10/22/02
Avi Pradhan
921 S.W Morrison
Portland, OR 97205
Re: Brahma Premananda Ashram Addition, at 11505 S.W Tigard Or. 97223
Dear Sir,
We have received your letter dated October 17 2002, Addressing the number of
the guestrooms and anticipated occupant load so as we may have a better
understanding of proper occupancy classification for your project.
As per your letter, We have placed the occupant load of 10 or less for your
facility. It will be reviewed as a congregate residence with a limited occupant load
of 10, Thus you will not be required to meet all of the requirements for a R1
(apartment or hotel) but will be reviewed as a R3 (large single family residents).
If this assumption is incorrect, Please contact this office as soon as possible.
Si, c'erel;
v
) . .
D.41 J nes
Senior Plans Examiner
C. File
Via facsimile
13125 SW Hall Blvd., Tigard, OR 97223 (503) 639-4171 TDD (503) 684 -2772
/Vag -o� 4,
AVI PRADHAN - ARCHITECTURE
OCTOBER 17TH 2002
MR. DARYL JONES
SENIOR PLAN EXAMINER
CITY OF TIGARD,
13125 SW HALL BLVD. FAX (503) 624 -3681
TIGARD OR 97223
RE: BRAHMA PREMANANDA ASHRAM ADDITION, AT 11505 SW. HALL BLVD.,
TIGARD OR 97223.
DEAR SIR:
I WOULD LIKE TO BRING THIS TO YOUR ATTENTION THAT PLANS SHOW
THAT THERE ARE 8 SINGLE GUEST ROOMS ARE BEING ADDED TO THE
EXISTING HOUSE, WHICH HAS 2 BEDROOMS. CONSIDERING THIS
ARRANGEMENT, THERE WILL TO BE MORE THAN 10 PERSONS STAYING AT
THE FACILITY, WHICH IS MORE LIKE A LARGE HOUSE THAN ANY
COMMERCIAL LODGING FACILITY.
I REQUEST YOU TO REVIEW THE PLANS CONSIDERING THE ABOVE INFO
AND ISSUE THE BUILDING PERMIT.
THANK YOU.
S I NCEREL -.
;lid "RADHA
ARCHITECT.
x
A HARD COPY OF THIS LETTER IS MAILED TO YOUR OFFICE.
A R C H I T E C T
Arizona • California • Connecticut
New York • New Jersey • North Carolina • Oregon
921 S.W. Morrison • Suite 415
Portland, Oregon 97205
Phone: (503) 222 -2140 • Fax: (503) 222 -4942
133, o2- h7
AVI P RA D H A N • A R C H I T E C T U R E
APRIL 4TH 2002
MR. DARYL JONES
SENIOR PLAN EXAMINER
CITY OF TIGARD,
13125 SW. HALL BLVD.
TIGARD, OR 97223
RE: BUILDING PERMIT AT 11505 SW. HALL BLVD, TIGARD, OR 97223
FOR BRAHMA PREMANANDA TEMPLE.
DEAR SIR,
HEREWITH I AM SUBMITTING 3 COPIES OF REVISED DRAWINGS FOR YOUR
REVIEW. ITEMS SHOWN ON YOUR REVIEW SHEETS ARE CORRECTED AS
FOLLOWS.
1. PLEASE NOTE THAT NOTES ARE ADDED ON A -14 SHOWING UL
NUMBERS FOR 1HR. CONSTRUCTION. FRONT PORCH STRUCTURAL
COLUMNS, BEAMS AND CEILING WILL MEET 1HR RATING, ALSO
SPRINKLER HEADS ARE ADDED IN THIS AREA.
2. ACCESS CLEARANCE OF 18" IS ADDED TO EXIT DOORS,
SHEETS A -02, A -03.
3. FIRE EXTINGUISHERS SHOWN SHEETS A -02, A -03. (3) LOWER LEVEL,
(2) UPPER LEVEL.
4. PLUMBING FIXTURES SHOWN ON THE PLANS ARE ADEQUATE FOR THE
OCCUPANT LOAD. PLEASE SEE THE SEPARATE LETTER.
5. CERAMIC TILE FINISH 6'-O" IS ADDED TO REST ROOM WALLS ON
SHEET A -09.
6. A THREE COMPARTMENT SINK IS SHOWN IN THE KITCHEN, THIS SHOULD
PROVIDE REQUIRED HAND WASH. THE DISHWASHER WILL BE A SMALL
RESIDENTIAL TYPE, IT WILL NOT REQUIRE STEAM HOOD.
7. FOOTING DRAINS ARE SHOWN ON SHEET A -07, A -08 & A -13.
8. & 9. DRAWINGS ARE CORRECTED TO SHOW ENGINEERS CALCS.
10. & 11. DETAILS ARE ADDED ON SHEET S -6 SHOWING THESE ITEMS.
12. RETAINING WALL DETAILS ARE CORRECTED TO COMPLY WITH
PAGE 16 & 17 OF STRUCTURAL CALCS. RECEvED
A R C H I T E C T 7
Arizona • California • Connecticut
APR - R 7f
New fork •New Jersey •North Carolina • Oregon CITY UT HUARD
BUILDTh G .DIISION
921 S.W. Morrison • Suite 415
Portland, Oregon 97205
Phone: (503) 222 -2140 • Fax: (503) 222 -4942
13. WATERPROOFING FOR BELOW GRADE WALLS WILL BE 'MAR FLEX 500',
'CARLISLE CCW -701' OR APPROVED EQUAL.
14. & 15. KITCHEN GREASE DUCT ENCLOSURE IS 2HR RATED SEE A -02,
3/Al2 & A14- WALL TYPE 5, DUCT MATERIAL BLACK IRON 14G..
16. CUT SHEETS FOR HVAC UNITES ARE ENCLOSED.
17. GAS RISER DIAGRAM IS AND PIPE SIZES ARE SHOWN ON M -03.
18., 19.,& 20. SEE REVISED KITCHEN LAY -OUT, AND REVISED P -05
FOR THESE ITEMS.
21. & 22. ROOF DRAIN SIZE AND LOCATION IS COORDINATED WITH CIVIL
DRAWINGS AND 4 SCUPPER OVERFLOWS ARE SHOWN ON SHEET A- 04,P01.
23. GREASE INTERCEPTOR IS RELOCATED OUT SIDE THE BUILDING.
SEE P -01 & P -05.
24. BOOSTER PUMP AND BACK FLOW PREVENTER IS ELIMINATED. A 2 V
WATER SERVICE IS SHOWN.
25. EJECTOR PUMP AND BASI IS ELIMINATED. SANITARY WASTE IS
WITH GRAVITY FEED 6" , TO SAN. MANHOLE.
26. THE FIRE PUMP BOOSTER IS ELIMINATED.
27. FDC LOCATION WILL BE COORDINATED BY SPRINKLER CONTRACTOR
AS SHOWN ON THE CIVIL DRAWINGS.
28. ENTRANCE PORCH IS RE DESIGNED FOR 1HR FIRE RATING AND
SPRINKLER HEADS ARE ADDED SEE FP -2.
29. & 31. SPRINKLER CONTRACTOR WILL SUBMIT SYSTEM CALCS.
30. THE GREASE HOOD HAS INTEGRATED FIRE SUPRESSION SYSTEM. SEE
KITCHEN EQUIPMENT SPECS.
32. AUDIO /VISUAL ALARM IS PROVIDED IN BOTH TOILETS. SEE E -07.
33. COMPLIED ON SHEET E -07.
34. THE CUT SHEETS FOR FIRE ALARM SYSTEMS WILL BE SUBMITTED
FOR APPROVAL BY SPRINKLER /FIRE ALARM CONTRACTOR.
PLEASE REVIEW THE DRAWINGS AT YOUR EARLIEST, TEMPLE BUILDING
COMMITTEE WOULD LIKE TO HAVE GROUND BRAKING ON JUNE 8TH 2002.
THANK YOU.
SINCE LY,
A J P' ADHAN ' ":'.-
P ? -�
ne , ,, ,,
j 1 1 I
CITY OF TIG�
January 15, 2002 OREG
Victor M Nobleza
fige6 -1-1-5 Hall Blvd
Tigard, Or 97223
RE: Brahma Premananda Temple application
The City of Tigard Building Division has reviewed the submitted building plans for the above
referenced address in accordance with the Oregon Structural Specialty Code (OSSC), 1998
edition and the Uniform Fire Code, 1997 edition as amended by Tualatin Valley Fire & Rescue.
The following items need to be addressed and are not in compliance with the above mentioned
Codes:
A01 -A13
1) A2.1 Occupancy's are required to meet V l hr minimum construction. Current
plans don't show enough detail to be in compliance with this requirement.
Please provide additional details to assure code compliance of all walls, roof
ceiling, and entry canopy, system meet this level of protection.
2) Building is required to be in compliance with ADA. Doors LD02, LD06,
UDO3 and UDO4 need the minimum access clearances along the sides of 18 ".
3) Fire extinguishers are required 1/3000 sqft. minimum of two per floor.
Currently only one per floor is shown on plans.
4) Plans are not in compliance with Table 29 -a for the minimum of plumbing
fixtures. Provide additional details showing fixture heights and spacing in
compliance with ADA.
5) Sanitation: Walls within two feet of the front and sides of urinals and water
closets shall have a smooth hard non absorbent surface. To a height of not less
than 48 inches.
6) Note: Kitchen shows only one pair of sinks, Please check with the health
department for the minimum amount of sinks required.
7) Footing drains are shown on the civil plans and not referenced on the details
or Structural sheets.
S1-S6
8) Upper level framing S3: Beam size along grid line 2 is different than what is
shown on the engineering provided please correct.
9) Footing plan 51: pier footings at B6 & F6. Specifications need to be
transferred to the plans from the Engineers calc's to the footing schedule.
13125 SW Hall Blvd., Tigard, OR 97223 (503) 639 -4171 TDD (503) 684 -2772
10) Footing plans S 1: Column details for grid line 2 are '/2 on the plans and the
balance is in the Engineers calc's. Please incorporate into the plans all
specifications, details and crossections.
11) Please detail the connections between different wall types and their locations.
Plans call for several basement wall types and retaining walls that intersect.
All of these walls have different rebar requirements, footing details, and
surfacing materials.
12) S2 details differ from engineering on pages 16 &17 please specify which
detail is applicable and where.
13) All below grade walls are required to be waterproofed please specify product
and application method.
M1 -M4
14) Kitchen Grease ducts that penetrate the ceilings; floors, roofs or walls shall be
in closed with in a rated shaft. And shown on the architectural sheets.
15) Grease ducts shall be a minimum of 16gauge steel.
16) Provide cut sheets on all HVAC equipment and weight loads. Engineer shall
review all HVAC loads for seismic and static loading on the structure.
17) M3 sheet indicates the use of gas for the roof top units. Please provide a gas
line drawing showing all connected loads in BTU's, size of pipe, gas pressure,
and total run.
18) Commercial dishwashers require a class 2 hood for steam.
Pl -P5
19) Food prep sinks shall be indirectly connected to the drainage system by means
of an airgap or airbreak into an approved receptor.
20) Receptors shall be approved for the use and purpose and shall have shape and
capacity to prevent splashing and flooding. Receptors shall be readily
accessible for inspection and cleaning.
21) Rain drains and Storm drains, tie -in locations do not match civil drawings for
connection points and pipe size.
22) Plans show rain drains connected to overflow drains using the same riser,
UPC 1105.4 states overflow drains shall be piped to an approved point of
discharge and shall be independent of any other piping system.
23) Plans show a grease interceptor, located in lounge: interceptors shall be
readily accessible for servicing and periodic removal of accumulated grease,
scum, oil, or other floating substances.
24) Civil plans show a 2" domestic water line connected to a city main. City main
pressure is recorded at 107 psi (static) and 98 (residual). Plumbing plans show
a 3" domestic riser, reduced pressure back flow preventer and Booster pumps?
25) Plans show a sewage ejector pump and basin, Civil plans show the sewer
lateral at 213.65 approximately 40 "inches below finish floor elevation. Pump
may not be required.
Fp l -FP -3
26) Room LL 11 has several space conflicts between these drawings and others.
Clearances, working spaces, power panels, water riser location, sprinkler riser
location, and fire pump and booster pumps may not be required due to water
pressure at this location.
27) FDC is not allowed to be on the side of the structure see civil drawings for
proper location. Also the Ashram will be required to have sprinklers and a
separate FDC located with -in 70 feet of a fire hydrant.
28) Main entrance, canopy, is required to be protected by sprinkler system.
29) Sprinkler system should be differed submittal and designed by a sprinkler
contractor.
30) Type 1 grease hoods require fire suppression systems.
31) Submit sprinkler calculations and cut sheets.
Fire Alarms
32) Plans show visual only devices in the toilet room's UFC sec 1007.3.3.3.4
states alarms in toilet rooms shall be both visual and audible.
33) Building is being provided with access control devices. Note all door contacts
shall fail in the open posisition upon activation of the smoke or fire detection
system.
34) Provide all cut sheets on the devices in the system.
City of Tigard Engineering Comments:
Condition #11 (ODOT ROW dedication for Hall)
Condition #14 (Pay fee in -lieu of undergrounding = $880.00
Due to the items identified as noted above the plan review has been terminated, until the items
have been properly addressed. In no way should this partial review be considered as a complete
review.
Please submit revised plans showing compliance with codes.
If you have any questions regarding this review, please contact me at (503) 369 -4171 ext. 392.
Si ,
D 1 ones
lan Examiner
c.
Hap Watkins, Supervising Inspector
Building Inspectors
File