CITY OF TIGARD
•
OREGON
April 4, 1995 =
•
-
John Howell
8457 N.E. Going Street
Portland, OR 97220
Project: Foundation Engineering Plan Check #3 -29C
Subject: Building Plan Review (1991 UBC with Oregon Amendments)
Dear Mr. Howell:
The plans for this project were reviewed for conformity with applicable codes.
The following comments are noted:
aS PV) \ ". Existing toilet room number 7 shall be constructed and made to comply with
all of the accessibility requirements of CH. 31. Plans do not show full
compliance with the code.
2. Provide not less than one -hour materials on the under side of the stair
stringers and walls of the proposed storage area under the stairs (Section
3306(1).
1 ) 3. The relocation of the existing plumbing vent shall comply with the
plumbing code. Plumbing permit is required.
4. The structural stability of the proposed new guardrail shall withstand not
less than 50 lb. /lt. applied at right angles to the top of the rail.
Provide detail.
Please make the necessary changes to the plans and submit 3 revised sets (4 floor
plans) for completion of the plan review process.
Sincere ,
•avi• Scott, P.E.
Building Official
DS:wh