided.
07.01.04 Additional Provide square footage of the new addition over Dr. Sepp Submit with
#11 SF Above the garage. Revised
Garage Plans
07.01.04 Additional Please review item #2 for details of the process Dr. Sepp Submit with
#12 SF Above to follow. In addition, please provide 4- copies Revised
Garage of the truss details, lateral analysis and design Plans
intent for the additional SF to the office space
for plan review.
07.01.04 City of City of Tigard, plan review conditions of Dr. Sepp Before
#13 Tigard — approval comments dated December 15, 2003, Occupancy
Plan Review which are attached for your review, need to be
Comments addressed and closed -out prior to Certificate of
Occupancy.
Jurisdictional Meeting / Project Overview
IMP cLair July 1, 2004
Page: 4 of 4
AR # Subject Define Action Responsible Date Due
Party
07.01.04 Inspection All required inspection requests are to be Dr. Sepp 24 -hours
#14 Requests handled through CLAIR Company. Please call and /or Prior to
(800) 838 -8855, 24 -hours in advance for General When
inspection needs. The following inspections are Contractor Inspection
required; is Needed
1) Structural - Framing, Roof/ Wall Sheathing,
Shearwalls, Insulation, Suspended Ceiling &
Final
2) Mechanical — Rough & Final
3) Electrical — Rough -In / Cover, Dwelling
Service /Feeder, Exterior Lighting & Final
4) Plumbing — Rough -In / Top -out & Final
5) Other — Driveway / Approach, Sidewalk —
ADA Ramps, Pre - Paving & Final Occupancy
07.01.04 Special Property Owner to contract with Special Dr. Sepp Prior to the
#15 Inspections Inspection Agency to inspect the epoxy anchor Installation
hold- downs. of Hold -
Downs
07.01.04 Certificate of Once all inspections have been completed and City of After
#16 Occupancy permits finaled, City of Tigard will issue the Tigard Inspections
Final Certificate of Occupancy for the entire are Finaled
structure.
07.01.04 Fire Hazard Please remove large amount of debris that is Dr. Sepp As Soon As
#17 placed up against the house. City of King City Possible
considers this a potential fire hazard.
Completion of Minutes
These meeting minutes were prepared by Deborah Martisak of Clair Company, Inc. Any
additions or corrections are requested submitted in writing within 48 hours of receipt of these
meeting minutes. If no corrections are received, these minutes will be deemed an accurate
account of the items discussed.
•
—4411
December 15, 2003 CITY OF TIGARD
OREGON
Mike Roloff
Roloff Construction, Inc.
11004 SW 37 Ave.
Portland, OR 97219
RE: Change of Use /Occupancy – Building Permit
Project Information
Address: 16035 SW Pacific Hwy Floor Area: 2,500 Sq.Ft.
Permit #: BUP2002 -00369 Stories: 3
Occupancy: B Construction Type: V -N
Tenant: Dr. Sepp Sprinklered: No
Jurisdiction: King City Fire Alarm: No •
• The scope of this project is the conversion of a single - family dwelling to business
occupancy, dentist office. This review was performed under the provisions of the
Uniform Code for Building Conservation (UCBC), 1997 edition, Oregon Structural
Specialty Code (OSSC), 1998 edition and Uniform Fire Code (UFC), as amended
by Tualatin Valley Fire & Rescue, 1999 edition. The plans are approved subject
to the following
Plan Review Comments
1. The proposed use is a dentist office. The main floor will be utilized for
customers and the top floor will contain an administrative office for the
dentist. The lower floor and the remainder of the top floor will not be used
and may be future space. Any other modifications of this future space will
be under the jurisdiction of the City of King City.
2. The lateral analysis by Tim Covert, Structural Engineer, requires Simpson
Set Epoxy Anchors to be installed. Carlson Testing, Inc. has been
identified as the special inspection agency that will perform these
inspections. Please send reports to Hap Watkins, Inspection supervisor at
13125 SW Hall Blvd., tiger, OR 97223. OSSC Chapter 17
3. The frontage road improvements required by the Oregon Department of
Transportation shall be completed and approved prior to use or occupancy
of the building.
13125 SW Hall Blvd., Tigard; OR 97223 (503) 639 -4171 TDD (503) 684 -2772
•
•
4. All land use conditions required by the City of King City shall be completed
and approved by King City prior to the use or occupancy of the building.
5. A minimum of (1) fire hydrant shall be located within 250 feet of all
portions of the building and at least (1) additional hydrant shall be located
within 500 feet of the closest portion of the building. UFC 903.4
6. Fire lanes as required by the Fire Marshal shall be marked and maintained
as required by ORS 98.810 through 98.812. UFC 901.4.5.1
7. An accessible entry with an accessible route connecting to the accessible
• parking space is required. If the existing door and threshold are to be
used, the threshold may be 3 /4 inch high if a beveled edge is provided on
each side. OSSC 1108.1.1.2 and 1113.3.6.2 -
8. The accessible entry doors and doors on the path of travel to the
• accessible restroom, as well as the restroom, shall have lever type
hardware that does not require tight grasping, pinching or twisting to
operate. OSSC 1109.3.2 and 1109.9.8
9. The accessible restroom shall be signed with the international symbol of
access as required by OSSC 1108.4.12.1
10.A minimum 2A:10BC fire extinguishers shall be provided in the building so
the travel distance to an extinguisher does not exceed 75 feet. UFC
Standard 10 -1
11.A copy of the approved plans shall be on the job site at all times and
available to the City of Tigard inspectors for inspection purposes. OSSC
Section 106.4.2.
12.A final inspection and Certificate of Occupancy is required prior to
occupying for the intended use of this building or parts thereof. OSSC
Section 109.1.
If you have questions regarding this review, please call me at, (503) 718 -2448.
Sincerely,
Gary Lampella
Building Official
c. Hap Watkins, Inspection supervisor
Clair Company
File