For Agenda of .1-4 ~ a5- Duo
Tigard City Council Meeting Minutes
Date: March 21, 2006
Time: 6:30 p.m.
Place: Tigard City Hall, 13125 SW Hall Boulevard
Tigard, Oregon
Attending: Mayor Craig Dirksen Presiding
Councilor Sally Harding
Councilor Sydney Sherwood
Councilor Nick Wilson
Councilor Tom Woodruff
Agenda Item Discussion & Comments Action Items follow u
Workshop 1.1 Mayor Dirksen called the City Council to Order
Meeting at 6:30 p.m.
1.2 Council Present: Mayor Dirksen, Councilors
Harding, Sherwood, Wilson, and Woodruff.
1.3 Pledge of Allegiance
1.4 Council Communications & Liaison Reports
Mayor Dirksen reported that several City
Council members met last week in Washington
D.C. with Congressional leaders and delegates
from other jurisdictions. It was noted that
these meetings appeared to be valuable in
furthering the City of Tigard's interests for the
future.
Councilor Harding noted she attended a recent
D.A.R.E. graduation at Templeton Elementary
School. School officials thanked the City of
Tigard for its support.
Mayor Dirksen advised that the Youth
Advisory Summit was held last week. The
Summit was attended by 50 high school and
middle school students and focused on drug
abuse. Speakers included young people talkin
Council Meeting Minutes Page 1
March 21, 2006
Agenda Item Discussion & Comments Action Items follow u
about the affect that drug abuse has had in their
lives. Mayor Dirksen extended his thanks to
Assistant to the City Manager Newton and
supporters of "Tigard Turns the Tide."
1.5 Call to Council and Staff for Non-Agenda
Items
See Agenda Item No. 9.
2. Joint Meeting Staff Presenters: Finance Director Sesnon;
with Budget Financial Operations Manager Imdieke
Committee - Staff
Response to The following information was reviewed:
Financial Strategy
Task Force - Review of proposals for development of a
Report comprehensive communication plan to provide
Recommendations information on the results of the performance
audits, property tax rate education and
information, how efficient the City is in providing
services, and how City services are actually funded.
- A comparison analysis of tax rates on assessed
property only (ad valorem taxes) with fire and park
districts included, where appropriate. A similar
chart will be published in the May edition of the
Cityscape.
- Discussed franchise fees and how the City of
Tigard compares. City Manager Prosser indicated
the City, as well as the League of Oregon Cities,
had previously prepared this comparative
information.
- Recommendation to prepare a `Budget in Brief
document, which is condensed into a format that is
interesting and understandable. This document
would be published after Budget adoption.
- Discussed the performance audit that is planned
for key areas/programs, especially those in the
General Fund. This is the right direction to take;
however, it should not become an "exercise in
validation." The proposed budget will include an
amount to fund the audit. It was suggested to have
Council Meeting Minutes Page 2
March 21, 2006
Agenda Item Discussion & Comments Action Items follow u
continuing citizen involvement consisting of
individuals who will be involved in the audit
process (advisory).
- Goals and objectives of the Finance Department
will include a process review for procurement.
- Further efficiencies by identifying duplicative
efforts.
- Continue adjusting fees and charges to recover
costs.
- Seek City Council support of any reasonable
County tax measure that would bring additional
revenue to the City.
- Maximize grant revenues and the City's share of
revenues from other agencies (State, County, Clean
Water Services).
- Any local option levy should capture the cost of
the program or service as well as the cost of all
related support services and overhead. There was
discussion on the result if a levy is passed initially
and then not renewed by the voters; hence,
programs/services/administration overhead would
all "go away."
- Develop and pursue corporate/private sector
funding or sponsorship of programs and projects
when possible.
- Continue to pursue cooperative agreements with
other agencies. At a recent meeting with the
School District, officials identified 20 ways to work
together.
- Consider outsourcing by contracting with private
providers for services.
- Analyze future financial impact of new program
initiatives, capital acquisitions, and construction
projects. Staff will show five-year projections of
financial impacts.
Council Meeting Minutes Page 3
March 21, 2006
Agenda Item Discussion & Comments Action Items follow u
- Grants were discussed. When applying for ,
grants, consider how much must be matched by
the City. Also, the grant should fund a program
the City has already identified (relates to
established goals). It was noted, however, that
grants are often "opportunity-driven."
- Discussed how grant revenues are tracked. A
special audit is triggered if the City expends more
than $500,000 of federal funds in a fiscal year.
- Councilor Woodruff requested to see
information about "tracking of grants overall."
- Councilor Harding suggested a volunteer be
sought to track the available grants; i.e., from the
League of Oregon Cities "Grant Station."
- Agreement among Budget Committee members
that the overall approach to a local option levy
should be considered carefully.
- Discussion on offering voters the opportunity to
vote on individual projects or programs thereby
providing a direct link to taxes and services.
Terminology applied to such a proposal included
"ala carte taxes" or "cafeteria taxes." It was noted
that this was submitted as a strategy to consider,
although, it might be difficult to implement.
3. Proposed Staff Presenter: City Engineer Duenas
Capital
Improvement The PowerPoint presentation overview is on file in
Program Projects the City Recorder's office. The overview included:
for 2006-07 - Formulation Process
- Program Areas
- Priorities for FY 2006-07
- Proposed Projects
- Tigard Downtown Projects
- Citywide Projects
There was discussion on the following:
- Senior Center Remodel/Seismic Upgrade; look Staff will follow up with
at applying fora ant; this is a time-sensitive representatives from the
Council Meeting Minutes Page 4
March 21, 2006
Agenda Item Discussion & Comments Action Items follow u
project. Discussed looking at other alternatives adjacent church property to
for a senior center such as the adjacent church's determine about potential
property, which might be relocating. senior center
facility.
- Hall Boulevard/99W Project; discussed the
possibility of the City participating in this County
project. Also discussed potential purchase of
property to incorporate a median to serve as a
pedestrian refuge on 99W.
- Reviewed additional street projects, including:
- 108`h/Durham Road intersection
signalization
- Wall Street improvements, including
removing one pond and realigning
Pinebrook Creek
- Tigard/Tiedeman intersection improve-
ments. There might be an opportunity for
additional transportation improvements if
one of the railroad tracks is removed.
Perhaps if one railroad crossing is closed,
there might be an opportunity to add a
crossing at Ash Avenue. There was
discussion about problems associated with
the railroad transportation system within the
City and a need to address the system of
trains and signals.
- The bridge/viaduct at 99W might be
replaced, representing another opportunity
to resolve some Tigard transportation issues.
- Skate Park funding was reviewed. The City
will apply again for a state grant. This time
the City will make some assurances about the
amount it will match if the grant is awarded.
- It was noted the pedestrian barricade at
Hall/Fanno Creek bridge needs to be
repaired.
- Water supply projects were reviewed,
including the City's participation in projects
as a partner with the joint Water
Commission.
Council Meeting Minutes Page 5
March 21, 2006
Agenda Item Discussion & Comments Action Items follow u
- Funding for land acquisitions will be set
aside over several fiscal years.
- CIP projects scheduled for one year, but not
completed, will be carried forward to the
next fiscal year.
4. Downtown Staff Presenter: Senior Planner Nachbar
Capital
Improvement The PowerPoint overview, "Capital Improvement
Project Priorities and Strategy for the Downtown" was
Priorities /Budget presented to the City Council.
Three strategic goals and action plans for these
goals were reviewed:
1. Stimulate new development to generate "tax
increment" revenues. Redevelopment potential
was discussed.
2. Assist Main Street as it transitions to a more
dynamic commercial district. Support of a
pedestrian-oriented commercial district and a
visually attractive and safe streetscape was
discussed. The unknown impact of the
Commuter Rail on some of the properties was
noted. Over time, it is anticipated that land uses
will change.
3. Capitalize on Fanno Creek Park as a key public
gathering space and amenity for new
development. The first step is to produce a new
Master Plan for the Park. The Park will be used
to strengthen the marketability and value of
projects for developers and create important
civic spaces for the community.
Redevelopment projects will be pursued that
have a public space, park or plaza as a part of
the project to develop public support.
While the Urban Renewal Plan does not include
the use of condemnation, agreements with
property owners would be considered.
Capital improvement priorities and the budget for
downtown were reviewed. Projects were ranked
Council Meeting Minutes Page 6
March 21, 2006
Agenda Item Discussion & Comments Action Items follow u
according to criteria in an attempt to be more
objective and review projects critically. Identified
projects also relate to the goals for the downtown.
During the discussion of the budget review, it was
noted the $100,000 figure for land acquisition was
based on the assumption that the land to be
acquired is located in the floodplain and has no
development value. At this time, there is no
commitment to any design for Burnham Street as
this will be discussed by the Council later. A work
program is being prepared to identify and
implement potential Development Code changes.
Some of the older properties have substandard
parking facilities. It might be possible to work
with Clean Water Services to reduce some of the
setback requirements near the creek. Mayor
Dirksen noted some downtown parking
requirement adjustments to the Code have already
been adopted. Having regulations in place to
accommodate business that might want to locate in
the downtown will be key.
5. Joint Meeting Staff presenter: Public Works Director
with the Koellermeier
Intergovernmental
Water Board IWB Members present: Patrick Carroll, Beverly
(IWB) to Discuss Froude, Bill Scheiderich; Councilor Woodruff is
Participation in the City Council liaison to the IWB.
the Expansion
and Modification Also present was Mark Knudson of Carollo
of the Willamette Engineers, the engineering consultant for
River Water Sherwood and the Tualatin Valley Water District
Supply (T VWD).
The City of Tigard continues to work on securing a
long-term water source by exploring all options.
The City is a member of the Willamette River
Water Coalition (WRWC), which was formed to
preserve access to the Willamette River as a
potential municipal and industrial water source.
This is not to say that all members of the coalition
plan to utilize the Willamette River as a water
source, but rather the are committed to
Council Meeting Minutes Page 7
March 21, 2006
Agenda Item Discussion & Comments Action Items follow u
preserving access to this option.
According to the WRWC agreement, any member
deciding to expand or modify the Willamette River
water supply system is required to provide fellow
members with 90-day notice to give other
members the opportunity to participate in the
proposed expansion. Tigard has received such
notices from the City of Sherwood and TVWD.
Council received an outline of key points of this
matter; a copy is on file in the City Recorder's
office. Estimates for the extent and estimated
costs for a potential Tigard participation were also
reviewed in the outline.
During discussion points included:
• TVWD has invested in the Willamette River
water treatment plant to varying degrees.
• There are 115 million gallons/day (mgd)
remaining for intake capacity at the Willamette
River water treatment plan.
• TVWD is considering the Willamette River
water supply because of uncertainty about the
cost and ability to purchase water from the
City of Portland. It appears now that Portland
might be willing to negotiate a 10-year
agreement. TVWD will continue to consider
the Willamette River source.
• There is an opportunity for the City of Tigard
to consider buying capacity in the Willamette
River water system through participation in
paying for part of the regional transmission
system.
• The costs for Tigard's participation were
reviewed. (See outline.)
• City of Tigard continues to work with Lake
Oswego on a joint project also. Pipelines will
need to be built for this project, which will be
longer than the pipelines for the Willamette
River supply would be.
• Portland might offer Tigard a ten-year
contract; although, the City of Tigard has not
received anything from Portland. If a ten-year
contract is mutuallagreeable, this will give
Council Meeting Minutes Page 8
March 21, 2006
Agenda Item Discussion & Comments Action Items follow u
Tigard more time to consider how to address
its other potential water source options.
• A contract with Portland does not offer the
opportunity to own infrastructure.
• One option might be to approach this
incrementally; that is to install a pipeline now
for use later.
• Blended water (water from two different
sources such as the joint Water Commission
and the Willamette River) would not happen
because of the hydraulics of the system.
• As a consideration, the City needs to look at
long-term investment now because if the City
does not buy-in now, the water system will not
be sized for larger capacity needs in the future.
• Intake capacity would also need to be
increased if the City went with the Lake
Oswego option.
• Capacity from the Willamette River is such
that it could be the sole option for water.
• Pursuing multiple sources maintains potential
options.
• Discussed the concerns to commit to the
Willamette River pipeline. The options for
Tigard are unfolding at this time, yet complete
information for all of them is not available.
• The City needs to make a decision about the
Willamette River water option in May.
• Lake Oswego has the potential to provide 15
mgd and when accompanied by use of wells
and water from Portland, Tigard would have
enough water for the next 20 years. Worst
case, if the City of Portland backs away from a
ten-year agreement, the City of Tigard would
need to enter into a "bridge" contract with
Portland until other sources can be developed.
• There was mention of Areas 63 and 64m' the
urban growth boundary and the future
significant water needs for this area.
• There is a need for each of the agencies
represented in the IWB to review the options.
• TVWD has an ordinance in effect that says it
will check-in with their voters before they go
forward with water from the Willamette River.
There is still much planning to do. Other
issues include acquiring right-of-way, obtaining
Council Meeting Minutes Page 9
March 21, 2006
Agenda Item Discussion & Comments Action Items follow u
permits and addressing environmental issues.
• There was mention that if the City of Bull
Mountain is formed, they would need to work
through issues to demonstrate their ability to
provide water. Assets that belong to the Water
District would be transferred.
• The Lake Oswego source would require
pumps.
Recommended procedure for City of Tigard:
• Use the month of April to allow time for the
Intergovernmental Water Board to discuss this
matter.
• City Council will review again; tentatively
scheduled for April 25, 2006.
6. Council Input Staff Presenter: City Engineer Duenas
on the Draft
2008-2011 STIP The PowerPoint presentation overview is on file in
(State the City Recorder's office.
Transportation
Improvement City Engineer Duenas reported that a resolution
Program) has been prepared advising the state that the City
supports certain projects for the 2008-2011 STIP.
Councilor Wilson commented that Metro has
acknowledged the importance of Highway 99. It
appears from the proposed list that the projects for
this region are sparse; a large share of the funding
is being funneled toward Highway 26. Growth
identified for jobs and for residential development
for the next ten years is not occurring in the same
locations.
Council members indicated their support for the
overpass replacement on Highway 99W and
pavement overlay on Hall. City Council members
talked about contribution by the City of Tigard to
the projects, and if this would mean Tigard could
give input on the scope and design. Support was
also expressed for the I-5 project.
Council Meeting Minutes Page 10
March 21, 2006
Agenda Item Discussion & Comments Action Items follow u
9. Non Agenda
Items City Council and City Manager Prosser discussed
the fact that no tentative date has been set for the
joint meeting with the School District Boards and
the City Councils of neighboring jurisdictions.
City Council agreed staff should continue to
pursue a date for this meeting.
CouXcilor Harding suggested that CIP be referred *Community Investment Program
to as "g~j*pA T^"°°*MYP"r T~r.~ rrom " City Council (minutes corrected on April 25, 2006)
members concurred that this was a good idea.
10. Executive Not held.
Session.
11. Adjournment 10:17 p.m. Motion by Councilor
Woodruff, seconded by
Councilor Harding, to
adjourn the meeting.
The motion was approved
by a unanimous vote of
Council present.
Mayor Dirksen Yes
Councilor Harding Yes
Councilor Sherwood Yes
Councilor Wilson Yes
Councilor Woodruff Yes
C( n-E. Gt~
erne Wheatley, City Recor er
Attest:
142~ City of Tigard Council President,
Date: --4,01-?
1 Aadm%cathy\c=\2006t060321.doc
Council Meeting Minutes Page 1 I
March 21, 2006
G)
7GARD CITY COUNCIL
RKSHOP MEETING
March 21, 2006
6:30 p.m.
TIGARD CITY HALL
13125 SW HALL BLVD
F TIGARD, OR 97223
PUBLIC NOTICE:
Upon request, the City will endeavor to arrange for the following services:
• Qualified sign language interpreters for persons with speech or hearing impairments; and
• Qualified bilingual interpreters.
Since these services must be scheduled with outside service providers, it is important to allow as much
lead time as possible. Please notify the City of your need by 5:00 p.m. on the Thursday preceding the
meeting by calling: 503-639-4171, ext. 2410 (voice) or 503-684-2772 (TDD - Telecommunications
Devices for the Deaf).
SEE ATTACHED AGENDA
COUNCIL AGENDA - MARCH 21, 2006 page 1
AGENDA
TIGARD CITY COUNCIL WORKSHOP MEETING
MARCH 21, 2006
6:30 I'M
1. WORKSHOP MEETING
1.1 Call to Order - Tigard City Council
1.2 Roll Call
1.3 Pledge of Allegiance
1.4 Council Communications & Liaison Reports
1.5 Call to Council and Staff for Non-Agenda Items
Non-Agenda Item (see No. 9 below)
6:35 I'M
2. JOINT MEETING WITH BUDGET COMMITTEE - STAFF RESPONSE TO
FINANCIAL STRATEGY TASK FORCE REPORT RECOMMENDATIONS
• Staff Report: Finance Department
7:15 I'M
3. PROPOSED CAPITAL IMPROVEMENT PROGRAM PROJECTS FOR 2006-07
• Staff Report: Engineering Department
7:55 PM
4. DOWNTOWN CAPITAL IMPROVEMENT PROJECT PRIORITIES/BUDGET
• Staff Report: Community Development Department
8:35 I'M
5. JOINT MEETING WITH THE INTERGOVERNMENTAL WATER BOARD (IWB)
TO DISCUSS PARTICIPATION IN THE EXPANSION AND MODIFICATION OF
THE WILLAMETTE RIVER WATER SUPPLY SYSTEM
• Staff Report: Public Works Department
9:25 PM
6. COUNCIL INPUT ON THE DRAFT 2008-2011 STIP (STATE TRANSPORTATION
IMPROVEMENT PROGRAM)
• Staff Report: Engineering Department
9:35 PM
7. COUNCIL INPUT ON THE BURNHAM STREET DESIGN CONCEPT OPTIONS
• Staff Report: Engineering Department and Community Development Department
COUNCIL AGENDA - MARCH 21, 2006 page 2
8. COUNCIL LIAISON REPORTS
9. NON AGENDA ITEMS
9.1 Joint Meeting with Tigard-Tualatin School District Board and the Councils of Tualatin,
King City, and Durham is on the tentative agenda for early April, but no date has been
identified. It is the School District's turn to host the meeting. Staff requests Council
members review their calendars to determine if staff should request postponement of
this meeting.
10. EXECUTIVE SESSION: The Tigard City Council may go into Executive Session. If an
Executive Session is called to order, the appropriate ORS citation will be announced
identifying the applicable statute. All discussions are confidential and those present may
disclose nothing from the Session. Representatives of the news media are allowed to attend
Executive Sessions, as provided by ORS 192.660(4), but must not disclose any information
discussed. No Executive Session may be held for the purpose of taking any final action or
making any final decision. Executive Sessions are closed to the public.
10:00 PM
11. ADJOURNMENT
i Aadmtcathytcca\2006t060221.doc
COUNCIL AGENDA - MARCH 21, 2006 page 3
AGENDA ITEM # "
FOR AGENDA OF March 21, 2006
CITY OF TIGARD, OREGON
COUNCIL AGENDA ITEM SUMMARY
ISSUE/AGENDA TITLE Staff Response to Financial Strategy Task Force Report Recommendations
PREPARED BY: Robert Sesnon DEPT HEAD OK AA CITY MGR OK
ISSUE BEFORE THE COUNCIL
The Financial Strategy Task Force presented their final report to City Council during the February 21, 2006. Included
in their report were several recommendations. The Council at that time directed staff to review these recommendations
and return to the Council with implementation options.
STAFF RECOMMENDATION
Review staff s responses to the Task Force's recommendations and provide direction on pursuing performance audits
of select operations.
INFORMATION SUMMARY
---In response to projected general fund deficits in future years, the City Council created a citizen-based task force for the
purpose of exploring options to address this looming fiscal problem. The task force met several times and evaluated
many of the city's numerous programs and the services it provides its residents, and also reviewed the City's current fees
and charges and compared them with other surrounding jurisdictions. The outcome of this review was a report that
identified several recommendations, which the task force presented to City Council during the February 21 st meeting.
At that time staff was directed to review the report and develop options for addressing the task force's
recommendations. Each of the recommendations, and staff responses, are as follows:
7. The City needs to develop a communication plan that is comprehensive and will provide information on the results of the performance
audits, property tax rate education and information, how efficient the City is in providing services, and how City services are actually funded.
Key to the propery tax education and information is communicating how Tigard's tax rate compares to surroundingjurisdictions (showing
that the tax rate is significantly lower). Task Force members also felt that this communication plan and message needs to be consistent and
shared often with citizens.
Staff proposes using a combination of channels to communicate to Tigard's citizens. Upon completion of the
performance audits staff will issue press releases and also publish summaries on the City's web site as well as in the
Cityscape newsletter. The web site and Cityscape newletter will also be primary tools for cummunicating property
tax information and city service funding. The methodology and display of the effective tax rates will address
questions raised during the February 21 st City Council meeting.
Staff recommends pursuing the publishing of a "Budget in Brief' pamphlet that summarizes the City's resources
and requirements and communicates effective tax rates.
2 After reviewing the mix of City services provided, the Task Force members did not find that the City is pmviding any services that
the City should not be providing. Therefore, the Task Force is not recommending a change in current services provided.
No response necessary
3. Performance audits should be conducted in key areaslpmgrams, especially in the General Fund-
a. The cost of audits should be added into the budget as soon as possible.
b. The audits must be conducted by a credible independentparly which could include the use ofpmfessional organisations andl or
graduate students rather than simply an audit firm. This could reduce the cost oj'the performance audits.
C. Continued citi.Zen involvement in the performance audit pmcess is important.
d. The results of the audits would then be used to eithergain Ocreny that eliminates the pmmjected budget shor falls or to communicate
how effective and eclent City pmgrams are.
e. If the audits show that no ignificant cost savings can be reali.Zed, then prepare options for a local option levy. Please see
recommended appmach to local option levy outlined later.
Should the City Council wish to pursue hiring an outside firm to conduct such reviews, it will be important to first
define the scope of work. As discussed during the prior City Council presentation, reviewing all the operations of a
specific department is too broad an approach. Rather, the need exists to define which of the various operations
should be examined. Once the scope of work is agreed upon, staff will obtain proposals from qualified
management consulting firms. $75,000 has been included in the FY 2006/07 proposed budget for this purpose.
It should be cautioned that while such reviews often can identify ways in which the operations may be made more
efficient, immediate financial savings may not result. Rather, the particular operations can perhaps absorb
additional workload and thus slow down the need for additional staff and resources in the future.
4. The City should continue adjusting fees and charges to recover costs and make periodic adjustments as needed. The City should
continue reviewing fees and charges on an annual basis.
Staff concurs and will continue, as part of the annual budget process, to update the fee schedule as necessary for the
budget committee's review and ultimate adoption by the City Council.
5. The City should support any reasonable County tax measure that would bring additional revenue to the City. This will be
extremely important in the resolution of future library funding through the Washington County Cooperative Library Services (I ICCLS).
This is a City Council decision.
6. The City should monitor and make sure that the City is maximi#nggrant revenues and the City's share of revenues from the State
of Oregon, Washington County, and Clean Water Services.
Staff concurs and will continue to seek out and apply for grant monies whenever possible.
7. In any local option levy proposal, the rate should capture not only the cost of the program or service, but also the cost of all related
support services and overhead.
Staff concurs with this recommendation.
8. The City should develop and pursue corporate/ private sector funding andl or sponsorsh ps forpmgrams and projects whenever
possible.
Staff concurs and will develop a list of ideas for the City Council's consideration.
9. The City should initiate and continue to pursue any existing efforts in developing cooperative agreements with other local jurisdictions.
This could include equipment sharing and minimising the duplication of delivering services.
Staff concurs with this recommendation. The city already has cooperative agreements for the mailing and receipt of
utility bills with Clark County, public safety dispatch services with Washington County Consolidated
Communications Agency (WCCCA), and mutual aid agreements with several other jurisdictions. Additionally, city
executive staff met last week with TTSD staff to explore other ways in which the two agencies may cooperate.
In addition to the several cooperative agreements with other public agencies, the city currently contracts with
private providers for city facility landscape maintenance, fleet maintenance, janitorial services, street sweeping, and
several other functions. In each of these cases it was deternzined to be more cost-effective to contract the service to
the outside vendor rather than using additional city staff to perform the given function.
gram initiatives and capital
70. The financial impact on futurr City budgets should always be analyzed when considering new pro
acquisition or construction.
Staff concurs with this recommendation. Presently, effects on operating expenditures as a result of new programs
and facilities are addressed in the budget document, but in summary form only. In the future, staff will provide
financial forecasts which clearly identify the financial impact on ongoing operating costs. This information will be
provided in the FY 2007-08 budget at a program/project level so that the full cost of the program or project is
made clear.
OTHER ALTERNATIVES CONSIDERED
All options have been included in the discussion above.
COUNCIL GOALS AND TIGARD BEYOND TOMORROW VISION STATEMENT
This addresses the following City Council adopted goal for 2006:
Stabilize Financial Picture
Review Financial Strategy Task Force recommendations
Take appropriate actions to control costs
ATTACHMENT LIST
Financial Strategy Task Force Report to Tigard City Council dated January 25, 2006
FISCAL NOTES
Based on information staff has received from other jusisdictions, preliminary estimates for completing performance
audits will range from $10,000 to $40,000 for each department. The scope of work must be more clearly defined
before more accurate estimates may be obtained.
The cost of publishing budget brief pamphlets is estimated to be about $1,000 for a quantity of 2,000.
Financial Strategy Task Force
Report to Tigard City Council
January 25, 2006
Background
The Tigard City Council created a citizen-based task force which was asked to help in
developing recommendations that could assist the Council in taking actions to improve
the City's financial future and address the projected funding shortfalls. The City Council
asked that members of the Task Force conduct a comprehensive review and that the
recommendations developed address revenue, expenditures, and how services are
provided by the City.
The creation of the Task Force came about as the result of the FY 2005-06 budget
hearings where the variance between the projected growth of City expenditures and
revenues was discussed as part of the five-year financial forecast presentation. The City
Council and members of the Budget Committee determined that more citizen
involvement and input was needed to identify what steps the City should take next in
addressing the City's financial future.
Citizen members of the City's Budget Committee, members of the Committee for Citizen
Involvement, a representative from the Downtown Task Force, and a representative from
the Transportation Financing Strategies Task Force were asked to participate on the
Financial Strategy Task Force. The Task Force held five meetings where members of the
Task Force reviewed the five-year financial forecast for all City funds as well as the
services provided by City departments. Members of the Task Force also reviewed both
the applicable Tigard Municipal Code and state statutes that govern the programs and
services that the City must provide. A presentation on the City's visioning process was
also made along with the results of the most recent progress report that was published.
Using the information that was provided by staff in the presentations, Task Force
members broke into small groups and reviewed existing City programs and compared
these to what other local jurisdictions are providing in the surrounding area as well as
those that are legally required. Members then discussed and identified what the most
logical funding source would be for City programs. Also, members of the Task Force
reviewed and evaluated how the City's current fees and charges compare to other
surrounding jurisdictions and the rational for each fee and charge.
As a result of their review of City programs and funding sources, the Task Force
members developed a strategy that could be used in evaluating levels of service and
identifying potential efficiencies in program operations. The strategy includes
conducting performance audits in selected City departments and programs. By
conducting performance audits, the City would receive valuable information on any cost
saving measures and whether there is still a need to pursue other revenue options,
including a local option levy. Therefore, members recommended that performance audits
be conducted first to determine whether new revenues are needed.
General Observations
After reviewing the City's programs and funding sources, the Task Force members
determined that the programs and services that the City is providing is consistent with
what other jurisdictions are providing and meeting the requirements of the law. Task
Force members found that many City programs are self sustaining through dedicated
funding sources and these funding sources cannot be used for General Fund purposes.
Since the operating funding shortfalls are projected to occur primarily in the General
Fund, the Task Force members concentrated their discussion primarily in this area. They
noted that the two major departments that are funded through the General Fund are Police
and Library. Because of this, the Task Force members felt that the initial performance
audits and budget prioritization efforts should be focused in these two areas.
As a result of their work, the Task Force identified key steps and recommendations that
the City should take in addressing the City's financial future.
Task Force Recommendations
1. The City needs to develop a communication plan that is comprehensive and will
provide information on the results of the performance audits, property tax rate
education and information, how efficient the City is in providing services, and
how City services are actually funded. Key to the property tax education and
information is communicating how Tigard's tax rate compares to surrounding
jurisdictions (showing that the tax rate is significantly lower). Task Force
members also felt that this communication plan and message needs to be
consistent and shared often with citizens.
2. After reviewing the mix of City services provided, the Task Force members did
not find that the City is providing any services that the City should not be
providing. Therefore, the Task Force is not recommending a change in current
services provided.
3. Performance audits should be conducted in key areas/programs, especially in the
General Fund:
a. The cost of audits should be added into the budget as soon as possible.
b. The audits must be conducted by a credible independent party which could
include the use of professional organizations and/or graduate students
rather than simply an audit firm. This could reduce the cost of the
performance audits.
c. Continued citizen involvement in the performance audit process is
important.
d. The results of the audits would then be used to either gain efficiency that
eliminates the projected budget shortfalls or to communicate how effective
and efficient City programs are.
e. If the audits show that no significant cost savings can be realized, then
prepare options for a local option levy. Please see recommended
approach to local option levy outlined later.
2
4. The City should continue adjusting fees and charges to recover costs and make
periodic adjustments as needed. The City should continue reviewing fees and
charges on an annual basis.
5. The City should support any reasonable County tax measure that would bring
additional revenue to the City. This will be extremely important in the resolution
of future library funding through the Washington County Cooperative Library
Services (WCCLS).
6. The City should monitor and make sure that the City is maximizing grant
revenues and the City's share of revenues from the State of Oregon, Washington
County, and Clean Water Services.
7. In any local option levy proposal, the rate should capture not only the cost of the
program or service, but also the cost of all related support services and overhead.
8. The City should develop and pursue corporate/private sector funding and/or
sponsorships for programs and projects whenever possible.
9. The City should initiate and continue to pursue any existing efforts in developing
cooperative agreements with other local jurisdictions. This could include
equipment sharing and minimizing the duplication of delivering services.
10. The financial impact on future City budgets should always be analyzed when
considering new program initiatives and capital acquisition or construction.
Overall Approach to Local Option Levy
The Task Force recommends a sequential set of actions as an overall financial strategy.
The City would only proceed to the next sequential step if the prior step fails to remedy
the projected budget shortfalls.
The sequential actions are:
1. Conduct performance audits in key areas/programs (primarily programs funded
using General Fund resources) to identify opportunities for improved efficiencies
and cost savings.
2. Begin prioritizing General Fund programs now so department directors can
clearly articulate what programs/services are least important in their areas and the
associated costs of each program - department directors should be encouraged to
rank prioritize from least to more important up to 15% reductions in overall
department budget.
3. Carefully organize and articulate a local option levy campaign in the community
that logically explains that performance audits have not identified cost savings
and thus the City has two options - increase revenue with a local option levy or
eliminate the lowest prioritized services.
3
4. Determine the magnitude of the budget shortfall and provide the community with
a series of local option levies (cafeteria style) that allow residents to make specific
choices among the lowest prioritized services and the associated tax. Programs
approved by voters would continue and all others would be eliminated. To
maintain credibility with the community, all services not approved by voters must
be eliminated.
Attachments
1. PowerPoint presentation on Tigard's Financial Outlook dated August 24, 2005.
2. Financial Ballot Measure Survey
3. Fees and Charges Comparison Chart
4. Comparison of Local Jurisdiction's Permanent Tax Rates
5. Results of Task Force Exercise in Ranking Programs and Funding Sources
6. Matrix of Tigard Municipal Code and State Statutes to City Programs
7. General Fund Programs/Division Funding Sources Chart
8. Comparison Chart of Services Provided by Surrounding Jurisdictions
4
AGENDA ITEM #
FOR AGENDA OF March 21, 2006
CITY OF TIGARD, OREGON
COUNCIL AGENDA ITEM SUMMARY
ISSUE/AGENDA TITLE Proposed Capital Improvement Program Projects for FY 2006-07
PREPARED BY: A.P. Duena~ DEPT HEAD OK CITY MGR OK tA EJ_V1
ISSUE BEFORE THE COUNCIL
Presentation of the current FY 2006-07 draft CIP (Capital Improvement Program) project list for discussion, input,
revisions and suggestions for additional projects.
STAFF RECOMMENDATION
That Council review and discuss the draft project list, provide input on the existing list, suggest additional projects (if
any), and provide any other direction necessary for staff to finalize the project list for submittal through the City's
budget formulation process.
INFORMATION SUMMARY
The CIP formulation process for FY 2006-07 began in December 2005. The first of two public meetings to
introduce the project list and to receive public input on the proposed projects was conducted on December 7, 2005.
The draft list was posted on the City of Tigard webpage.on the same day. The meeting was held as an open-house
event to provide the public an opportunity to view information and converse with staff regarding the proposed CIP
projects. Since then, the City has received numerous comments on the draft list and suggestions for additional
projects. The City conducted a second public meeting on Wednesday, January 25, 2006 to provide another
opportunity for public input.
The formulation process includes Planning Commission and City Council input before the draft project list is
submitted through the City's budget process. The Planning Commission reviewed, discussed and provided input on
the draft list at its meeting on Match 6, 2006. The Planning Commission recommendations are:
• Seek to incorporate a median (for pedestrian refuge) on Highway 99W as part of the County's Hall
Blvd/Highway 99W intersection project.
• Consider adding capacity (additional turning lanes) at the Tiedeman Avenue/Tigard Street intersection. In
response, we have added a project to analyze that intersection to determine what improvements are
needed to provide that added capacity.
This workshop meeting on March 21, 2006 provides Council with an opportunity to discuss and provide input on
the draft project list updated as of March 10, 2006. Attached are the following for your review prior'to the meeting:
• Draft List of Proposed Projects for FY 2006-07 (updated as of March 10, 2006)
• Executive Summary of the Public Input and Staff Responses on the Draft 2006-07 CIP Project List
OTHER ALTERNATIVES CONSIDERED
N/A
COUNCIL GOALS AND TIGARD BEYOND TOMORROW VISION STATEMENT
The projects in the FY 2006-07 CIP strongly support the Council goals to "Implement Downtown Plan" and "Improve
99W Corridor." In addition, specific projects in the various systems support other important Council goals for 2006. In
general, the projects in the FY 2006-07 CIP all promote the Tigard Beyond Tomorrow goals in Growth and Growth
Management, Transportation and Traffic, Urban and Public Services and Community Character and Quality of Life.
ATTACHMENT LIST
1. Draft List of Proposed Projects for FY 2006-07
a. List by System
b. List by Funding Source
2. Executive Summary of the Public Input and Staff Responses on the Draft FY 2006-07 CIP Project List
FISCAL NOTES
The specific projects and project funding are as shown on the draft list. The proposed FY 2006-07 CIP (after
Council comments) will be submitted through the City's budget formulation process for eventual adoption in June
2006. The adopted CIP will be effective July 1, 2006.
lAenpNgus1council agenda summades13.21-08 proposed capft improvement program projects for N 2008-07 els.doc
City of Tigard Page I of 3
Report - Project Details by Type created on:
CIP Year: FY 2006-07 3/10/2006 12:55:45 PM
City Facilities System Program $1,795,197
Audio/Visual Control System for Council Chambers $83,000
cip year: FY 2006-07 Facility Fund $831000
Status: Proposed
description:
This project is carried over from FY 2005-06 for the provision and installation of audio, visual,
and control systems for the Tigard City Council Chambers.
Card Reader Installation $18,500
cip year: FY 2006-07 Facility Fund $18,500
status: Proposed
description:
The City has several IDF or network wiring rooms throughout its facilities. The FBI is requiring
that all IDF rooms be accessed via a card reader system. This project installs card readers at
each IDF room and replaces the one at the Library coffee bar.
City Facility Security Upgrades $10,000
cip year: FY 2006-07 Facility Fund $10,000
status: Proposed
description:
City facilities are access controlled by a combination of key entries and electronic card entries.
The current key system patent will expire in 2007, which will require the City to implement a new
key system. In addition, the City desires to install additional card reader entries to reduce the
number of,entries with key access. This effort will provide better overall access control.
This upgrade will be phased in over several fiscal years.
Citywide Facility Master PLan $50,000
cip year: FY 2006-07 Facility Fund $50,000
status: Proposed
description:
This project provides funding for a consultant to prepare a Master Plan for City Hall buildings and
determine if remodeling of the buildings would be required. The project also includes extra
funding to finance the remodeling if needed.
Commuter Rail Station Enhancement $100,000
cip year: FY 2006-07 Facility Fund $100,000
status: Proposed
description:
The proposed 14.7-mile Commuter Rail line will share freight train tracks with the Portland &
Western railroad running through eastern Washington County. In addition to serving Tigard, the
line will also serve five stations in Beaverton, Washington Square, Tualatin and Wilsonville. The
Tigard Commuter Rail station will be located in the downtown adjacent to the existing TriMet Bus
station approximately 300 feet east of Main Street on the north set of tracks. The existing tracks
on the south side will be removed. A Park and Ride facility will also be constructed south of the
Commuter Rail line.
This project provides funding for the design and construction of specific enhancements such as
streetscaping, lighting, landscaping to enrich the combined TriMet Bus/Commuter Rail site that
hall/rlannrtmantc/anvinaarinrr/r.in nrniPrtc/nrniPrt tvnP rem... 1/10/7.006
City of Tigard Page 2 of 3
will function as a transportation hub in downtown Tigard. Construction is anticipated to begin in
late 2006 with service scheduled for 2008.
Consolidation of Public Works Facilities (Water Building) $630,000
cip year: FY 2006-07 Facility Fund $630,000
status: Proposed
description:
The Public Works staff and crews are currently housed in several locations, which leads to
inefficiencies in coordination and communication. This project begins the process to consolidate
as many of the Public Works Department staff and crews in one building as possible. The Water
Building will be reconfigured as needed for efficient operation to accommodate the Public Works
staff and crews. Public Works will move from the Ash Street offices to the Water Building after
the work is completed.
This project will include architectural, engineering and construction expenses.
Library Parking Lot Expansion $180,000
cip year: FY 2006-07 Facility Fund $180,000
status: Proposed
description:
This project modifies and expands the existing Library parking lot at the northeast corner of the
Hall Blvd/Wall Street intersection to provide additional parking spaces for the patrons visisting
the Library. The project also relocates the Library entrance immediately east of Hall Blvd to
approximately 370 feet east of the street to connect to the proposed Wall Street. This project will
be constructed in conjunction with the Hall/Wall Street - Phase 2 project to minimize impacts to
the Library and other properties in close proximity.
Library Projects - Houghton - Root Donations $427,697
cip year: FY 2006-07 Facility Fund $427,697
status: Proposed
description:
Library Property - Voluntary Cleanup $26,000
cip year: FY 2006-07 Facility Fund $26,000
status: Proposed
description:
Outside Entrance to PC-4 conference room $15,000
cip year: FY 2006-07 Facility Fund $15,000
status: Proposed
description:
This project modifies the existing conference room at the northeast corner of the Permit Center
Bldg. Installation of a new door will allow the public to enter the room without entering the main
entrance when conducting public meetings.
PD Underground Storage Tank Upgrade $40,000
cip year: FY 2006-07 Facility Fund $40,000
status: Adopted
description:
Decomission and remove existing underground storage tank for the emergency back up
generator at the Police Department. Install above ground storage tank of same capacity (500
gallons).
1,++„•// immi7 firtarri-nr Rnv/n;tv hall/rlP»artmPntc/Pnuineerinu/r.in nrniectc/nrniect tvne ren... 3/10/2006
City of Tigard Page 3 of 3
Police & Records Storage Remodel $15,000
cip year: FY 2006-07 Facility Fund $15,000
Status: Proposed
description:
The project remodels the current Public Works operations building to accommodate storage of
Police evidence and city records. The remodel includes architect fees, construction costs including
modifications to plumbing, electrical and heating systems, purchase of a generator and above
ground tank, man lift and shelving units for storage. By remodeling the operations facility, Police
and City records will be able to store records and evidence in one location consequently reducing
overall operating costs and enhancing more efficient operation.
Senior Center Remodel Design (including Seismic Upgrade) $200,000
cip year: FY 2006-07 Facility Fund $200,000
status: Proposed
description:
The Senior Center needs to be remodeled and enlarged to meet the current and fast-growing
needs of Tigard's senior population. In addition, as part of the on-going maintenance and update
of City facilities, the Center needs to be upgraded to meet current seismic standards. This project
includes engineering design, construction documents and construction costs.
7_..a_.//......... a:-_A ..«..-/n.4.. UnII /.io,+o,-►w,n„tC fan ninaarinrtlrir~ r%rniartc/nrniPr..t tcmp rP.n qi1 ni~nnr;
O
City of Tigard Page 1 of 2
Report - Project Details by Type created on:
CIP Year: FY 2006-07 3/10/2006 12:59:55 PM
Parks System Program $1,828,363
BPA Trail Feasibility Study $15,000
cip year: FY 2006-07 Parks Capital Fund $15,000
status: Proposed
description:
This is a proposed pedestrian trail that would extend along the Bonneville Power Administration
(BPA) power line easement from SW Beef Bend Road to SW Barrows Road. A consultant will be
contracted to develop a preliminary trail alignment study.
Clute Property House Demolition $15,000
cip year: FY 2006-07 Parks Capital Fund $15,000
status: Proposed
description:
This house is being demolished to create space for a future small, neighborhood park on City
owned property.
Fanno Creek Trail (Hall to Fanno Creek) $30,000
cip year: FY 2006-07 Parks Capital Fund $30,000
status: Proposed
description:
This trail segment will be from Hall Blvd. to Fanno Creek, north of the bridge accross Fanno
Creek. This segment will connect to the existing trail south of the bridge.
Fanno Creek Trail Master Plan $60,000
cip year: FY 2006-07 Parks Capital Fund $60,000
status: Proposed
description:
The Fanno Creek Greenway Trail is a 15-mile recreational and commuter trail that connects the
Willamette River in southwest Portland to the Tualatin River near Cook Park. When completed,
the Fanno Creek Trail will provide the first regional multi-use trail on the west side of the
Portland region, linking existing parks and recreational facilities. More than 50% of the Tigard
portion of the trail has been completed.
This project provides funding to prepare a Master Plan to identify available rights-of-way along
the creek to construct the remaining portion of the trail in the future.
Land Acquisition $579,513
cip year: FY 2006-07 Parks Capital Fund $579,513
status: Proposed
description:
This project is directly related to the Council goal of "Address growth - Identify and acquire open
space and park land". The use ranges from neighborhood parks to greenspace to pocket parks.
Northview Park - Shelter & Path Installation $25,000
cip year: FY 2006-07 Parks Capital Fund $25,000
status: Proposed
description:
City of Tigard Page 2 of 2
This will continue the park master plan by adding a picnic shelter and a path system within
Northview Park.
Parkland Acquisition - Downtown $100,000
cip year: FY 2006-07 Parks Capital Fund $100,000
status: Proposed
description:
Skate Park Development & Construction $426,300
cip year: FY 2006-07 Parks Capital Fund $426,300
status: Proposed
description:
This project constructs a 15,000 square foot, in-ground skate park in the area of the City Hall
parking lot approved by City Council. Funding for this project will come from private donations,
general fund and system development charges. At this point, private donations are expected to
raise approximately $40,000 and the balance will come from a combination of the General Fund
and the Parks SDC fund. These funding sources will be consolidated and transferred into the
Parks Capital Fund.
Tree Replacement/ Planting $50,000
cip year: FY 2006-07 Parks Capital Fund $50,000
status: Proposed
description:
This continues the yearly program to plant new trees in greenways and parks, remove old and
hazardous trees, and maintain and protect existing trees. Funding for this is from the fee
developers pay when it is not possible to protect existing trees on property that is being
developed.
Tualatin River/Cook Park Trail from Garden to Bridge $97,530
cip year: FY 2006-07 Parks Capital Fund $97,530
status: Proposed
description:
This 1300 foot trail segment will connect the Cook Park Trail to the newly constructed Tualatin
River Bicycle and Pedestrian Bridge. The funding for this project will come from a state grant,
Park SDCs and the fund balance.
Washington Square Regional Center Trail $430,020
cip year: FY 2006-07 Parks Capital Fund $430,020
status: Proposed
description:
This project provides funding for a conceptual design, final design and construction of a trail on
the south side of Ash Creek between Highway 217 and Hall Boulevard. The trail will be
approximately 3,000 feet long by 10 feet wide and will be a multi-use bicycle and pedestrian
path. By providing this trail, pedestrians and bicyclists will, be able to bypass the traffic on Hall
Boulevard, Greenburg Road, Scholls Ferry Road and Nimbus Avenue.
L u~.//......... 4:....«.7 n../n:4.. b.nll/rl uv.nr4m n«.4c./nr. nineur:nn/nirrrnianfe/rrnian4 }mn rer~ zii WIMA
City of Tigard Page 1 of 7
Report - Project Details by Type created ori:
CIP Year: FY 2006-07 3/13/2006 11:45:19 AM
Street System Program $6,803,000
72nd Avenue/ Dartmouth Street Intersection Signalization $500,000
cip year: FY 2006-07 Traffic Impact Fee Fund $300,000
status: Proposed Gas Tax Fund $200,000
description:
The 72nd Avenue/Dartmouth Street intersection is un-signalized, is configured as an "all-way stop" and is
one of the most heavily-traveled intersections in Tigard. The multiple lanes on both streets are not
conducive to the orderly movement of traffic. Both 72nd Avenue and Dartmouth Street in the vicinity of the
intersection are virtually at capacity since they have become desirable routes attracting most local traffic in
Tigard. Therefore, the intersection operating conditions are poor and show significant delay in the AM and
PM peaks. In addition, the traffic volumes will most likely increase as large vacant properties in Tigard
Triangle are developed. Increased traffic volumes would make the intersection unsafe and even more
difficult for orderly movement of traffic.
This project installs a traffic signal and constructs necessary roadway improvements to improve the traffic
handling capacity of the intersection.
The design is scheduled to be completed in the summer of 2006 and construction is scheduled for the fall of
2006 or spring of 2007.
The intention at this time is to explore the formation of a reimbursement district to allocate the project costs
among upcoming developments. $127,642 has been collected from developers. The amount of $372,358
will be contributed by the City for the improvements, which would be fully or partially reimbursed by the
developments as they occur within the proposed district.
Ash Avenue Connection Feasibility Study (Fanno Creek to Scoffins St) $40,000
cip year: FY 2006-07 Gas Tax Fund $40,000
status: Proposed
description:
This project provides funding for a corridor study to determine a feasible' alignment for Ash Avenue between
Fanno Creek and Scoffins Street. If the recommendation from that study is to retain the extension of Ash
Avenue, the design of the street, which may be initiated as early as FY 2007-08 will incorporate
improvement concepts developed by the Downtown Comprehensive Streetscape Design Plan.
Ash Avenue Construction (Burnham Street to Railroad Tracks) $220,000
cip year: FY 2006-07 Gas Tax Fund $220,000
status: Proposed
description:
Bull Mountain Road (at Hwy 99W) Right-Turn Lane Widening $75,000
cip year: FY 2006-07 Traffic Impact Fee Fund - $75,000
status: Proposed Urban Services
description:
This project widens the right-turn lane on Bull Mountain Road at Highway 99W. The current eastbound lane
from Bull Mountain Road to southbound Highway 99W is not wide enough to accommodate truck turning
movements and other large-sized vehicles. In addition, the turning radius is substandard, which makes it
difficult for vehicles to stay within the lane while maintaining the travelling speeds. The outfall of the storm
drain pipe that runs underneath the road is also broken off and is in need of repair. This project provides
funding to relocate an existing planter strip to provide space for widening of the right-turn lane and repair
the existing storm drain outfall. It also enlarges the curb return radius for safe turning movements.
Coordination with Washington County and the Oregon Department of Transportation on the design of the
improvements is in progress. The funding provided is for completion of the project, which is expected to
begin in late FY 2005-06.
Bull Mountain/Roshak Road Intersection $100,000
cip year: FY 2006-07 Traffic Impact Fee Fund -
Urban Services $100,000
status: Proposed
City of Tigard Page 2 of 7
description:
This project incorporates the half-street improvements designed by a new subdivision north of the
intersection. The joint project improves the horizontal alignment of Bull Mountain Road and enhances the
street's capacity to accommodate additional traffic volumes generated by new developments in close
proximity. Completion of the project will provide a dedicated left-turn lane from Bull Mountain to Roshak
Road, and two through-lanes. Also included in the project are minor drainage work and new striping pattern
to accommodate the additional lane. This project is funded from the Urban Services TIF fund in the amount
of $100,000, allocated in two fiscal years FY 2005-06 and FY 2006-07, with the subdivision providing
necessary funding for the half-street improvements required for its development.
Burnham Street Improvements $750,000
cip year: FY 2006-07 Gas Tax Fund $750,000
status: Proposed
description:
This project completes the design of Burnham Street between Main Street and Hall Boulevard and provides
funding to initiate right-of-way acquisition. Based on current design standards, the street requires a
minimum paved width of 44 feet with sidewalks and landscaped strips on each side of the street. The 44-
foot paved width may consist of two travel lanes, a center-turn lane and two bike lanes. However, the
elements proposed for the street may be modified to incorporate design concepts recommended by the
Tigard Downtown Comprehensive Streetscape Plan, which is currently underway. Those recommendations
are expected to be completed in the summer of 2006. The final design for Burnham Street is scheduled to
be completed in December 2006. Right-of-Way acquisition is anticipated to occur in the fall and winter of
the fiscal year and construction to begin in the spring of 2007 if feasible.
Commercial Street (at Main Street) Intersection Treatments $75,000
cip year: FY 2006-07 Gas Tax Fund $75,000
status: Proposed
description:
This project designs and constructs appropriate treatments on Commercial Street at Main Street. Specific
improvements identified in the Tigard Downtown Comprehensive Streetscape Plan, including signage,
monuments, streetscape enhancements, light fixtures, landscaping, etc., will be incorporated into the
project to ensure consistency of the overall design theme required for downtown Tigard. This project
requires coordination with the Commercial Street Improvements project, which is scheduled for construction
in early-fall of 2006, to minimize impacts to the street and develop a cost-effective approach for both
projects.
Commercial Street Improvements (Lincoln Avenue to Main Street) $400,000
cip year: FY 2006-07 Gas Tax Fund $400,000
status: Proposed
description:
This project involves construction of half-street improvements with sidewalk on the north side of the street
to provide a continuous sidewalk on Commercial Street from Lincoln to Main Street. The total paved width of
Commercial Street after improvements is 28 feet curb-to-curb, which will accommodate two travel lanes
and parking spaces on one side of the street. Due to close proximity of existing homes, trees, bridge piers,
and railroad tracks, planter strips will be placed wherever feasible. The preliminary design has been
completed and necessary rights-of-way are being acquired from three properties.
Construction of the project was originally scheduled for the spring of 2006. However, in order to incorporate
the design concepts of the Downtown Comprehensive Streetscape Plan into the project and to assure the
rights-of-way are acquired in time for the improvements, the construction has been re-scheduled to early-
fall of 2006. Completion of the project will provide a safe and convenient pedestrian route to downtown
services and the planned commuter rail station. This project has been approved for CDBG funding in the
amount of $91,300 with local matching funds of $208,700 coming from the Gas Tax Fund.
Downtown Comprehensive Streetscape Design $25,000
cip year: FY 2006-07 Gas Tax Fund $25,000
status: Proposed
description:
The Tigard Downtown Improvement Plan, which was completed in September 2005, identifies eight
"catalyst projects" and smaller-scale "brand-Tigard" projects with the potential to enhance the development
environment of downtown Tigard.
The first step towards implementation of the catalyst projects is to create a Comprehensive Streetscape
Plan for the downtown area. The plan will identify an overall theme for the downtown area, establish design
City of Tigard Page 3 of 7
details for streets, public spaces, gateways, commuter rail station, parking lots, and recommend
improvements suited for downtown streets. The plan will be designed by a Landscape Architect consultant
and is scheduled to be completed in the summer of 2006. Completion of the plan will provide general design
guidelines and a package of projects that can be implemented over a period of years as funding sources
become availalbe.
Durham Road/108th Avenue Intersection Signalization $150,000
cip year: FY 2006-07 Traffic Impact Fee Fund $150,000
status: Proposed
description:
This project was funded in FY 2005-06 for installation of a traffic signal at the Durham Road/108th Avenue
intersection. Traffic volumes on Durham Road have steadily increased since the mid 80's and will continue
to increase as the street provides a direct connection between two state highways, Highway 99W and Hall
Boulevard. Due to the increase in traffic volumes on Durham Road, traffic attempting to turn left from 108th
Avenue onto the street experiences excessive delay. The problem has become worse as the residential
developments along 108th Avenue are completed and generate impacts on the operations of traffic
movements at this intersection. A traffic analysis conducted in March 2005 indicates installation of a traffic
control signal on or about 2006 will enhance traffic safety at the intersection.
Funding provided for this project is for the design and installation of a traffic signal, including necessary
roadway improvements, to provide safe and controlled turning movements for traffic at the intersection.
Hall Blvd and Highway 99W Gateway Treatments $75,000
cip year: FY 2006-07 Gas Tax Fund $75,000
status: Proposed
description:
This project designs and constructs landscape and streetscape improvements at the intersection of Highway
99W and Hall Blvd. The improvements will incorporate the design concept established by the Downtown
Comprehensive Streetscape Plan.
Hall Blvd Half-street Improvements (Fanno Creek to 450 feet north) $150,000
cip year: FY 2006-07 Traffic Impact Fee Fund $150,000
status: Proposed
description:
This project widens Hall Blvd on the east side of the'street from the existing Fanno Creek Bridge to
approximately 450 feet north. The current northbound travel lane, which is less than 12 feet, will be
widened to 12 feet. The narrow roadway shoulder will be replaced with a paved 6-foot bike lane. The new
sidewalk will be installed at the ultimate location of the right-of-way required for an arterial (50 feet from
the street centerline), which can accommodate a 5-lane street section in the future as needed. A planter
strip will separate the bike lane and the sidewalk. Mitigation of the storm water generated by the additional
impervious area will also be addressed in the design. The existing bridge will not be widened as part of this
project.
Hall Boulevard (at McDonald Street) Right-turn Lane Widening $125,000
cip year: FY 2006-07 Traffic Impact Fee Fund $125,000
status: Proposed
description:
This project, which was funded in FY 2005-06, will be extended into FY 2006-07 to complete the design and
acquisition of rights-of-way for construction of a southbound right-turn lane on Hall Boulevard at McDonald
Street; as indicated by the conditions of approval for the development of the Library. In addition to widening
the street, curb and sidewalk are proposed along the new segment of the street to improve pedestrian
safety. An ODOT permit will be required for the improvements. A traffic study has been completed
identifying required design elements such as lane width, storage lane, corner radius, etc. Construction of the
project is tentatively scheduled to begin in late-spring of 2007.
Hall Boulevard Crosswalk (at Fanno Creek Pathway) $80,000
cip year: FY 2006-07 Gas Tax Fund $80,000
status: Proposed
description:
This project is carried over from FY 2005-06 for installation of a crosswalk on Hall Blvd to provide a mid-
block crossing for Fanno Creek Trail users. Since Hall Boulevard is a state route, location of the crosswalk
requires approval from the Oregon Department of Transportation (ODOT). Upon completion of the project,
the crosswalk will provide a mid-block crossing on a heavily-traveled, two-lane state route with a posted
City of Tigard Page 4 of 7
speed limit of 40 mph. Flashing beacons will be installed prior to or at the crossing to alert the on-coming
two-way traffic of pedestrians crossing the street.
Hall Boulevard Sidewalk (Spruce St to 850' south) $100,000
cip year: FY 2006-07 Gas Tax Fund $100,000
status: Proposed
description:
This project is carried over from FY 2005-06. It enhances pedestrian movements along Hall Blvd south of
Spruce Street by installing sidewalks on the west side of the street for approximately 850 feet. Hall
Boulevard at this location is a narrow two-lane roadway without sidewalks forcing pedestrians to use the
existing bike lane and occasionally encroach into the travel lane. The close proximity of existing homes,
landscape and limited right-of-way on this state route preclude placement of planter strips at some
locations. This project has been approved for Community Development Grant (CDBG) funding in the amount
of $136,725 with local matching funds of $108,275 coming from the Gas Tax Fund, for the total of
$245,000, of which $100,000 is allocated in FY 2006-07 to complete the project.
Hall Boulevard/Wall Street Intersection - Phase 2 $700,000
cip year: FY 2006-07 Traffic Impact Fee Fund $700,000
status: Proposed
description:
This project constructs a common access to Hall Boulevard for the Library and the Fanno Pointe
Condominiums as required by the Oregon Department of Transportation (ODOT). To ensure the project is
constructed expeditiously for safe crossings at the entrance to the Library, the City divided the project in
two phases: Phase 1 is the installation of a traffic signal at the entrance to the Library, which is scheduled to
be completed in December 2005. Phase 2 is the construction of approximately of 370 feet of the common
access, which has the same alignment with the proposed Wall Street, connecting Hall Boulevard to Hunziker
Street. Wall Street is not proposed for construction at this time.
Pinebrook Creek will be re-aligned for construction of the access. Because the re-alignment work is
characterized as in-stream work, the Division of State Lands permit requires the work to be performed
between July and October. Construction of the project is scheduled to begin in early-summer of 2006.
Highway 99W Corridor Improvement & Management Plan $20,000
cip year: FY 2006-07 Gas Tax Fund $20,000
status: Proposed
description:
Highway 99W carries over 50,000 vehicles per day, half of which is regional through traffic. This highway is
currently overwhelmed by the existing traffic volumes. There are no significant parallel routes to this
highway, and the traffic congestion will continue to worsen as traffic increases during the next few years.
The intersections of Highway 99W with Hall Boulevard, Greenburg Road, and McDonald Street are
bottlenecks that seriously hamper the smooth flow of traffic. At peak travel hours, cut-through traffic uses
the City of Tigard's collector and arterial system to avoid the Highway 99W traffic congestion. This traffic
adversely impacts the arterial and collector street system in the City.
The City has received a Transportation and Growth Management (TGM) grant to develop the plan. The study
will evaluate various alternatives for improvement of the highway (including development of new parallel
routes and connections that can feasibly be made between developments parallel to the highway) between
Durham Road and Interstate 5. The intent of the study is to address current traffic deficiencies, present
design alternatives and propose strategies that would provide for effective traffic circulation, connectivity
and operational improvements to the highway and its corridor. The study would provide a plan for
management of the corridor and a package of projects (both large and small) that can be implemented over
a period of years as funding sources are identified and designated for these projects. The allocated funding
is to provide a local matching fund required by the TGM grant.
Main Street Safety Improvements $75,000
cip year: FY 2006-07 Gas Tax Fund $75,000
status: Proposed
description:
This project includes minor safety improvements on Main Street including installation of light fixtures, bulbs-
out, marked crosswalks, etc. A study will be conducted to determine the feasibility and locations of the
improvements.
Pavement Major Maintenance Program (PMMP) $1,160,000
City of Tigard Page 5 of 7
cip year: FY 2006-07 Street Maintenance Fee $950,000
status: Proposed (SMF)
Gas Tax Fund $210,000
description:
The City has been active in implementing the yearly Pavement Major Maintenance program 'of corrective and
preventative maintenance on streets in Tigard. The program, which includes rehabilitation alternatives, has
the abilities to 1) restore the pavement's structural integrity, 2) increase riding. quality, and 3) improve
traffic safety. More importantly, through this pavement preservation strategy, the City was able to
encounter a good return on its maintenance investments, which would have been significantly higher if it
used different approaches, i.e. reconstruction, when the streets are allowed to deteriorate. The City will
continue to monitor and evaluate the pavement conditions after streets have been rehabilitated to
document the effectiveness of the treatments. So far, the streets that have received treatments, have
shown signs of exceeding their expected service lives. Streets scheduled to be included in this year's
program are:
- 68th Avenue (Highway 99W to Atlanta Street)
- 72nd Avenue (Baylor Street to 1,000 feet north)
- 79th Avenue (Bond to Ashford Street)
- 100th Avenue (Sattler Road to Murdock Street)
- 136th Avenue (south of Walnut Lane)
- Durham Road (Summerfield Drive to Serena Court)
- Garden Park Place Loop (at 110th Avenue)
- Lomita Avenue (90th Avenue to end)
- Pine Street (east of 69th Avenue)
- Upper Boones Ferry Road (72nd Avenue to Interstate 5).
The project list is subject to change due to actual bid proposals submitted. at the time the project is
advertised for construction. The lowest submittal bid price could exceed the proposed budget, which would
require the City to move some streets from the current fiscal year to FY 2007-08. The Gas Tax fund will
provide funding for improvements of the areas outside the existing edges of pavement if needed.
Rehabilitation of the streets, including reconstruction if necessary, within the existing edges of pavement
will be funded through the Street Maintenance Fee Fund.
Sidewalk Improvements $100,000
cip year: FY 2006-07 Gas Tax Fund $100,000
status: Proposed
description:
The existing network of sidewalks in Tigard is not continuous outside of the newer residential subdivisions.
The City recognizes continuity and connectivity are key issues for pedestrians and intends to address these
issues through this project The first priority is to provide sidewalks between transit amenities such as bus
stops and key activity centers. Extension of existing sidewalks at various locations in the City to provide
safe paths to schools for students will also be considered.
Street Striping Program $15,000
cip year: FY 2006-07 Gas Tax Fund $15,000
status: Proposed
description:
This is an annual program that provides funding for installation of new striping on streets that demonstrate
the need for replacement of existing stripes, pavement markings and pavement markers. This year's
program includes new striping on the following streets:
- Sequoia Parkway (Upper Boones Ferry to Bonita Road)
- Canterbury Lane (Highway 99W to 103rd Avenue)
- 112th Avenue (400 west of Highway 99W)
- Walnut Street (121st to Tiedeman Avenue)
- 71st Avenue (Highway 99W to Spruce Street)
- 72nd Avenue (Hermoso Way to Highway 99W)
- 91st Avenue (Greenburg Road to Lincoln Street).
Stop bars will also be re-painted at various locations.
Tigard Street/Tiedeman Avenue Intersection Traffic Feasibility Study $50,000
cip year: FY 2006-07 Gas Tax Fund $25,000
status: Proposed Traffic Impact Fee Fund $25,000
City of Tigard Page 6 of 7
description:
Traffic volumes at the Tigard Street/Tiedeman Ave intersection, which appear to exceed the capacity of this
unsignalized intersection, cause long queues and delays for the traffic approaching the intersection
especially during peak hours. This project provides funding for a feasibility study to identify transportation
impacts and recommend improvements that will improve traffic safety and circulation for pedestrians and
motorists at the intersection.
Tigard Triangle Street Improvements LID No.1 $1,750,000
cip year: FY 2006-07 Tigard Triangle LID #1 Fund $1,750,000
status: Proposed
description:
The Tigard Transportation System Plan (TSP) identifies the Tigard Triangle as an area where the street
infrastructure needs to be significantly upgraded to meet the City's established standards. The formation of
a Local Improvement District (LID) for construction of street improvements would address some of the
deficiencies identified in the TSP.
Specht Development, Inc. submitted a petition requesting the formation of an LID to improve certain streets
within the Tigard Triangle. The proposed improvements include street and utility improvements to 68th Ave,
69th Ave and 70th Ave between Dartmouth and Baylor Street and Dartmouth Street and Clinton Street
between 68th and 70th Ave, all within the Tigard Triangle.
In the Council meeting of February 28, 2006, City Council approved the establishment of the proposed LID
and directed staff to proceed with the Preliminary Engineer's Report. This project provides funding to
complete the report and to construct the improvements for the district if it is formed.
Traffic Calming Program $8,000
cip year: FY 2006-07 Gas Tax Fund $8,000
status: Proposed
description:
The Traffic Calming Program is an annual program that installs traffic calming measures aimed at slowing
vehicle speeds within residential neighborhoods. Speed humps have been favored by the majority of
residents and have been installed in many cases because they have proven effective in reducing speeds by
4 to 6 mph. Streets are selected for the program using the following criteria: traffic speed, volume, number
of accidents, existence of sidewalks, cut-through traffic and neighborhood's participation.
In consideration of the comments from Tualatin Valley Fire & Rescue district (TVF&R), the speed humps
have been re-shaped to accommodate emergency vehicles, which are now referred as speed cushions. This
year's program includes the installation of speed cushions on:
- O'Mara Street (Hill Street to Hillview Court)
- Ventura Drive (east of 72nd Avenue)
- 114th Avenue (south of Gaarde Street)
- Fern Street (west of 138th Avenue)
- 106th Avenue (north of Dakota Street).
Other streets may be added to the program depending upon neighborhood interest and the street ranking in
the program rating system.
Walnut Street (116th to Tiedeman Avenue) ROW Acquisition $40,000
cip year: FY 2006-07 Gas Tax Fund $40,000
status: Proposed
description:
This project provides funding to acquire the remaining rights-of-way for the improvements of Walnut Street
between 116th and Tiedeman Avenue. The design has been completed and most of the rights-of-way have
been acquired in FY 2004-05. Acquisition of the rights-of-way is necessary for future widening and
reconstruction of the street. The narrow two-lane street is proposed to be widened to a three-lane roadway
with curb, sidewalk and bike lanes. Construction of the project is scheduled to begin in FY 2009-100
Walnut Street Improvements (135th to 121st Avenue) $20,000
cip year: FY 2006-07 Gas Tax Fund $20,000
status: Proposed
description:
This project is the last phase of a three-phase project funded through the Washington County MSTIP3.
City of Tigard Page 7 of 7
The first phase improved the Walnut/121st Avenue intersection, which was completed by the County in
August 2001. The second phase constructed the Walnut/Gaarde Street intersection and its approaches and
installed a traffic signal at the intersection. The project was completed by the City also in 2001.
Phase 3 is constructed by the County, which began in the spring of 2005. The project widens Walnut Street
between 135th and 121st Avenue to provide a 44-foot paved roadway that consists of two travel lanes, a
center-turn lane and two bike lanes. Planter strips are also installed wherever possible. The project also
reconfigures and separates the Walnut Lane/135th Avenue intersection from Walnut Street. Certain
improvements, such as extension of sanitary sewer lines, upgrades of waterlines and installation of
pavement overlay, are also included in the project and are funded by the City. The construction is
anticipated to be completed in the summer of 2006.
City of Tigard Page I of 3
Report - Project Details by Type created on:
CIP Year: FY 2006-07 3/10/2006 1:01:42 PM
Sanitary Sewer System Program $2,500,000
79th Ave Sanitary Sewer Outfall $80,000
cip year: FY 2006-07 Sanitary Sewer Fund $80,000
status: Proposed
description:
This project installs approximately 1,000 feet of sanitary sewer pipe between 79th Avenue and
the CWS 60-inch interceptor running adjacent to Fanno Creek. Construction of the new pipe is
necessary to provide an outfall to a proposed sanitary sewer extension district on 79th Avenue
that will serve approximately 10 lots on the street. This project will be constructed in conjunction
with the 79th Avenue Storm Drainage Outfall project to minimize impacts to private properties.
Benchview Terrace Sanitary Sewer Access Road $40,000
cip year: FY 2006-07 Sanitary Sewer Fund $40,000
status: Proposed
description:
A small creek and drainage from surrounding developments are eroding about 250 feet of a road
used by City maintenance crews to reach a sanitary sewer. The road is accessed from Greenfield
Drive, just south of the intersection at Benchview Terrace. The purpose of the project is to repair
the damage caused by erosion by stabilizing the creek and redirecting drainage.
Bonita Road at Milton Court - Pipe Removal $30,000
cip year: FY 2006-07 Sanitary Sewer Fund $30,000
status: Proposed .
description:
In FY 2002-03 the City installed approximately 250 feet of 8-inch sanitary sewer pipe to replace
an existing pipe that had severe bellies and poor grade. This segment of the line is located at the
Fanno Creek crossing west of the Bonita Road/Milton Court intersection. At the time of
construction, the City decided to abandon the existing pipe in place with the intention of
removing it at a later time. This project is the removal of the pipe crossing Fanno Creek at this
location.
Citywide Sanitary Sewer Extension Program $2,000,000
cip year: FY 2006-07 Sanitary Sewer Fund $2,000,000
status: Proposed
description:
This 5 year-program, which began in FY 2001-02, extends sanitary sewer services to all
developed but un-sewered areas Citywide. The City uses the formation of reimbursement districts
to construct the sewers. As residents connect to the new sewer line, they have to pay their
proportionate share of the cost of the line, plus the normal connection fee.
The FY 2005-06 program proposed to include six reimbursement districts to provide
approximately 95 connections to existing homes. However, in order to provide adequate time to
purchase easements for construction of the outfalls for 4 districts, last year's program completed
only 2 districts: Ash Avenue (at Garrett Street) and 93rd Avenue/Mountainview Lane to provide
connections to 37 lots.
The following 6 districts are proposed for FY 2006-07:
- 87th Avenue (north of McDonald Street)
- 97th Avenue (between Murdock and Pembrook Street)
- 100th Avenue (between Inez and McDonald Street)
i_.i_./l__---__.._ rare/in/Inn,
City of Tigard Page 2 of 3
- Ann Street (between 121st and 116th Avenue)
- Hillview Street (at 102nd Avenue)
- Fairhaven Street (east of 115th Avenue).
These districts will provide approximately 79 connections to existing homes.
The program will need to be extended for several years beyond the original 5-year to address
complex design issues, wetland permits and right-of-way acquisitions. Approval from City Council
is required to form each district and construct the sewer extensions.
The Commercial Area Sewer Extension Program is also funded from the Sanitary Sewer Fund and
offers commercial entities the opportunity to participate in reimbursement districts for extension
of sewer service to commercial areas. The current incentive programs for early connection in
residential neighborhoods are not offered to the commercial sector. Funding .is provided to
accommodate potential projects that may surface during the fiscal year from the commercial
sector.
Commercial Street Sanitary Sewer Repair (Lincoln to Maint St) $50,000
cip year: FY 2006-07 Sanitary Sewer Fund $50,000
status: Proposed
description:
This project replaces approximately 50 feet of a severe damaged pipe on Commercial Street
between Lincoln and Main Street that has caused frequent infiltration. This project will be
designed and constructed in coordination with the Commercial Street Improvements project
between Lincoln and Main Street.
McDonald Street (at Hall Boulevard) Sanitary Sewer Connection $100;000
cip year: FY 2006-07 Sanitary Sewer Fund $100,000
status: Proposed
description:
This project connects a previously built but unconnected sanitary sewer on McDonald Street to
the existing sanitary sewer system located on Merlyne Ct. This project includes installation of 240
feet of 8-inch sewer main and.2 manholes. Completion of the project will provide 10 connections
to existing homes.
Red Rock Creek Sanitary Sewer Repair $50,000
cip year: FY 2006-07 Sanitary Sewer Fund $50,000
status: Proposed
description:
Red Rock Creek has eroded away the soil and base rock from a sanitary sewer manhole and
approximately 20 feet of 8-inch main just downstream of the manhole. The manhole and pipe are
at risk of collapse due to this erosion problem. This project, located at 6900 SW 69th Ave., will
address the problem.
Sanitary Sewer Major Maintenance Program $100,000
cip year: FY 2006-07 Sanitary Sewer Fund $1001000
status: Proposed
description:
The Sanitary Sewer Fund will be used to contract out sewer repair projects that are beyond the
repair capabilities of the City's Public Works Department. This program is expected to be a
continuing program in future years as routine maintenance would avoid restoration costs that
could be several times higher. The Sanitary Sewer Major Maintenance Program in FY 2006-07 will
include sewer repair projects located at various locations in the City.
~i1 n/7nnJ<
City of Tigard Page 3 of 3
Sanitary Sewer Master Plan $50,000
cip year: FY 2006-07 Sanitary Sewer Fund $50,000
status: Proposed
description:
Sanitary sewers in some areas.receive an excessive amount of storm water through unauthorized
connections or deteriorated lines. The storm water causes overloading of sewers and increases
the cost of operating the treatment plant. The proposed project provides funding to analyze and
identify the sources of the stormwater entering the sewers and prepare a plan to reduce the
sources.
The project also identifies lines of inadequate capacity by conducting flow monitoring of existing
lines to determine the extent of the capacity deficiency. A prioritized list of capacity improvement
projects will be prepared as part of this project.
City of Tigard Page I of 3
Report - Project Details by Type created on:
CIP Year: FY 2006-07 3/10/2006 1:02:14 PM
Storm Drainage System Program $781,000
79th Avenue Storm Drainage Outfall $90,000
cip year: FY 2006-07 Storm Sewer Fund $90,000
status: Proposed
description:
This project constructs approximately 1,000 feet of 18-inch storm drain line east of 79th Avenue
for discharge of storm runoff into Fanno Creek. The project also installs an energy dissipator
manhole and riprap for water to flow through prior to discharging to the creek. Construction of
this project will be combined with the 79th Avenue Sanitary Sewer Outfall project to minimize
impacts to private properties. A 20-foot utility easement will be dedicated by a property owner
for construction and maintenance of the storm drain and sanitary sewer pipes. Completion of this
project will provide a direct point of connection for future upgrades of the storm drainage system
on the street.
Derry Dell Creek at Fanno Creek and Walnut St - Culvert
Improvements $125,000
cip year: FY 2006-07 Water Quality/Quantity $125,000
status: Proposed Fund
description:.
This project will replace two existing culverts: the first one is at Derry Dell Creek as it crosses
under Walnut Street, and the second one is under an existing sanitary sewer main at the outfall
of Derry Dell Creek into Fanno Creek. This project includes the design of both culvert
replacements in preparation for construction of the project scheduled for the summer of 2008.
Completion of the project will increase capacity of the culvert at Walnut Street to resolve flooding
and maintenance issues and allow fish passage into derry Dell Creek. This project will aso
accomplish culvert replacement goals identified in the Healthy Streams Plan.
Derry Dell Creek Wetland & Vegetated Corridor Enhancement $3,000
cip year: FY 2006-07 Storm Sewer Fund $3,000
status: Proposed
description:
In FY 2004-05, the City enhanced wetland areas and the vegetated corridor along Derry Dell
Creek at 110th Avenue. The enhancement is required by the DSL, the Corps of Engineers, and
CWS due to impacts generated by the installation of a sanitary sewer pipe across the creek.
Intallation of planting materials was completed in that fiscal year. In FY 2005-06, the City
provided funding to hire a consultant to perform field inspections and monitor the growth of the
vegetation. A report has been submitted to the agencies describing the site conditions and
proposing a plan to maintain the current growing rate. This project provides funding for the
second year report, including field inspections, monitoring and reporting to the agencies. Funding
will also be allocated in FY 2007-08, to complete the monitoring work as required by the permit.
Durham Rd at 108th Ave - Stream Bank Stablization $150,000
cip year: FY 2006-07 Storm Sewer Fund $150,000
status: Proposed
description:
A creek bank and a portion of the segmental-block retaining wall south of Durham Road have
been eroded and undermined due to high stream flow oufalling from a 36-inch culvert under the
street. The contributing factors to the problems are a large boulder, which was placed in the
middle of the stream, and the culvert alignment, which does not line up with the creek. This
project removes and reconstructs a portion of the retaining wall, removes the existing boulder,
and extends the culvert for proper alignment with the creek. Preliminary design has been
onto/rrn;Pnf f'tlnP rP„ z/i n/~nn~
City of Tigard Page 2 of 3
completed. Environmental permits are now being acquired because the project site is located
within a sensitive area according to the City's Wetlands and Stream Corridors map. Contruction
will occur between July and October to meet the in-water work window requirement. Bank
stabilization is the responsibility of adjacent property owners.
Gaarde Street Phase II Wetland Mitigation $3,000
cip year: FY 2006-07 Storm Sewer Fund $3,000
status: Proposed
description:
This project provides funding to inspect and report mitigation measures required by the DSL, the
Corps of Engineers and CWS to offset the loss of 0.009 acres of wetland associated with the
widening of Gaarde Street. The offsite mitigation area is along the Fanno Creek Greenway
immediately north of Tigard Street. The vegetated enhancement area is located along the Fanno
Creek trail south of the Burnham Business Park. Initial vegetation management and plant
installation were completed in FY 2004-05. In FY 2005-06, the City provided funding for field
inspections and preparation of the first monitoring report to be submitted to the agencies. The
proposed funding is for the second year report, including field inspections, monitoring and
reporting to the agencies. Funding will also be allocated in FY 2007-08, to complete the last
report as required by the permit.
Highland Drive (109th Ave to 500' west of Greens Way) - Storm
Drain Pipe Replacement $25,000
cip year: FY 2006-07 Storm Sewer Fund $25,000
status: Proposed
description:
The existing storm drainage system on Highland Drive from 109th Ave to 500 feet west of
Greens Way consists of 12-inch pipes that have been crushed in numerous places and are in
need of repair. This project includes installation of new pipes, manholes, and catch basins. This
project was funded in FY 2005-06 from the Storm Sewer Fund to improve the existing storm
drainage system.
The work that will be performed in conjunction with the new pavement overlay also is scheduled
for this street. The overlay work is funded from the Street Maintenance Fee Fund. The proposed
funding for the storm drain replacement is required to complete the remaining work, which is
anticipated to be carried over into FY 2006-07.
Hiteon Creek Riparian Enchancement - Phase 2 Construction $90,000
cip year: FY 2006-07 Water Quality/Quantity $90,000
status: Proposed Fund
description:
This project constructs riparian enhancement features, including modifications of riparian buffer
areas, to promote treatment of high flows. It also includes placement of large woody debris and
minor channel improvements. This project addresses the "Stormwater Outfall Retrofit" goal
identified in the Healthy Streams Plan prepared by Clean Water Services.
Pine Street Storm Drainage System Upgrade $95,000
cip year: FY 2006-07 Storm Sewer Fund $95,000
status: Proposed
description:
This project upgrades the existing storm drainage system on Pine Street, which is shallow and
undersized and is not able to collect storm ruoff from surrounding properties. Flooding has
occurred (at least in the yard of one house) and a temporary ditch has been installed to handle
the overflow of the runoff. The FY 2005-06 CIP provided funding to resolve the problem by
replacing the existing 6-inch pipe with 12-inch, and installing manholes and catch basins for
frequent collections of storm runoff. The funding proposed for FY 2006-07 is required to complete
1-//_--14:---A --r.-/n;4.. 'k llI ~CS'~9Y4'rYIOH~O ~an ninaarinnlrin r%rniPntc/nrnir>rt tvnp rpn vi omm
City of Tigard Page 3 of 3
the construction, which begins in late FY 2005-06.
Red Rock Creek (at Dartmouth Street) Culvert Replacement $100,000
cip year: FY 2006-07 Water Quality/Quantity $100,000
status: Proposed Fund
description:
As part of the 72nd Ave/Dartmouth Street Intersection improvements, the Red Rock Creek
culvert under 72nd Ave will be improved to increase capacity, allow fish passage and stabilize the
creek channel near the intersection.
Storm Drainage Major Maintenance $100,000
cip year: FY 2006-07 Storm Sewer Fund $100,000
status: Proposed
description:
This yearly program addresses minor storm drainage problems requiring more than normal
maintenance effort by the City's Public Works department. The Storm Drainage Major
Maintenance Program in FY 2006-07 includes projects located at various locations in the City.
City of Tigard Page 1 of 5
Report - Project Details by Type created on:
CIP Year: FY 2006-07 3/10/2006 2:07:07 PM
Water System Program $7,052,470
550' Zone Beaverton Connection $200;000
cip year: FY 2006-07 Water Fund $84,000
status: Proposed Water SDC Fund $116,000
description:
The City's water system is currently connected with' the City of Beaverton (Joint Water
Commission) in the 410' elevation zone. This project will create a second connection to serve the
550' elevation zone. This project may also allow the City to delay construction of a 550' zone
reservoir on the north side of Bull Mountain for several years.
550' Zone Improvements: 10 MG transfer pump station upgrade $50,000
cip year: FY 2006-07 Water CIP Fund $50,000
status: Proposed
description:
The existing transfer pump station, located on the 10 MG reservoir site at Bull Mountain
Road/125th Avenue, serves both the 550-foot and 713-foot service zones. The Water Distribution
System Hydraulic Study identified a need to replace this pump station with one that would
provide a higher pumping capacity to both service zones. Construction of this improvement
increases pumping capacity from 2,000 gpm to 3,300 gpm for the 713-foot service zone. The
pump station will also provide 3,900 gpm to the 550-Foot Zone Reservoir No. 2 listed previously.
Along with the piping improvements listed below, the existing pump station at the Canterbury
site (Pump Station No. 1) will be abandoned.
550' Zone Improvements: Reservoir No. 2 Supply Lines $200,000
cip year: FY 2006-07 Water CIP Fund $200,000
status: Proposed
description:
This improvement is needed for existing and future needs in both transmission and distribution to
serve the new reservoir and pump station upgrade projects listed above. A new line will be
constructed between the new transfer pump station and Reservoir No. 2, ranging in size from 18-
inch to 24-inch. Design work will include selection of the most feasible route for this line.
550' Zone Reservoir No. 2 $500,000
cip year: FY 2006-07 Water CIP Fund $500,000
status: Proposed
description:
This reservoir will be located on Bull Mountain and will serve the south and eastern portions of
the 550-foot pressure zone. Constructing this reservoir will eliminate some of the demand
currently supplied by the 713-Foot pressure zone. Supply to the reservoir will be provided
through the transfer pump station upgrade and supply piping projects separately listed.
ASR Expansion Studies $400,000
cip year: FY 2006-07 Water CIP Fund $400,000
status: Proposed
description:
The City's hydrogeologist of record will assist Staff in locating potential sites for additional aquifer
storage and recovery (ASR) wells. In addition, test wells must be drilled by a qualified well driller
in order for the hydrogeologist to determine suitability of the well for ASR purposes. Therefore,
these studies will include both consulting services and drilling services.
httn://www.tiLard-or.Rov/city hall/departments/engineering/cip projects/project type rep... 3/10/2006
City of Tigard Page 2 of 5
Burnham Street - 16-inch Waterline Replacement (Tie to Street
Project) $100,000
cip year: FY 2006-07 Water Fund $50,000
status: Proposed Water SDC Fund $50,000
description:
Burnham Street is a major collector and is subject for reconstruction in FY 07/08. The installation
of a 16
Defective Meter Replacements (1 1/2 -Inch & Larger) $40,000
cip year: FY 2006-07 Water Fund $40,000
status: Yearly Program
description:
This has been one of the long-term projects for the Public Works Department. The large meter
replacement program is for the systematic testing, repair and/or replacement of all 1 1/2-inch and
larger water meters. Meters of this size have developed problems where actual water flows are
inaccurately measured; most of the time, the volume of water is under-reported. The result is
that water customers could be using more water than they are being assessed. Testing and or
replacement of these water meters have proven to make financial sense in that the investment is
recouped by the additional revenues received due to accurate meters.
Defective Meter Replacements (Smaller Sizes) $15,000
cip year: FY 2006-07 Water Fund $15,000
status: Yearly Program
description:
This has been another one of the long-term projects for the Public Works Department and is
similar to the program for 1 '/z-inch meter replacements. But this program is for the smaller
meters. Meters of this size have also developed problems where actual water flows are
inaccurately measured; most of the time, the volume of water is under-reported. The result is
that water customers could be using more water than they are being assessed. Testing and or
replacement of these water meters have proven to make financial sense in that the investment is
recouped by the additional revenues received due to accurate meters.
Lake Oswego Feasibility Study $130,000
cip year: FY 2006-07 Water CIP Fund $130,000
status: Proposed
description:
This project will involve an intergovernmental agreement (IGA) with the City of Lake Oswego to
determine the feasibility of the two cities becoming partners to expand the Lake Oswego
treatment plant and improve transmission lines between the two cities to enable Tigard to obtain
long term water supply from Lake Oswego's system. This option will be considered by Council
along with the other source options Tigard is considering.
Menlor Reservoir Recirculation $45,000
cip year: FY 2006-07 Water Fund $45,000
status: Proposed
description:
Menlor reservoir is developing a water quality issue in that, at certain times of the year, water
does not circulate throught the reservoir thus allowing chlorine residuals to diminish to below
state standards. This project will install a small circulatory pump system that will address this
problem.
Meter Installations $60,000
http://www.tigard-or.gov/city_hall/departments/engineering/cip_projects/proj ect_type_rep... 3/10/2006
City of Tigard Page 3 of 5
cip year: FY 2006-07 Water Fund $60,000
status: Yearly Program
description:
This on-going program ties in with the Water Service Installations program. When new water
customers, or existing customers who need an additional water service, apply for a new service,
Public Works staff install the service line and will set the new meter:
Replace Well House #2 (Gaarde Site) $70,000
cip year: FY 2006-07 Water Fund $70,000
status: Proposed
description: .
The existing well house at Well #2 is approximately 40 years old and needs to be replaced and
upgraded for security reasons.
Scoggins Dam/Tualatin Water Supply $430,000
cip year: FY 2006-07 Water CIP Fund $430,000
status: Proposed
description:
Secure 550' Reservoir #1 Site $3,000,000
cip year: FY 2006-07 Water CIP Fund $2,700,000
status: Proposed Water SDC Fund $300,000
description:
This reservoir is shown in the City's Water System Master Plan and will be located on the north
side of Bull Mountain. These funds will be used to locate and secure a suitable site.
Secure 550' Reservoir #2 Site $1,200,000
cip year: FY 2006-07 Water CIP Fund $1,200,000
status: Proposed
description:
The Public Works Department is in the process of securing a permanent location for the 550-foot
zone Reservoir No. 2. The general location of this reservoir will be near Bull Mountain Road, west
of Greenfield Drive.
Telemetry Upgrade $200,000
cip year: FY 2006-07 Water Fund $200,000
status: Proposed
description:
The existing telemetry system is out of date and the software and hardware are no longer
supported by the manufacturer or local representatives. The City has also experienced failures of
controllers at various sites due to the aging of the overall system. Replacement of controllers can
take up to three weeks, which is not adequate for the City's need to have continuous monitoring
ability of the water system. The upgrade process will enable the City to have up to date
technology that is more user friendly, and to explore modes of communication other than the
phone line system currently used.
Funds for 06/07 would only be used if the project is not 100% complete by June 30, 2006.
Walnut Street (121st to Tiedeman) Relocate 12-Inch Line w/Street
Construction $39,000
cip year: FY 2006-07 Water Fund $39,000
status: Proposed
httn://www.tigard-or.Lyov/city hall/departments/enaineering/cip proiects/proiect tvpe rep... 3/10/2006
City of Tigard Page 4 of 5
description:
This project is in conjunction with the Walnut Street improvements to be completed by
Washington County and the City over the next two years. Due to grade and alignment issues the
existing 12" water line needs to be upgraded.
Water Line Replacement-Walnut (135th to 121st) $44,720
cip year: FY 2006-07 Water Fund $22,360
status: Under Construction Water SDC Fund $22,360
description:
This project is in conjunction with the Walnut Street improvments to be jointly completed by
Washington County and the City. Funds for this year would only be used if the street project
were not 100% complete by June 30, 2006.
Water Main Oversizing $95,000
cip year: FY 2006-07 Water SDC Fund $95,000
status: Yearly Program
description:
During the course of the year the City may find the need to upsize a planned pipeline through a
new development, thus accomplishing an identified capital improvement as listed in the "Water
Distribution System Hydraulic Study - May 2000."
Water Main Replacements $78,750
cip year: FY 2006-07 Water Fund $78,750
status: Yearly Program
description:
This on-going program is based on the needs identified in the "Water Distribution System
Hydraulic Study - May 2000", and is for the routine replacement of leaking, damaged and older
water mains throughout the water system. In most cases the existing mains have adequate
capacity and will be replaced with the same diameter water mains. This program is also for the
completion of loops in the system to maintain hydraulic efficiencies.
Water Reservoir Seismic Upgrade Evaluation $70,000
cip year: FY 2006-07 Water Fund $70,000
status: Proposed
description:
This is the beginning of an expected two-year program that will review all of Tigard's water
reservoirs for conformity to current seismic standards and recommend upgrades where needed.
Water Service Installations $10,000
cip year: FY 2006-07 Water Fund $10,000
status: Yearly Program
description:
This is another long-term program for the department. Each year the City adds new customers to
the system through individual building permits or additional water services. Customers apply for
a new water service, and Public Works staff installs the service line and will set the meter (see
Meter Installations line item).
Water Site Security Upgrades $75,000
cip year: FY 2006-07 Water Fund $75,000
status: Proposed
description:
This project will accomplish the water site security upgrades that were identified in the PW
Vulnerability Assessment and Emergency Response Plan. The security upgrades will include
http://www.tigard-or.gov/city hall/departments/engineering/cip projects/project type rep... 3/10/2006
City of Tigard Page 5 of 5
improvements to such things as access, fencing, intrusion alarms, and monitoring.
http://www.tiRard-or.aov/city hall/departments/enRineerina/city moiects/moiect tvpe ren... 3/10/2006
City of Tigard Page 1 of 1
Report - Fund Allocations created on:
CIP Year: FY 2006-07 3/10/2006 1:45:41 PM
Facility Fund $1,795,197
Audio/Visual Control System for Council Chambers $83,000
Card Reader Installation $18,500
City Facility Security Upgrades $10,000
_
Citywide Facility Master Plan _ _ $50,000
Commuter Rail Station Enhancement $100,000
Consolidation of Public Works Facilities (Water Building) $630,000
Library Parking Lot Expansion $180,000
Library Projects - Houghton - Root Donations $4271697
.
Library Property - Voluntary Cleanup _ $26,0_00
Outside Entrance to PC-4 conference room
_._ntra
PD Underground Storage Tank Upgrade _ _$40,000
Police l Records Storage Remodel--- $15,000
Senior Center Remodel Design (including Seismic Upgrade) _ $200,000
.
1,+M•/%nnxnzrtirtarrl-nreTnv/rite hall/rlannrtmante/inaina.arina/rin nrniar.ta/fimrl rannrtnen 'A/1 n11)nnA
City of Tigard Page 1 of 1
Report - Fund Allocations created on:
CIP Year: FY 2006-07 3/10/2006 1:46:33 PM
Parks Capital Fund $1,828,363
BPA Trail Feasibility Study $15,000
Clute Property House Demolition $15,000
Fanno Creek Trail (Hall to Fanno Creek) $30,000
Fanno Creek Trail Master Plan $60,000
Land Acquisition $579,513
Northview Park - Shelter & Path Installation _ _ $25,000
Parkland Acquisition - Downtown $100,000
Skate Park Development & Construction $426,300
Tree Replacement/Planting $50,000
Tualatin River/Cook Park Trail from Garden to Bridge $97,530
Washington Square Regional Center Trail $430,020
httn://www.tiLard-or.Rov/city hall/departments/engineering/cip projects/fund report.asp 3/10/2006
City of Tigard Page 1 of 1
Report - Fund Allocations created on:
CIP Year: FY 2006-07 3/10/2006 1:46:07 PM
Gas Tax Fund $2,478,000
72nd Avenue/Dartmouth Street Intersection Signalization__ $200,000
Ash Avenue Connection Feasibility Study (Fanno Creek to Scoffins St) ~_--~$40,000
Ash Avenue Construction (Burnham Street to Railroad Tracks) $220,000
Burnham Street Improvements $750,000
Commercial Street (at Main Street) Intersection Treatments $75,000
Commercial Street Improvements (Lincoln Avenue to Main Street) $400,000
Downtown Comprehensive Streetscape Design $25,000
Hall Blvd and Highway 99W Gateway Treatments $75,000
Hall Boulevard Crosswalk (at Fanno Creek Pathway) $80,000
Hall Boulevard Sidewalk (Spruce St to 850' south) $100,000
Highway 99W Corridor Improvement & Management Plan $20,000
Main Street Safety Improvements _$75,000_
Pavement Major Maintenance Program (PMMP)~- $210,000
_ _
Sidewalk Improvements $100,000
Street Striping Program $15,000
Tigard Street/Tiedeman Avenue Intersection Traffic Feasibility Study $25,000
Traffic Calming Program $8,000
Walnut Street (116th to Tiedeman Avenue) ROW Acquisition $40,000
_
Walnut Street Improvements (135th to 121st Avenue) $20,000
httn-//www.tiga.rd-or.gov/citv hall/denartments/engineering/cin nroiects/fund renort.asn 3/10/2006
City of Tigard Page 1 of 1
Report - Fund Allocations created on:
CIP Year- FY 2006-07 3/10/2006 1:48:57 PM
Street Maintenance Fee (SMF) $950,000
Pavement Major Maintenance Program (PMMP) $950,000
http://www.tigard-or.gov/city hall/departments/engineering/cip-projects/fund report.asp 3/10/2006
City of Tigard Page 1 of 1
Report'- Fund Allocations created on:
CIP Year: FY 2006-07 3/10/2006 1:51:15 PM
Traffic Impact Fee Fund $1,450,000
72nd Avenue/Dartmouth Street Intersection Signalization_ _ $300,000
Durham Road/108th Avenue Intersection Signalization $150,000
Hall Blvd Half-street Improvements (Fanno Creek to 450 feet north) $150,000
Hall Boulevard (at McDonald Street) Right-turn Lane Widening $125,000
Hall Boulevard/Wall Street Intersection - Phase 2 $700,000
Tigard Street/Tiedeman Avenue Intersection Traffic Feasibility Study $25,000
http://www.tigard-or.gov/city hall/departments/engineering/cip projects/fund report.asp 3/10/2006
City of Tigard Page 1 of 1
Report - Fund Allocations created on:
CIP Year: FY 2006-07 3/10/2006 1:51:39 PM
Traffic Impact Fee Fund - Urban Services $175,000
Bull Mountain Road (at Hwy 99W) Right-Turn Lane Widening $75,000
Bull Mountain/Roshak Road Intersection $100,000
http://www.tigard-or.gov/city_hall/departments/engineering/cip_projects/fund_report.asp 3/10/2006
City of Tigard Page 1 of 1
Report - Fund Allocations created on:
CIP Year: FY 2006-07 3/10/2006 2:54:53 PM
Tigard Triangle LID #1 Fund $1,589,500
Tigard Triangle Street Improvements LID No.1 $1,589,500
httD://www.tigard-or.i2ov/citv hall/denartuents/engineering/cip uroiects/fund renort.asn 3/10/2006
City of Tigard Page 1 of 1
Report - Fund Allocations created on:
CIP Year: FY 2006-07 3/10/2006 2:03:22 PM
Sanitary Sewer Fund $2,500,000
79th Ave Sanitary Sewer Outfall $80,000
Benchview Terrace Sanitary Sewer Access Road $40,000
Bonita Road at Milton Court - Pipe Removal $30,000
Citywide Sanitary Sewer Extension Program $2,000,00_0
Commercial Street Sanitary Sewer Repair (Lincoln to Maint St) $50,000
McDonald Street (at Hall Boulevard) Sanitary Sewer Connection $100,000
Red Rock Creek Sanitary Sewer Repair $50,000
Sanitary Sewer Major Maintenance Program $100,000
Sanitary Sewer Master Plan $50,000
http://www.tigard-or.gov/city_hall/departments/engineering/cip_projects/fund report.asp 3/10/2006
City of Tigard Page 1 of 1
Report - Fund Allocations created on:
CIP Year: FY 2006-07 3/10/2006 1:47:18 PM
Storm Sewer Fund $466,000
79th Avenue Storm Drainage Outfall $90,000
Derry Dell Creek Wetland & Vegetated Corridor Enhancement $3,000
Durham Rd at 108th Ave - Stream Bank Stablization $150,000
Gaarde Street Phase II Wetland Mitigation_ $3,000
Highland Drive (109th Ave to 500' west of Greens Way) - Storm Drain Pipe $25,000
Replacement
Pine Street Storm Drainage System Upgrade $95,000
Storm Drainage Major Maintenance $100,000
http://www.tigard-or.gov/city hall/departrnents/engineering/cip projects/fund report.asp 3/10/2006
City of Tigard Page 1 of 1
Report - Fund Allocations created on:
CIP Year: FY 2006-07 3/10/2006 1:53:28 PM
Water Fund $859,110
550' Zone Beaverton Connection $84,000
Burnham Street - 16-inch Waterline Replacement (Tie to Street Project) $50,000
Defective Meter Replacements (1 1/2 -Inch & Larger) $40,000
.
Defective Meter Replacements (Smaller Sizes) $15,000
Menlor Reservoir Recirculation $45,000
Meter Installations $60,000
Replace Well House #2 (Gaarde Site) $70_,000
Telemetry Upgrade $200,000
Walnut Street (121st to Tiedeman) Relocate 12-Inch Line w/Street Construction $39,000
Water Line Replacement-Walnut (135th to 121st) y -$22,360
Water Main Replacements $78,750
Water Reservoir Seismic Upgrade Evaluation $70,000
Water Service Installations $10,000
_
Water Site Security Upgrades $75,000
http://www.tigard-or.gov/city_4all/departments/engineering/cip_projects/fund report.asp 3/10/2006
City of Tigard Page 1 of 1
Report - Fund Allocations created on:
CIP Year: FY 2006-07 3/10/2006 1:53:02 PM
Water CIP Fund $5,610,000
550' Zone Improvements: 10 MG transfer pump station upgrade _ $50,000
550' Zone Improvements: Reservoir No. 2 Supply Lines - $200,000
550' Zone Reservoir No. 2 $500,000
ASR Expansion Studies $400,_000
Lake Oswego Feasibility Study $130000
Scoggins Dam/Tualatin Water Supply $430,000
Secure 550' Reservoir #1 Site _ $2,700,000
Secure 550' Reservoir #2 Site $1,200,000
http://www.tigard-or.gov/city_hall/departments/engineering/cip_projects/fund report.asp 3/10/2006
City of Tigard Page 1 of 1
Report - Fund Allocations created on:
CIP Year: FY 2006-07 3/10/2006 1:54:22 PM
Water Quality/Quantity Fund $315,000
Derry Dell Creek at Fanno Creek and Walnut St - Culvert Improvements $125,000
Hiteon Creek Riparian Enchancement - Phase 2 Construction $90,000
Red Rock Creek (at Dartmouth Street) Culvert Replacement $100,000
http://www.tigard-or.gov/city_hall/departments/engineering/cip_projects/fund report.asp 3/10/2006
City of Tigard Page 1 of 1
Report - Fund Allocations created on:
CIP Year: FY 2006-07 3/10/2006 1:53:56 PM
Water SDC Fund $583,360
550' Zone Beaverton Connection $_116,0_00
Burnham Street - 16-inch Waterline Replacement (Tie to Street Project) ~w M$50,000
Secure 550' Reservoir # 1 Site $300,000
Water Line Replacement-Walnut (135th to 121st) $22,360
Water Main Oversizing $95,000
httv://www.tigard-or.gov/city hall/departments/engineering/cip pr6jects/fund report.asp 3/10/2006
r~
t,
PIN
EXECUTIVE SUMMARY
Responses to Public Input
on
FY 2006-07 Capital Improvement Program
March 10, 2006
Prepared by Engineering Department
Capital Improvement Division
Executive Summary - FY 2006-07 CIP
March 10, 2006
Page 1 of 16
EXECUTIVE SUMMARY
The Capital Improvement Program (CIP) formulation process for Fiscal Year 2006-07 began in
December 2005. The proposed CIP projects were posted on the City of Tigard's webpage on
December 7, 2005 initiating the process. That same night, City staff from the Engineering and
Public Works Departments hosted the first of two public meetings in Town Hall. The open-house
style event provided the public an opportunity to view information and converse with staff
regarding the proposed CIP projects for FY 2006-07. Overall, the event was well-received by the
public and staff collected a small handful of completed comment cards. These were forwarded to
the appropriate departments for response.
In an effort to receive more public input, the Engineering Department coordinated with the Times
to announce the 2°d public meeting on Wednesday, January 25, 2006. 5,000 informational flyers, with
comment space and return address information, were inserted in the December 29, 2005 Times
newspaper. In order to allow for sufficient response time from City staff before the January 25, 2006
public meeting, we asked that comments be returned by January 18, 2006. Any comments received
on or after January 18, 2006, are responded to in this summary report. Other efforts to notify the
citizens of Tigard regarding the CIP formulation process were made by posting the public meeting
dates and times on the City of Tigard Events Calendar, December 2005 Cityscape issue and bulletin
boards in and around City Hall and the library. Press Releases were also submitted to the Times and
the Oregonian containing the scheduled events in the CIP formulation process and contact
information for receiving comments.
Throughout 2005 and into the FY 2006-07 CIP formulation process, a total of thirty-nine (39)
comments were received by the Engineering Department. These comments were received via postal
system, email, telephone and comment cards from the CIP public open house meetings on
December 7, 2005 and January 25, 2006. Comments provided input on the draft CIP list and
nominated projects for the City's consideration. Before the CIP formulation process began on
December 7, 2005, City staff responded directly to citizens at the time each individual comment was
received. The public was issued a draft summary of these responses at the January 25, 2006 public
meeting.
Citizens were notified through the City's webpage that they could continue to submit their input for
the FY 2006-07 CIP through January 27, 2006. The public was also informed that comments
received after January 27, 2006 will not be included in the Council packet. However, CIP project
candidates and comments submitted after the deadline will be considered on a case-by-case basis
until the CIP budget is submitted for consideration in the City's formal budget formulation process.
All correspondence and published notices for public information throughout the CIP Formulation
Process for FY 2006-07 are included in the final pages of this summary (see Attachments). However,
due to the size of the Summary, a total of 60 pages, the attachments were not included in the packets
submitted to City Council and Planning Commission. Instead, they will be available upon request.
Executive Summary - FY 2006-07 CIP
March 10, 2006
Page 2 of 16
SUMMARY OF COMMENTS & RESPONSES
The following is the summary of public comments and staffs responses:
1. 93`a Avenue Sanitary Sewer Reimbursement District
Public Comment- A 93`s Avenue resident came into the Permit Center to inquire about joining the
members of the proposed 93rd Avenue Sanitary Sewer Reimbursement District.
Staff Response - Engineering Department staff fielded the citizen's inquiry and evaluated the
feasibility of their joining the 93`d Avenue Sanitary Sewer Reimbursement District. Since the
citizen's lot could be served by the district's sanitary sewer infrastructure, the citizen was notified
of the feasibility and invited to attend a neighborhood meeting for the proposed 93rd Avenue
Sanitary Sewer Reimbursement District on December 14, 2005. Formation of the district is
scheduled for February 28, 2006 and construction is anticipated to begin in early May 2006.
2. North Dakota Street - Sidewalk
Public Comment - A citizen raised concern over new development along North Dakota Street
between 109`h Avenue and 115`h Avenue. The concern is that the newly developed area will have
more people walking and driving making North Dakota Street very busy. The citizen suggests
that the building fees collected by the City from the developers be used to enlarge the walking
and biking paths along North Dakota Street, especially at the Fanno Creek bridge. Pedestrian
residents of this community, seeking exercise and bus stop access, are frequently put within
dangerous proximity to speeding cars as they travel along North Dakota Street.
StafResponse - In response to their email, the citizen was contacted via telephone and given an
opportunity to discuss his concern in more detail with staff. Two private development housing
projects, within the area of concern, are under construction. As required by the City, the
developers will build half-street improvements including roadway widening, concrete curb and
gutter and sidewalks. Given the area's existing potential for future private development, it's
highly likely that additional properties will develop in a similar fashion providing future street
and sidewalk improvements. A conceptual study is being conducted for installation of a
pedestrian bridge over Fanno Creek in the future, if feasible.
3. Fanno Creek Trail - Marked Crosswalk on Tiedeman Avenue
Public Comment -A Tigard citizen requested, via email, a marked crosswalk for the Fanno Creek
Trail across Tiedeman Avenue to connect the existing pedestrian path along the Fanno Creek
Trail from just north of Fowler Middle School to Woodward Park. The citizen mentioned the
Fanno Creek Trail crosswalk at North Dakota Street as an example of what could be installed.
The message mentioned that there is currently no designated place for crossing Tiedeman
Avenue and as a result, people cross at different locations. The message indicated that a
designated, marked crosswalk, would improve pedestrian and bicycle safety across Tiedeman
Avenue along the Fanno Creek Trail.
Staff Response - Upon receiving the comment, the Engineering Department staff discussed the
request for a Tiedeman Avenue crosswalk and compared its situation to the Fanno Creek Trail
crosswalk at North Dakota Street. The situation with the North Dakota Street crosswalk was
worse in that there were no existing signs to alert motorists of pedestrians or sidewalks for
pedestrians to traverse the offset alignment for the Fanno Creek Trail. At Tiedeman Avenue,
pedestrians have existing sidewalks along the offset alignment for the trail and experience good
visibility to view oncoming traffic. To alert motorists in advance of unexpected pedestrian
Executive Summary - FY 2006-07 CIP
March 10, 2006
Page 3 of 16
entries into the roadway, two (2) W11-2 "Pedestrian" (MUTCD; 2003) signs were installed in
1996, in each direction. The City realizes that there are unprotected Fanno Creek Trail street
crossings at various locations throughout the City. In an effort to remedy this situation at some
locations, the City is proposing to install a mid-block crosswalk on Hall Boulevard at Fanno
Creek Trail in FY 2006-07. However, the project is contingent upon ODOT's approval since the
proposed crosswalk is located on a State route.
4. Tiedeman Avenue - Intersection at Greenburg Road
Public Comment - A Tigard citizen submitted an email to Engineering via the Public Works
Department. The email asked if there were any future plans to fix the intersection at Greenburg
Road and Tiedeman Street. The citizen explained that heavy traffic, including big trucks, has
created potholes and given the pavement a beating at the corner when turning from Greenburg
Road to Tiedeman Street. The potholes have been repaired when they become too bad to ignore
but the citizen wants to know when a more permanent fix will happen. The citizen also said that
driving through there during rush hour and having to avoid these potholes is very disconcerting.
The citizen expressed his opinion that the pavement at the corner of Greenburg Road and
Tiedeman Street needs to be completely removed and replaced instead of ongoing pothole
repair. The citizen conceded that the street maintenance fee may not be able to fund the repair
of every road in Tigard but that the City should at least be pothole free and that repair of main
arterial roads, such as these, get priority funding from the fee.
Staff Response - In an email response, staff told the citizen that the City will continue to repair
potholes as they appear in the next few months. Staff agreed that the right turn lane from
Greenburg to Tiedeman and, the westbound lane on Tiedeman leading away from the
intersection'are in poor condition. Staff explained that fiber optic cable trenching some years ago
by a telecommunications company has led to premature pavement failure on this street segment.
Staff mentioned that the City did perform some dig-out repairs, but they were not sufficient to
resolve the issues. Staff has revisited the entire intersection to establish the scope for the
upcoming pavement overlay project and determined the extent of project limits. A pavement
overlay project for Greenburg Road, between Tiedeman Road and Center Street including the
Greenburg/Tiedeman intersection, is scheduled for construction in Spring 2006.
5. McDonald Street - Lighted Crosswalk at SW 93`d Avenue
Public Comment - A Tigard citizen submitted an email to Engineering via Mayor Craig Dirksen
requesting a lighted crosswalk on McDonald Street at 93rd Avenue because of concern for the
safety of the Woodland Heights staff working nights at this nearby assisted living facility. The
citizen also expressed that the current pedestrian crossing situation provides opportunity for a
serious accident. To illustrate this concern, the citizen presented the scenario that if a crossing
pedestrian were to slip and fall on wet or slippery pavement, a car traveling 45-50 mph might be
unable to stop and would most likely hit the person. The citizen also mentioned that it was his
understanding that last year a similar occurrence had already happened in which the
administrator of Woodland Heights was almost hit by a car that couldn't stop. Fortunately, the
administrator was able to avoid being hit by rolling into the curb and out of the vehicle's path.
The citizen does not want the administrator's near miss to become something more critical for
someone else. The citizen concluded by saying that they are truly concerned for the safety of
both men and women who must cross this street everyday and night.
Staff Response - In an email response, staff thanked the citizen for his request and input
concerning a lighted crosswalk at the 93`d/McDonald Street intersection. In general, the citizen
Executive Summary - FY 2006-07 CIP
March 10, 2006
Page 4of16
was told that the City was in the process of formulating the Capital Improvement Program (CIP)
for Fiscal Year 2006-07. The citizen was invited to attend the December 7, 2005 meeting to
provide comments on the projects proposed for the fiscal year and to suggest other projects as
well. The citizen did not attend the meeting. At this time, staff is pursuing a more thorough
traffic study to determine if a pedestrian crosswalk is warranted.
6. McDonald Street - Widening of Intersection at SW 97`'' Avenue
Public Comment - A citizen recommended the widening of the 97th Avenue intersection with
McDonald Street for the purpose of providing turning lanes on McDonald Street. The citizen
said traffic volumes are heavy and vehicles have a hard time making the turning movements in
and out of 97`s Avenue especially when school buses are turning left from McDonald Street to
97' Ave to pickup or drop off students at the two nearby schools on 97 h Avenue.
StafRerponse - The Engineering Department performed research with respect to the right-of-
way constraints associated with the potential widening of McDonald Street at 97`h Avenue. It
was determined that a substantial amount of right-of-way acquisition and earthwork movement
would be required to add an exclusive left-turn lane to westbound McDonald Street at 97`''
Avenue. Upon realizing the close proximity of existing homes and the large scope of work
involved with the addition of a left turn lane, the Engineering Department contacted the Tigard-
Tualatin School District to discuss the possibility of school busses using Satder Street instead of
McDonald Street on their way toward Twality Junior High and Templeton Elementary School to
reduce traffic volume on McDonald Street. To this date, the discussions are still in progress.
Once staff's recommendation is implemented, the McDonald Street gaps in traffic flow would
be more frequent and would help the turning movements in and out of 97`h Avenue without the
need for expensive widening.
7. Englewood Park - Replace culverts /asphalt areas
Public Comment - A Tigard citizen representing a Tigard environmental advocacy organization
commented that the installation of approximately four culverts and existing depressed areas of
asphalt in the wetlands have changed the hydrology in Englewood park and may be blocking
fish passage. The citizen believed that this consequently affects plant diversity and overall
biological diversity of the park. In addition, the citizen felt that park users are unable to access
these areas for 4-6 months of the year because of standing water. The citizen suggested that
arched wooden bridges replace the culverts to improve habitat, hydrology and availability of use
to citizens.
Staff Response - The preliminary design has begun since January 2006, for riparian enhancement
and channel improvement in the area noted. All design solutions to reestablish biodiversity in
the area will be assessed. The most cost effective design solution, that delivers the most
biodiversity for the dollar, will be selected. At this time, bridging the area and leaving the culverts
in-place with modified existing stream channels will be evaluated.
8. Fanno Creek Trail - Replace parts of with boardwalks
Public Comment - A Tigard citizen representing a Tigard environmental advocacy organization
commented that there are a number of low, wetland areas on the trail which flood quite often in
the winter and spring months, making the trail un-useable, even after 1 or 2 inches of rain. The
citizen suggested that the City replace the asphalt with a boardwalk to allow users to have access
to the trail in the winter. The citizen also expressed that this would allow for better runoff
Executive Summary - FY 2006-07 CIP
March 10, 2006
Page 5 of 16
drainage, improved hydrology, and would prevent users from trampling all the vegetation next to
the trail that currently occurs.
Staff Response - Low spots along the existing Fanno Creek Trail, to the north of Fowler Junior
High from Tiedeman Avenue to Tigard Street, were paved with additional asphalt to raise the
elevation of its original profile as constructed in 2000. In addition, culverts were added at various
low spots to further prevent water from flowing over and settling on the trail surface. The City
recognizes that many areas along Fanno Creek Trail throughout Tigard are submerged when we
experience a significant period of heavy rainfall as trails are constructed in the 100-year
floodplain and. are intended to be creek-side paths.
9. Summerlake Park
Public Comment No. 1 - A Tigard citizen representing a Tigard environmental advocacy
organization commented that a number of years ago, he worked with a former City of Tigard
Parks director to develop interpretive signage at the park. The citizen would still like to see this
completed so visitors can learn about bird species, etc. The citizen also felt that the interpretive
signs would serve as an educational tool, in particular, asking that people not feed ducks and
geese and further explain why this is discouraged. The citizen could recommend several good
places for signage including the area by the bridge crossings in the center of the park where they
would be highly visible.
Staff Response No. 1 - Interpretive signage has been placed in the Rhododendron Garden by
volunteers. The Parks Division would welcome an opportunity to work with additional
volunteers to place signs elsewhere in the park.
Public Comment No. 2 - A Tigard citizen submitted a comment card describing his experience
with City-planted evergreen trees obstructing their lake view. The City relocated the trees, but
the citizen wished to emphasize the importance of the City's consideration of the public in the
lake area. The citizen also suggested that the City direct voluntary efforts to clear blackberry
brush around the lake and called attention to the old white pipes by the bridge.
Staff Response No. 2 - The Public Works Volunteer Coordinator was contacted and has requested
a copy of the comment card. The clearing of blackberry brush around Summerlake Park will be
considered by the coordinator for the Public Works Volunteer Coordination Program. Tigard
has a variety of opportunities for volunteers to choose from including one-time events and
ongoing projects. Volunteers will work with staff to remove blackberry, English ivy, and other
non-native species from parks and undeveloped areas.
10. Land Acquisition - Various Locations within the City
Public Comment No. 1 - A Tigard citizen recommended, on a comment card submitted at the
December 7, 2005 CIP Open House meeting, that the east side of Greenburg Road, adjacent to
Ash Creek, be acquired for wetland protection and as an environmental buffer on the north side
of Ash Creek.
Staff Response No. 1 - This property was evaluated in the Park and Recreation Advisory Board's
Park and Greenway Property Evaluation Process. The status of the evaluation is confidential at
this time.
Public Comment No. 2 - A Tigard citizen representing a Tigard environmental advocacy
organization at the December 7, 2005 CIP Open House meeting, suggested the City use some of
the CIP funds to begin land acquisition of several parcels in the pursuit of adding to the current
Executive Summary - FY 2006-07 CIP
March 10, 2006
Page 6 of 16
shortage of open space/parks system in Tigard as well as protecting valuable resources including
large old-growth trees and wildlife. The citizen conceded that while these funds most likely are
not sufficient to purchase the land, they could be enough to fund an option to purchase,
allowing the City to meanwhile work on funding the full cost of the land.
The citizen submitted the following list of properties for consideration:
• Ash Creek and adjoining Gates property - The 9 acre Ash Creek parcel is the largest
remaining predominantly Western red cedar forest left in the entire Metro area with
some of the highest wildlife and habitat values left in the City. The residents in this area
ate without a park. This site has been approved for development, but the landowner is
willing to negotiate a selling price and the citizens of this community want this property
protected and made into a "nature park." The citizen explained that many of their
associates had worked for several years with Metro and the Three Rivers Land
Conservancy to purchase this site, raising over $500,000. Further, the City refused to
fund the remaining portion of $300,000. Now, a second chance has arrived, since the site
was under LUBA appeal and remanded to the City Council. The citizen expressed that
they have their share of funding to purchase this site.
• Black Bull - An 8-acre parcel along Fanno Creek off North Dakota Street. The site has
wetland, floodplain and riparian values, as well as high wildlife values including 2 State
listed species.
• Gage Property off Bond St. - A 3.5 acre forest surrounded by houses and used as a park
already, with two trails through it. It has a stream at one end, and mature Douglas fir,
cottonwood, Oregon ash, Oak and Douglas Hawthorn. The citizen felt that this is a
beautiful site.
• Proge , along Ash Creek off Shady Lane - This is a 3.5 acre wetland and forest along
Ash Creek and is one of the last undeveloped parcels along Ash Creek with a great
number of birds including herons, kingfishers, and many species of songbirds.
• Fanno Creek east of the Library (Fields site - This is a wetland and forest complex east
of the creek and library which have extremely high wildlife and habitat values and
includes several listed species and rare plants. The citizen felt that acquisition of this
parcel would greatly complement the open space around the library and provide acreage
to the park system which is currently deficient in both open space and parks.
Staff RAponse No. 2 -
- Ash Creek and adjoining Gates property
- Black Bull
- Gage Property off Bond St.
- Property along Ash Creek off Shady Lane
- Fanno Creek east of the library (Fields site)
Most of these properties were identified as properties to be considered by the Park and
Recreation Advisory Board's "Park and Greenway Property Evaluation Process". This
document is considered confidential at the present time. However, it can be said that owners of
several of these properties have told the City that their properties are not for sale. In general,
some additional information will be available in approximately 6 months but is currently
confidential.
Executive Summary - FY 2006-07 CIP
March 10, 2006
Page 7 of 16
Public Comment No. 3 - The same Tigard citizen who submitted the previous comment (No. 2)
representing a Tigard environmental advocacy organization expressed his wholehearted support
for more land acquisition for open space and parks, but felt that $579,513.00 is nowhere near the
amount needed to provide the needs of Tigard citizens. The citizen stated that in some areas of
Tigard, this amount would only buy 1 or 2 acres, at most. He would like to see an amount of
approximately $3-6 million dollars to buy some wonderful properties in Tigard, as a start. The
citizen also stated that Tigard citizens have been asking the City to buy important sites for years
and have made numerous recommendations. They also expressed their opinion that the City
abandons their mode of thinking that all open spaces will be developed because this is not what
the citizens of Tigard want or need. The citizen continued by expressing that numerous ongoing
surveys demonstrate Tigard citizens' desire for more open space and connection to the natural
world. He also recommended that all current funds allocated for trails, shelters, etc., borrowed
funds, and funds from the November Open Spaces Bond Measure sponsored by Metro be
reserved for purchasing open space and additional lands.
Staff Berponse No. 3 - The $579,513.00 of funding for FY 2006-07 is in addition to the $579,513
in this year's budget which totals $1,159,026.00. This money will be leveraged with the possible
$1,326,780 funding coming from Metro if Metro's November 2006 bond measure is successful.
In addition, the City is currently looking at 15 greenway properties totaling 43.4 acres, and 7
active park properties totaling 19.3 acres combining for 62.7 acres. The estimated purchase price
of 44.8 acres totals approximately $6.9 million. The estimated value of the remaining potentially
donated 17.9 acres totals $3.7 million.
11. Monitoring and Evaluation (M&E)
Public Comment - A Tigard citizen representing a Tigard environmental advocacy organization
said there is currently no M&E program for all of the parks and open spaces in the City. The
citizen felt that monitoring and evaluating the success of restoration programs is essential to
determine the success or failure of the City's restoration efforts. It also allows for determination
of fish and wildlife usage of protected habitats providing helpful information for making
improvements for a particular species. For example, songbirds in a forested setting need
sufficient cavities for nesting. Or if the understory is diverse and in good condition so that it
provides hiding, roosting, and nesting habitat and a variety of food sources. Or if the City is
planting trees, shrubs, and herbaceous plant species that are native to that area. Or if the City is
protecting the existing biological diversity while also working to increase the biological diversity
where necessary. The citizen presented these as some of the questions the City needs to be
asking as the City restores its parks and open spaces, where needed. The citizen continued by
recommending the M&E program be done seasonally, by a part time biologist/ecologist.
Further, the citizen expressed that this position is greatly needed in the City of Tigard, since
there is no one on staff with this expertise. The citizen believed that current Parks staff is too
busy with their heavy workload and a part-time biologist/ ecologist would allow for an annual
M&E program, providing a measure of success of the City's restoration efforts and how the
money is being allocated. In general, the citizen would like to see a large sum of funding be
made available for land acquisition under the CIP program. The citizen felt that land in Tigard is
becoming very scarce, and the City needs to act quickly in order to be able to meet the needs as
indicated in the Tigard Parks Master Plan, and to meet the needs of the citizens of this
community, who just last year expressed their desire and willingness for more open space
acquisition and protection in Tigard.
Executive Summary - FY 2006-07 CIP
March 10, 2006
Page 8 of 16
Staff Response - At the present time, all City of Tigard Parks Restoration Programs are monitored
for vegetative success. Funding is an issue for a part time biologist/ecologist position.
12. Ann Street Sanitary Sewer Reimbursement District
Public Comment - A Tigard citizen expressed his hope, both verbally and on a comment card
submitted at the December 7, 2005 CIP Open House meeting, that the Citywide Sewer
Extension Program begin the process of forming the Ann Street Sanitary Sewer Reimbursement
District. The citizen, along with the other 6 to 8 homes within the proposed district, stated that
this ongoing process has taken 3 years.
Staff Response - The Engineering Department will include the Ann Street Sanitary Sewer
Reimbursement District into the Fiscal Year 2006-07 CIP.
13. Highway 99W - Northbound TriMet Bus Stop at Bull Mountain Road
Public Comment - A citizen recommended sidewalk improvements on Highway 99W at the Bull
Mountain Road bus stop. This bus stop serves the park and ride at a nearby church. The
improvements would also need to address the problem of seasonal mud flows at the bus stop.
The citizen said that if the project is implemented, it would carry out City/TriMet Memorandum
of Understanding (MOU) for improving transit services in the City. The preliminary design and
cost estimate can be provided by TriMet.
Staff Response - Engineering Department staff will investigate the feasibility of this recommended
project. Currently, the proposed CIP budget for FY 2006-07 contains $75,000.00 to be used for
various small Sidewalk Improvement projects throughout the City ]units. If this project is
determined to be feasible, the funds would come from the $75,000 budget.
14. Skate Park
Public Comment No. 1 - A Tigard citizen commented, on a comment card submitted at the
December 7, 2005 CIP Open House meeting, that the City of Tigard has sufficient population
to constitute a skate park. Further, the citizen felt that the City needs a skate park for this type of
density. The citizen reminded the City that the Jim Griffith Memorial Skate Park Project has
gone on for the last 4 years and suggested that Tigard City Council allocate the additional money
needed to construct this project. The citizen expressed that the time is rightl
Public Comment No.2 - A Tigard citizen pleaded, on a comment card submitted at the December
7, 2005 CIP Open House meeting, that the City consider Tigard youth when considering City
parks. The citizen expressed his belief that a skate park would benefit a large number of Tigard
youth that do skateboard, in-line skate and BMX bike ride. The citizen commented that he
personally knows many youth in Tigard that now have to travel outside the City to visit skate
parks in other areas. The citizen also felt that the skate park would save the City money in
property damage maintenance costs. Finally, the citizen expressed his opinion that Tigard youth
just need a safe, fun place to skate.
Public Comment No.3 - A Tigard citizen representing a Tigard environmental advocacy
organization reemphasized his awareness that there have been problems trying to raise private
funds to construct the skate park. He confirmed his support for the project, but also expressed
his objection to the use of public funds, specifically System Development Charges (SDC). He
would rather see these funds used for land acquisition.
Staff Response - In an earlier response to the first two comments, staff expressed that Council had
appropriated $150,000 in Parks SDC funds toward the $405,000.00 needed for the construction
Executive Summary - FY 2006-07 CIP
March 10, 2006
Page 9 of 16
of the skate park, which would be built on City Hall property. The project remains in the City's
CIP process. The third comment arrived recently and staff provided the following update
regarding the skate park funding. The Council has directed staff to budget additional City funds
in Fiscal Year 2006-07 so this project can be completed. Additional funds from the Parks SDC
fund, and additional funds from the General Fund, along with cash donations make up the
$405,000 available for the construction of the skate park in FY 2006-07 (Parks SDC = $324,000,
General Fund = $41,000, Cash Donations = $40,000).
15. Cook Park - Tualatin River Trail
Public Comment- A Tigard citizen commented, on a comment card submitted at the December 7,
2005 CIP Open House meeting, that the City defer the paving of the proposed trail from Cook
Park to the railroad underpass because they believe it's the sole wildlife access from river to
wetlands.
StafResponse - The gently sloping property through which the proposed trail extends is covered
with pasture grasses with fescue along the entire route. Native vegetation remains near the
eastern or downstream portion of the trail. The impact of the trail on vegetation is mainly to
pasture grasses and fescue. The alignment minimizes riparian impact by preserving all existing
trees.
The proposed trail is located on the edge of the meadow and is routed to avoid wildlife
disturbances. The geese and ducks will over fly the trail. Because it will be set at grade, the trail
also will not interfere with hydrology or pose an undue barrier to wildlife movements between
the riparian and wetland areas.
A counter balancing environmental benefit of paving is that the grasslands involved are of
limited value and will be mitigated by the enhancement of the area between the river bank and
trail using native plants. As a result of required and voluntary projects, the net effect of the trail
project will improve the overall biological conditions of the riparian area along the Tualatin
River.
The landward side of the trail also is scheduled for restoration. Several City and CWS plantings
projects have already been carried out to restore the former conditions.
The project has been designed to comply with all permit and environmental standards. Staff
concludes that the Tualatin River Trail project should not be removed from the proposed FY
2006-07 CIP as recommended by the citizen.
16. Hiteon Creek - Fish Passage
Public Comment - A Tigard citizen expressed his desire, on a comment card submitted at the
December 7, 2005 CIP Open House meeting, that the City include fish passage design at all
street crossings (culverts).
Staff Rerponse - One culvert that has been analyzed by the City's and Clean Water Services' staff
to provide fish passage is Springwood Drive. It is the opinion of the staff that the cost to retrofit
the culvert at Springwood Drive will not justify the benefit. For this reason, areas upstream of
Springwood Drive will be designed to focus on significant improvement of water quality from
highly urbanized areas so that the cleanest water possible will be delivered to the fishes that live
downstream of the improvement
Executive Summary - FY 2006-07 CIP
Match 10, 2006
Page 10 of 16
17. Red Rock Creek - Sanitary Sewer Repair
Public Comment- A Tigard citizen commented, on a comment card submitted at the December 7,
2005 CIP Open House meeting, that he wanted the City to protect natural habitats and restore
some areas as part of this proposed sanitary sewer repair.
Staff Kesponse - All necessary permits will be obtained before this repair performed. Every effort
will be made to minimize disruption to sensitive areas and the project will include restoration of
disturbed areas.
18. Hall Boulevard/Wall Street Intersection - Phase 2
Public Comment No. 1 - A Tigard citizen suggested, on a comment card submitted at the
December 7, 2005 CIP Open House meeting, that the City defer construction of this proposed
project until the Wall Street crossing at Fanno Creek is approved.
Staff Response No. 1 - This project provides a common access for the Tigard Public Library and
the Fanno Pointe Condominiums as required by the Oregon Department of Transportation
(ODOT). The access will be approximately 370 feet long with curbs and sidewalks on both sides
of the access. The construction is scheduled for summer 2006. Extension of Wall Street beyond
the 370 foot segment to cross over Fanno Creek is not proposed at this time.
Public Comment No. 2 - Upon receiving the list of proposed FY 2006-07 CIP projects at the first
public meeting on December 7, 2005, a Tigard citizen representing a Tigard environmental
advocacy organization reemphasized his opposition, via email, to the proposed project. The
citizen claimed that construction of this project will destroy wetlands and open space to the
south of the library, which were to be protected according to the bond measure for the library.
He suggested that the project be dropped from the list of proposed projects.
Staff Response No. 2 - The Hall Boulevard/Wall Street Intersection project also includes re-
alignment of Pinebrook Creek to accommodate developed flows from surrounding sites. All
disturbed areas will be seeded and planted upon completion of the construction. An Alternative
analysis was prepared for the Wetland permit application in order to minimize impacts to
existing wetlands. The proposed impacts have been approved by the Oregon Department of
State Lands and the US Army Corps of Engineers. A Comp Plan Amendment permit has been
applied and the public heating is scheduled for early-May 2006 prior to the construction.
19. Pine Street - 66`h to 69`h Avenue
Public Comment - A Tigard citizen suggested, on a comment card submitted at the December 7,
2005 CIP Open House meeting, that the City defer construction of this proposed project for an
unspecified number of years. The citizen did not provide a reason for this deferment.
Staff Response - The scope of work associated with Pine Street is necessary to improve the
existing storm drainage and pavement. The City has deferred this work for several years due to
lack of funding and feels that the improvements should not be put off any longer. This project is
scheduled for construction in the summer or fall of 2006.
20.72 d Avenue - Spruce to Locust Street
Public Comment - A Tigard citizen suggested, on a comment card submitted at the December 7,
2005 CIP Open House meeting, that the City add sidewalk improvements to the east side of 72nd
Avenue from Spruce to Locust Street.
Executive Summary - FY 2006-07 CIP
March 10, 2006
Page 11 of 16
Staff Response - The Engineering Department staff performed a brief discussion concerning the
scope of work involved with providing a new sidewalk as was suggested by the Tigard citizen.
Staff believes that an expensive half-street improvement would be necessary to construct the
sidewalk. The improvements would include backfilling the existing open ditch, installing a storm
drain pipe with manholes and catch basins, and paving the backflled area before installing curb
and sidewalk. As was previously mentioned, the CIP budget for FY 2006-07 contains only
$75,000.00 to be used for various small Sidewalk Improvement projects throughout the City
limits. This project would require additional money from the limited Gas Tax Fund. The
Engineering Department will keep this potential project candidate under consideration in the
near future.
21. 114`' Avenue - Speed Cushion Installation
Public Comment - During the December 7, 2005 CIP Open House meeting, a Tigard citizen
discussed speeding concerns on 114'h Avenue and suggested the City's Speed Cushion
Installation Program be utilized. They also submitted a comment card and requested a traffic
survey be performed on the street from Bull Mountain Road to Gaarde Street.
Staff Response - The Engineering Department staff performed the traffic survey on 114'' Avenue
for possible installation of speed cushions on the street. The installation is warranted and
scheduled for construction in the spring of 2006.
22. Storm Drainage Design (Tigard) - Hall Blvd Sidewalk Installation
Public Comment - With respect to all the recent rains, a Tigard resident, via email, asked the
Engineering Department to specify the design basis for Tigard stoma sewers. In particular, the
resident asked if the proposed storm drainage improvements for the Hall Boulevard Sidewalk
Improvements (Spruce Street to 850 ft south) are adequate. The resident specifically asked if the
City uses a 25-year, 100-year, or other precipitation event.
Staff Response - The City's storm drainage design is guided by the CWS and Washington County
Road Improvement Design Standards. In general, storm drainage in streets is designed for 25-
year storms. The Hall Blvd Sidewalk project was designed for a 25-year event although ODOT
indicates a 10-year storm design is sufficient.
23. Street Lighting and Storm Drainage - Various Locations within the City
Public Comment - A Tigard citizen submitted a comment card distributed through the Times
expressing his request for more illuminated street light in the "dark zones" of some of Tigard
busier streets. These include McDonald Street, just west of Hall Boulevard and 121" Avenue,
just south of Walnut Street. In addition, the citizen also expressed his desire for better drainage
after heavy rain storms in a couple areas in Tigard. These areas include Tiedeman Street by the
railroad tracks and the intersection of 119d'Place and Gaarde Street.
Staff Response - The Engineering Department staff will investigate the feasibility of allocating the
Street Lighting Improvement fund toward the improvements in the areas mentioned on
McDonald Street and 121" Avenue. If the improvements are not warranted or if the cost is not
feasible, staff will monitor the locations for future improvements. Drainage issues on Tiedeman
Street at the 119`' Place/Gaarde Street intersection will be investigated for improvements, if
needed. The improvements would be funded through the Storm Sewer Fund.
Executive Summary - FY 2006-07 CIP
March 10, 2006
Page 12 of 16
24. Storm Drainage - Tigard Goodwill Store
Public Comment - A Tigard citizen submitted a Tigard Times comment card describing his
observation of a "dirty, always-full, or open" storm drain inlet in front the Tigard Goodwill
store, just to the left of the main entrance door. He specified that the inlet is in the parking lot,
but not far from the front door where people get out of their vehicles to "load furniture."
Staff Response - This storm drain inlet is on a private property. The City is only responsible for
maintenance of facilities within the public right-of-way.
25. Highway 99W - Elevated Express Lanes
Public Comment - A Tigard citizen submitted a Tigard Times comment card suggesting a proposal
for alleviating traffic congestion on Highway 99W approaching downtown Tigard. The citizen
proposed that Tigard construct "low profile, attractive, elevated express lanes directly over the
existing lanes of 99W." The citizen suggested the express lanes begin at the intersection of
Johnson Street with the eastbound ramp rising over the George Morlan Plumbing parking lot. In
addition, there could be one expressway exit at Highway 217 and another exit at 72°a Street. The
expressway would end at I-5. The citizen felt that separating the amount of motorists using
Highway 99W to reach Highway 217 and I-5 from local traffic could improve trip time for both
users. With respect to merchant concerns regarding missed business revenue from the
expressway, the citizen felt that the separation would actually increase local business revenue
because of the improved local access.
Staff Response - Elevated expressways are extremely expensive and most likely would not be
justifiable as a solution to traffic circulation problems on and adjacent to Highway 99W. In
response to the Council goal to "Improve 99W", the City applied for and received a Federal
grant to prepare a Highway 99W Corridor Improvement and Management Plan. The plan will
identify projects for improvements to Highway 99W and potential land use changes to alleviate
congestion and improve traffic circulation. The plan will recommend both transportation
system improvements and potential land use changes that address the excess traffic demand on
the highway and promote transportation-efficient development patterns that support compact,
mixed-use and pedestrian friendly developments. Analysis of potential transportation system
improvements will include evaluation of the following: street widening, access management,
intersection improvements, parallel roadway connections, potential backage roads, and other
off-highway improvements. A major focus will be on off-highway improvements that would
draw local traffic from the highway and thus alleviate congestion along that corridor.
The products expected from the study are a plan for management of the corridor, identification
of land use change opportunities, and a package of projects that can be implemented over a
period of years as funding sources are identified and designated for these projects. The actual
work to develop the plan is expected to begin in April 2006 and should be completed within 8
to 10 months.
26. Downtown Comprehensive Streetscape Design
Public Comment- Upon receiving the list of proposed FY 2006-07 CIP projects at the first public
meeting on December 7, 2005, a Tigard citizen representing a Tigard environmental advocacy
organization expressed his concern, via email, that CIP funds were being spent on Downtown
projects that could have been postponed and funded with future Urban Renewal Funds.
Executive Summary - FY 2006-07 CIP
March 10, 2006
Page 13 of 16
Staff Re.ponse - Downtown Streetscape Design is one of the key projects identified by the City
Council and the Citizen Advisory Group as part of the Tigard Downtown Improvement Plan
(IDIP) for downtown. This project has already been funded and is under contract. It was
funded from the Gas Tax Fund and is not anticipated for funding with Urban Renewal funds.
Funds are needed now to provide a conceptual design for downtown streets including Burnham
Street, which has been a priority, and presents an immediate need. Completion of the
Conceptual design is a necessary step prior to beginning the final engineering design. Burnham
Street is scheduled for final design next fiscal year, FY 2006-07. There is no guarantee that Tax
Increment Financing will be approved for use in the Downtown, and Burnham Street. is a
project that has been a priority, and would have been funded with or without the use of Urban
Renewal Funds. Given the passage of the May Ballot Measure for Urban Renewal, it will take
several years before significant Tax Increment can be accumulated to fund any projects. Given
the cash projections for Downtown Urban Renewal, and an affirmative vote for Tax Increment
Financing, it would have taken until 2009 to have enough money to fund this Streetscape Design
Project with Urban Renewal Funds, resulting in final design for Burnham Street delayed until
2010. This would have conflicted with our current CIP priorities for Burnham Street and overall
priorities the City Council has set for the Downtown.
In summary, the City uses its usual funding sources for CIP projects to fund Downtown
projects that it had planned to fiend as part of its normal Capital Improvement Program. Other
projects more specific to the Downtown will be scheduled for Urban Renewal Funds when and
if that becomes an available funding source.
27. Downtown Streetscape Improvements
Public Comment- Upon receiving the list of proposed FY 2006-07 CIP projects at the first public
meeting on December 7, 2005, a Tigard citizen representing a Tigard environmental advocacy
organization expressed his concern, via email, that CIP funds were being spent on Downtown
projects that could have been postponed and funded with future Urban Renewal Funds.
Staff Response - City has identified $100,000 of the $150,000 allocated in FY 2005-06 to be
earmarked for use to partly fund the cost of a Pedestrian Shelter as part of the Commuter Rail
Station. The Urban Renewal Plan as written and adopted does not allow funds to be expended
for Commuter Rail Improvements. The remaining $50,000 will become available for general CIP
projects in the upcoming Fiscal Year 2006-07.
28. Hall Boulevard Crosswalk
Public Comment- Upon receiving the list of proposed FY 2006-07 CIP projects at the first public
meeting on December 7, 2005, a Tigard citizen representing a Tigard environmental advocacy
organization expressed the fact, via email, that his comments on this section of the Fanno Trail
have been repeatedly submitted over the past four years. The citizen recommended that the trail
continues south along the west side of Hall Boulevard and then crosses at Wall Street. The
citizen believed this is safer and more environmentally conscious than the current proposed
location to the north of the bridge near City Hall.
Staff Re.ponse - The City has proposed a Fanno Creek Trail from east of Hall Boulevard, directly
across the existing trail, to Fanno Creek to join up with the new trail segment behind the library.
The proposed trail also includes a wooden pedestrian bridge across the creek. The
recommended alignment by the citizen, which utilizes the existing sidewalk sections over the
existing bridge on Hall Boulevard, is determined to be unsafe and inaccessible to wheelchairs.
Executive Summary - FY 2006-07 CIP
March 10, 2006
Page 14 of 16
The City is proposing to install a marked crosswalk and flashing beacon across Hall Boulevard
to provide connectivity between the existing and proposed paths.
29. Walnut Street Improvements
Public Comment- Upon receiving the list of proposed FY 2006-07 CIP projects at the first public
meeting on December 7, 2005, a Tigard citizen representing a Tigard environmental advocacy
organization requested, via email, that funds need be added for replanting an area where "skunk
cabbage" previously existed. The citizen explained that the area had been filled with rip rap
without any environmental mitigation by the City after the culvert was replaced.
Staff Response - The current Washington County MSTIP Walnut Street project includes funding
and environmental mitigation planting plans for the site mentioned by the citizen. The
mitigation will be completed as part of the Walnut Street Improvement project currently
managed by Washington County.
30. Library Parking Lot Expansion
Public Comment- Upon receiving the list of proposed FY 2006-07 CIP projects at the first public
meeting on December 7, 2005, a Tigard citizen representing a Tigard environmental advocacy
organization expressed, via email, his opposition to the destruction of any open spaces or
wetlands south of the library.
Staff Rerponse - The proposed library parking lot expansion project will not encroach onto any
wetlands. Further, the open space that will be occupied by the expansion was part of the original
library construction site.
31. Niche Analysis
Public Comment - A Tigard citizen representing a Tigard environmental advocacy organization
expressed his opinion that $50,000.00 seems like an excessive amount of money for consultants
to be paid to analyze the Niche. The citizen recommended $5,000.00 be spent for this purpose.
The citizen also suggested that the citizens be asked if the Niche should be remodeled or simply
removed from its City Hall site at no cost to the City.
Staff Response - This project has been expanded to include a Citywide facilities analysis.
32. BPA Trail Feasibility Study
Public Comment - A Tigard citizen representing a Tigard environmental advocacy organization
expressed his support for this project but thought that the $120,000.00 is a bit excessive for the
study. The citizen suggested that $10,000.00 - $25,000.00 is more appropriate and would allow
for the remaining funds to be used for open space acquisition. He also asked how much
consultants charge per hour.
Staff Reponse -This is a proposed pedestrian trail that would extend along the Bonneville Power
Administration (BPA) power line easement from SW Beef Bend Road to SW Barrows Road. A
consultant will be contracted to develop a preliminary trail alignment study. Since the December
7, 2005 meeting, the City has adjusted the funding for the BPA Trail Feasibility Study to
$15,000.00 for the design of a preliminary alignment. The hourly rate charged by consultants
depends upon the scope of services, the duration required for completion of a project and the
technical experience of consultants.
33. Fanno Creek Trail (Hall Boulevard to Fanno Creek)
Executive Summary - FY 2006-07 CIP
March 10, 2006
Page 15 of 16
Public Comment - A Tigard citizen representing a Tigard environmental advocacy organization
expresses his support, via email, for this project but thinks that the $120,000.00 is a bit excessive
for the project. He suggested that $10,000.00 - $25,000.00 is more appropriate and would allow
for the remaining funds to be used for open space acquisition. The citizen also asked how much
consultants charge per hour.
Staff Response - This project connects the Fanno Creek Trail behind City Hall across Hall Blvd to
the future Fanno Creek bridge crossing and connecting to the trail segment behind the library
installed last year. The budget proposed for this project is $30,000.00, not $120,000.00 as
indicated. Please refer to staff response to comment No. 32 for the hourly rate.
34. Tree Replacement/Planting
Public Comment - A Tigard citizen representing a Tigard environmental advocacy organization
expressed his support, via email, for this project but thought that the $120,000.00 is a bit
excessive for the project. He suggested that $10,000.00 - $25,000.00 is more appropriate and
would allow for the remaining funds to be used for open space acquisition. The citizen also
asked what the consultants charge per hour?
Staff Response - The Tree Mitigation Fund is used primarily for street tree plantings. If site
preparation is required for a restoration project, the fund will also be utilized.
The proposed budget of $50,000 is based on various tree mitigation projects that have been
planned for FY 2006-07. This amount is needed to complete these projects. Also please refer to
staff response to comment No. 32 for the hourly rate.
35. Washington Square Regional Center Trail
Public Comment- Upon receiving the list of proposed FY 2006-07 CIP projects at the first public
meeting on December 7, 2005, a Tigard citizen representing a Tigard environmental advocacy
organization expressed his opposition, via email, to this project due to the lack of land
acquisition along Ash Creek. The citizen believed Ash Creek is getting hammered by
developments and wanted habitat protection for fish and wildlife. The citizen also suggested an
offset trail distance of 200 feet from the creek, so as not to disturb sensitive areas and wildlife.
Staff Response - A Biological Assessment and Wetland Impact Study will be conducted prior to
designing the trail's alignment. The alignment will be situated at a location to minimize riparian
impact and wildlife disturbances. The final design will comply with all permit and environmental
standards.
iAen0\2006-2007 y dplcip process for fy08-071esecut1ve summary fy 2006-07.doc
Executive Summary - FY 2006-07 CIP
March 10, 2006
Page 16 of 16
Ii
FY 2006-07 Presentation Overview
Capital Improvement
Program Formulation Process
• Program Areas
• Priorities for FY 2006-07
March 21, 2006 • Proposed Projects
- Tigard Downtown Projects
- Citywide Projects
• What's Next?
tr,.
2
Formulation Process { Program Areas
• Citywide meeting (December 7, 2005) Street System Program
• 2nd Citywide meeting (January 25, 2006) i - Traffic Studies
• Planning Commission (March 6, 2006) - Traffic Safety-Related Projects
• City Council (March 21, 2006) j - Pavement Major Maintenance
• Finalize Project List (March - May 2006) - Traffic Calming Program
• Presentations in May and June 2006 - Major Street Capital Improvements
- Bridge Replacements
3., 4
T iProgram Areas Program Areas
• Sanitary Sewer System Program Parks System Program
- Sanitary Sewer Major Maintenance - Citywide Parks
- Trail Systems
- Sanitary Sewer Capital Improvements
- Sewer Extension Program - Open space and greenspaces
Water System
Storm Drainage System Program Program
•
- Storm Sewer Major Maintenance City Facilities System Program
- Storm Drainage Capital Improvements
g 6
G
1
. r '
a
i
Priorities for FY 2006-07 Priorities for FY 2006-07
• Continue implementation of projects to I • Construct the Wall Street approach to Hall
improve the Tigard downtown Boulevard to provide joint access for the
• Complete the Highway 99W Corridor library and Fanno Pointe
Improvement and Management Plan Construct improvements to Hall Blvd
• Identify and initiate projects to improve Expand the library parking lot
traffic circulation across and on
Highway 99W Install additional traffic calming measures
• Continue to implement the Street Continue with the Citywide Sewer
y Maintenance Fee funded projects $ j Extension Program projects
I
Priorities for FY 2006-07 Priorities for FY 2006-07
• Perform storm and sanitary system repairs • Implement water system improvements
• Implement planned Parks projects aimed at improved delivery and adequate
water supply
• Acquire park property as open space or for Review City facility requirements
park development Consolidate Public Works to the extent
• Improve at least one existing park feasible
• Design and construct trail projects • Pursue implementation of alternative
• Design and construct a skate park funding sources for major street
10 improvements
~
Tigard Downtown Projects Tigard Downtown Projects
• Burnham Street Improvements Completion of Streetscape Design Project
• Commuter Rail Station Enhancement - Downtown park land acquisition
• Main Street Safety Improvements Skate Park design and construction
• Ash Avenue (Design, rights-of-way acquisition, Hall Blvd/99W Intersection Project
and construction) enhancements
• Commercial Street Improvements (Lincoln to Senior Center Remodel
Main) Consolidation of Public Works Staff at the
• Commercial Street/Main Street Intersection Water Building
Treatment
11 12
2
i
Burnham Street Burnham Street
• Catalyst project in support of the Downtown
revitalization effort'
• Streetscape design project will determine -
what the street will look like
• Full improvements in accordance with the
Streetscape concept layout
• Project begins with design and rights-of-way
acquisition
13 14
Burnham Street Commuter Rail Station
j Enhancements
~ x y~~,~- ~ ~ > , ,mss
15 16
I
J
ter Rail Platform Location r Commercial Street
-Commu (Lincoln Avenue to Main Street)
I I . Existing narrow road with pedestrian traffic
• Project will widen the street and provide a
sidewalk on one side
CDBG Funding/Gas Tax Fund
F Right-of-way needed from either railroad or
TriMet
Gateway treatment part of streetscape design
• project
is
171
3
i
Commercial Street
(Lincoln Avenue to Main Street) Main Street Safety Improvements
widening on Specific improvements currently being
r north side to identified
` provide a
pedestrian Staff will be working with the City Center
+ f walkway to
t Advisory Commission and Streetsca P
e
Main Street
Working Group to identify concerns
T~ NIntersection Projects identified will be designed and
treatment
a~ nduded as a implemented next fiscal year
portal into the
downtown
19 20 J
r
Ash Avenue Improvements Skate Park
I t
Skate Park
Secondary access
to the Commuter
4 Location
xy Rail parking lot
along Ash Avenue
u i vx
corridor Tigard City Hall 8
Permit Center
21 22 i ,
Senior Center Remodel Public Works Consolidation
' Consolidation
Remodel and of Public
Seismic Works staff in
Upgrade of the Water
i.r Senior Center.... _ Building
Frees up City
property for
future
downtown
development
23 24
4
Hall Boulevard/Highway 99W Hall Boulevard/Highway 99W
• MSTIP 3 Project,
• County has initiated the project ~N~, `
• Design will begin in March 2006'
• Construction begins early 2007
• City is seeking to incorporate ` • :.t
enhancements suitable for a major z yr
gateway into the City
25 r 26
i
Highway 99W Corridor Improvements
Study of the Highway 99W corridor to
Street Projects - Evaluate various alternatives for improvement
- Look for potential parallel routes or connections
- Review both land use and physical improvements
to improve circulation and reduce congestion
- Funded through a TGM grant
- Result will be a package of projects and land use
strategies that can be implemented to improve
conditions on Highway 99W
2$
i
Hall Boulevard Hall Boulevard Improvements
Widening of Widening of
' Hall on east
~-4 Hall at
McDonald to k side north of
' add a right- Fanno
- turn lane *A Creek
r, y
29 30
5
~
Hall Boulevard Improvements Dartmouth/72nd Avenue
Intersection
I
• All-way stop needs to be signalized
Widening of ~
Widening
on east i • Project widens the approaches and
Hall
- ,K side north of installs a traffic signal system
Fanno Uses funds collected from developers to
I ` Creek
partially fund the project
` Formation of a reimbursement district is
being considered to fund the balance
31 32
i
I 1
Dartmouth/72nd Avenue
Intersection 108th Avenue/Durham Road
G?; Development occurring along 108th
• Left-turns onto Durham are difficult during
peak travel hours
f' Traffic analysis shows signal is justified at
that location
• Project will design and construct a traffic
signal at the intersection
33 34 j
108th Avenue/Durham Road 108th Avenue/Durham Road
v
7 7
35 36
6
r
Wall Street Wall Street Extension
• Construction of 370 feet of Wall proposed
,I
- Would provide joint access for library and Fanno I. O
Pointe Condominiums
li
- Environmental permits have been obtained !
- Comprehensive Plan Amendment pending to - Wall Street
remove one pond and realign Pinebrook Creek
• Construction projected for summer and fall
2006 I .
37 38
J
Wall Street ( Tigard St/Tiedeman Ave
Intersection
I! A Study of
f i" 1. ! a Intersection
Improvoments
/h
needed
39 - _l 40
Highway 99W@ Bull Mountain Rd Pavement Overlays
Right-turn lane
improvement 68th Avenue Parkway (99W to Atlanta
Street)
• 72nd Avenue (Baylor Street to 700 ft South)
79th Avenue (Churchill Way to Ashford
Street
j 100th Avenue (Sattler Road to Murdock)
Pine Street Reconstruction (east of 69th)
41 42
7
Pavement Overlays 68th Avenue Parkway
i
• Upper Boones Ferry. Road (72nd Avenue
to Interstate 5
• 136th Avenue (south of Walnut Lane)`
• Garden Park Place Loop (at 1loth
Avenue) f
• Durham Road (Summerfield Drive to
Serena Court)
143 44
Pine Street 79th Avenue
Reconstruction
r - -;34w - of the existing
street plus
far' paved
shoulders and
appropriate
drainage
h Y '
,•Rr-~ ~N 11 "AY';
7 s„e r:
45 t1 _ 46 1
Proposed Tigard Triangle LID
i
• Specht Properties has
requested formation of Sanitary Sewer Projects
an LID
• Council has approved
preparation of a
Preliminary Engineer's
Report
• Formation will depend
on the findings of the
47 report 48
8
r
Citywide Sanitary Sewer r
Extension Program FY 2006-07 Sanitary Sewer Extensions
• Proposed projects include: Sewer Project Lots Status
- 93rd Avenue (at Mountainview Lane) 10011 Avenue 21 Planned
- Ann Street (between 121St and 116th) I Ann Street 6 Planned
- 87th Avenue (north of McDonald Street) 971' Ave/1001^ Ave 21 Planned
- 97th Avenue (between Murdock and Hillview Street 6 Planned
Pembrook Street) Fairhaven Street 19 Planned
- Hillview Street (at 102nd Avenue) 871h Avenue 6 Planned
- Fairhaven Street (east of 115th Avenue) 93rd Avenue 33 Planned
Subtotal 112
491 50
Sewer Projects
• 79th Avenue Sanitary Sewer Outfall
• Benchview Terrace Sanitary Sewer Storm Drainage Projects
Access Road
• Sanitary Sewer Repairs
- Commercial Street
- Red Rock Creek near 691h Avenue
• Sanitary sewer plan to reduce infiltration
and inflow
51 52
Ia Storm Drainage Projects Durham Road @ 108th Avenue
• 79th Avenue Storm Drainage Outfall Retaining wan "
• Culvert Improvements repair needed
- Derry Dell Creek at Fanno Creek 1 7 ti
- Derry Dell Creek at Walnut Street }
- Red Rock Creek at Dartmouth/72"d Ave , ' t ` sY rj s
• Highland Drive Storm Drainage Pipe
Replacement
• Hiteon Creek Riparian Enhancement
53 ! 54 "
9
Culvert Replacement Highland Drive
72"d and Dartmouth
Cls` Combined
Culvert r M w
replacement ; ~t-' storm drainage
rep improvement
with
and pavement
Intersection overlay
Improvements slaw
71
55 56
City Facility Projects
• Consolidation of Public Works Facilities
- Public Works will move into the water building
City Facility Projects Senior Center Remodel and Seismic Upgrade
• PD Underground storage tank upgrade
• Police & Records storage remodel
- Remodel of existing Public Works operations building
for consolidation of records and evidence in one
location
• Citywide Facility Analysis
• Library Parking Lot Expansion
57 58
PD Underground Storage Tank Police Records Storage
Decommissioning t•
of the existing Analysis for
underground fuel b
#5r~ rt
tank for the proposed
emergency backup - remodel of
generator AG Public Works
Building for
f r r~ - Police
Installation of a new * _ ,Y
above-ground tank Records
Storage
. 60
10
i
{
Library Parking Lot Expansion
HIIParks Projects
i
V7 'i
U *4I
&fi _ a 62
r
Parks Projects Parks Projects
• Northview Park (Shelter and Path)
• Fanno Creek Trail Park
- From Hall Blvd to Shelter Shelter
- Hall Boulevard Crosswalk at trail intersection installation
• Tualatin River Pedestrian Bridge , and path
• Washington Square Regional Center Trail construction
• Skate Park (from donations primarily). n
• Tualatin River Trail (Cook Park to bridge) r,•r~r
• Park land acquisition Ty - -
63 64 j
i"
Parks Projects Parks Projects
Fenno Creek Trail north of
Fanno Creek on Library Fanno Creek, site wdh crosswalk on Hall
Boulevard'
I Park and Trail f
'Segment ~.P'. r . , .
north of
s
Fanno
Creek - l4a,.~.
66 '
11
Parks Projects Parks Projects
x~ t rasa " Washington
> r::,~ F r Square.
n r..cnr vl Regional
5, Center Trail
Project
Cook Park Trail from
67 68 Garden to Bridge
Parks Projects
Skate Park
Location Water Projects
_ Tigard City Hall &
r : - Permit Center
Ise
69 70
Water Projects Water Projects
• Secure two 550-foot reservoir sites Lake Oswego Feasibility Study
• 550-foot zone - 10 MG transfer pump Menlor Reservoir Recirculation
station upgrade Replace Well House #2 (Gaarde Site)
• Aquifer storage & recovery expansion • Telemetry Upgrade
studies Existing system is out of date
• Water line replacements in conjunction New technology will allow for continuous
with street projects monitoring of water status
• Miscellaneous other water projects
71 72
12
ASR Production Well What's Next?
• Incorporation of revisions, if any
Submittal through the City's Budget
Process
Presentations to:
Budget Committee (May 2006)
- - Planning Commission (May 15, 2006)
s - City Council approval (June 13, 2006)
Program effective July 1, 2006
73 74
13
AGENDA ITEM #
FOR AGENDA OF March 21, 2006
CITY OF TIGARD, OREGON
COUNCIL AGENDA ITEM SUMMARY
ISSUE/AGENDA TITLE Downtown CIP Priorities / Budget
PREPARED BY: Phil Nachbar DEPT HEAD OK CITY MGR OK
ISSUE BEFORE THE COUNCIL
Staff has devised a Downtown Implementation Strategy and initial set of priorities for Capital Improvements in the
Downtown for FY 06-07. Staff is presenting its CIP priorities for the Downtown which are a part of the larger
strategy. Pending Council agreement, staff will use the CIP priorities for identifying and allocating funds for the
upcoming FY 06-07.
STAFF RECOMMENDATION
That Council review and concur with or modify the proposed CIP Priorities and Budget for the Downtown.
INFORMATION SUMMARY p
A primary City Council goal continues to be the implementation of the Downtown Plan. Council approved the
Tigard Downtown Improvement Plan on September 27, 2005, and adopted the Urban Renewal Plan on December
13, 2005. Staff has identified the implementation of the Downtown Plan as a key work element and begun to
formulate a more specific strategy to address the anticipated use of Tax Increment Financing and the prioritization
of Capital Improvements. Having a strategy is critical to the success of these to two aspects of implementation.
OTHER ALTERNATIVES CONSIDERED
None considered at this time.
COUNCIL GOALS AND TIGARD BEYOND TOMORROW VISION STATEMENT
Community Character & Quality of Life (Direction Statement): A clear direction will be established for a
pedestrian-friendly downtown and will be implemented.
Central Business District (CBD): (2) The downtown will provide a gathering place for the community and honor
the sense of a small town village.
ATTACHMENT LIST
Attachment 1: Memo to Council dated 3/8/06 - Capital Improvement Priorities and Strategy for the
Downtown
Attachment 2: Downtown CIP Project Ranking
Attachment 3: Spreadsheet - Tigard Downtown CIP Projects
FISCAL NOTES
No fiscal impact at this time.
MEMORANDUM
TIGARD
TO: City Council
FROM: Phil Nachbar, Senior Planner
RE: Capital Improvement Priorities and Strategy for the Downtown
DATE: March 8, 2006
Capital Improvement Priorities and Strategy for the Downtown-Overview
In recognition of the priority City Council has placed on the Downtown, For FY 06-07, Staff has
made a more deliberate effort to evaluate, and identify key Downtown CIP projects that relate to an
overall Strategy for the Downtown. The approach this year was to identify Strategic goals, and then
rank projects according to these goals.
Staff has developed a larger Implementation Strategy of the Downtown which will be presented to
City Council at a later time. Since the more immediate concern is to identify and allocate funding
for CIP projects for FY 06-07, this presentation identifies the projects, their suggested budget
amounts and why they were included in this year's City Budget. There are three key concepts that
make up our Strategy for the Downtown;
Key Goals in the Downtown Implementation Strategy for Ranking CIP Projects
1) Stimulate new development to generate "tax increment" revenues
2) Assist Main St. as it transitions to a more dynamic commercial district
3) Capitalize on Fanno Creek Park as a key public gathering place, and amenity for new
development.
All three aspects to the Downtown-creating new development, assisting a Main Street Transition,
and restoring / expanding Open Space-are all important for different reasons. Creating new
development opportunities is critical to establishing an Urban Renewal Funding base to fund future
public improvements. Assisting Main Street as it evolves towards a thriving commercial district will
happen in phases, and providing assistance as this occurs insures its success. And finally, restoring
and expanding the Fanno Creek Trail System is a key to creating public space, an amenity for new
housing, and the "Green / Sustainable" thematic environment for the Downtown. Keeping all
three aspects in mine when thinking about the Capital Improvement Program, and how to prioritize
projects and allocate funds is the challenge.
Ranking Capital Improvement Projects
All of the potential Capital Improvement Program (CIP) projects were ranked using a Goal
Achievement Matrix using nine (9) criteria of equal weight. The criteria were developed based on
multiple objectives and were reviewed by Staff and endorsed by the City Center Advisory
Committee (CCAC). They include 1) visual impact 2) ability to implement the TDIP projects in
short-term 3) supports potential new development 4) supports Main St. Transition 5) executes
"Open Space" objectives 6) optimizes available funding 7) meets Developer objectives 8) feasibility
of implementation and 9) enhances Commuter Rail. Projects for FY 06-07 were ranked from 1 to
21. Only those projects from 1 through 11 were put into the budget for FY 06-07.
After ranking and creating a budget, both were re-evaluated and brought before the City Center
Advisory Council (CCAC) for review and input. For FY 06-07, both the prioritization and budget
levels for capital improvement projects were endorsed by the CCAC, with some minor
modifications to the order of priordes.
Nine of the top eleven (11) CIP projects for the Downtown were submitted for budget approval
for FY 06-07. Main St. "Brand Tigard Visual Enhancements (#7) and Main St. Facade
Improvement Program (#8) will not use traditional CIP funding sources but are being researched
for possible inclusion in the budget.
Downtown CIP Project Ranking
1. Commuter Rail Enhancements
2. Burnham St. (Main St. to Hall Blvd.)
3. Fanno Creek Public Area Land Acquisition
4. Fanno Creek Master Plan
5. Ash Ave (Burnham St to Rail)
6. Gateway-Hall Blvd. @ 99W
7. Fanno Creek Trail Expansion (Main St. to Grant St.)
8. Commercial St. @ Main St Intersection
9. Commercial St. (Main St. to Lincoln St.)
10. Main St. Safety Improvements
11. Main St. "Brand Tigard" / Visual Enhancements (not CIP)
12. Main St. Facade Improvement Program (not CIP)
Brief Project Descriptions
1) Commuter Rail: Upgrade to Commuter Rail Shelter
2) Burnham St (Hall Blvd to Main St: Final engineering and ROW only
3) Fanno Creek Public Area Land Acquisition: Acquisition of floodplain properties to expand the park
area.
4) Fanno Creek Master Plan: A Master Plan for Fanno Creek Park (Hall Blvd, to Main St), including
the public area outdoor space / plaza / amphitheatre, and connections to Downtown, and west of
99W.
5) Ash Avenue (Burnham St. to Rail This includes ROW for a secondary access from the Commuter
Rail Park & Ride to Burnham St. It is scheduled to be constructed in time for the opening of the
Commuter Rail in the Fall 2008.
6) Gateway-Hall Blvd. 299W: The City will provide design suggestions to Washington County, the
organization managing redesign of the intersection. Potential design modifications will be making
the intersection more pedestrian friendly, incorporating Downtown's a "Green theme", and
Gateway treatments.
7) Fanno Creek Trail Expansion (Main St to Grant St: Expansion of the Trail to Grant St including
acquisition of property.
8) Commercial St. Q Main St Intersection: Intersection improvements at the intersection to create a
more attraction intersection as it connects with Main St.
9) Commercial St. (Main St. to Lincoln St.): Street and sidewalks improvement on Commercial St. west
of Main St. to Lincoln St.
10) Main St. Safety Improvements: This project was recommended by the CCAC. Staff is identifying
specific improvements which will address safety concerns.
11) Main St "Brand Tigard"/ Visual Enhancement: This is not yet funded but Staff is working with the
CCAC to develop ideas and funding sources for temporary improvements to Main St. to support its
transition. Ideas have included street trees, a lighted mural under the two 99W overpasses, lighting.
12) Facade Improvement Program: Not yet funded, but Staff is working with the CCAC to consider a
program and funding sources to provide a matching grant program for improving storefronts on
Main St.
Downtown CIP Project Ranking March 7,'06
fi ofi $40
DO,
Project J~~ C,>~° Score
1 Commuter Rail Enhancements 4 5 4 4 3 4 1 3 4 32
2 Burnham St. Main St. to Hall Blvd. 4 5 5 4 3 2 4 3 1 31
3 Fanno Creek Public Area Land Acquisition 3 4 4 1 5 4 4 4 2 31
4 Fanno Creek Master Plan 3 4 4 2 5 4 4 4 1 31
5 Ash Ave (Burnham St to Rail) 2 4 3 4 1 3 3 4 5 29
6 Gateway-Hall Blvd. 99W 4 4 4 2 1 3 4 5 2 29
7 Fanno Creek Trail Expansion (Main St. to Grant St.) 4 4 2 2 5 4 2 4 1 28
8 Commercial St. Main St Intersection 4 4 2 4 1 5 1 4 3 28
9 Commercial St. (Main St. to Lincoln St.) 4 4 2 3 1 5 3 5 1 28
10 Main St. Safety Improvements 3 2 3 4 2 3 3 3 4 27
11 Main St. "Brand Tigard" / Visual Enhancement 4 4 3 5 1 1 4 3 2 27
12 Main St. Fagade Improvement Program (not CIP) 4 4 3 5 1 1 3 4 2 27
13 Fanno Creek / Main St. Gateway 4 1 2 4 5 1 3 1 2 23
14 Gateways-Main @ 99W North 4 4 2 3 1 1 1 3 2 21
15 Gateway-Main 99 South 4 4 2 3 1 1 1 3 2 21
16 Commercial St. (Hall Blvd. to Main St.) 4 3 3 1 1 1 1 3 3 20
17 Main St. Streetsca a Improvements 5 2 2 3 1 1 1 2 2 19
18 Gateway-Burnham St. @ Hall Blvd 4 4 2 1 1 1 1 3 2 19
19 Ash St. North of Rail / Scoffins Feasibility Stud 1 3 1 3 1 1 3 3 1 17
20 . Land Acquisition for Redevelopment 1 1 5 1 1 1 3 1 1 15
21 Ash Avenue Extension (Scoffins St. to Burnham St) 3 1 1 1 1 1 4 1 2 15
22 Greenburg Rd / 99W feasibility (near complete) 1 3 2 2 1 1 1 2 1 14
Tigard Downtown CIP Projects March 10.'06
Total Pro'ect FY 06-07 Bud et Prelimina
Costs Fundin Source
Comprehensive Streetscape Design
Streetsca a Design 175,000 25,000 Gas Tax
Street Improvements
Burnham St.
Engineering 350,000 350,000
ROW 400,000 400,000
Construction 1,650,000 0
Under roundin Utilities 250,000 0
2,650,000 750,000 TIF*/Gas Tax
Commercial St. Main to Lincoln
Engineering 40,000 40,000
ROW 0 0
Construction 360,000 360,000
400,000 400,000 Gas Tax/CDBG/SMF
Ash Ave. Burnham St. to Rail
Engineering 40,000 40,000
ROW 650,000 180,000
Construction 260,000 0
950,000 220,000 Gas Tax
Downtown Improvements
"Brand Tigard"
Storefront Fa de Improvement Program 200,000 0
Main Street Visual Enhancement 25,000 0
Commercial St. Main St Intersection 75,000 75,000 Gas Tax
Commuter Rail Enhancements 85,000 100,000 Facility Fund
Main Street Safe Improvements 75,000 75,000 Gas Tax
460,000 250,000
Gateway / Intersection Treatments
Hall Blvd 99W Intersection Improvements
Construction 75,000 75,000
75,000 75,000 Gas Tax
Fanno Creek Public Area
Land Acquisition
Fanno Creek Park Extension
Stevenson property 2.5 ac 75,000 75,000
Stevens Marine 1.3 ac 25,000 25,000
100,000 100,000 Parks SDC's
Design / Feasibility Studies .
Fanno Creek Master Plan 60,000 60,000 Parks SDC's
Ash St North / Soffins Ave. Feasibility Stud 40,000 40,000 Gas Tax
100,000 100,000
* Traffic Impact Fee
Total Annual 4,910,000 1,920,000,
Capital Improvement Priorities
and Strategy for the Downtown
City Council Work Session
March 21, 2006
M
Downtown Tigard
t C, - m - -
Urban Renewal Area
Q
Building FootPnnt - " - - -
Taxlot Boundary
Three Strategic Goals for
the Downtown
Goal 1: Stimulate New
Development to generate
"tax increment" revenues
• Work with property owners on key sites to
assist in relocation and property assembly
• Construct Capital Improvements in
conjunction with "opportunity sites"
_ to~►n -Tigard
Down rnent
Redevelop -
potential _ F-
P/9i i .
^,`urban Renewal Area 1 '
1...x-3
Cluster Area
- - City property _ = -
BO, ding Footprint
- -
Taxlot BoundarY
C tiigh potential -
Goal 2: Assist Main Street as it
transitions to a more dynamic
commercial district
• Support a "Main Street Transition"
towards a more attractive, pedestrian-
oriented commercial district.
• Change the perception of Downtown by
making temporary "Brand Tigard"
improvements along Main Street.
Main Street Transition
11 1y,-y 1 l ~ .6
'>'._'S 1 /r^J /I.A.~Y yl ''};5S 5~5 Luc:-•a~.~~ sa 1_~`~_ - ~i
oACltlt ~Il:i -5T5
1 - - t y 1 5 155 CIA7'% AV
L +l'en~r~ 1 115ti ,1 3 'a
~3zt
40
1 L1s41 R1:1 ri.4 ?e C'IAL. L 1 `SLAIN STRM. RETAFI 1511
a
a 1
.ate.............. 10 +11+i 1 u.
i ~ r yY
a ~il I
p 1
TRANSIT RCctOML.
HUH
91i;=--.7•='•i=1!.\ p
THE"IILAR r' 1 ~I' ` 11lTAIk.
p
Mal n Street Proyed-Examples
- Commuter Rail "Gateway" at Main Street
- Commercial Street realignment /intersection
treatment
- Create Gateway on Main St. to Fanno Creek Park
- Safety Improvements-sidewalk bulbs, lighting, cross
walk modifications
- Landscape-Street trees, planting to convey "green
theme"
- Building facade improvements-exterior design,
painting, cleaning, awnings
- Lighted murals under 99W Overpass at Tigard and
Commercial Sts.
Goal 3: Capitalize on Fanno Creek Park as a
key public gathering space, and amenity for
new development
• Anew Master Plan for Fanno Creek Park is the
first step to assigning value to the mission of co-
developing Fanno Creek Park and Tigard's
Downtown.
• Prioritize Fanno Creek Park to strengthen the
marketability and value of projects for
developers and create important civic spaces for
the community.
• Pursue redevelopment projects that have a
public space, park or plaza as a part of the
project to develop public support.
Downtown Tigard
Fanno Creek
Open Space
Urban Renewal Area \ / - -
Cluster Area
i
- - City Property
Building Footprint
Taxlot Boundary
Fanno Cr Park
Green Corridor
High Potential ~
Capital Improvement Priorities
/ Budget for Downtown
Downtown CIP Project Ranking March 21, X06
qO
~ roc o;qQ
coo ~ ~y ~ ca ~~m ~m
yam Fm\m a~ 4 Q 4C
4Z 4~1
'y q,
~F oy aO oo q,\~~ mm
° ~ 4°~ oJ' ~m 4cF~~ m~u
Project ~~~~e score
1 Commuter Rail Enhancements 4 5 4 4 3 4 1 3 4 32
2 Burnham St. Main St. to Hall Blvd. 4 5 5 4 3 2 4 3 1 31
3 Fanno Creek Public Area Land Acquisition 3 4 4 1 5 4 4 4 2 31
4 Fanno Creek Master Plan 3 4 4 2 5 4 4 4 1 31
5 Ash Ave Burnham St to Rail 2 4 3 4 1 3 3 4 5 29
6 Gateway-Hall Blvd. 99W 4 4 4 2 1 3 4 5 2 29
7 Fanno Creek Trail Expansion (Main St. to Grant St. 4 4 2 2 5 4 2 4 1 28
8 Commercial St. Main St Intersection 4 4 2 4 1 5 1 4 3 28
9 Commercial St. Main St. to Lincoln St. 4 4 2 3 1 5 3 5 1 28
10 Main St. "Brand Tigard" / Visual Enhancement 4 4 3 5 1 1 4 3 2 27
11 Main St. Fagade Improvement Program (not CIP) 4 4 3 5 1 1 3 4 2 27
12 Fanno Creek / Main St. Gateway 4 1 2 4 5 1 3 1 2 23
13 Gateways-Main 99W North 4 4 2 3 1 1 1 3 2 21
14 Gateway-Main 99 South 4 4 2 3 1 1 1 3 2 21
15 Commercial St. Hall Blvd. to Main St. 4 3 3 1 1 1 1 3 3 20
16 Main St. Streetsca a Improvements 5 2 2 3 1 1 1 2 2 19
17 Gateway-Burnham St. @ Hall Blvd 4 4 2 1 1 1 1 3 2 19
18 Ash St. North of Rail / Scoffins Feasibility Stud 1 3 1 3 1 1 3 3 1 17
19 Land Acquisition for Redevelopment 1 1 5 1 1 1 3 1 1 15
20 Ash Avenue Extension Scoffins St. to Burnham St) 3 1 1 1 1 1 4 1 2 15
21 Greenbur Rd / 99W feasibility near complete 1 3 2 2 1 1 1 2 1 14
FCapital wntown Tigard ,
Improvement
Projects
~o m
3' 5
Q Urban Renewal Area -1
4. -
Cluster Area i
City Property
is
Building Footprint i
Taxlot Boundary
Fanno Cr Park
Green Corridor ,
High Potential _ _ , - - - -
~ i
: Tigard Downtown C{P Projects March 21,'06
Total Pro'ect FY 06-07 Bud et Prelimina
Costs Funding Source
Comprehensive Streetscape Design
Streetscape Design 175,000 25,000 Gas Tax
Street Improvements
Burnham St.
En ineerin 350,000 350,000
ROW 400,000 400,000
Construction 1,650,000 0
Under roundin Utilities 250,000 0
2,650,000 750,000 TIF*lGas Tax
Commercial St. (Main to Lincoln
En ineerin 40,000 40,000
ROW 0 0
Construction 360,000 360,000
400,000 400,000 Gas Tax/CDBG/SMF
Ash Ave. Burnham St. to Rail
Engineering 40,000 40,000
ROW 650,000 180,000
Construction 260,000 0
950,000 220,000 Gas Tax
Downtown Improvements
"Brand Tigard"
Storefront Fagade Improvement Program 200,000 . 0
Main Street Usual Enhancement 25,000 0
Commercial St. Main St Intersection 75,000 75,000 Gas Tax
Commuter Rail Enhancements 85,000 100,000 Facility Fund
Main Street Safety Improvements 75,000 75,000 Gas Tax
460,000 250,000
Gateway/ Intersection Treatments
Hall Blvd 99W Intersection Improvements
Construction 75,000 75,000
75,000 75,000 Gas Tax
Fanno Creek Public Area
Land Acquisition
Fanno Creek Park Extension
Stevenson property 2.5 ac 75,000 75,000
Stevens Marine 1.3 ac 25,000 25,000
100,000 100,000 Parks SDC's
Desi n /Feasibility Studies
Fanno Creek Master Plan 60,000 60,000 Parks SDC's
Ash St North / Soffins Ave. Feasibility Stud 40,000 40,000 Gas Tax
100,000 100,000
" Traffic Impact Fee
Total Annual 4,910 000 1,920,000
AGENDA ITEM # 15-
FOR AGENDA OF March 21, 2006
QTY OF TIGARD, OREGON
COUNQL AGENDA ITEM SUMMARY
ISSUE/AGENDA TITLE Joint Meeting with the Intergovernmental Water Board an to Discuss Participation
in the Expansion and Modification of the Willamette River Water SppplySystem
PREPARED BY: Dennis Koellermeier DEPT HEAD OK QTY MGR OK
ISSUE BEFORE THE COUNCIL
No action required. Council is asked to hear a presentation and participate in a discussion.
STAFF RECOMMENDATION
No recommendation at this time.
INFORMATION SUMMARY
The City of Tigard continues to work on securing a long-term water source by exploring all possible options. To
this end, the City is a member of the Willamette River Water Coalition (WRWq. This coalition, formed in 1997, is
composed of the cities of Tigard, Tualatin, Sherwood and Gladstone, as well as the Tualatin Valley Water District
(TVWD) and the Canby Utility Board. The coalition was formed to preserve access to the Willamette River as a
potential municipal and industrial water source. This is not to say all members of the coalition plan to utilize the
Willamette River as a source of water, but rather they are committed to preserving access to this option.
According to the )XRWC agreement, any member deciding to expand or modify the Willamette River water supply
system is required to provide fellow members with 90-day notice; thus affording other members the opportunity to
participate in the proposed expansion. Tigard has received such notices from the City of Sherwood and the TVWD.
These agencies have indicated their intent to use the Willamette River water source and have informed the WRWC of
their plans to expand the water supply system Tigard is now required to formally notify the WRWC whether or not it
wishes to participate in either of these expansion projects. Tigard's responses to Sherwood and the TVWD are due May
2, 2006, and May 30, 2006; respectively. In April, the Council will be asked to provide direction on this issue.
At this workshop meeting, an engineering consultant, representing both Sherwood and the TVWD, will make a
presentation. Staff will also present a legal analysis of the 1999 charter amendment which prohibits the City from using
the Willamette River as a drinking water source without voter approval.
OTHER ALTERNATIVES CONSIDERED
Not applicable.
VISION TASK FORCE GOAL AND ACTION COMMITTEE STRATEGY
Tigard City Council, Other Important Goals for 2006
■ Secure Long-Range Water Source(s)
Tigard Beyond Tomorrow, Urban & Public Services
• Water & Storm Water Goal # 2: "Equity position in a regional water system by 2007." - Strategy # 1:
"Continue to explore all options open to Tigard where the City can buy into the source and the associated
infrastructure and become a part owner of the source/system."
ATTAC ENIENT LIST
1. Notification to the WRWC from the City of Sherwood
2. Cover Letter and Notification to the WRWC from the TVWD
FISCAL NOTES
Should Tigard decide to participate in the either expansion, a project agreement will be adopted. This agreement will
establish participation, cost shares, operation and maintenance responsibilities, and governance.
Attachment 1
4
NOTIFICATION TO THE WILLAMETTE RIVER WATER COALITION
BY THE CITY OF SHERWOOD, OREGON
A PROPOSAL TO EXPAND AND MODIFY THE
WILLAMETTE RIVER WATER SUPPLY SYSTEM
Distributed to WRWC membership on January 25, 2006
Response by WRWC members due no later than May 2, 2006
The City of Sherwood, Oregon offers this Proposal to Expand and Modify the Willamette River
Water Supply System for consideration by the Willamette River Water Coalition (WRWC)
membership pursuant to Section 5.1 of the 2003 WRWC Intergovernmental Agreement.
The goal of this Proposal is to coordinate with the WRWC members and the City of Wilsonville
in developing the Willamette River as a long-term source of high quality drinking water at a
competitive cost. Implementation of the proposed improvements (the Project) will provide the
Project participants an ownership interest in a water supply system that will provide high quality
water at a competitive cost in a manner that is consistent with the Regional Water Supply Plan.
This Project will further support the goal of the WRWC to make efficient use of the water rights
held by the WRWC for the collective benefit of WRWC members.
The City of Sherwood, Oregon proposes to expand and modify the existing Willamette River
Water Supply System, consisting of the existing Willamette River Water Treatment Plant and
associated supply, treatment, pumping, storage, and transmission facilities. In summary, the
proposed Project includes:
1. Extension of the existing finished water transmission main from the Willamette Water
Treatment Plant in Wilsonville to a location approximately half way between the cities of
Wilsonville and Sherwood.
2. Construction of a new finished water reservoir at an overflow elevation of approximately
400 ft, to be located approximately half way between the cities of Wilsonville and
Sherwood.
3. Construction of a new finished water transmission main from the proposed new reservoir
to the City of Sherwood's existing Sunset Park reservoir.
The final scope, schedule, and budget for the Project are currently under development.
It is anticipated that the Project will result in an initial increase in demand on the existing
Willamette River Water Supply System of approximately 5 million gallons per day (mgd) to
serve the City of Sherwood, plus any additional demands resulting from other participants in the
Project. The Project will be sized to serve the future capacity requirements of the City of
Sherwood and it is intended that future increases in demand will be met using the Willamette
Notification to the Willamette River Water Coalition by Q
The City of Sherwood, Oregon 4
January 25, 2006
Page 2
River Water Supply System. In accordance with the WRWC agreement, the WRWC will
transfer/assign sufficient water rights to the Project to allow it to function at planned capacity.
It is anticipated that the City of Sherwood will be the lead agency, responsible for the permitting,
design, and construction of the Project. A project agreement will be negotiated between Project
participants. Unless, otherwise agreed to by the parties participating in the Project, the
participants will own the proposed improvements and the Project will be operated and
maintained as outlined in Section 4 of the WRWC Agreement.
Section 5.1 of the WRWC Agreement requires WRWC members to notify the WRWC of their
acceptance or rejection of the Proposal to Expand and Modify the Willamette River Water
Supply System by no later than 90 days following receipt of the notice. Acceptance of this
Proposal by a member will be considered acceptance of participation in the Project by that
member. Rejection of this Proposal by a member or failure of a member to respond within 90
days will be considered a rejection of participation in the Project by that member. A final project
agreement establishing participation, cost shares, operation and maintenance responsibilities, and
governance will be adopted following the conclusion of the notice period.
The City of Wilsonville and the Tualatin Valley Water District (TVWD) initiated development
of the Willamette River as a drinking water supply option. Over the last three years, the
Willamette River Water Supply System has proven to be a reliable, cost effective source of high
quality water for our communities. It is the goal of the City of Sherwood to become a partner
with these agencies and the WRWC to further expand water supply from this important regional
water resource.
Attachment 2
Tbalatin Valley Water District
P.O. Box 745 • Beaverton, Oregon 97075 • Phone: (503) 642-1511 • Fax: (503) 6494733 • www. tvwd.org
Gregory E. Diloreto
General Manager March 1, 2006
Bernice Bagnatl Kelly Ross
Chief Financial Amanda Rich
Officer Willamette River Water Coalition
12725 SW 66th Ave., Suite 107
Debra Erickson Portland, OR 97223
Manager, Human
Resources
RE: Tualatin Valley Water District's Notification of Proposal to Expand the
Date Fishback Willamette Water Supply System
Mmtager, Operations
& Field Services Dear Kelly and Amanda:
Todd Heidgerken Pursuant to Section 5.1 of the 2003 Willamette River Water Coalition (WRWC) agreement,
Manager, Community the Tualatin Valley Water District (TVWD) is providing you with a proposal to expand and
& Intergovernmental modify the Willamette River Water Supply System. Details of the proposal are attached for
Relations
your consideration. Questions regarding this proposal can be directed to TVWD Project
Representative, Stu Davis at 503-848-3025 (direct) or email stu@tvwd.org.
Brenda Lennox
Manager, Customer
& Support Services I would request we be included on the agenda for the March,29 WRWC Board meeting in
order to provide an overview of the TVWD project and to answer any questions.
Gary Pippin
It is assumed that receiPt of this letter and the TV WD ProPosal via email will begin the 90
Manager, ,
Engineering Services day period for WRWC members to declare'their. intentions regarding their participation in
this project. Given that time is of the essence in completing the proposed project, TVWD
would appreciate responses from the WRWC members in less than the 90 day period, if
feasible.
Thank you for your consideration of our proposal. I can be reached at 503-848-3014 or by
email, greg@tywd.org should you have any questions.
Sincerely,
4Gry dEDiL reto
General Manager
cc: WRWC Board Members
WRWC Staff Representatives
WATER - not to be taken for granted
Letter to WRWC, Kelly Ross & Amanda Rich, 03-01-06.doe/Greg/Pattyr j/3/l/2006
NOTIFICATION TO THE WILLAMETTE RIVER WATER COALITION
BY THE TUALATIN VALLEY WATER DISTRICT
A PROPOSAL TO EXPAND AND MODIFY THE
WILLAMETTE RIVER WATER SUPPLY SYSTEM
Distributed to WRWC membership on March 1, 2006
Response by WRWC members due no later than May 30, 2006
The Tualatin Valley Water District (TVWD) offers this Proposal to Expand and Modify the
Willamette River Water Supply System for consideration by the Willamette River Water
Coalition (WRWC) membership pursuant to Section 5.1 of the 2003 WRWC Intergovernmental
Agreement.
The goal of this Proposal is to coordinate with the WRWC members and the City of Wilsonville
in developing the Willamette River as a long-term source of high quality drinking water at a
competitive cost. Implementation of TVWD's proposed Water Supply Improvements Program
(the Project) will provide the Project. participants an ownership interest in a water supply system
that will provide high quality water at a competitive cost in a manner that is consistent with the
Regional Water Supply Plan. This Project will further support the goal of the WRWC to make
efficient use of the water rights held by the WRWC for the collective benefit of WRWC
members.
The Tualatin Valley Water District proposes to expand and modify the existing Willamette River
Water Supply System, consisting of the existing Willamette River Water Treatment Plant and
associated supply, intake, treatment, pumping, storage, and transmission facilities. In summary,
the proposed Project includes:
1. Expansion of the existing treatment, pumping, clearwell storage, and transmission
facilities at the Willamette River Water Treatment Plant in Wilsonville to add
approximately 55 mgd of finished water delivery capacity to the existing treatment plant.
2. Construction of a new finished water transmission main with a capacity of approximately
70 mgd from the Willamette River Water Treatment Plant in Wilsonville to a location in
the TVWD service area.
3. Possible construction of a new finished water reservoir with a capacity of approximately
20 million gallons at an overflow elevation of approximately 465 feet at the terminus of
the proposed new transmission main at a location in or near the TVWD service area.
The final scope, schedule, and budget for the Project are currently under development. In
addition, the Project may be discontinued or postponed at the discretion of the TVWD Board.
Notification to the Willamette River Water Coalition by
The Tualatin Valley Water District
March 1, 2006
Page 2
The approximate capacities noted above are based on meeting TVWD's requirements. These
capacities would need to be increased to meet the requirements of other WRWC members
wishing to participate in the Project. It is anticipated that the WRWC will allocate sufficient
water rights to the Project to allow it to function at planned capacity.
It is anticipated that TVWD will be the lead agency, responsible for the permitting, design, and
construction of the Project. A project agreement will be negotiated between Project participants.
Unless, otherwise agreed to by the parties participating in the Project, the participants will own
the proposed improvements and the Project will be operated and maintained as outlined in
Section 4 of the WRWC Agreement.
Section 5.1 of the WRWC Agreement requires WRWC members to notify the WRWC of their
acceptance or rejection of the Proposal to Expand and Modify the Willamette River Water
Supply System by no later than 90 days following receipt of the notice. Acceptance of this
Proposal by a member will be considered acceptance of participation in the Project by that
member. Rejection of this Proposal by a member or failure of a member to respond within 90
days will be considered a rejection of participation in the Project by that member. Final notice of
acceptance or rejection by WRWC members in less than 90 days would be especially welcome
given that time is of the essence in completing the proposed Project.
A Project agreement between participants in the Project will be adopted following the conclusion
of the notice period. The Project agreement will establish participation, cost shares, operation
and maintenance responsibilities, and governance associated with the proposed Project.
The City of Wilsonville and the Tualatin Valley Water District initiated development of the
Willamette River as a drinking water supply option. Over the last three years, the Willamette
River Water Supply System has proven to be a reliable, cost effective source of high quality
water for our communities. TVWD now intends to expand water supply from this important
regional water resource to meet the District's current and future water supply requirements.
•
City of Tigard &
Intergovernmental Water Board
Potential Participation in
Willamette Water Supply
Improvements
Mark Knudson, P.E. E COrOLl.O
March 21, 2006 < e n G i n e e r s
•
Presentation Overview
• WRWC Agreement
• Sherwood Proposal
• TVW D Proposal
• Comparison / Summary
Tampleb.ppt <E cnro~~o
•
•
WRWC Agreement
• Members:
- Cities of Tigard, Tualatin, Sherwood &
Gladstone
- TVWD
- Canby Utility Board
• Members provide 90-day notice of
proposed projects to expand or modify
• City of Sherwood - Notice on Jan 25, 2006
• TVWD - Notice on March 1, 2006 , ,
Tampbb ppt 4E ccirOLe O ,
•
Sherwood Proposal
• Existing supply issues:
- Limited well capacity to meet demands
- Water quality concerns with existing wells
- Costs of existing supply from Portland
- Anticipated future growth
• Approved by voters - November 2005
• Objectives:
- At least 5 MGD by 7/1/07
- Ultimate capacity of - 20 MGD < carOLLO
TampNb ppt E e n G I n e e r 5.
is
2
•
Sherwood Proposal
• Projects:
- Purchase 5 MGD of existing supply from
Willamette treatment plant at Wilsonville
- Extend existing 48" transmission main from
Wilsonville to Sherwood (portion shared
with Wilsonville)
- New 4 MG reservoir at 400' HGL
• Sub-regional transmission - only Willamette
• Response to WRWC due 5/2/06
T~&mP~ <E caro~~o s
•
Sherwood Proposal
• Key Assumptions
- 20 MGD to Tigard at existing HGL 475'
- Costs in March 2006 dollars
• Potential Tigard Participation
- Supply/Treatment: $ 25M - $ 30M
- Shared Pipeline: $ 15M - $ 25M
- Pump Station: $ 5M - $ 10M
- Tigard Transmission: $ 35M - $ 45M
- Total: $ 80M - $ 110M
#
Twnple4 PPS caro~~o e
•
3
•
TVWD Proposal
• Existing supply issues:
- Existing Portland contract expires 6/30/07
- Uncertainty of Portland supply after 7/1/07
- Costs of existing supply from Portland
• Objectives:
- 55 MGD as soon as possible after 7/1/07
- Ultimate capacity of - 70 MGD
Tampleb PM <E cn Gr0 e o
•
TVWD Proposal
• Projects:
- 55 MGD expansion of existing water
treatment plant at Wilsonville
- New 92" transmission main from WTP at
Wilsonville to d rv\ND
- New 20 MG reservoir at 465' HGL
• Regional transmission improvements may
include JWC & Portland sources
• Response to WRWC due 5/30/06
Tampl ft.ppt 4 caro~~o a
•
4
•
TVWD Proposal
• Key Assumptions
- 20 MGD to Tigard at existing HGL 475'
- Costs in March 2006 dollars
• Potential Tigard Participation
- Supply/Treatment: $ 25M - $ 30M
- Shared Pipeline: $ 18M - $ 33M
- Pump Station: not required
- Tigard Transmission: $ 25M - $ 30M
- Total: $ 68M - $ 93M
Twnpkb.ppt 4 caroLLo 0
•
Summary
Tampkb.ppt <4 cciroLLo 10
•
5
•
Summary of Proposals
FACTOR SHERWOOD TVWD
WTP Expansion None Add 55 MGD
Pipeline Scope - 4 miles of 48" - 20 miles of 92"
(Wilsonville to Sherwood) (Wilsonville to TVWD)
Target HGL 400'- 420' 465'- 530'
Timeline Next 2 years 2 - 10 years
Regional Options Willamette Willamette, JWC,
Supply Portland Supply
Tempbb.ppl <E caro~~o
•
Potential Tigard Costs (20 MGD)
FACTOR SHERWOOD TVWD
Buy-in to WTP -$25M-$30M -$25M-$30M
Shared Pipeline $ 15M - $25M - $ 20M - $ 35M
Booster Pumping $ 5M - $10M Likely not needed
Tigard Pipeline $ 35M - $45M - $ 25M - $30M
Total Capital $ $ 80M - $110M - $ 70M - $95M
Txnpbb.ppt <E caro~~o,z
•
6
AGENDA ITEM #
FOR AGENDA OF March 21, 2006
CITY OF TIGARD, OREGON
COUNCIL AGENDA ITEM SUMMARY
ISSUE/AGENDA TITLE Council Input on the Draft 2008-2011 STIP (State Transportation Improvement
Program)
PREPARED BY: A.P. Duenas DEPT HEAD OK CITY MGR •K
ISSUE BEFORE THE COUNCIL
Council discussion, input and direction on the draft Region 1 project lists for the 2008-2011 STIP (State Transportation
Improvement Program).
STAFF RECOMMENDATION
That Council provide input on the draft project lists and provide direction on which projects to include in a resolution
of support to be transmitted to ODOT (Oregon Department of Transportation) before the April 14, 2006 public
comment deadline.
INFORMATION SUMMARY
ODOT is requesting public input and comment on draft project lists for the 2008-2011 STIP. The draft STIP is
ODOT's project funding and scheduling document. It identifies the highest priority transportation projects to be
funded in 2008-2011. The draft STIP projects are divided into the following four project categories:
Modernization Projects (150% list)
Preservation Projects (230% list)
Safety Projects (100% list)
Bridge Projects (100% list)
ODOT is most interested in public input on the modernization project list. They will accept public comment on the
other three categories, but project selection on those categories would most likely be based on ODOT's technical
criteria and funding availability.
The following projects appear to be the most important ones in this part of Region 1 and should be strongly supported
for inclusion in the final STIP for 2008-2011.
Modernization Projects
• I-5 SB/ I-205 Merge: Acceleration Lane (scheduled for 2010). This project constructs an
acceleration lane at the merge of I-205/I-5 southbound for improved operations and safety. This
project would reduce the severe backups experienced on I-5 adjacent to Tigard and should improve
traffic movements into and out of the City.
FISCAL NOTES
The project estimates are provided by ODOT as shown on the specific project lists. There is no City funding
involved at this point on any of these projects.
iAeng\gus\council agenda summades\321-06 council input on the draft 2008-2011 slip ais.doc
• I-5: Wilsonville Interchange (scheduled for 2011). This project would improve the Wilsonville
interchange with I-5. The bottleneck on 1-5 extends from Tigard down to Wilsonville. South of
Wilsonville, the traffic flow on 1-5 becomes much freer. Any project that seeks to improve traffic flow
on I-5 from Tigard to Wilsonville should be supported for funding.
Preservation Projects
• OR141 and OR210: Hall Blvd, Boones Ferry Road, Scholls Ferry Road (scheduled for 2010 or
2011). This is a pavement inlay and overlay project that covers the full length of Hall Boulevard from
Scholls Ferry Road near the Washington Square Regional Center to Durham Road. The initial feedback
from ODOT staff is that this project would require more funding than is currently available and most
likely would not make the final 100% list. However, it is important for the City to support this
preservation project to improve the rideability and existing pavement condition on Hall.
Bridge Projects
• OR99W over Portland/Western Railroad in Tigard (scheduled for 2009). This project replaces the
Highway 99W overpass over the railroad in Tigard. Freight mobility is the driving factor behind the
replacement of this overpass. The existing overpass cannot take overweight loads and poses a barrier to
movement of freight up and down the 99W corridor. The entire overpass was not constructed to deal
with seismic activity and needs to be redesigned and replaced to meet current standards. This project
presents a rare opportunity for the City to provide input on the placement of the piers to improve
access to the Tigard downtown via Tigard and Commercial Streets. Although the bridge project list is
considered 100%, it would be in the City's best interest to show strong support for this project to
ensure that it does not get eliminated from the list and to give notice to ODOT of intention to actively
participate in the design review of the project to ensure enhancement of the downtown area.
Council discussion and input on these and any other projects on the four lists is requested. Based on Council input and
direction, a resolution will be prepared for Council consideration at the March 28, 2006 meeting. Council approval on
March 28 h of a resolution expressing support of projects important to the City would provide sufficient time for
transmittal of the resolution to ODOT prior to the April 14, 2006 deadline for comments.
OTHER ALTERNATIVES CONSIDERED
None
COUNCIL GOALS AND TIGARD BEYOND TOMORROW VISION STATEMENT
The STIP projects within and around the Tigard area help meet the Tigard Beyond Tomorrow goals of "Improve
Traffic Flow" and "Improve Traffic Safety." The replacement of the 99W overpass provides an opportunity to directly
support the Council goal to "Improve the Downtown."
ATTACHMENT LIST
1. ODOT Region 1 150% Candidate Modernization Project List for 2008-2011 STIP
2. ODOT Region 1 Candidate Preservation Project List for 2008-2100 STIP
3. ODOT Region 1 Candidate Safety Project List for 2008-2011 STIP
4. ODOT Region 1 Draft Bridge Project List for 2008-2011 STIP
ODOT Region 1 150% Candidate Modernization Project List for 2008-2011 Statewide Transportation Improvement Program (STIP)
Key Project Name Pre Project Description
County RTPff Freight.
Numtier Estimate'
2008 Regjon 1 Allocauon 19.362M + (DSTIP = 81.5M) -A119-00 x 1,tM0
13720 1-205/Mall Light Rail Unit 3 $ 5,000 Capital funding for light rail project Clack/Mult
13957 US26: Staley's Junction Improvement $ 500 Interchange Improvements at US26 and 01147. Washington State Rt, OFAC
13762 Sellwood Bridge EIS (D-STIP) $ 1,500 $ 1,500 Funding for EIS work. Multnomah 1012
13955 2008 PE, RAN and Utilities for 1-5 Delta Park Phase 1 $ 2,104 Funding for project development, right of way acquisition and utility relocations. Multnomah
-------------------Ph--
-1 (Vi-
-ctory-
12076 1-5: Delta Parka se- -
- Blvd. - Lombard St.) $ 16,000 $ 67,000 Constructs third lane SB. Fully funds project programmed in the 2006-2009 STIP. Multnomah State Rt, OFAC
13957 US26: Staley's Junction Improvement $ 5,000 $ 12,000 Fully funds project programmed in 2006-2009 STIP. Washington State Rt, OFAC
14030 1-84: Replace/Lengthen Bridge Structure MP64.44 (Hood River exit 64) $ 1,539 $ 1,539 Fully funds an OTIA 3 Bridge replacement project on 1-84 in Hood River at OR35. Hood River N/A State Rt, OFAC
TBD 1-5: Delta Park Phase 2 (Access Improvements at Columbia Blvd) $ 9,000 $ 60,000 Access improvements at 1-5/Columbia Blvd. This phase funds protective right of way Multnomah 4006 State Rt, OFAC
acquisition and begins preliminary engineering.
Subtotal $ 40,643 $ 142,039
2009 Re 1'on 1 tllocatiQn=$17.199M+(4STIP-$g
13759 Pedestrian & Bicycle Elements for Pres projects $ 1,000 $ 1,000 Funds bicycle and pedestrian facilities for 2008-2011 STIP Preservation Projects. Various
13953 US26: Langensand Rd - Brightwood Loop Rd $ 1,400 $ 1,400 Constructs safety improvements between mp27 and mp41. Clackamas State Rt
13964 2009 PE, R/W and Utilities for US26 Glencoe Road $ 3,117 Funding for project development, right of way acquisition and utility relocations. Various
Constructs new interchange at US26 and Glencoe Road. This phase funds preliminary
12885 US26: Sunset Hwy @ Glencoe Road $ 6,000 $ 26,000 engineering and protective right of way acquisition. Also funds PE and construction for Washington State Rt, OFAC
Glencoe Rd (US26 - West Union).
TBD US30: Widening at Van Street $ 1,700 $ 1,700 Widens US30 and constructs a left turn lane to Van St.(Clatskanie). Columbia N/A State Rt
TBD US30: Widening at Tide Creek $ 1,100 $ 1,100 Widens US30 and constructs a turn lane to Tide Creek. (Columbia City). Columbia N/A State Rt
Subtotal $ 14,317 $ 31,200
2010-~, _ Reylon;3lrAtlocation=175481111 +~{DSTIP=.~¢51k,: • ,t 7 7
TBD 1-5 SB / 1-205 Merge: Acceleration Lane $ 3,000 $ 3,000 Constructs acceleration lane at merge of 1-20511-5 SB for improved operations and safety. Washington State Rt
Q TBD US26: 185th Ave - Cornell Road Widening $ 19,500 $ 19,500 Continues widening from Come[] Road to SW 185th. Washington 3011 State Rt
TBD Troutdale Marine DrBackage Road $ 7,900 $ 7,900 Completes Interchange Area Management Plan and constructs a new 2-lane road from 1-84 Multnomah Amend
EB off ramp (Marine Dr.) to 257th. Project in local Transportation System Plan.
Subtotal $ 30,400 $ 30,400
2611' Region ,t Allocatlon'=$17'.508M+{QSTIP->$451kZ _
TBD US26: Springwater Interchange Phase 1 $ 5,800 $ 5,800 Constructs at-grade intersection to serve Springwater industrial area. Multnomah phase of State Rt
2051
*TBD I-5: Wilsonville Interchange $ 10,500 $ 25,000 Funds interchange improvements at 1-5 and Wilsonville. Project to be phased. Clackamas 6138 State Rt, OFAC
TBD OR212/OR224 Sunrise Corridor $ 7,000 $ 60,000 Funds preliminary engineering and protective right of way acquisition. OFAC
Subtotal $ 23,300 $ 90,800
Candidate List of 150% $ 108,660 $ 290,039
Region 1 Modernization Target w/ DSTIP $ 73,979 Region 1 Target = $73.979M available for 08-11 STIP includes $2.402M for DSTIP
Bold = Projects funded in the 2006-2009 STIP 08/09 already programmed = $14.621 M
OFAC = Project identified on Oregon Freight Advisory Committee Recommendations for High Priority Freight Mobility Projects
State Rt = Project on Oregon Slate Highway Freight System
* Project cost based on planning level estimates and are subject to revision after project scoping. January 24, 2006
1
ODOT Region 1 Candidate Preservation
Project List for 2008-2011 Statewide Transportation Improvement Program (STIP)
Key m - -
Project Name In current Protect Description County
Number STIR
2008 _ -RegionlACtualAllocaUOn=510.7291+ x1,OOO
13715 US 2b: E. Mountain Air Dr. - E. Lolo Pass Rd. $ 2,411 - Clackamas
13716 US 26: MP 44.03. MP49.2 $ 2,135 Clackamas
13708 US 30: Yeon Steel Preservation $ 2,605 Multnomah
13712 US 26: BE 51st -1-205 (East Portland Freeway) $ 2,000 Multnomah
13713 US 26: MP37.26 - MP39 $ 1,353 Multnomah
13972 Reserve PE & RW Preservation 2008 $ 726 Various
13970 Reserve Utilities Preservation 2006 $ 292 _ Various
2009 Region l Actual Anocation.= $13.098M 4
13706 OR224: Jct Hwy 172 - Jct Hwy 161 $ 3,146 Clackamas
13709 OR213: MP7.7 - MP 10.75 $ 1,276 Clackamas
13710 OR213: S. Henricl Road - S Monte Carlo Wy $ 813 Clackamas
13971 Reserve Utilities Preservation 2009 $ 304 Various
13973 Reserve PE & RW Preservation 2009 $ 754 Various
13707 US26: North Plains - Cornell Rd $ 9,636 Washington
TBD OR213: Oregon City bypass 1-205-Conway $ 4,300 Pavements Committee selected this project for funding in 2009, project will Clackamas
be added to the 2006-2009 STIP via OTC amendment
Amounts programmed may include funds from other programs lie. Operations and Safety)
2010 R:0Ion 1 Allor'ation $19.41.1 Pre-
- EStlfi7dl4'~
2011 _ Rcyi0n 1 Allocation =$20.3M _ _e210911`1 MP End MR 0.0130.
TBD OR43: 1-5 - TerMiliger (Macadam) 0 2.79 $ 5,900 Urban Multnomah
TBD ORB: Sunset Hwy - Hwy 217 (Canyon Road) 0.05 3.18 $ 3,150 Urban Washington
TBD OR43: McVey-1-205 6.7 11.66 $ 3,750 Urban Clackamas
TBD ORB: Minter Br. Rd. - Forest Grove 11.28 17.46 $ 8,810 Urban - Project runs through City of Hillsboro - Wi11 need to be supplemented Washington
with other funds
TBD OR141 and OR210: Hall, Boones Ferry, Scholls Ferry 2.57 various $ 6,770 Urban - Beaverton / Tigard - Wi11 need to be supplemented with other funds Washington
TBD OR10: Farmington Rd (SW 198th - SW173rd) 5.88 7.53 $ 1,160 Urban - Will need to be supplemented with other funds Washington
TBD OR219: ORB -Farmington Rd. 0 5.43 $ 2,960 Urban/ Rural Washington
TBD US26: Military Cr. Rd. - Wolf Cr. 26 37.4 $ 4,620 Rural Washington
TBD US26: Wolf Cr. - West Fork Dairy Cr. 37.4 45 $ 4,500 Rural Washington
TBD OR47: US26 - Banks 80.8 82.85 $ 1,170 Rural Washington
TBD OR99E: MILK Viaduct - Kellog Cr. 1.31 5.97 $ 6,440 Urban Multnomah
TBD US30B: NE 60th - Sandy Blvd 9.2 11.25 $ 2,050 Urban Multnomah
TBD OR99E: 1-5 - Columbia Blvd -6.09 -4.01 $ 3,410 Urban Multnomah
TBD OR99E: Nast - MP 13.04 9.19 13.04 $ 5,450 Urban Clackamas
TBD US26: 1-205 - Gresham (SE 182nd Ave) 5.75 9.96 $ 2,960 Urban - Will need to be supplemented with other funds Clackamas
TBD OR213: 82nd (NE. Killingsworth - Hwy. 224) 0 10.18 $ 15,790 Urban - Will need to be supplemented with other funds Multnomah /
Clackamas
TBD OR213: 1-205 - Conway 0 4 $ 5,740 Urban Clackamas
TBD OR99E: City of Canby 20.46 22.11 $ 3,300 Urban Clackamas
TBD US308: Lombard Street 1.31 6.25 $ 21,930 Urban - Will need to be supplemented with other funds Multnomah
TBD OR211: OR213 -Mathias Rd (Molalla) 11 13 $ 1,480 Urban - Will need to be supplemented with other funds Clackamas
TBD US30: City of Cascade Locks 29.7 30.33 $ 930 Project runs through City of Cascade Locks Hood River
TBD US26: Sandy - MP 30 (add 33.2-34.1 if needed) 22.49 34.1 $ 8,250 Urban / Rural - Project runs through City of Sandy Multnomah
T8D OR281/282: Hood River - OR35 0 5.09 $ 3,620 Urban / Rural Hood River
TBD OR211: Meadowbrook- Hult Rd. 16.39 20.89 $ 1,580 Rural Clackamas
TBD OR224: Rock Cr. - Eagle Cr. 8.15 17.92 $ 3,440 Rural Clackamas
TBD OR224: Estacada - Forest Bdry. 23.84 31.56 $ 3,180 Rural Clackamas
TBD OR211: Sandy - Eagle Cr. -0.23 5.94 $ 2,160 Rural Clackamas
TBD US26: MP49.2 -62.15 49.2 62.15 $ 11,420 Rural Clackamas
TBD OR35: Jct. US26 - Polallie Cr 57.2 73.18 $ 11,740 Rural Hood River
Total $ 157,660 **Pre-estimate figures are for paving work only and does not include other
features (drainage, curbs, sidewalk)
Region 1 Preservation Target for 2010 and 2011 $39.7M Region 1 Target (Urban) _ $173M, Target Lane Miles = 53.6
Region 1 Target (Rural) _ $22.OM, Target Lane Miles = 88.1
Total Preservation Target for 2008-2011 $67.827M
Bold = Projects funded in the 2006.2009 STIP 08/09 already programmed = $28.127
* Project cost based on planning level estimates and are subject to revision after project scoping. February 6. 2006
ODOT Region 1 Candidate Safety Project List for 2008-2011 Statewide Transportation Improvement Program (STIP)
Key
Number Project Name Project Name ;i
~ l
2008 Reglon 1 Allocation J15.160M 20IJ9 R9 Ion ;1 Actual = $12.610M _
12840 US26: Wildwood - Wemme Clackamas 13721 OR 219 @ East Laurel Rd. Washington
13764 2008 Safety Project Various 13765 2009 Safety Project Various
13723 OR213: Cascade Hwy S. @ S Mulino Rd [Left turn] Clackamas 13728 OR 99E: MP 14.0. MP 14.9 (Oregon City) Clackamas
13729 Light Emitting Diode (LED) Signal Upgrade Various 13722 US 26: Salmonberry Road - Viewpoint Sec (HEP) (Tillamook State Forest) Washington
13724 OR213: Cascade Hwy S @ S Barnards Rd Clackamas 13730 Reserve PE & RW Safety 2009 Various
13732 2008 Button Replacement Program Various 13731 2009 Button Replacement Program Various
13744 Reserve PE & RW Safety 2008 Various 13975 Reserve Utilities Safety 2009 Various
13725 OR 219: Midway - McFee Creek Washington 13733 2009 Safety Reserve Various
13974 Reserve Utilities Safety 2008 Various
2110 Regibn I Allocation n`$13.832M
D11._. _ R,, on 1 Allocation =_$14.456M
Pre-
Projoct Name B.'aw MP. End MP Project Description Safety Issuo County
- Estimate' ---i
TBD 15: N Vancouver Av - Burnside Bridge 301.70 302.60 Mad SB Exit Only Lane to Morrison Bridge (add to Paving Project) Rear End & Side Swipe Multnomah
TBD 1-5: Interstate Bridge - Jantzen Beach 307.77 307.98 Low ITS signing (Operations) SB Rear End Multnomah
TBD OR 99E@Columbia Blvd. -4.01 Mad WB Right Turn Lane on Columbia Blvd Rear End & Turning Multnomah
TBD OR 99W Capitol Hwy.-SW Huber 6.21 6.30 Mad SB Left turn lane to Capitol Hwy, Two way SW Huber Turning Multnomah
TBD 1-84: 1-205 to 122nd 9.70 10.00 Mad EB Exit Only Lane, add to 1-84 Paving Project Rear End & Side Swipe Multnomah
TBD US 30: Ramp to Lewis & Clark Bridge 48.71 48.74 Low Acceleration Lane Rear End Columbia
TBD US 26: 122nd to 136th 7.21 7.90 High Construct center turn lane, bike lanes sidewalks Rear End &Tuming Multnomah
TBD US 26: Zig Zag River - Bruin Run Rd 46.02 47.39 High EB & WB passing lanes, 16'median, realign curve; Add to 2008 Paving Project Lane Departure Clackamas
TBD US 26: Bruin Run Rd - Ski Bowl 47.39 52.50 High Extend WB passing lane, 16' median (add to 2009 Rock fall Project) Lane Departure Clackamas
TBD US 26: Vista Ridge Tunnel to 1-405 South 73.70 2C74.05 Mad Two lane ramp to 1-405, Close Montgomery On Ramp Rear End Multnomah
TBD OR 213: Foster Road WB Right Turn Lane 5.76 High WB Right Turn Lane Rear End Multnomah
TBD OR 213: Foster Road EB Right Turn Lane 5.76 High EB Right Turn Lane Rear End Multnomah
TBD OR 47: South Fork Dairy Cr - Kemper Rd 86.20 86.80 High Realign curves and widen shoulders Lane Departure Columbia
TBD US 30 Bypass: NE122nd to NE141 st 12.40 13.49 Mad Channelization Turning & Rear End Multnomah
TBD OR 219 @ Midway 8.00 8.50 Mad Realign curve and widen shoulders Lane Departure Washington
TBD OR 219 @ Wolsborn 9.60 9.90 High Realign curve and widen shoulders; requires bridge Lane Departure Washington
TBD OR 217: Allen Blvd. - Denny Rd 2.48 3.02 Low Congested Weave Corrections Rear End Washington
TBD OR 213: Mulino-Blackman's Comer 11.30 16.10 Mad Widen Segments with narrow shoulders (add to STIP Paving Project) OH Road Clackamas
TBD OR 224 @ Johnson Rd 3.60 3.80 Low Add third lane eastbound through signal Rear End Clackamas
TBD OR 224: Carver - Barton 9.21 15.00 High Realign curves and widen shoulders (add to STIP Paving Project) Lane Departure Clackamas
TBD OR 224 @ Tong Rd 10.00 10.60 High Channelization (add to STIP Paving Project) Lane Departure Clackamas
TBD OR 224 @ SE 197th Ave 11.30 11.70 High Realign curves widen shoulders (add to STIP Paving Project) Lane Departure Clackamas
TBD OR 224: MP 12.2 - 232nd Ave 12.20 13.50 High Realign curves and widen shoulders (add to STIP Paving Project) Lane Departure Clackamas
TBD OR 224 @ SE 232nd Ave 13.50 13.90 High Channelization requiring a bridge (add to STIP Paving Project) Lane Departure Clackamas
TBD OR 212 Sunnyside Road-Royer Road 2.50 2.85 Mad 2nd eastbound lane Rear end & turning Clackamas
TBD Region 1 Reflective Pavement Markers Low Bi-yearly projects to replace pavement markers (Operations) Region-wide
TBD Funding for Durable Striping in Preservation Projects High Operations Region-wide
Total for 2008-2011 STIP $56.058M
Cost Low <$1,000,000; Medium $1,000,000 to $3,000,000; High > $3,000,000
Bold = Projects funded in the 2006-2009 STIP 'Cost estimates and years to be determined during project scoping.
* Project cost based on planning level estimates and are subject to revision after project scoping. February 6, 2006
ODOT Region 1 Draft Bridge Project List for 2008-2011 Statewide Transportation Improvement Program (STIP)
Key Project Name Bridge ID Pre' k Project Description County Freight
Number Estimate
2008 x : oa0 - -
14014 OR43: Willamette River Bridge (Orion CityL _ _ _ - _ _ 02552 - _ _ 32514 Rair and Rehabilitation _ _ _ Clackamas Yes _
TBD US26: West Fork Dairy Creek, MP 46.30 02 673_ $ 2,024 Replace bridge with new Prestressed Beam bridge (1 mile east of US26%OR47) Washington Yes
Place deck overlay; Retrofit rails, Repair cracked girders with post-tensioning; Repair
TBD Nehalem River, OR47 (Banzer) 03140A $ 1,346 cracked stringers with post-tensioning; Repair cracked cols with ext stirrups, post-tensioning; Columbia No
Repair cracked caps with post-tensioning
TBD OR 213 Milk Creek 02120 $ 3,000 Replace bridge which lies between a preservation and safety project. Multnomah No
TBD 1-205: Columbia River N Channel, (Glenn Jackson) 09555 $ 2,565 Repair bad deck joints. Multnomah Yes
Subtotal $ 12,449
300s ~ z _
_
14180 Lewis and -a Aoa9view)BridgePamtin~Proi_ect__________02046_ $ 10j834 ±p-iatBndge,Partnersh~wy.StateofWa_shigtton___________-_________ Columbia _ as
TBD OR99E: Parrot Creek 00580 $ 1,525 Remove wearing surface & place deck overlay Clackamas No
TBD Mt Scott Creek & Union Pacific RR (82nd Ave)@MP9.67 02135A $ 378 Retrofit old picket fence railing each side. Bridge is north of Milwaukie Expressway. Clackamas No
TBD OR47: Nehalem River (Miles Bridge - Vemonia) 02323 $ 3,300 Replace bridge. #2 Priority Recommendation from NW Area Commission on Transportation. Columbia No
TBD OR99W over Portland/Western RR (Tigard) 02532 $ 7,615 Replace bridge with new Prestressed Beam Bridge. Washington Yes
Subtotal $ 23,652
2010°, _ _ _ _ - -
TBD OR99E: SE Water Street Viaduct, (McLoughlin Blvd) @ MP12.29 02374 $ 389 Retrofit rails to type F at curb; Repair deck joints; Repair cracks in superstructure; Repair Multnomah No
cracks in substructure; Repair & dean rocker bearings; Rail transitions.
TBD OR99E: Partial Viaduct, SB @ MP13.86 07164 $ 693 Replace with Soldier pile retaining wall Clackamas No
TBD 1-205: Willamette R & OR99E & OR43,(George Abernethy) 09403 $ 12,823 Place deck overlay; Repair strip seal expansion joints; Repair open expansion joints; Repair Clackamas Yes
other deck joints.
TBD 1-5 SB Over the Union Pacific RR S8588E $ 8,152 Overlay; Retrofit rails; Joint repair. Multnomah Yes
Subtotal $ 22,057 _
2011. 77.71TBD OR8: Dairy Creek on TV Highway 00744B $ 1,508 Retrofit rails with new historic type rails; Joint repair; Corbel catcher blocks; Cable restraints; Washington No
Other Phase 1 seismic retrofit work; Rail transitions; New RC end panels
TBD OR99W over SW Multnomah Blvd 02010 $ 4,498 Replace bridge with new Prestressed Slabs Br with 7' sidewalks, historic rails. Multnomah No
Subtotal $ 6,006
Total for 2008-2011 STIP $ 64,164
Bold = Projects funded in the 2006-2009 STIP
Freight = Bridge in on State Highway Freight System
Federal Earmark
TBD 1-5: SW Iowa Street Viaduct (MP298.2) 08197 $ 20,000 Replace Structure Multnomah Yes
* Project cost based on planning level estimates and are subject to revision after project scoping. February 6, 2006
1
Council Input
Draft 2008-2011 STIP
March 21, 2006
STIP (State Transportation
Improvement Program)
❖ ODOT's (Oregon Department of
Transportation) project funding and
scheduling document
❖ ODOT is requesting public input on
the draft STIP for 2008-2011
❖ Comment period ends April 14, 2006
1
l
Project Categories
❖ Modernization (150% list)
❖ Preservation (230% list)
❖ Safety Projects (100% list)
❖ Bridge Projects (100% list)
D
Key Projects
❖ Modernization projects of importance to
Tigard
❖ I-5 SB/I-205 Merge: Acceleration Lane
❖ Improves operations and safety
❖ Reduces backups on I-5
❖ Provides smoother and faster merge from I-205
to I-5
❖ I-5: Wilsonville Interchange:
❖ Improves the interchange
❖ Reduces congestion on I-5 north of Wilsonville
2
Key Projects
❖ Preservation Project
❖ OR141 and OR210
❖ Pavement overlay project
❖ Project limits - Hall Boulevard from Scholls
Ferry Road to Durham Road
❖ Bridge Project
❖ OR99W over Portland/Western Railroad
in Tigard
❖ Replaces existing overpass
Replacement of 99W Overpass
❖ Freight mobility is the driving factor
❖ Overpass not designed for overweight trucks
❖ Structure is not designed for seismic activity
❖ Provides an opportunity for the City to
become involved in the design
❖ Could provide better access into the
Downtown via Tigard and Commercial
Streets
❖ Could be aesthetically designed in
harmony with the Tigard Downtown Plan
3
Recommendations
❖ That Council provide input on the projects
❖ That Council express strong support for the
overpass replacement on Highway 99W and
pavement overlay on Hall
❖ That Council support be provided via
resolution
❖ Resolution will be submitted for Council
consideration at the March 28, 2006 meeting
❖ If approved, resolution will be transmitted to
ODOT before the April 14, 2006 deadline
4
AGENDA ITEM #
FOR AGENDA OF March 21, 2006
CITY OF TIGARD, OREGON
COUNCIL AGENDA ITEM SUMMARY
ISSUE/AGENDA TITLE Burnham Street Design Concept Options PREPARED BY: A.P. Duenas DEPT HEAD OK CC Eng CITY MGR OKo
ISSUE BEFORE THE COUNCIL
Presentation of design concept options on the Burnham Street project for discussion, input and direction.
STAFF RECOMMENDATION
Staff recommends that Council provide input on the design concepts and provide direction needed to move ahead with
the design of the project.
INFORMATION SUMMARY
At the February 21, 2006 Council meeting, Council was presented with design concept options for Burnham Street
developed by the City's Streetscape design consultant (OTAK). Following that meeting, the consultant has been
working with City staff to examine the street layouts in greater detail to develop design options for further discussions
with the SWG (Streetscape Working Group) and the CCAC (City Center Advisory Commission). The meeting with the
Streetscape Working Group is scheduled for March 9, 2006 and the CCAC meeting is scheduled for March 16, 2006.
Following these meetings, the recommendations of the two groups will be brought to Council for discussion and
direction at the workshop meeting on March 21, 2006.
Once Council direction is provided, the project timeline for design, right-of-way acquisition, and construction will be
established.
OTHER ALTERNATIVES CONSIDERED
N/A
COUNCIL GOALS AND TIGARD BEYOND TOMORROW VISION STATEMENT
The Burnham Street Improvement Project is a major catalyst project identified in the Tigard Downtown Improvement
Plan and is a key element in the effort to meet the Council Goal to "Implement the Downtown Plan." The
improvements to Burnham Street meet the Tigard Beyond Tomorrow goals of "Improve Traffic Safety" and "Improve
Traffic Flow."
ATTACHMENT LIST
None
FISCAL NOTES
The amount of $300,000 is provided in the FY 2005-06 Capital Improvement Program budget for design and right-
of-way acquisition on Burnham Street. Funding will be included in the FY 2006-07 CIP budget to complete the
design, acquire right-of-way, and possibly begin construction prior to the end of the fiscal year.
n
Burnham Street Design Concept Options
City Council Meeting
March 21, 2006
.
~ w
Burnham Street
Option 1
Key Elements
• 3 Lanes - Hall Blvd. to Main St.
• Landscaped Median - Hall Blvd. to Main St.
• On-Street Parking - Ash St. to Main St.
• Bike Lanes - Hall Blvd. to Ash St.
Potential Future Roundabout at Ash St.
1
r
9 9 ~ 'a
me f Ad . T
~ ' ems. I ~ ,
•.R\ A etOtoeMUL? a fl..
t,
1..... tl~AG I. mm e a 11 ml . ....J
T,p,d D.-.- sovahup. Dip Pl.. - rqa
' n~w~su,+sene.nc~Qpnaip 0 ~J
Burnham Street
Option 1 Sections
Main St. to Ash St. Ash St. to Hall Blvd.
Ali
2
r;OPTION 2iexpandedGreenHeert
:y, ~ Davebp"patkxdh e-r: '4
. ~ amphMeateApb~a for puhlfi
~ng'
oON rram Ae
AsAWft wdh performing arm
k Providewaterf" , vpln r`
Y 1. M physca1 or Moral COrmBGtgfl b .F•
6i6imiawidene r/
< : > < + wrwrectipn b Fime Ci G
4 F'
ENarge~eritrance @ Fennp
~ ''v! • ^c+ ~ 'u,.~GJMan Sl wgh wkkr welkway~.•
Create"ewa street oil poroons
s 61 Main end Burift Bkeete r
.Crite'ceri(ralcbriVb*wea~
r r r Y}" _ • " Use eengar mateiela to uNly Iha
1°f '+'i i ~ i.•"~..; .~Gc ' BnWe OOR BIea r. •t'
a n t } ~ Provbe atraq treJ romeNony
it
::;1 t J fAx Ya t,
t Y Y ! ya F rt^J .Y[[t 5 ' 4 k w:~
F. ✓.ri S Y.. rS~J1 ''l .
+T
• Y r 2 L. 4Ax- f.-'
Burnham Street
Option 2
Key Elements
3 Lanes - Hall Blvd. to Ash St.
• 2 Lanes - Ash St. to Main St.
Landscaped Median - Hall Blvd. to Ash St.
• On-Street Parking - Hall Blvd. to Main St.
No Bike Lanes
3
Burnham Street
Option 2 Plan
y T~ m ~rmemuuaum
4 011eMaN aaM1WMM M eseeae^we• . eTMm _ _ ~df I
ii I~iRfff~11~a1~• 11~M! ~t•.-~t• e~ Yb11~I•
I T.
t3 4P {i
y~n.~n~c t
~ vmonu _
C
i. _ oa.. o.°.xxr...... .a
NAM
t j _v.0 r i t l
n2 p PWe
B a
Thad Doudim S Option 2
Burnham Street
Option 2 Sections
Ash St. to Main St. Ash St. to Hall Blvd.
. "aarw L
taw a Pdy7 Tod Uinno , t gw=& r*MIN ff zll ~P U= 6$ua~t
UNP a= Lo. ~ aim ~
gDqam?
CIE, -Wk"'P RCGM "13 ` `rlaat~n•.
4
TIF Eligible Capacity
Improvements
• Signalization
• Channelization
• Widening for additional lanes
• Drainage work
• Pedestrian safety
• Lighting
• Street extensions
• Bike lanes
What are considered capacity
improvements on Burnham
Street?
• Adding 3rd lane - yes
• Adding bike lanes - yes
• Adding parking - no
• Adding sidewalks - yes
• Adding street lights - yes
5
Burnham Design Options
Comparison
OPTION LANES ON-STREET BIKE LANES R.O.W. REQUIRED
PARKING
3 Lanes 74' (minimum)
OPTION 1 w/median Both sides Both sides - Main to Ash
- Main to Hall -Main to Ash only -Ash to Hall only 68' (minunum)
- Ash to Hall
Eliminate bike lanes
Both sides to provide additional 74 (mtnvnum)
OPTION 1 A Same -Main to Hall parking - Main to Hall
2 Lanes
-Main to Ash
Both sides 74' (minimum)
OPTION 2 3 Lanes -Main to Hall None -Main to Hall
w/median
-Ash to Hall
Reduces R.O.W. to
OPTION 2A Same Eliminate parking Provide bike lanes 62'- Main to Ash
-Ash to Hall -Ash to Hall Reduces R.O.W. to 68'- Ash
to Hall
Both Options Assume:
12 foot min. sidewalk width (includes pedestrian and furnishing
zones)
Dedicated turn lanes at Main, Ash, and Hall intersections
Burnham Street
Funding/Timing Comparisons
Option TIF Addresses LT Timing Funding Breakdown Impact on other CIP
Capacity needs (completion) IS TIF /Gas Tax) Projects
(loss of Gas Tax)
Option 1 yes yes 1 years + $1.35 to / 1.55 m No impact
3-lane Main to Hall Fall 2008
(Bike Lanes - Ash
to Hall, Parking Ash
to Main)
Option IA yes yes 2 years + $1.40 m / 1.55 m No impact
3-lane Main to Hall Fall 2008
(Parking - Main to
Hall)
Option 2 Yes/part yes 2 years+ S1.40k / 1.55 m No impact
3/2 lane Fall 2008
Compromise
(74-foot ROW
throughout)
Option 2A Yes/part yes 2 years + S1.30k / 1.55 to No impact
312 lane Fall 2008
Compromise
(62-foot and 68-foot
ROW)
Option 3 no no 5 years + $0 / 2.75 m -51.20 million
2-lane option Fall 2010 All gas tax funding in
(Parking - Main to upcoming fiscal years
Hall) directed to the project
6
CCAC Recommendation
(Option 2: 3/2 Lane Compromise)
• Full 74-foot right-of-way for
maximum flexibility
• Medians - Hall to Ash where
appropriate
• 2 lanes (Main to Ash)
• 3 lanes (Ash to Hall)
• Parking on both sides (Main to Hall)
• No bike lanes (Main to Hall) - Look
at other options to provide bike lanes
Key Points
• All options can be designed to discourage
Burnham as a "Cut Through" street
• Bike lanes qualify for TIF, parking does not
• Providing parking will allow modification for bike
lanes at a later time
• Main to Ash section is more pedestrian-oriented
and the 2-lane option accommodates this
• Ash to Hall 3-lane option provides future
capacity and pedestrian crossing safety
7
Burnham Design Options
Comparison
.
OPTION LANES ON-STREET BIKE LANES R.O.W. REQUIRED
PARKING
3 Lanes 74' (minimum)
OPTION 1 w/median Both sides Both sides - Main to Ash
- Main to Hall -Main to Ash only -Ash to Hall only 68' (minimum)
- Ash to Hall
Eliminate bike lanes 74' (minimum)
Both sides to provide additional
OPTION 1A Same -Main to Hall parking -Main to Hall
2 Lanes
-Main to Ash
Both sides 74' (minimum)
OPTION 2 3 Lanes -Main to Hall None -Main to Hall
w/median
-Ash to Hall
Reduces R.O.W. to
OPTION 2A Same Eliminate parking Provide bike lanes 62'- Main to Ash
-Ash to Hall -Ash to Hall Reduces R.O.W. to 68'- Ash
to Hall
Both Options Assume:
12 foot min. sidewalk width (includes pedestrian and furnishing
zones)
Dedicated turn lanes at Main, Ash, and Hall intersections
Burnham' Street
Funding/Timin-g Comparisons
Option TIF Addresses LT Timing Funding Breakdown Impact on other CIP
Capacity needs (completion) TIF / Gas Tax) Projects
(loss of Gas Tax)
Option 1 yes yes 2 years + $1.35 in / 1.55 in No impact
3-lane Main to Hall Fall 2008
(Bike Lanes - Ash
to Hall, Parking Ash
to Main)
Option 1A yes yes 2 years + $1.40 in / 1.55 in No impact
3-lane Main to Hall Fall 2008
(Parking - Main to
Hall)
Option 2 Yes/part yes 2 years + $1.40k / 1.55 in No impact
3/2 lane Fall 2008
Compromise
(74-foot ROW
throughout)
Option 2A Yes/part yes 2 years + $1.30k / 1.55 in No impact
3/2 lane Fall 2008
Compromise
(62-foot and 68-foot
ROW)
Option 3 no no 5 years + $0 / 2.75 in -$1.20 million
2-lane option Fall 2010 All gas tax funding in
(Parking - Main to upcoming fiscal years
Hall) directed to the project