Resolution No. 99-44 CITY OF TIGARD,OREGON
RESOLUTION NO.99-U�
A RESOLUTION AMENDING AN INTERGOVERNMENTAL AGREEMENT WITH METRO TO
OBTAIN FUNDING FOR CERTAIN OPEN SPACE AND TRAIL ACQUISITION OR
ENHANCEMENT PROJECTS PURSUANT TO THE LOCAL SHARE COMPONENT OF THE
METRO OPEN SPACES GENERAL OBLIGATION BOND MEASURE.
WHEREAS, On May 19, 1995, the electors of Metro, a metropolitan service district,approved a ballot
measure authorizing Metro to issue$135.6 million in bonds for open space,parks,trails,and streams(the
"Measure");and
WHEREAS, the Measure provided$25 million from bond proceeds be expended by local parks providers
for specified projects;and
WHEREAS, the City is a local parks provider that has received approval for funding for projects as
specified by the Measure;and
WHEREAS, the City and Metro entered into a contract to expend the pass-through funds to implement
certain listed projects.
NOW,THEREFORE,BE IT RESOLVED by the Tigard City Council that:
SECTION 1: The City's project list,which was submitted to Metro in September 1997, is hereby
modified as set forth and attached as Exhibit"A". The modification is based on the
following findings.
A. The Council finds that the purchase price of the Cache Creek forest parcel located
within the Bull Mountain target arca exceeds the amount allocated for land
acquisition within this area.
B. The Council finds that the amount budgeted for the Tualatin River Pedestrian Bridge
Design exceeds the amount needed to complete this project by$43,500. Council
therefore wishes to re-allocate this$43,500 in surplus funds to the purchase of the
Cache Creek forest parcel in the Bull Mountain target area.
GC. The Council wishes to transfer$22,525 in fimds budgeted for land acquisition within
the Fanno Creek Trail target area to the purchase of the Cache Creek forest parcel in
the Bull Mountain target area.
H
D. Council finds that the Fanno Creek Trail Corridor project earmarks funds for the
q acquisition of land within the trail corridor. Council finds that the restoration and
eru,aucenieut of disturbed areas and the construction of"irails are eligible activities
aunder the Greenspaces Bond measure. Council therefore wishes to modify the
paraf,ieters of this project to inc ludo natural area restoration and trail construction as
RESOLUTION NO.99-11�
Page 1
elements of the Fanno Creek Trail Corridor project. Council also wishes to extend
the northern boundary of the project area from Tiedeman Avenue to Tigard Street.
This new boundary replicates the boundary of the Fanno Creek Trail Corridor
® Regional Target Area
E. The Colmcil finds that a public press identical to rhe process used to select the
initial sites was used to recommend the modification. The City Council considered
the modification at its regular meeting on May 11, 1999.
F. The Council finds that the modification has been discussed with and received
tentative approval from Mel Huie,Local Share Coordinator of Metro's Regional
Parks and Greenspaces Department.
G. The Council acknowledges the modification to the list will not increase Metro's
financial obligations under the existing intergovernmental agreement.
PASSED: This rPo t d day of ,1999.
yor-City of Tigard
ATTEST:
(�-dlPil fn.l (.R A
City Recorder-City of Tigard
i_\citywide\ s4p=wp=1GA.am=d.dw
4
0
H
ti
H
RESOLUTION NO.99-4q
Page 2
® Exhibit "A"
v
City of Tigard
Greenspace Project List and Budget
Project Old$ New
Tualatin River Tracts 25,000 25,000
Activity: land acquisition
Status: complete
Fern Street Forest Parcel 125,000 125,000
Activity: land acquisition
Status: complete
Bull Mountain Forest Area(Cache Creek) 279,000[+66,025] 345,025
Activity: land acquisition
Status: complete
Tualatin Fiver Pedestrian Bridge Design 50,000[-43,500] 6,500
Activity: preliminary design
Status: complete
Fanno Creek Trail Corridor 279,000[-22,525] 256,475
Activity: land acquisition
trail construction
natural area restoration
Status: on-going
1
Total 758,000 758,000
i
i
/II rt_/A./d nc,noCL,135•_1�9