Specifications 'fCE COPY
Il
1 PROJECT MANUAL
I FOR
I
I
1 T/GARD HIGH SCHOOL
ADDITION / REMODEL,
1 PHASE II
I v Eo
%i,
I May 1
' [ igard - Tualatin ._ School District o -c\ GAR
, 01
6960 S andburg Road v, p1NG \�\S
6
Tigard, Oregon 97223
I
I May 3, 2004
I
I
II _ j City of Tigard
1
i Approved Plans ( ^22
gy f5P Date
o 4.t - 000/C
D U L L O L S O N W E K E i„ f. , UAHA A
c ;b \<.. iurl l`�
J
I.
PROJECT MANUAL
FOR:
I TIGARD HIGH SCHOOL
ADDITION / REMODEL
PHASE II
for
(OWNER)
Tigard - Tualatin School District
6960 Sandburg Road
Tigard, Oregon 97223
(ARCHITECT)
Dull Olson Weekes Architects, Inc.
319 SW Washington St., No. 200
I . Portland, OR 97204
PH: 226-6950 / FAX: 273-9192
MF,D
Qt. 2282
: 1 1"
•
4 ,)
44 : OF CO
May 3, 2004
TABLE OF CONTENTS
I DIVISION 0 - BIDDING REQUIREMENTS, CONTRACT FORMS, AND CONDITIONS OF THE CONTRACT
By General Contractor
DIVISION 1 GENERAL REQUIREMENTS
•
By General Contractor
I DIVISION 2 - SITEWORK
Section 02010 Sitework General Requirements
I 02060 Building Demolition 5
02200 Site Demolition 4
02315 Earthwork 4
I 02316 Trenching, Backfilling and Compaction 8
02350 Geotextile Fabric 7
02370 SIope Protection and Erosion Control 5 5
02510 Exterior Water Distribution 6
I 02620 • Foundation Drainage 6
02630 Storm Drainage System 9
02740 Asphalt Concrete Paving
I 02750 Site Concrete
02800 Site Furnishings 12
2
02810 Irrigation
02920 Soil Preparation 8
I
02930 Lawns 4
02950 Plant Material
02990 Landscape Warranty 4
pm .
2
DIVISION 3 - CONCRETE
•
I Section 03100 Concrete Formwork 5
03201 Reinforcing and Concrete 10
03600 Grout
03930 Composite Fiber Reinforcement 4
6
DIVISION 4 - MASONRY • I Section 04100 Mortar and Masonry Grout - 4
04320 Veneer Masonry System 7
DIVISION 5 - METALS
I
Section 05120 Structural Steel
05210 Steel Joists 6
I 05310 Metal Deck 6
05400 Cold - Formed Metal Framing 4
05500 , Metal Fabrications 5
05515 Metal Ladders 11
1 05800 Expansion Control 2
3
I
I 02054 TIGARD HIGH SCHOOL ADDITION / REMODEL PHASE I.1 MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 231 TOC -I
Printed 5/3/04
I .
I TABLE OF CONTENTS
I DIVISION 6 - WOOD & PLASTIC
Section 061 12 Framing and Sheathing 6
06181 Glue - Laminated Structural Units 4
I 06200 Finish. Carpentry 5
06410 Custom Casework
10
I DIVISION 7 - THERMAL & MOISTURE PROTECTION
Section 07130 Bentonite Waterproofing
3
07160 Dampproofing
I 3
07212 Board Insulation 2
07213 Batt and Blanket Insulation
07250 Fireproofing
7
I 07260 Intumescent Mastic Fireproofing 4
07270 Firestopping 6
07420 Prefinished Composite Building Panels 4
I 07530 Membrane Roofing
07533 Single Ply Membrane Roofing 12
7
07611 Preformed Sheet Metal Roofing 7
07620 Sheet Metal Flashing and Trim 5
I 07631 Gutters and Downspouts 4
07710 Manufactured Roof Specialties _ 2
07820 Aluminum Framed Skylights 6
I 07900 Joint Sealants 8
DIVISION 8 - DOORS & WINDOWS
Section 08000 Door and Relite Schedule 21
IN
08110 Metal Doors and Frames 5
0821 - 0 Wood Doors • I S
08255 Integrated Metal Door Assemblies 4
08305 Access Doors
08331 Coiling Doors
I 08380 Acoustic Door and Relite Assemblies 4
08410 Aluminum Entrances and Storefront 7 • 08700 Door Hardware 12
08800 Glazing
I 7
DIVISION 9 - FINISHES
I Section 09001 Interior Finish Legend
09100 Metal Support Systems 3
09120 Ceiling Suspension System.
3
09220 Portland Cement Plaster (Stucco) 8
09260 Gypsum Board Systems 5
09311 Ceramic Floor Tile 5
I 09321 Ceramic Wall Tile 4
09511 Suspended Acoustical Ceilings 5
09512 Adhesive Applied Acoustical Ceilings
09520 Acoustical Wall Panels
3
3
I 09605 Concrete Floor Vapor Emission Sealer 3
09650 Resilient Flooring 5
09680 Carpeting
5
I 02054 TIGARD HIGH SCHOOL ADDITION / REMODEL - PHASE II_
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J TOC -2
I Primed 5 /3/04
•
I TABLE OF CONTENTS
I 09830 Elastomeric Coatings
09860 Graffiti Resistant Coatings 4
09900 Painting 3
I 09950 Wall Coverings
9
3
DIVISION 10 - SPECIALTIES
I Section 10100 Visual Display Boards
10120 Tacksurfaces 4
3
10170 Plastic Toilet Compartments
I 10251 Clocks • 3
10400 Identifying Devices 8
10508 Metal Lockers
10522 Fire Protection Specialties 4
I
3
10650 Operable Partitions
10800 Toilet and Bath Accessories 4
4
I DIVISION 11 - EQUIPMENT
Section 11130 Audio — Visual Equipment
I 11600 Fume 1 - foods
3
DIVISION 12 - FURNISHINGS
I Section 12345 Laboratory Casework
12381 Music Specialty Casework
4
12512 Horizontal Louver Blinds
3
ill 12693 Entry Mats
0
DIVISION 13 - SPECIAL CONSTRUCTION
I Not Used.
DIVISION 14 - CONVEYING SYSTEMS
I 14245. Hydraulic Passenger Elevator 10
DIVISION IS - MECHANICAL
I Section .
15050 Basic Mechanical Materials and Methods
1
15060 Pipes and Pipe Fittings 1 8
I 15090 Supports and Anchors 8
15100 Valves 4
15240 Mechanical Sound and Vibration Control 2
15250 Mechanical Insulation 2
I
3
15300 Fire .Protection
15400 Plumbing 4
15500 Heating, Ventilation and Air Conditioning 6
I 15750 Heat Transfer i
15850 Air Handling 6
15875 UVC Fixtures for HVAC Equipment 2
I 15880 Air Distribution 6
15900 Controls
g Adjusting, 40
15990 Testing, ] �, and Balancing 6
I 02054 TIGARD HIGH SCHOOL ADDITION / REMODEL - PHASE
II
MAY 04
TIGARD — TUALATIN SCHOOL DISTRICT 201' TOC-3
I Printed 5/3/04
TABLE OF CONTENTS
' DIVISION 16 - ELECTRICAL
Section 16050 Basic Electrical Materials and Methods 8
16110 Conduits, Raceways and Fittings 4
16120 Conductors
•
3
16130 Boxes 2
16140 Wiring Devices 2
16170 Circuits and Motor Disconnects 2
16180 Elevator Power Module Switch
2
' 16190 Supporting Devices 3
1.6195 Electrical Identification 2
16425 Switchboards 2
16450 Grounding 2
' 16460 Energy Efficient Dry Type Transformers 2
16470 Panelboards 2
16475 Overcurrent Protective Devices 2
16500 Lighting Fixtures and Lamps
16723 Fire Alarm and Detection System 3 3
16730 Intercom and Paging System
3
16735 GPS Wireless Clock System 4
16740 Data, Telephone, and CA.TV Systems
16900 Lighting Controls
6
END OF TABLE OF CONTENTS
1
I
1
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL - PHASE 11
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 231 TOC -4
Printed 5 /3/04
1
SECTION 02010
SITEWORK GENERAL REQUIREMENTS
'
PART 1 GENERAL
' 1.1 GENERAL REQUIREMENTS
A. Drawings and general provisions of the Contract, including General and other Conditions and
' Division 1 — General Requirements sections, apply to the work specified in this section.
1.2 WORK INCLUDED
A. It is the intent of these specifications and the accompanying drawings to describe complete and
functional site construction and utility systems. Furnish and install all material and equipment in
accordance with these documents. Include all incidental items and work not specifically shown
t or specified but required by good practice in a complete system.
B. The drawings are diagrammatic and are based on existing information. They should be
' followed as closely as possible, yet are not intended to show every item in its exact location or
all the details of the equipment. Where required by job -site conditions, relocate and provide
fittings, etc., as required. Any deviations from the drawings must be approved by the owner's
' representative.
1.3 RELATED WORK
A. The special conditions of this specification apply to the work specified in Sitework Division 2
that encompasses Sections 02010 through 02930.
B. Refer to Division 1 for the General Requirements of the contract.
1.4 REFERENCES
' A. American Concrete Institute (ACI)
B. American Society of Mechanical Engineers (ASME) .
' C. American Public Works Associate (APWA)
' D. American Associate of State Highway and Transportation Officials (AASHTO)
E. American Society for Testing and Materials (ASTM)
F. American Concrete Pipe Associate (ACPA)
G. Occupational Safety and Health Act (OSHA)
H. Oregon Department of Transportation (ODOT)
I. California Department of Transportation (CALTRANS)
J. National Sanitation Foundation (NSF)
' K. Washington Department of Transportation (WDOT)
L. Uni-Bell Plastic Pipe Associate (UNI)
' M. Uniform Plumbing Code (UPC)
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02010 -1
Printed 04 /20/04
SECTION 02010 I
SITEWORK GENERAL REQUIREMENTS
N. Uniform Building Code (UBC)
1
O. Uniform Fire Code (UFC) '
P. American Water Works Association (AWWA)
1.5 DEFINITIONS ,
A. Not used in this section.
1.6 SUBMITTALS
A. The submittals shall be properly bound with sections clearly identified. Submittals for each
section need to be complete. Partial submittals for a section shall be returned unreviewed.
B. The submittals shall contain performance data and technical specifications on all materials and
equipment to be used on the project.
C. Shop drawings shall be included with the submittals where specifically requested in the
specifications, where necessary to determine clearance, where the contractor proposes alternate
equipment or material arrangements, and when requested by the owner.
D. All shop drawings must be reviewed and approved by the general contractor prior to being
submitted to the engineer. Any shop drawings submitted without contractor's approval stamp
shall be rejected.
E. Review of submittals or shop drawings by the owner and engineer does not relieve the
contractor from the requirements of the contract documents unless specific approval has been
requested for a given deviation.
F. By submitting, the contractor /supplier certifies that the materials or equipment proposed is
satisfactory for the application intended.
G. Fabrication of materials and installation of equipment is not authorized prior to approval of shop
drawings and vendor data.
H. Alternate items installed without the owner's approval shall be replaced with the specified '
materials at the contractor's expense. The contractor assumes full responsibility that alternate
items or procedures will meet the job requirements and is responsible for cost of redesign and of
modifications to this and other parties' work caused by alternate items furnished under work of
this section.
1.7 QUALITY ASSURANCE
A. For work on this project, comply with the applicable and/or specifically referred standards and
codes published herein. Where any of the codes and standards are at variance with the drawings
and specifications, the more stringent requirements shall take precedence. ,
B. Contractor shall be skilled in his trade and is solely responsible for compliance with health and
safety regulations, performing work in a safe and competent manner, and in installation
procedures required for the work outlined in these documents.
C. Maintain the highest standards of workmanship throughout the project. Utilize workers only in
their areas of skill, expertise, qualifications and experience. Under no c provide ,
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD- TUALATIN SCHOOL DISTRICT 23J 02010 -2
Printed 04/20/04
' SECTION 02010
SITEWORK GENERAL REQUIREMENTS
' any on the job training without direct supervision and thorough review of the quality of the work
step by step.
' D. Inspect all material and equipment upon arrival at the site and return or refmish any which is not
in new condition. All refinishing is subject to owner's approval.
' E. All equipment, valves, and instruments shall be installed in such a way that all components
requiring operation or maintenance are readily accessible.
' F. Soils engineer or an independent testing laboratory will be retained by the owner to observe
performance of work in connection with excavating, trenching, filling, backfilling, and grading.
G. Readjust all work performed that does not meet technical or design requirements, but make no
deviations from the contract documents without specific and written approval from the owner.
1.8 DELIVERY, STORAGE AND HANDLING
A. The equipment and materials specified herein shall be delivered f.o.b. factory with freight
allowed to the jobsite and include full -value insurance coverage while in transit.
' B. Contractor shall inspect the equipment and materials for damage upon delivery and shall
immediately report damage to owner and replace or repair such damage to the satisfaction of
owner.
' C. Handle materials as recommended by the manufacturer, with approved equipment in a manner
that will prevent damage.
D. Store materials in a secure area designated by owner off the ground and in an orderly manner
that will prevent damage.
•
' E. Store materials subject to temperature or humidity damage in a controlled environment as
recommended by the manufacturer and approved by owner. •
F. Dangerous and highly combustible materials shall be packaged, shipped, and stored in
compliance with Federal, OSHA, State, and local safety and fire codes as approved.
' 1.9 SCHEDULING AND SEQUENCING
A. Not used in this section.
PART 2 PRODUCTS
2.1 Not used in this section.
' PART 3 EXECUTION
3.1 COORDINATION
' A. Contractor shall be responsible for continual coordination of the work with other trades so as to
avoid conflicts in installation. Cooperate with other trades to assure that construction proceeds
' in an orderly and timely manner.
B. The contractor shall be familiar with the site configuration and constraints. Methods of
construction issues such as clearances from existing trees, existing utilities, and site features are
the responsibility of the contractor.
' 02034
APR 04 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
TIGARD- TUALATIN SCHOOL DISTRICT 23J 02010 -3
Primed 04/20/04
SECTION 02010 I
SITEWORK GENERAL REQUIREMENTS
3.2 MATERIALS AND WORKMANSHIP
A. Furnish all materials and equipment in new condition, free from defects and of size, materials,
make, type and quality specified. Installation shall be in a neat and workmanlike manner.
B. When two or more items of the same kind, type or class are required, use items of a single
manufacturer.
C. Workmanship shall be first class throughout and performed only by competent and experienced 111 workmen in a manner satisfactory to the project coordinator and/or engineer. Constant
supervision of the work, either by the contractor or his competent representative, shall be
maintained. Work insulated or concealed before being inspected and approved shall be opened
and uncovered upon request at the contractor's expense. '
3.3 DEMOLITION
A. General: The installation of work under this contract includes removal of certain existing site I
paving, structures, utilities and vegetation. The extent of this work has been noted on the
drawings; however, it is probable that relatively minor additional removal or relocation of
various site features may be necessary in order to install new work as shown. The contractor
shall allow for and reflect in his bid the cost of this work, based on examination of present
conditions.
3.4 PROTECTION
A. Protect all work, material and equipment from loss or damage until project is accepted by
the owner.
B. As the work progresses, keep all equipment covered and cap all piping that may temporarily be
left unconnected. '
C. Notify all other trades of any required precautions necessary to protect the work and personnel.
3.5 INSPECTION '
A. Contractor shall inspect his work to ensure the installation and workmanship are in accordance
with acceptable industry standards and applicable codes for the work being done and with these
specifications.
B. All materials, equipment, and workmanship shall be subject to inspection at any time by owner.
Correct any work, materials, or equipment not in accordance with these contract documents or
found to be deficient or defective.
3.6 CLEANING ,
A. Maintain premises and public properties free from accumulations of waste, debris and rubbish
during construction. '
3.7 START -UP
A. Contractor shall be responsible for proper operation of all systems, minor subsystems, and ,
services provided under this section. He shall coordinate start-up procedures, calibration and
system check -out with all subcontractors involved. Any system operational problems shall be
diagnosed; all correctional procedures shall be initiated with the various subcontractors as ,
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02010 -4
Printed 04/20/04
SECTION 02010
SITEWORK GENERAL REQUIREMENTS
' required to bring the system into compliance with the design, and the problem then shall be
rechecked to verify that the system operates normally. Any knowledge of remaining difficulties
' shall be brought to the attention of the owner.
3.8 CUTTING AND PATCHING
' A. Cut work as required for installation and patch to match original conditions as directed and
approved by owner. Prior to cutting any existing work, locate all concealed utilities to eliminate
any possible service interruption or damage.
1 3.9 CONNECTION TO EXISTING SERVICES
A. Arrange time of connection with owner's representative. Hold duration of service outage as
short as possible. All existing utilities and tie -in points should be considered active utilities
unless otherwise indicated.
B. In general, site utilities shall terminate 5' from the building line. It is the contractor.'s
responsibility, however, to connect to existing stubs from buildings where indicated and to
coordinate the utility connections.
END OF SECTION
1
1
I
1
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02010 -5
Printed 04 /20/04
SECTION 02060
I BUILDING DEMOLITION
PART 1 GENERAL
I 1.01 GENERAL REQUIREMENTS
I A. Drawings and g eneral p rovisions o f t he C ontract, in cluding Ge neral a nd o ther C onditions and
Division 1 - General Requirements sections, apply to the work specified in this Section.
1.02 WORK INCLUDED
I
A. Demolition of designated portions and/or entire structures, including the complete removal of
foundations.
I B. Minor Interior Demolition for remodeling of existing structures to remain.
I C. Backfilling, to subgrade, where foundations and utilities are removed.
D. Disconnect, cap, and remove and identify utilities.
E. Removal of materials from site.
1.03 RELATED WORK
I A. Section 01010 - Summary of Work: - Precautions Concerning Asbestos.
01 ) B. Section 01500 — Construction Facilities and Temporary Controls: Barricades and landscape
protection.
C. Section 01500 — Construction Facilities and Temporary Controls: Dust control.
I D. Section 01500 — Construction Facilities and Temporary Controls: Cleaning during construction.
I E. Section 01700 - Contract Closeout: Project record documents.
1.04 SUBMITTALS
I A. Submit demolition and removal procedures and schedule under provisions of Section 01300.
B. Permits and notices authorizing demolition.
I C. Permit for transport and disposal of debris.
I D. Submit record documents under provisions of Section 01300 and 01700.
1.05 EXISTING CONDITIONS
I A. Conduct demolition to minimize interference with adjacent structures and school activities.
B. Provide, protect, and maintain temporary barriers and security devices.
I t. Arrange and pay for disconnecting, removing, and capping utility services within areas of
demolition. Disconnect and stub off.
I
I 02054 TIGARD HIGH SCHOOL ADDITION / REMODEL - PHASE II
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02060 -1
Printed 5/3/04
SECTION 02060 I
BUILDING DEMOLITION
I
D. Conduct operations with minimum interference to public or private thoroughfares. Maintain
protected egress and access at all times.
I
E. Do not close or obstruct roadways or sidewalks without permits.
F. Maintain mechanical and electrical services to Owner occupied areas. Advise Owner in a timely
I
manner (minimum of 24 hours in advance) when u tilities, p lumbing, H VAC, a nd/or e lectrical
service is to be interrupted.
G. Provide, erect and maintain protected pedestrian egress at all times. I
1.06 PRE- DEMOLITION MEETING
I
A. Contractor to schedule meeting minimum of seven (7) days prior to start of demolition.
B. Attendance: Contractor, demolition superintendent, Architect and District representative.
I
PART 2 PRODUCTS
I
Not Used.
I
PART 3 EXECUTION
') 3.01 PREPARATION
IN
A. Prevent movement or settlement of adjacent structures. Provide bracing and shoring as needed.
B. Erect and maintain waterproof closures for exterior openings. Maintain in a waterproof condition I
for the duration of time all such construction is exposed to the weather.
C. Protect existing structures which are not to be demolished.
I
D. Disconnect, remove, and cap designated utility lines within demolition areas.
E. Erect and maintain temporary partitions to prevent spread of dust, fumes and smoke, to other parts
of the existing building.
F. Protect existing items which are not indicated to be altered. I
G. Mark location of disconnected utilities. Identify utility, indicate capping locations and distance
from finish floor on Project Record Documents.
H. The Owner will within seven days notice from Contractor transfer any undesignated and
freestanding furnishings and equipment out of the Work area. I
3.02 EXECUTION
A. Noise Control: Maintain a reasonable degree of quietness throughout progress of the Work so as ,
to not disturb classes in session in adjoining rooms or buildings or annoy residents of the
) neighborhood. Rotary machines and tools must operate below OSHA noise and fume standards.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL - PHASE II
I MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02060 -2
Printed 5/3/04
I SECTION 02060
BUILDING DEMOLITION
Concrete sawing and jack hammering shall be performed after regular school hours up to 9:00 p.m
I (confirm with applicable city regulatory agencies).
B. Demolish indicated structures and appurtenances in an orderly and careful manner.
I C. Stage demolition as necessary to meet Owners access /egress and mechanical /electrical
requirements.
I D. Cease operations and notify Architect immediately if adjacent structures appear to be endangered.
Do not resume operations until corrective measures have been taken.
I E. The Contractor shall employ a demolition foreman knowledgeable in identification of asbestos
containing materials and shall instruct workmen at the Site to be on the look -out for materials that
may contain asbestos fibers and to not disturb or attempt to remove such materials.
I F. The Contractor shall carefully demolish walls, ceilings, etc., which contain concealed space to
allow visual inspection for any material which may be suspect of containing asbestos fibers prior to
total scheduled demolition.
I G. Should the Contractor discover any materials which he suspects of containing asbestos fibers, the
Contractor shall stop working immediately and shall not carry on any activities in that area that
I could disturb such materials. The School District will evaluate the circumstances and instruct the
Contractor on how and when to proceed with the Work.
H. The Contractor shall take every precaution to prevent the spread of asbestos fibers throughout the
Work under this Contract. The Contractor shall not break up and/or attempt to remove or actually
remove from the Work area any material suspected of containing asbestos fibers (i.e., pipe
insulation, sprayed on fireproofing).
I I. Asbestos fibers carried around the Work area or into the existing structure due to the Contractor's
carelessness or failure to follow the procedures herein shall, at the Contractor's expense, be cleaned
I up in accordance with E.P.A. requirements.
J. Items requiring demolition and removal include, but are not limited to, the following:
1. Exterior and interior walls.
2. Metal flashing and accessories.
3. Roofing including membrane, flashings, and decking.
4. Doors and Frames.
I 5. Window framework and glazing.
6. Casework.
7. Asphalt paving.
I 8. Flooring Finishes (Tile and other materials containing asbestos to be removed by
District.)
9. Mechanical equipment.
10. Plumbing fixtures.
I 11. Electrical equipment.
K. Salvaged Items:
I 1. Remove materials to be re- installed or retained in manner to prevent damage. Store and
protect under provisions of Section 01600.
2. Coordinate with Owner for lists of items to be salvaged.
I
I 02054 TIGARD HIGH SCHOOL ADDITION / REMODEL - PHASE II
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02060 -3
Printed 5/3/04
SECTION 02060
BUILDING DEMOLITION
L. Remove materials to be re- installed or retained in manner to prevent damage. Store and protect
under provisions of Section 01600. '
M. Demolition Drawings are diagrammatic and are intended to assist the Contractor in establishing the
general scope of work. Include all demolition work required to complete the project whether or
not specifically shown on demolition Drawings.
N. Except where noted otherwise, immediately remove demolished material from site.
O. Remove and promptly dispose of contaminated, vermin infested, or dangerous materials
encountered.
P. Do not burn or bury materials on site.
Q. Remove foundation walls and footings completely.
R. Remove designated concrete slabs on grade and asphaltic paving.
S. Keep work sprinkled to minimize dust. Provide hoses and water main or hydrant connections for
this purpose as approved by governing authority.
T. Backfill areas excavated as a result of demolition as required to subgrade. Use backfill material
specified in Division 2.
U. Rough grade and compact areas affected by demolition to subgrade maintain site grades and
contours.
V. Remove demolished materials from site as work progresses. Leave site in clean condition.
END OF SECTION
i
1
i
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL - PHASE II
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02060 -4
Printed 5/3/04
SECTION 02200
SITE DEMOLITION
' PART 1 GENERAL
1.1 GENERAL REQUIREMENTS
A. Drawings and general provisions of the Contract, including General and other Conditions and
other Division 1 — General Requirements sections, apply to the work specified in this Section.
i 1.2 WORK INCLUDED
' A. All site demolition work shall be done as shown on the drawings and as necessary to fully
complete all work. Contractor shall furnish all labor and material necessary to cut, alter,
remove, or temporarily remove and replace existing construction where indicated, specific
herein, or as necessary for completion of the project.
1.3 RELATED SECTIONS
' A. Not used in this section.
1.4 REFERENCES
' A. American National Standards Institute (ANSI), ANSI A 10.6: (1990) Demolition Operations
1.5 DEFINITIONS
A. Not used in this section.
1.6 SUBMITTALS
A. Submit proposed salvage, demolition and removal procedures for approval before work is
started. Demolition plan shall include procedures for careful removal and disposition of
' materials specified to be salvaged, coordination with other work in progress, a disconnection
schedule of utility services, a detailed description of methods and equipment to be used for each
operation and of the sequence of operations.
' 1.7 QUALITY ASSURANCE
A. The work includes demolition or removal of all construction indicated or specified. Do not
' begin demolition until authorization is received from the Owner's representative. Remove
rubbish and debris daily, unless otherwise directed; do not allow accumulations inside or outside
the building. Store materials that cannot be removed daily in areas specified by the Owner's
representative.
B. Use adequate numbers of skilled workmen who are thoroughly trained and experienced in the
necessary crafts and who are completely familiar with the specified requirements and methods
' needed for proper performance of the work of this section.
1.8 DELIVERY, STORAGE AND HANDLING
A. Comply with federal, state and local hauling and disposal regulations. Safety requirements shall
conform to ANSI A10.6.
1.9 SCHEDULING AND SEQUENCING
A. Not used in this section.
i
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD- TUALATIN SCHOOL DISTRICT 23J 02200 -1.
Printed 04/21/0.4
SECTION 02200 1
SITE DEMOLITION
1.10 DUST AND DEBRIS CONTROL '
A. Prevent the spread of dust and debris to occupied portions of the building and avoid the creation
of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or
objectionable conditions such as, but not limited to, ice, flooding, or pollution.
B. Vacuum and dust the work area daily. Sweep pavements as often as necessary to control the
spread of debris that may result in foreign object damage potential to aircraft.
1.11 PROTECTION
A. Traffic Control Signs: Where pedestrian and driver safety is endangered in the area of removal
work, use traffic barricades with flashing lights.
B. Existing Work: Protect existing work that is to remain in place, be reused, or remain the
property of the Owner. Repair items that are to remain which are to be salvaged and which are
damaged during performance of the work to their original condition, or replace with new. Do
not overload structural elements or pavements to remain. Provide new supports and
reinforcement for existing construction weakened by demolition or removal work. Repairs,
reinforcement, or structural replacement must have Owner approval.
C. Weather Protection: Protect electrical and mechanical services and utilities. Where removal of
existing utilities and pavement is specified or indicated, provide approved barricades, temporary
covering of exposed areas, and temporary services or connections for electrical and mechanical
utilities.
D. Protect electrical and mechanical services and utilities. Where removal of existing utilities and
pavement is specified or indicated, provide_approved barricades, temporary covering of exposed.
areas, and temporary services or connections for electrical and mechanical utilities.
1.12 BURNING '
A. Burning will not be permitted.
1.13 RELOCATIONS '
A. Perform' the removal and reinstallation of relocated items as indicated with workmen skilled in
the trades involved. Repair items to be relocated that are damaged or replace damaged items
with new undamaged items as approved by the contracting officer.
1.14 SITE ACCESS I
A. Do not obstruct vehicle traffic on adjacent streets, drive lanes, fire lanes, parking areas,
easements, and loading areas, without written permission from Owner and public authorities
having jurisdiction.
B. Do not obstruct foot traffic and power driven ground maintenance equipment traffic on park
drive lanes, walks, playing fields, playgrounds, and building exit passageways without written
permission from Owner and public authorities having jurisdiction.
C. Do not obstruct the Owner's and public use of adjacent facilities without prior written
permission from Owner.
1
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02200 -2
Printed 04/20/04
SECTION 02200 -
SITE DEMOLITION
' PART 2 PRODUCTS
' 2.1 Not used in this section.
PART 3 EXECUTION
' 3.1 EXISTING SITE FACILITIES TO BE REMOVED
A. Utilities and Related Equipment: Remove existing utilities as indicated and terminate in a
' manner conforming to the nationally recognized code covering the specific utility. Remove
meters and related equipment and deliver to Owner. If utility lines are encountered that are not
shown on drawings, contact the Owner for further instructions.
' B. Paving and Slabs: Remove ground, scarified, sawcut, concrete and asphaltic concrete paving
and slabs including aggregate base as indicated to permit installation of new work. Provide neat
sawcuts at limits of pavement removal as indicated.
' 3.2 ENVIRONMENTAL REQUIREMENTS
' A. Do not perform coring and sawing of concrete and masonry from 5:00 p.m. to 8:00 a.m. on
weekdays in densely populated neighborhoods without permission from Owner's representative.
B. Schedule other noisy construction activities with Owner's representative.
' C. During dry weather, sprinkle exposed soil materials and demolition debris with water to limit
dust in the air.
D. Do not cause soil erosion, flooding, or contaminated runoff with sprinkling activities.
E. Do not begin site demolition until known hazardous materials have been removed from the .
construction area.
3.3 FILLING
' A. Fill holes, open basements, and other hazardous openings in accordance with Section 02315,
"Earthwork."
3.4 DISPOSITION OF MATERIAL
' A. Title to Materials: Except where indicated, all materials and equipment once removed, and not
reused, shall become the property of the contractor and shall be removed from the project site.
1 The Owner will not be responsible for the condition or loss of, or damage to, such property after
contract award. Materials and equipment shall not be viewed by prospective purchasers or sold
on the site.
B. Reuse of Materials and Equipment: Remove and store materials and equipment listed and
indicated to be reused or relocated to prevent damage, and reinstall as the work progresses.
C. Salvaged Materials and Equipment: Remove materials and equipment that are indicated and
specified to be removed by the contractor and that are to remain the property of the Owner, and
deliver to a storage site, as directed within 10 miles of the work site.
1 3.5 CLEANUP
A. Debris and Rubbish
'
02054
APR 04 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
TIGARD - TUALATIN SCHOOL DISTRICT 23J 02200 -3
Printed 04/20/04
- SECTION 02200
SITE DEMOLITION
1. Remove and transport debris and rubbish in a manner that will prevent spillage on
pavements, streets or adjacent areas. Limit to 3/8 cubic yard capacity buggies or other
conveyances used on roofs and within the building to transport removed debris to chute
locations. Clean up spillage from pavements, streets and adjacent areas. Conform to
other applicable requirements under Section 02350.
END OF SECTION
t
1
1
1
1
1
I
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02200 -4
Printed 04/20/04
SECTION 02315
EARTHWORK
i
PART 1 GENERAL
1.1 GENERAL REQUIREMENTS
A. Drawings and general provisions of the Contract, including General and other Conditions and
Division 1 — General Requirements sections, apply to the work specified in this section.
1.2 WORK INCLUDED
A. Excavation and fill to attain indicated grades.
B. Excavation and fill for building construction.
C. Excavation for parking, grading, and sidewalks.
D. General rough and finish grading.
E. Surface dressing and base course for pavements and sidewalks.
F. Surface dressing and crushed rock leveling course for structures and floor slabs.
Earthwork for storm water detention basins.
1 G.
1.3 RELATED WORK
A. Section 02316 - Trenching, Backfilling and Compaction
B. Section 02350 - Geotextile Fabrics
' C. Section 02370 - Slope Protection and Erosion Control
1.4 REFERENCES
A. American Society for Testing and Materials (ASTM)
1. ASTM D698 Moisture Density Relation of Soils
2. ASTM D1556 Density of Soil in Place by Sand Cone Method
3. ASTM D 1557 Moisture Density Relations of Soil and Soil Aggregate
4. ASTM D2922 Moisture Density Relation of Soil & Soil Aggregate by Nuclear
' Methods
5. ASTM D3017 Moisture Content of Soil in Place by Nuclear Methods
' B. Oregon Department of Transportation / Oregon Chapter American Public Works Association
1. Oregon Standard Specifications for Construction (OSSC)
. 1.5 DEFINITIONS
A. Not used in this section.
•
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02315 -1
Printed 04 /20/04
SECTION 02315
EARTHWORK
1.6 SUBMITTALS
A. Soil compaction test results.
I
B. Certified Laboratory Test Reports: Test reports including grain size distribution, optimum
moisture content and plasticizing index shall be submitted for the following:
1. Structural fill material
2. General backfill beside structures.
3. Aggregate base course and leveling course material.
4. Drainage aggregate material.
C. Manufacturer's Certificates of Compliance: Synthetic fiber filter cloth.
D. Contractor Furnished Shoring and Sheeting Plan: Describe materials or shoring system to be
used. Indicate whether or not any components will remain after filling or backfilling. Provide
plans, sketches, or details, along with calculations by a registered professional engineer.
Indicate sequence and method of installation and removal.
E. Dewatering System: Describe methods to be employed in removing water from exposed
surfaces and diverting water from other areas or structures. Describe the basic components of
the dewatering system proposed and its planned method of operation. During the operation of
the plan, submit the dewatering performance records weekly.
1.7 QUALITY ASSURANCE
A. Approval Required: All fill material subject to approval of the owner /soils engineer. '
B. Backfilling Prior to Approval:
1. Do not allow or cause any of the work performed or installed to be covered up or '
enclosed by work of this section prior to all required inspections, test and approvals.
2. Should any of the work be enclosed or covered up prior to approval, uncover work at no
additional cost to owner.
3. After work has been completely tested, inspected and approved, make all repairs and
replacements necessary to restore the work to the condition in which it was found at the
time of uncovering; all at no additional cost to the owner.
C. Unfavorable Weather: Do not place, spread, or roll fill material during unfavorable weather ,
conditions. Do not resume operations until moisture content and soil density are satisfactory to
the owner.
1.8 DELIVERY, STORAGE AND HANDLING
A. Deliver and store materials in a manner to prevent contamination or segregation.
B. Store synthetic fiber filter cloth to prevent exposure to direct sunlight in accordance with the
manufacturer's recommendations.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02315 -2
Printed 04 /20/04
SECTION 02315
EARTHWORK
1.9 SCHEDULING AND SEQUENCING
A. Not used in this section.
1.10 PROTECTION
A. Shoring and Sheeting: Provide shoring and sheeting where indicated. Prevent undermining of
pavements and slabs. Slope banks where space permits.
' B. Dewatering: Include the disposal of surface water which may accumulate in open excavations,
unfinished fills, or other low areas. Remove water by trenching where approved, pumping, or
other methods to prevent softening of exposed surfaces. Surface dewatering plan shall include
' the rerouting of any storm water run -off or natural drainage if necessary.
C. Utilities: Movement of construction machinery and equipment over pipe and utilities during
construction shall be at the contractor's risk. Perform all work adjacent to privately owned
1 utilities as indicated in accordance with procedures outlined by utility company. For work
immediately adjacent to or for excavations exposing a utility or other buried obstruction, use
hand or light equipment excavation. Support uncovered lines or other existing work as affected
by the contract excavation.
D. Protection and Restoration of Surfaces: Protect newly graded areas from traffic, erosion, and
settlements. Repair and re- establish damaged or eroded slopes, elevations, or grades and restore
surface construction prior to acceptance. Protect existing streams, ditches, and storm drain
inlets from water -borne solid by means of straw bale dikes and/or filter fabric dams as indicated.
PART 2 PRODUCTS
2.1 STRUCTURAL FILL MATERIAL
A. On -Site Material: Excavated onsite native material shall not be used as structural fill material
under structures, pavements, or sidewalks.
B. Imported Structural Fill Material: Selected natural fill material from off -site borrow shall
consist of the following or a blend thereof well graded free draining or crushed rock up to 3" in
maximum size with not more than 5% of fines passing through a #200 sieve. Imported
' structural fill material shall be used under the building from subgrade elevation to leveling
course elevation. Thickness of base rock structural fill material shall vary in accordance with
depth of subgrade and design finish floor elevation. Imported structural fill shall extend a
minimum of 4 feet beyond the exterior building line. Perimeter slopes of structural fill shall be
' 45° minimum.
C. Imported Leveling Course Material: Place compacted 6" layer of 3/4" minus, free - draining,
' crushed rock with less than 5% fines passing through the #200 sieve under all building floor
slabs.
' 2.2 GENERAL BACKFILL BESIDE STRUCTURES
A. On -Site Material: Clean, on site native material, is suitable for use as General Backfill Beside
Structures if it can be placed in accordance with these specifications. Excavated onsite native
' material shall not be used as Structural Fill Material under structures or pavements. Stock piled
onsite excavated native material used as general backfill shall be free of all organic material and
shall be within 3% of optimum moisture content.
1
02034 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02315 -3
Primed 04/21 /04
SECTION
EARTHWORK
B. Imported Material: Imported fill material for General Backfill Beside Structures from off-site
borrow shall consist of the following or a blend thereof well graded free draining or crushed
rock up to 3" in maximum size with not more than 5% of fines passing through a #200 sieve.
2.3 ASPHALTIC CONCRETE PAVING AGGREGATE BASE COURSE MATERIAL
A. Base Course Material: 1 -1/2" minus well graded crushed rock with less than 5% of fines passing
through a #200 sieve.
B. Leveling Course Material: 3/4" minus well graded crushed rock with less than 5% of fines
passing through a #200 sieve. 1
2.4 DRAINAGE AGGREGATE MATERIAL
A. Medium aggregate 3/4 or 5/8 to 1/4 inch, clean washed medium sized drain gravel with less than ,
5% passing through a #200 sieve.
2.5 RIPRAP MATERIAL I
A. All riprap material shall meet the Test Requirements of OSSC, Section 00390 - Riprap
Protection.
1
B. Riprap material shall be angular in shape. The thickness of a single rock shall not be less than
1/3 its length. Rounded rock will not be accepted. Riprap shall be free from overburden, spoil,
shale and organic material. Non - durable rock or shale is not acceptable.
C. Gradation requirements shall be as follows:
Percent (by weight) Weight of Rock (lbs.)
( )
Class 50 Class 100 Class 200
20.0 50 - 30 100 - 60 200 - 140
30.0 30 -15 60 -25 140 -80
40.0 15 -2 25 -2 80 -8
10.0 2 -0 2 -0 8 -0
2.6 TOPSOIL MATERIAL
A. See Landscaping Specifications.
2.7 GEOTEXTILE FILTER FABRIC
111
A. See Section 02350, "Geotextile Fabrics."
PART 3 EXECUTION ,.
3.1 QUANTITIES
A. The construction documents make no representation or warrantees of soil quantities. Contractor
is responsible for determining all quantities of materials necessary to complete the project.
B. All necessary imported soil materials as shown in the design documents shall be supplied by the
Contractor. Excess onsite excavated material not used elsewhere on the project shall be
removed from the site at the end of the project at the Contractor's expense.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02315 -4
vmuea 04/20/04
SECTION 02315
EARTHWORK
3.2 SITE STRIPPING AND FILL
' A. Site Stripping: All topsoil and organic bearing material, including fill, shall be stripped and
wasted off site. If organic soils are found after the stripping operation, localized areas
containing these materials shall be over- excavated and backfilled with engineered structural fill.
' B. Grubbing: Grub out all stumps and roots larger than 1 -1/2 inches in diameter. Remove all scrap
metal and foreign materials.
C. Disposal: Remove all existing paving, concrete, and structures as required for demolition.
Cleared and demolished materials to be removed from the site.
3.3 AVOIDANCE AND CORRECTION OF DETRIMENTAL OPERATIONS
A. Perform all operations involved in excavating, hauling, and placing of earthwork materials so no
damage or detriment to the completed or partially completed work results. At all times provide
sufficient drainage of completed or partially completed earthwork to prevent damage or loss due
to rainfall, surface water or any other cause.
' 3.4 ROUNDING OF CUTBANKS
A. As part of the earthwork, blend the tops of cutbanks with the adjacent ground by rounding as
•
called for by the plans.
3.5 TEMPORARY EXCAVATION AND SHORING
1 A. In general, cuts of less than four feet in depth may be made as steep as the soil can stand,
without shoring. Open cuts greater than four feet in depth shall be either shored or graded to a
safe slope. Temporary excavation slope should not be steeper than 1.5:1 (Horizontal:Vertical).
' B. The selection and construction of any shoring system should be the responsibility of the
contractor. The installation of any shoring system shall be conducted such that the safety of
' workmen, equipment, existing utilities and structures are ensured. All shoring systems shall be
in compliance with the current local, state and federal codes and practices and shall conform to
Section 02250, "Shoring and Bracing ".
' 3.6 DRAINAGE AND DEWATERING
A. Plan for and provide the structures, equipment, and construction for the collection and disposal
of surface and subsurface water encountered in the course of construction.
B. Dispose of surface water which may accumulate in open excavations, unfinished fills, or other
low areas. Remove water by trenching where approved, pumping, or other methods to prevent
softening of exposed surfaces.
C. Groundwater flowing toward or into excavations shall be controlled to prevent sloughing or
excavation slopes and walls, boils, uplift and heave in the excavation and to eliminate
interference with orderly progress of construction. French drains, sumps, ditches or trenches
will not be permitted within 3' of the foundation of any structure.
D. Operate the dewatering system until construction work below existing water levels is complete.
1
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD-TUALATIN SCHOOL DISTRICT 23J 02315-5
Printed 04/20/04
SECTION 02315 '
EARTHWORK
3.7 EXCAVATION I
A. Excavate for slabs, and other improvements to sizes and levels shown or required. Allow for
form clearance and for proper compaction of required backfilling material.
B. All footings bases to bear on firm, natural, undisturbed soil free of organic material or on
engineered fill.
C. All soft, wet soil, or soil of unusual condition shall be excavated to firm, natural, undisturbed
soil, and backfilled with specified fill materials. I
D. Contractor's Inadvertent Over - Excavation: Backlit' and compact all over - excavated areas as
specified for fill below at no additional cost to the owner.
E. Excess Fill Materials: All excavated materials not required for backfilling or other portions of
the work shall be removed from the site.
F. Pile Supported Foundations: Excavate to elevation of bottom of pile cap. Backlit' and compact
over excavations and changes in grade due to pile driving operations in accordance with the
requirements. 1
G. Rock: Remove rock to the elevations required by approved methods in such a manner that will
leave the foundation rock in an unshattered and solid condition. Roughen level surfaces and cut 111 slope surfaces into benches for bond with concrete. Protect shale from conditions causing
decomposition along joints or cleavage planes and other types of erosion. Removal of rock
beyond the lines and grades indicated unless previously authorized will not be grounds for claim
of additional payment.
3.8 FILLING AND BACKFILLING
A. Subgrade Preparation: Step, bench, or break up sloped surfaces steeper than one vertical to 4 '
horizontal so that the fill material will bond with or be securely keyed to the existing material.
Scarify existing surface to a minimum depth of 8" if subgrade density is less than the degree of
compaction specified and recompact. When the subgrade is part fill and part excavation or
natural ground, scarify the excavated or natural ground portion to a depth of 8" and recompact
as specified for the adjacent of overlying fill. Compact with equipment well suited to the soil
being compacted. Moisten or aerate material as necessary to provide the moisture content that
will readily facilitate obtaining the specified compaction with the equipment used.
B. General Backlit' Beside Structures: Place required backfill material adjacent to structures and
compact in a manner that prevents wedging action or eccentric loading upon or against the
structures. Step or serrate slopes bounding or within areas to be backfilled to prevent sliding of
the fill. Moisten or aerate material as necessary to provide the moisture content that will readily
facilitate obtaining the specified compaction with the equipment used. Do not place material on
surfaces that are muddy, frozen, or contain frost. Do not use equipment for backfilling
operations or for the formation of embankments against structures that will overload the
structure. Backfilling against concrete will be done only after the concrete has attained its 28-
day compressive strength.
C. Structural Fill: Place structural fill material under spread footing, concrete slabs not pile
supported, in loose lifts of 8 ". Do not place material on surfaces that are muddy, frozen, or
contain frost. Compact with equipment well suited to the soil being compacted. Moisten or
aerate material as necessary to provide the moisture content that will readily facilitate obtaining
the specified compaction with the equipment used. Compact each lift as specified herein before 1
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD- TUALATIN SCHOOL DISTRICT 23J 02315 -6
Printed 04/20/04
I SECTION 02315
EARTHWORK
I placing the overlaying lift. Compaction shall be accomplished continuously over the entire area.
Sufficient passes shall be made to ensure that specified density is obtained.
I 3.9 WET WEATHER EARTHWORK
A. If earthwork takes place in wet weather or wet conditions, where control of soil moisture content
I is not possible, the following recommendations are to be as follows:
1. Earthwork shall be accomplished in small sections and carried through to completion to
•
I minimize exposure to wet weather. If there is to be traffic over the exposed subgrade,
the subgrade shall be protected with a compacted layer of 1 -1/4" minus crushed rock, at
least 8" thick.
I 2. The ground surface in the construction areas shall be sloped and sealed with a smooth
drum roller to promote the rapid runoff of precipitation and to prevent ponding of water.
No soil shall be left uncompacted. Soils which become too wet for compaction shall be
I removed and replaced with clean granular material.
3. Work areas, soil stockpiles, or slopes shall be covered with plastic, and sloping, ditching
I sumps, dewatering and other measures should be employed as necessary to permit proper
completion of the work. Bales of straw and geotextile sediment fences shall be used to
control soil erosion.
1 3.10 COMPACTION STANDARDS
A. Native, in -situ soils underlying retaining wall foundations, building foundations, floor slabs
and/or pavements or structural fill shall be proof - rolled to a uniform dry density of 95% of the -
Modified Proctor maximum dry density (ASTM D1557).
B. All Structural Fill Material beneath footings, slabs, walls, and structures shall be spread in
I uniform lifts not to exceed eight inches in thickness and compacted to 95% of its maximum
Modified Proctor (ASTM D1557) dry density. The water content at the time of compaction
shall be within 3 percent of optimum.
I C. Structural Fill Material supporting pavement structures shall be placed in layers not exceeding 8
inches in compacted thickness. Each layer of structural fill shall be compacted to a uniform dry
I density of 95 percent of the Modified Proctor maximum dry density (ASTM D1557). It shall be
tested for compaction as construction progresses. Water content at the time of compaction shall
be within 3 percent of optimum.
I D. General Backfill beside structures shall be placed in layers not to exceed 8" in thickness and
compacted to 92 percent of its maximum modified proctor (ASTM D 1557) dry density. Water
content at the time of connection shall be within 3 percent of optimum.
I E. Retaining wall backfill should be compacted to 95 percent of the Modified Proctor dry density
(ASTM D1557) beyond 36 inches from the wall, and to 90 percent within 36 inches of the wall.
Lateral bracing shall be provided to support the wall prior to placement and compaction of the
I
backfill. Alternatively, the backfill within 36 inches of the wall may be placed in thin lifts, at
not more than 8 inches in loose thickness, and compacted with small compaction equipment. It
is the contractor's responsibility to select the appropriate compacting equipment and procedure
I to achieve the recommended compacted density, and to ensure that the compaction will not
result in damage to the retaining walls.
F. Base course and leveling course materials for paving areas shall be compacted to 95 percent of
the Modified Proctor dry density (ASTM D1557).
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
I APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02315 -7
Proved 04/20/04
SECTION 02315 -
EARTHWORK
3.11 GRADING '
A. Rough Grading: 1
1. Bring all finish grades to approximate levels indicated on drawings. Where grades are
not otherwise indicated, finish grades are to be same as adjacent sidewalks, curbs or the
obvious grade of adjacent structure.
2. Grade to uniform levels or slopes between points where grades are given. Round off
surfaces; avoid abrupt changes in levels.
3. Rough grade to allow for depth of concrete slabs, walks, and their gravel bases.
4. Grade for the paved drive area as indicated and specified herein and provide for drainage
as shown, allowing for thickness of surfacing material.
B. Finish Grading: At completion of job and after back filling by other crafts has been completed, '
refill and compact areas which have settled or eroded to bring to final grades.
C. Grading Tolerances: U
1. Rough Grade: Building and paving areas; 0.1 feet.
2. Finish Grade: Granular cushion under concrete slabs and paving, .01 foot. I
D. Treatment After Completion of Grading: After grading is completed and subsequent to testing
and inspection, prohibit further excavating, filling or grading except with the approval of owner.
3.12 SUBGRADE FILTER FABRIC
A. Place synthetic fiber filter fabric as indicated in Section 02350, "Geotextile Fabrics." 1
3.13 SPREADING TOPSOIL
A. See Landscaping Specifications.
3.14 DISPOSITION OF SURPLUS MATERIAL
A. Surplus or other soil material not required or suitable for filling backfilling or embankment,
shall be removed from owner's property. I
3.15 TESTING
A. Test fill materials for moisture density relations in accordance with ASTM D -1557. ,
B. Perform density tests in randomly selected locations and in accordance with ASTM D1556 or
ASTM D2922 and ASTM D3017 as follows:
1. One test per 10,000 square feet in each layer of lift.
2. One test per 500 cubic yard placed. '
END OF SECTION
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02315 -8
Printed 04 /20/04
SECTION 02316
TRENCHING, BACKFILLING AND COMPACTION
PART 1 GENERAL
1 1.1 GENERAL REQUIREMENTS
A. Drawings and general provisions of the Contract, including General and other Conditions and
Division 1 — General Requirements sections, apply to the work specified in this section.
1.2 WORK INCLUDED
' A. Work in this section includes, but is not necessarily limited to trenching and trench backfill
necessary for complete installation of all underground items not covered by other sections of
these specifications.
' 1.3 RELATED WORK
A. Section 02315 — Earthwork
B. Section 02350 - Geotextile Fabrics
C. Section 02510 — Exterior Water Distribution
D. Section 02630 - Storm Drainage System
E. Division 15 — Mechanical
' F. Division 16 - Electrical
1.4 REFERENCES
' A. American Society of Testing and Materials (ASTM)
1. ASTM D 1556 Density of Soil in Place by Sand Cone Method
2. ASTM D1557 Moisture Density Relations of Soil & Soil Aggregate
B. Oregon Department of Transportation/Oregon Chapter American Public Works
1. Oregon Standard Specification for Construction (OSSC).
1.5 DEFINITIONS
A. Not used in this section.
1.6 SUBMITTALS
A. Soil compaction test results.
B. Certified Laboratory Test Reports: Test reports including grain size distribution, optimum
moisture content and plasticizing index shall be submitted for the following:
' 1. Trench foundation material.
2. Pipe bedding material.
1
'
02054
APR 04 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
TIGARD - TUALATIN SCHOOL DISTRICT 23J 02316 -1
Printed 04/21/04
SECTION 02316
TRENCHING, BACKFILLING AND COMPACTION
3. Pipe zone material. '
4. Trench backfill material.
5. Drainage aggregate material.
C. Manufacturer's Certificates of Compliance: Synthetic fiber filter cloth.
D. Contractor Furnished Shoring and Sheeting Plan: Describe materials or shoring system to be
used. Indicate whether or not any components will remain after filling or backfilling. Provide
plans, sketches, or details, along with calculations by a registered professional engineer.
Indicate sequence and method of installation and removal.
E. Dewatering System: Describe methods to be employed in removing water from exposed
surfaces and diverting water from other areas or structures. Describe the basic components of
the dewatering system proposed and its planned method of operation. During the operation of
the plan, submit the dewatering performance records weekly. '
1.7 QUALITY ASSURANCE
A. Owner will employ and pay for independent testing laboratory to conduct compaction tests on
all backfilling operations.
B. Prior to any excavation, utility locates shall be done per OAR 952 -001. 1
1.8 DELIVERY, STORAGE AND HANDLING
A. Not used in this section.
1.9 SCHEDULING AND SEQUENCING
A. Not used in this section. 1
PART 2 PRODUCTS
2.1 TRENCH FOUNDATION MATERIAL
A. On -Site Material: Native material may be used as trench foundation if it is firm, clean, and
undisturbed.
B. Imported Material: Selected natural fill material from of site borrow shall consist of the
following or a blend thereof well graded free draining or crushed rock up to 1 -1/2" in maximum
size with not more than 5% of fines passing through a #200 sieve.
2.2 PIPE BEDDING MATERIAL
A. Imported Material: 3/4" minus well graded crushed rock with less than 5% of fines passing
through a #200 sieve. I
2.3 PIPE ZONE MATERIAL
A. Imported Material: 3/4" minus well graded crushed rock with less than 5% of fines passing '
through a #200 sieve.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD- TUALATIN SCHOOL DISTRICT 23J 02316 -2
Hinted 04 /20/04
SECTION 02316
TRENCHING, BACKFILLING AND COMPACTION
2.4 • TRENCH BACKFILL MATERIAL
' A. On -Site Material (Not Under Structures or Paving): Clean, on site native material, is suitable
for use as Trench Backfill Material in areas not under structures or paving if it can be placed in
accordance with these specifications. Excavated onsite native material shall not be used as
Trench Backfill Material under structures or pavements. Stock piled onsite excavated native
' material used as general backfill shall be free of all organic material and shall be within 3% of
optimum moisture content.
B. Imported Material (Under Structures or Paving): Selected natural fill material from off -site
' borrow shall consist of the following or a blend thereof well graded free draining or crushed
rock up to 1 -1/2" in maximum size with not more than 5% of fines passing through a #200
sieve.
PART 3 EXECUTION
' 3.1 GENERAL
A. All compaction with vibratory machinery must be completed on an owner nonproduction
weekend and coordinated with the owner.
' 3.2 TRENCH EXCAVATION
' A. Trench excavation and backfill in accordance with any and all specifications of any controlling
regulatory agency under which the work is being performed.
B. Excavate the trench to lines and grades shown or established with proper allowance for pipe
thickness. The subgrade upon which the bedding is to be placed shall be firm, undisturbed and
true to grade. If the trench is over - excavated, restore to grade with materials specified for pipe
bedding at no expense to owner. Place material over the full width of the trench and compact in
' layers not exceeding 6 inches deep to establish grade with allowance for the pipe bedding.
C. Dispose of all excess material (not required elsewhere on the project) offsite at contractor's
' expense.
D. Provide all materials, labor and equipment necessary to adequately shore trenches to protect the
work, existing property, utilities, pavement, etc., and provide safe working conditions in the
1 trench. Method of shoring in accordance with the contractor's design. Damages resulting from
improper cribbing or shoring will be the sole responsibility of the contractor.
' E. Locate excavated material in such a manner that it does not create a hazard to pedestrian or
vehicular traffic, nor interfere with the function of existing drainage facilities.
' F. Remove and dispose of existing and damaged sewer pipe and structures.
G. Plan and layout trenches to avoid root structures of trees indicated to remain.
' 3.3 DRAINAGE AND DEWATERING
A. Plan for and provide the structures, equipment, and construction for the collection and disposal
' of surface and subsurface water encountered in the course of construction.
B. If groundwater is present in excavations, the bottom shall be over - excavated an additional 12 -18
inches and replaced with compacted base course material.
' 02054
APR 04 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
TIGARD - TUALATIN SCHOOL DISTRICT 23J 02316 -3
Primed 04/20/04
SECTION 02316 1
TRENCHING, BACKFILLING AND COMPACTION
C. Surface water shall be directed away from excavation and construction sites so as to prevent
erosion and undermining of foundations. Diversion ditches, dikes and grading shall be provided
and maintained as necessary during construction. Excavated slopes and backfill surfaces shall be
protected to prevent erosion and sloughing. Excavation shall be performed so that the site and
the area immediately surrounding the site and affecting operations at the site shall be continually
and effectively drained.
D. Dewatering: Groundwater flowing toward or into excavations shall be controlled to prevent
sloughing of excavation slopes and walls, boils, uplift and heave in the excavation and to
eliminate interference with orderly progress of construction. French drains, sumps, ditches or
trenches will not be permitted within 3 feet of the foundation of any structure.
3.4 PAVED AREAS
A. Sawcut paved areas for utility trenching. Allow for new paving overlap beyond trench sidewall
as indicated. Do not disturb adjacent paving more than necessary.
3.5 PROTECTION '
A. Underground Utilities: Location of any existing utilities indicated is approximate. The
contractor shall physically verify the location and elevation of the existing utilities indicated
prior to starting construction. The contractor shall contact the contracting officer for assistance
in locating existing utilities.
B. Structures and Surfaces: Protect newly backfilled areas and adjacent structures, slopes, or
grades from traffic, erosion settlement, or any other damage. Repair and reestablish damaged or
eroded grades and slopes and restore surface construction prior to acceptance. Protect existing
streams, ditches, and storm drain inlets from water -borne soil by means of erosion control
measures as indicated on the contract drawings.
C. Channels and Ditches: Construct (rip -rap) rock protection in areas indicated to the lines and
thicknesses indicated to dissipate stream energy and prevent channel erosion. Place rip -rap on a
layer of filter fabric.
3.6 TRENCH FOUNDATION ,
A. Trench foundation is defined as the bottom of the trench in which the pipe bedding is to lay and
is responsible for support of the pipe.
B. When in the judgment of the owner, the existing material in the bottom of the trench is
unsuitable for supporting the pipe, excavate below the pipe as directed. Place backfill in trench 111 to subgrade or pipe bedding with trench foundation material over full width of the trench and
compact layers not exceeding 6 inches deep to the required grade.
3.7 PIPE BEDDING ,
A. Pipe bedding is defined as the furnishing and placing of specified materials on the trench
foundation so as to uniformly support the barrel of the pipe.
B. Pipe bedding consists of leveling the bottom of the trench or the top of the foundation material
and placing bedding material to the horizontal centerline of the pipe. Place specified bedding
material in at least two lifts. Place first lift to provide the minimum 6 inch depth of bedding
material shown on the plan before the pipe is installed. Spread bedding smoothly to proper
grade so the pipe is uniformly supported along the barrel and excavate bell holes at each joint to
permit proper assembly and inspection of the entire joint. Provide firm unyielding support along
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD- TUALATIN SCHOOL DISTRICT 23J 02316 -4
Printed 04/20/04
' SECTION 02316
TRENCHING, BACKFILLING AND COMPACTION
' the entire pipe length.
C. Place subsequent lifts of not more than 6 inches in thickness up to the horizontal centerline of
the pipe. Bring lifts up together on both sides of the pipe and carefully work under the pipe by
slicing with a shovel or other approved procedure. Pay particular attention to the area from the
flow line to the horizontal centerline of the pipe or top of bedding to insure that firm support is
obtained to prevent any lateral movement of the pipe during the final backfilling of the pipe
zone. Place pipe bedding full width of trench.
3.8 PIPE ZONE
A. Pipe zone is defined as the full width of the trench from the top of the bedding to 6 inches above
the top outside surface of the barrel of the pipe.
' B. Place specified pipe zone material carefully around the pipe in 6 inch layers and thoroughly
hand tamp with approved sticks supplemented by walking in and slashing with a shovel.
' Prevent pipe from moving either horizontally or vertically during placement and compaction of
the pipe zone material. Mechanical compactors are prohibited for placement of fill in the pipe
zone. Compact pipe zone to 90% of maximum density per ASTM D1557.
1 3.9 TRENCH BACKFILL
A. Trench backfill is defined as furnishing, placing and compacting of material in the trench
between the top of the pipe zone material and the bottom of the pavement base rock ground
surface or surface material as directed.
' B. Owner's representative will sample excavated material to determine suitability of native material
for use as trench backfill. Should native material not be acceptable, imported trench backfill
material will be used as previously specified under materials.
'
•
C. Backfill trench above the pipe zone to within 8 inches of the final surface grade shown on the
plans in lifts not to exceed 8 inches of loose depth. In unpaved areas, compact each lift to
minimum 92% of maximum density as determined by ASTM D1557 with mechanical vibrators
or impact tampers. Compact trench areas at paving and inside building areas to 95% of
maximum density as determined by ASTM D 1557.
3.10 MANHOLES, VAULTS, AND OTHER APPURTENANCES
A. Provide at least 12" clear from outer surfaces to the embankment or shoring. Remove unstable
soil that is incapable of supporting the structure to an overdepth of 12" and refill with pipe
' bedding material to the proper elevation. Compact to 90 percent of ASTM D 1557 maximum
density.
3.11 BURIED WARNING IDENTIFICATION TAPE
A. Install tape in accordance with manufacturer's recommendations except as modified herein.
Bury tape 12" below finished grade; under pavements and slabs, bury tape 6" below top of
' subgrade.
3.12 TEMPORARY TRENCH PLATING
A. When temporary steel plates are installed over a street cut, they shall be capable of carrying at
least an MS -18 loading. Place steel plates with a minimum of 12 inches bearing on all sides of a
cut. Anchor steel plates to minimize shifting. Shim the edges of all steel plates with cold m ix
asphalt.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD- TUALATIN SCHOOL DISTRICT 23J 02316 -5
Primed 04/20/04
SECTION 02316
TRENCHING, BACKFILLING AND COMPACTION
3.13 TOPSOIL AREAS '
A. Where trenches cross lawns, garden areas, pastures, cultivated fields or other areas on which
topsoil exists, remove the topsoil to a minimum 12 inch depth and place the material in a
stockpile. Do not mix the topsoil with other excavated material. After the trench has been
backfilled, replace the topsoil. In lieu of stockpiling the topsoil, approved imported topsoil may
be substituted. I
B. Maintain the finished grade of the topsoil level with the area adjacent to the trench until final
acceptance. Repair damage to adjacent topsoil caused by the contractor's operations. Remove
all rock, gravel, clay and other foreign materials from the surface. Regrade and add topsoil as
required.
3.14 PAVED AREAS 1
A. Use saws to cut Portland cement concrete pavement, curbs and sidewalks, regardless of
thickness. In bituminous pavement, when no pavement overlay will occur, saw -cut the
pavement along each edge of the area to be removed. Saw cutting is not required in roadways
• that will receive a pavement overlay.
B. Upon completion of backfill and just prior to pavement re- surfacing, saw the surfacing on both
sides of the trench a minimum of 6 inches wider than each top of the trench. In areas of any
undermined or damaged surfacing, re -saw to a width outside these areas. When saw - cutting,
follow lines parallel to the pipe centerline.
C. Where the width changes in areas of asphalt pavement re- surfacing, cut the transition between
the different widths at 45 degrees. When the pipe line changes direction, or there is a
connecting pipe line that requires the saw cut alignment to change at. an angle greater than 60
degrees, make a minimum 24 inch transition saw cut. If there is damaged or undermined
surfacing. Make the transition saw cut angle half the angle change in the direction of the pipe
line or connecting line. '
D. A second saw cut for concrete sidewalks, driveways and pavements will not be required unless
needed to reach firm subgrade.
3.15 FINISH OPERATIONS
A. Place final proper surface as required. Subsequent settlement of the trench during warranty
period will be considered result of improper compaction and shall be promptly corrected.
B. Pavement Repair: Repair pavement, curbs, and gutters as indicated. Do not repair pavement
until trench or pit has been backfilled and compacted as specified herein. Provide a temporary
road surface of gravel over backfilled portion until permanent pavement is repaired. Remove
and dispose of temporary road surface material when permanent pavement is placed. As a
minimum, maintain one -way traffic on roads and streets crossed by trenches. Fully open roads
and streets to traffic within 3 days.
3.16 FIELD QUALITY CONTROL '
A. Test bedding and backfill materials for conformance to specified requirements. Test bedding and backfill
for moisture- density relations in accordance with ASTM D 1557 as specified herein. Perform at least one
of each of the required tests for each material provided. Perform sufficiently in advance of construction so
as not to delay work. Provide additional tests as specified above for each change of source. Perform
density and moisture tests in randomly selected locations and in accordance with ASTM D 1556 as
follows:.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02316 -6
Printed 04 /20/04
SECTION 02316
TRENCHING, BACKFILLING AND COMPACTION
1. Bedding and backfill in trenches: One test per 100 feet in each lift.
2. Appurtenance Structures: One test per 10 square yards or fraction thereof in each lift.
END OF SECTION
1
1
1
1
1
' 02054
APR 04 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
TIGARD- TUALATIN SCHOOL DISTRICT 231 02316 -7
Printed 04/20/04
SECTION 02350
GEOTEXTILE FABRIC
PART 1 GENERAL
1.1 GENERAL REQUIREMENTS
A. Drawings and general provisions of the Contract, including General and other Conditions and
Division 1 — General Requirements sections, apply to the work specified in this section.
1.2 WORK INCLUDED
' A. Geotextile fabrics for silt fencing, riprap protection, subdrainage, and subgrade separation.
1.3 RELATED WORK
A. Section 02315 — Earthwork
' B. Section 02316 — Trenching, Backfilling and Compaction
C. Section 02370 — Slope Protection and Erosion Control
' D. Section 02620 — Foundation Drainage
1.4 REFERENCES
A. ASTM D 4354 — Standard Practice for Sampling of Geosynthetics for Testing
' B. ASTM D 4355 — Deterioration of Geotextiles from Exposure to UL Light and Water
C. ASTM D 4491 — Standard Test Methods for Water Permeability of Geotextiles
D. ASTM D 4632 — Standard Test Method for Grab Breaking Load and Elongation of Geotextiles
E. ASTM D 4751 — Standard Test Method for Determining Apparent Opening Size of a
Geotextile
F. ASTM D 4833 — Standard Test Method for Puncture Resistance of Geotextiles
1 1.5 DEFINITIONS
A. Not used in this section.
1.6 SUBMITTALS
1 A. Manufacturer's Data: Submit manufacturer's standard drawings or catalog cuts of each type of
geotextile fabric specified for the project.
B. Quality Assurance Certificates: Submit a certification that each type of geotextile fabric meets
the various ASTM specifications.
C. Sample: Submit a sample of each geotextile fabric.
' 1.7 QUALITY ASSURANCE
A. Manufacturer shall sample all geotextiles according to ASTM D 4354.
I -
I 02054
APR 04 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
TIGARD-TUALATIN SCHOOL DISTRICT 23J 02350 -1
Printed 04 /20/04
SECTION 02350 '
GEOTEXTILE FABRIC
B. All geotextiles shall be free of defects, cuts or tears and be resistant to ambient temperatures and
I
environmental conditions.
1.8 DELIVERY, STORAGE AND HANDLING
I
A. Protect geotextile at all times from UV rays or contamination by runoff or construction
activities. Traffic or construction equipment will not be permitted directly on the geotextile.
I
1.9 SCHEDULING AND SEQUENCING
A. Not used in this section.
I
PART 2 PRODUCTS
2.1 GEOTEXTILE FABRIC I
A. Woven or nonwoven geotextiles shall be composed of long chain, synthetic polymeric filaments
I
or yarns formed into a stable network that retains its relative structure during the handling and
placement.
B. At least 95% by weight of the long chain polymers shall be a polyolefin or polyester.
I
C. Geotextiles shall have the selvege finished so the outer fibers are prevented from pulling away
from the fabric.
I
D. Fabrics shall meet or exceed the properties specified in the following table. If the fabric
manufacturer's submittal lists typical or typical average values instead of minimum average
1 values, the required values in the table below will be increased 25 %.
Geotextile Test Drainage Riprap Sediment Subgrade
Property Method Geotextile Geotextile Fence Geotextile
I
Fabric Type - -- Nonwoven Woven Woven Woven
Minimum Grab ASTM D 90 lb 180 lb
Tensile Strength 4632
Apparent Opening ASTM D No. 70 No. 70 No. 30 No. 30
Size 4751
Minimum ASTM D 0.5 0.5 0.05 0.01
I
Permittivity (s -1) 4491
Minimum UV ASTM D - -- 70% 70% • - --
Retained Strength 4355 I
Minimum Puncture ASTM D 35 lb 80 lb - -- 80 lb
Strength 4833
Minimum Grab ASTM D 15% 15% - -- - --
I
Elongation 4632
PART 3 EXECUTION I
3.1 GENERAL .
A. Prepare the surface receiving the geotextile fabric to a smooth condition free of obstruction, I
depressions, and debris unless otherwise directed. Do not drag fabric on ground or mishandle in
any way.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2 i
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02350 -2
Primed 04/20/04
SECTION 02350
GEOTEXTILE FABRIC
B. Loosely place the fabric without wrinkles so that placement of the overlaying material will not
' tear the fabric.
C. During installation, cover the geotextile with the specified cover material as soon as possible.
Do not leave in uncovered condition for more than 5 days.
3.2 OVERLAPS
' A. Minimum overlap requirements for geotextiles.
Application Minimum Overlap
Drainage 12 inches
' Riprap 24 inches
Subgrade 24 inches
3.3 DRAINAGE GEOTEXTILE
A. When used in trenches for drains, place the geotextile in the trench as shown on plans to loosely
conform to the shape of the trench with no wrinkles or folds.
' 3.4 RIPRAP GEOTEXTILE
' A. Place geotextile under riprap according to details shown. Maximum drop height of riprap
material onto the fabric shall be 24 ". After placing riprap, backfill all voids in the riprap face so
that the geotextile is completely covered and not visible.
3.5 SUBGRADE GEOTEXTILE
A. Prepare subgrade according to Section 02315, "Earthwork ". Correct geotextile failures, as
evidenced by soil pumping or roadbed distortions, by removing any covering material in the
affected area and placing a geotextile patch on the exposed geotextile. Cover the patch with the
specified material and compact before proceeding.
1 END OF SECTION
r
I
' 02054
APR 04 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
TIGARD - TUALATIN SCHOOL DISTRICT 23J 02350 -3
Printed 04/20/04
' SECTION 02370
SLOPE PROTCTION AND EROSION CONTROL
PART 1 GENERAL
' 1.1 GENERAL REQUIREMENTS
A. Drawings and general provisions of the Contract, including General and other Conditions and
' Division 1 — General Requirements sections, apply to the work specified in this section.
1.2 WORK INCLUDED
' A. Erosion and sediment control measures taken during construction.
1.3 RELATED WORK
A. Section 02315 — Earthwork
1 B. Section 02316 — Trenching, Backfilling and Compaction
C. Section 02350 — Geotextiles
' 1.4 REFERENCES •
A. Not used in this section.
1.5 DEFINITIONS
A. Not used in this section.
1111 1.6 SUBMITTALS
' A. Contractor Developed Erosion and Sediment Control (ESCP): Develop a complete ESCP that
incorporates the design ESCP and all modifications into it.
' 1. Erosion and sediment control features, other than those shown on the plans, may be
required depending on the contractor's methods of operation and schedule.
2. Plan shall address treatment and/or prevention of erosion during construction. As a
' basis, the contractor may begin with the ESCP presented the project drawings.
3. For each phase of the scheduled work, indicate on the ESCP how the proposed erosion
and sediment control devices will divert and store flows, limit runoff from exposed areas,
filter sediment, and stabilize exposed soils during construction.
B. Implementation Schedule: Submit a complete earthwork implementation schedule which
' includes the following information if applicable:
1. Installing perimeter controls
1 2. Construction phasing
' 3. General site clearing and grubbing
4. Utility trenching
5. Earthwork for buildings •
' 02054
APR 04 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
TIGARD - TUALATIN SCHOOL DISTRICT 23J 02370 -1
Printed 04/20/04
SECTION 02370
SLOPE PROTCTION AND EROSION CONTROL
6. Earthwork for roads and paving '
7. Temporary stabilization of exposed soil surfaces
8. Work required in wetlands
9. Maintaining and monitoring temporary controls '
10. Storage and disposal of waste soil materials
11. Haul road and borrow pit controls '
12. Additional controls for wet season work
13. Completion of seeding prior to fall/winter months
C. Manufacturer's Data: Submit manufacturer's standard drawings or catalog cuts of the following
items:
1. Sediment control fencing
2. Erosion control blankets
1.7 QUALITY ASSURANCE
A. Codes and Regulations: All work shall conform to the applicable and local state codes, laws
and regulations including OSHA and Public Works Engineering Standards of local public
authorities with jurisdiction.
13. In particular, all erosion control and surface water design measures shall conform to City of
Tigard requirements. '
1.8 DELIVERY, STORAGE AND HANDLING
A. Not used in this section, t
1.9 SCHEDULING AND SEQUENCING
A. Not used in this section.
PART 2 PRODUCTS I
2.1 SEDIMENT CONTROL FENCING
A. Provide sediment fence geotextile per Section 02350, "Geotextile Fabrics." I
2.2 BIOBAGS
A. Bio- filter bags fill material shall be clean 100% recycled wood product waste. Size of bag shall
be generally 18" x 6" x 30" plastic mesh bags with /2" openings and weigh approximately 45
pounds. ,
•
1
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02370 -2
Printed 04/20/04
SECTION 02370
SLOPE PROTCTION AND EROSION CONTROL
2.3 STORM DRAIN INLET PROTECTION
' A. All gravels shall be washed clean prior to installation on the site. Gravel size shall be no larger •
than 1 -1/2" rock and shall be larger than any mesh openings.
t B. Wire mesh shall be no greater than %2" opening size.
C. Wrapped grates shall have fabric ends secured under the grate in such a manner as to not allow
the grate to lift and flows to pass by.
' 2.4 TEMPORARY GRASS COVER
A. Temporary grass cover must be established by October 1 or other erosion controls measures
such as additional mulch or erosion control blankets will be required until adequate grass
coverage is achieved. Seeding and protective mulch cover shall occur by September 1.
' B. Temporary grass cover shall be a dwarf grass mix "Pro -Time Companion" or approved equal.
General mix shall be as follows:
' 1. Dwarf Perennial Ryegrass80% by seed count
2. Creeping Red Fescue 20% by seed count
3. Application Rate 100 minimum per acre
2.5 MULCH
A. Mulch shall be straw, or hay, air dried, and free from seeds and course material. Minimum
application shall be 2 tons per acre and general depth shall be 3-4 inches.
PART 3 EXECUTION
3.1 PERIMETER CONTROLS
' A. Flag all construction site clearing limits. Do not disturb areas outside the flagging limits.
Maintain the flagging during the construction project.
B. Perimeter controls include interceptor ditches, berms in fill areas, and sediment fences. Install
all appropriate perimeter controls before beginning major site grubbing or grading operations.
3.2 WET SEASON WORK
A. Wet season work is defined as work between October 1 and May 30. Before working during the
' wet season, meet with local inspector and Owner's representative to review and update the
ESCP and to develop a schedule to ensure that appropriate controls are implemented and
maintained during the wet season work.
B. During wet season work, stabilize soil stockpiles at the end of each workday by diverting flows,
placing covers, or installing sediment barriers around the stockpiles. Limit excavation and bare
ground activities to only that which is required for immediate operations.
' C. If soil erosion and sediment resulting from construction activities is not effectively controlled,
the amount of disturbed area shall be limited to that which can be effectively controlled.
I
' 02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD- TUALATIN SCHOOL DISTRICT 23J 02370 -3
Primed 04/20/04
•
SECTION 02370 1
SLOPE PROTCTION AND EROSION CONTROL
D. Incorporate erosion and sediment control measures at the earliest practicable time and according
to the approved implementation schedule and these specifications.
3.3 STABILIZATION
A. Temporary Stabilization: Stabilize exposed soil surfaces not at finish grade at all times and soil
surfaces at finish grades when working outside the permanent seeding dates. Temporary 1
stabilization includes temporary seeding, mulching, and erosion control matting. Schedule
temporary stabilization on a 14 -day basis or more frequently if needed.
B. Permanent Stabilization: Permanently stabilize exposed soil surfaces at finished grade.
Permanent stabilization methods include riprap protection, seeding, and mulching. Permanent
stabilization includes stabilization of temporary features such as detours, stockpiles, and staged I earthwork. Immediately perform permanent stabilization at each completed excavation and
embankment area except for areas that are scheduled to be redisturbed.
C. If seed of any kind is applied and has not achieved 70% density of the surrounding existing
grass areas prior to the end of the permanent seeding dates, then apply additional stabilization
measures other than seeding.
3.4 SLOPE PROTECTION AND EROSION CONTROL
A. Site preparation should include the removal of all grasses, brush, and sod. Vehicle and foot
traffic should be minimized on bearing surfaces or above prepared subgrade areas to reduce the
amount of disturbed material that would need to be excavated prior to pouring foundation
concrete or the placement of structural fill.
B. Temporary cut slopes included at 1- 1 /2H:1V or steeper be covered with Visqueen sheeting and
have maintained cutoff or diversion ditches shall be at the top of the slopes to prevent surface
water flowing over the excavation face.
I
1
C. Maximum vertical cut section shall be 4 feet for slopes in unweathered glacial till. For cuts
greater than 4 feet high, that portion above the 4 foot vertical section shall be sloped back at not
steeper than 1 H:1 V. Permanent cut slopes shall be provided with cut -off or diversion ditches at
the top to prevent unrestricted flow of water over the cut bank.
3.5 BIOBAGS
A. At no time shall more than a six inch depth of sediment be allowed to accumulate behind bio-
filter bags or fiber rolls. Sediment should be removed or regarded onto the slope, or new lines
of barriers installed uphill o sediment laden barriers. 1
B. Once the upslope area in stabilized, bio- filter bags shall be removed or reused onsite. Fiber
rolls may be left onsite as a semi- permanent, biodegradable landscape feature. Bio- filter bags
fill material shall be incorporated as mulch after completion of site work and must be approved
by Unified Sewerage Agency. Removal will necessitate a post construction site visit. The bags
shall be disposed of at a local recycling or solid waste disposal facility.
3.6 MONITORING
A. Receiving Stream: Observe and record turbidity within 25 feet upstream and downstream of ,
locations where surface waters from the construction site enter the stream. If turbidity is
increased greater than 10% over existing background levels in the stream, further erosion and
sediment control measures will be necessary.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02370 -4
Printed 04/20/04
SECTION 02370
SLOPE PROTCTION AND EROSION CONTROL
B. Sediment Removal: Remove sediment and upgrade or repair as needed within 2 days after the
surrounding area has dried sufficiently to prevent further damage from equipment needed for
' repair operations. If rainfall continues over a 24 -hour period or other circumstances preclude
equipment operation in the area, hand carry and install additional sediment control measures as
needed to catch sediment until trapped sediment can be removed.
C. Catch Basins: Maintain catch basin inserts and other forms of inlet protection by removing
trapped sediment when storage capacity has been reduced by 50 %.
' D. Sediment Controls: Remove sediment from sediment fences, barriers, check dams, and
sediment traps once it has reached one third of the exposed height of the device or storage
depth. Replace aggregate and rock filter material with new aggregate material when sediment
reduces the filtering capacity of the device by one -half.
E. Biofilter Bags: Replace biofilter bags with clean washed bags when removing sediment from
them. Wash bags in an approved sediment control area.
F. Paved Areas: Keep all paved areas clean for the duration of the project. Use cleaning methods
that do not transport sediment -laden water to receiving streams.
' G. Construction Engineers: Add and remove aggregate or other specified material as needed to
maintain the proper function of the construction entrances.
•
3.7 FINISHING AND CLEAN -UP
A. Within 30 days of notification of acceptance of permanent stabilization, remove temporary
erosion and sediment control devices and materials from the area. Remove accumulated
sediment control devices and materials from the area. Remove accumulated sediment before
removing the devices and materials.
' B. Immediately shape and permanently stabilize areas affected by the removal process. All
temporary erosion and sediment control features that are not incorporated into the permanent
work remain the property of the contractor.
C. Do not remove temporary erosion and sediment control devices before permanent stabilization
is accepted.
END OF SECTION
1
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD- TUALATIN SCHOOL DISTRICT 23J 02370 -5
Printed 04 /20/04
SECTION 02510
EXTERIOR WATER DISTRIBUTION
PART 1 GENERAL
1.1 GENERAL REQUIREMENTS
A. Drawings and general provisions of the Contract, including General and other Conditions and
Division 1 — General Requirements sections, apply to the work specified in this section.
1.2 WORK INCLUDED
' A. Provide exterior water distribution system as detailed on drawings. System piping and
appurtenances include:
' 1. Fire water and potable water piping.
1.3 RELATED WORK
A. Section 02315 - Earthwork
B. Section 02316 - Trenching, Backfilling and Compaction
1.4 REFERENCES
A. American Society of Testing and Materials (ASTM)
1. ASTM 2855 Making Solvent- Cemented Joints with Poly (Vinyl Chloride)
(PVC) Plastic Pipe and Fittings
0 2. ASTM C9I3 Precast Concrete Water and Wastewater Structures
' 3. ASTM A 48 Gray Iron Castings
4. ASTM A 88 Seamless Copper Water Tube
' B. American National Standards Institute
1. ANSI B16.12 Cast Iron Threaded Drainage Fittings
2. ANSI B16.18 Cast Copper Alloy Solder Joint Pressure Fittings
' 3. ANSI B 16.22 Wrought Copper and Copper Alloy Solder Joint Pressure
Fittings
' 4. ANSI B 16.26 Cast Copper Alloy Fittings for Flared Copper Tubes
C. American Water Works Association
1 1. AWWA C 104 Cement Mortar Line for Ductile -Iron Pipe and Fittings for Water
2. AWWA C 105 Polyethylene Encasement for Ductile -Iron Piping
1 3. AWWA C 110 Ductile -Iron and Gray -Iron Fittings
4. AWWA C 115 Flanged Ductile Iron Pipe with Threaded Flanges
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD- TUALATIN SCHOOL DISTRICT 23J 02510 -1
Printed 04/2 1/04
SECTION 02510
EXTERIOR WATER DISTRIBUTION
I
5. AWWA C 151 Ductile Iron Pipe Centrifugally Cast
6. AWWA C 509 Resilient Seated Gate Valves
7. AWWA C 600 Installation of Ductile -Iron Water Mains and their Appurtenances
8. AWWA C 651 Disinfecting Water Mains
9. AWWA C 913 Precast Concrete Water and Wastewater Structures
1.5 DEFINITIONS
A. Not used in this section. 1
1.6 SUBMITTALS
A. Manufacturer's Data: Submit manufacturer's standard drawings or catalog data of the following '
items:
1. Fittings, joints, and couplings '
2. Pipe
3. Fire hydrants
4. Valves and valve boxes
B. Manufacturer's Certificates of Conformance: Submit manufacturer's certificates of
conformance or compliance for each of the following materials which are specified to conform
to publications referenced under paragraph "Materials ", in this section:
1. Pipe and fittings including factory- applied linings
2. Pipe joint materials
3. Cast -iron or welded steel frames, covers, and gratings
a. All tests performed by each applicable referenced publication shall have been
performed, whether specified in that publication to be mandatory or otherwise. For
tests which are not specified in the referenced publications to be performed at
111
definite intervals during manufacture, the tests shall have been performed within
three years of the date of submittal of certificates on the same type, class, grade, and
size of material as is being provided for the project.
C. Field/Installation Testing: Submit test results for each of the following installation tests:
1. Pipe pressure test I
2. Disinfection test results _
1.7 QUALITY ASSURANCE
A. Codes and Regulations:
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02510 -2
Pruned 04/21/04
SECTION 02510
EXTERIOR WATER DISTRIBUTION
1
1. All work and materials shall conform to City of Tigard requirements.
2. Whenever indicated materials, workmanship, arrangements or construction is of higher
quality or capacity than that required by the above codes, the drawings and/or
specifications shall govern.
3. Should there be any direct conflict between the state or local codes, laws or regulations
and the drawings and/or specifications, the state or local codes, laws or regulations shall
' govern.
B. Permits and Inspections:
1 1. Unless otherwise distinctly hereinafter specified, this Contractor shall apply and pay for
all necessary permits, fees and inspections required by any public authority having
jurisdiction.
C. Drawings:
1. The working drawings are generally diagrammatic. They do not show every offset, bend
or elbow required for installation in the space provided. They do not show every
dimension, component piece, section, joint or fitting required to complete the project.
All locations for work shall be checked and coordinated with existing conditions in the
' field before beginning construction under this section or any other section. Contractor is
responsible for providing a complete operating system.
2. Existing underground utilities lying within the limits of excavation under this section
shall be verified as to condition, size and location by uncovering, providing such is
permitted by local public authorities with jurisdiction, before beginning construction
' under this section or any other section.
1.8 DELIVERY, STORAGE AND HANDLING
' A. Not used in this section.
1.9 SCHEDULING AND SEQUENCING •
A. Not used in this section.
PART 2 PRODUCTS
1 2.1 GENERAL
' A. Provide the following materials where local jurisdiction will allow to within 5'0" of building
line.
B. Materials for underground utilities to bid as specified below. If upon field identification,
' existing utilities are of different material than specified below, notify owner.
C. All water supply pipe, fittings, valves, and appurtenances shall have a National Sanitation
I Foundation (NSF) approval.
2.2 WATER SUPPLY PIPING (4" DIAMETER AND GREATER)
A. Ductile Iron Piping: Ductile -iron pipe shall conform to AWWA C 151 and shall be minimum
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02510 -3
Printed 04/21/04
SECTION 02510 '
EXTERIOR WATER DISTRIBUTION •
Class 52 thickness. Pipe shall be Tyton joint pipe as manufactured by U.S. Pipe and Foundry
Co. or approved equal. Exposed piping in vaults or aboveground shall be flanged. Flanged
piping shall conform to AWWA C 115. Fittings below grade shall be mechanical joint type,
shall conform to AWWA C 110, and shall have pressure rating at least equivalent to that of the
pipe.
B. Flanged fittings shall conform to ANSI B16.12 and shall be faced and drilled 125 -pound ANSI.
Flange bolts and nuts shall be Grade 2 per AWWA C550 or AWWA Cl 10, standard course
thread and cadmium plated. Pipe and fittings shall have cement/mortar lining conforming to
AWWA C104, standard thickness. Pipe shall be encased in polyethylene per AWWA C105.
Rubber ring gaskets for push -on ductile iron pipe shall conform to ANSI A21.11, be suitable for
• pipe sizes and pressures and be furnished with the pipe. A non -toxic vegetable soup lubricant
shall be supplied from the pipe manufacturer. Gasket material for flanged joints shall consist of
1/8 -inch thick, full face one - piece, cloth - inserted rubber gaskets conforming to AWWA C207.
Pipe and fittings shall have cement/mortar lining conforming to AWWA C 104, standard
thickness. Pipe shall be encased in polyethylene per AWWA C 105.
2.3 TAPPING SLEEVES '
A. Tapping sleeves shall be ductile iron, epoxy coated steel, or stainless steel fittings. Branch outlet
from tapping sleeve shall be Schedule 10 minimum. Sleeve shall conform to locally municipality
requirements.
2.4 VALVES AND VALVE BOXES
A. Valve Boxes: Valve boxes shall be one piece, cast iron type as manufactured by Olympic
Foundry or approved equal. Valve box and cover shall be No. VB910 with a "W" cast into the
top. A 6 -inch D3034 PVC pipe shall be used as a spacer for the lower portion of valve box.
B. Gate Valves: Valves shall be iron body, bronze mounted, resilient seat, NRS with 0-ring seals.
Valves shall conform to AWWA C509. Manufactured by Kennedy, M &H, Clow, American
Flow Control, Mueller, or approved equal.
2.5 HYDRANTS ,
A. Fire hydrants shall be nominal 5 -1/4 -inch main valve opening with six inch bottom connections
and equipped with two 2 -1/2 inch hose nozzles and one 4 -1/2 inch pumped nozzle. Hydrants
shall be of the break -flange or safety-top type. Hydrants shall conform to AWWA C502. The
normal depth of bury shall be 4 feet. Nozzle threads shall be American National Standard. The
inlet connection shall be mechanical joint. Hydrants shall be yellow above the ground line.
Hydrants shall be Kennedy K -81 Guardian, Waterous Pacer, Mueller Centurion or approved
equal.
B. Confirm fire hydrant type, nozzle sizes, and thread configurations with local fire jurisdiction
prior to construction.
PART 3 EXECUTION
3.1 TRENCHING
A. Perform all necessary excavation and backfill required for the installation of work. Any piping
or other work damaged by the contractor's operations shall be repaired at contractor's expense.
B. Keep all excavations free of standing water. Excavations damaged or softened by water or frost
1 shall be re- excavated and filled back to original level with sand, pea gravel or other approved
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02510 -4
Printed 04/21/04
I SECTION 02510
EXTERIOR WATER DISTRIBUTION
I material by the Contractor at his own expense.
I C. Excavate site trenches to the necessary depth and width, removing rocks, unstable soil (muck,
peat, etc.), roots and stumps. Cost of additional excavation to facilitate utility crossovers,
additional offsets, extra bedding connections to existing utilities, connections to plumbing
fixtures, etc., shall be borne by the contractor. Excavation material is unclassified. Width of
I trench shall be adequate for proper installation of piping or conduit.
D. Increase depth as required to avoid other utilities. Encase piping in concrete in areas where
I depth of cover over pipe is less than vendor's recommended minimum depth or as required to
conform to municipal requirements for crossings. Obtain owner's approval prior to installing
such piping and encasement.
I .
E. Grade the bottom of the trench by hand to the line and grade to which the pipe is to be laid, with
thickness allowance for pipe and for greater base when specified or indicated. Pipe will
have a minimum 36 inches of cover. Before laying each section of the pipe, check the grade
I with a straightedge and correct any irregularities found. The trench bottom shall form a
continuous and uniform bearing and support the pipe on solid and undisturbed ground at every
point between bell holes, except that the grade may be disturbed for removal of lifting tackle.
I F. Provide pipe bedding under all pipes. Grade the top of the bedding to the bottom of the pipe
ahead of pipe laying for the full width of the trench. Bedding shall provide a firm support along
entire pipe length.
I G. At the location of each joint, dig bell (joint) holes of ample dimensions in the bottom of the
trench and at the sides where necessary to permit the joint to be made properly and to permit
easy visual inspection of the entire joint.
3.2 PIPE INSTALLATION
I A. Install all ductile iron piping and appurtenances in accordance with vendor's recommendation
and AWWA C600. Install PVC piping and appurtenances in accordance with manufacturer's
accommodations and AWWA C 605.
I B. Normally begin pipe laying at the downstream of the pipeline. The lower segment of the pipe
should be in contact with the shaped bedding throughout its full length. Bell or groove ends of
I rigid pipe and outside circumferential laps of flexible pipe should be placed facing upstream.
C. Inspect all pipe prior to placement in the trench and if necessary clean any material tending to
plug pipe.
I D. Provide proper tools, labor and equipment for efficient execution of the work. All pipe and
fittings to be carefully lowered into the trench to avoid contamination.
I E. Remove all lumps, blisters, and excess coal tar coating from the bell and spigot ends of each
pipe. Wire brush the outside of the spigot and the inside of the bell and wipe clean, dry, and
free from oil and grease before the pipe is laid. Wipe the ends of mechanical joint pipe and
I fittings and of rubber gasket joint pipe and fittings clean of all dirt, grease, and foreign matter.
Do not allow foreign material to enter the pipe while it is being placed in the trench. Do not
allow foreign material to enter the pipe while it is being placed in the trench.
I F. After the first length of push -on joint pipe is installed in the trench, secure pipe in place with
approved backfill material tamped under and along sides to prevent movement. Keep ends clear
of backfill. After each section is jointed, place backfill to the springline to prevent movement.
I 02054
APR 04 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
TIGARD - TUALATIN SCHOOL DISTRICT 23J 02510 -5
Punted 04/21/04
1
SECTION 02510 I
EXTERIOR WATER DISTRIBUTION
G. Lay and join pipe with push -on type joints in strict accordance with the manufacturer's
recommendations. Provide all special tools and devices, such as special jacks, chokers, and
similar items required for the installation. Lubricant for the pipe gaskets shall be furnished by
the pipe manufacturer, and no substitutes will be permitted under any circumstances.
H. Mechanical joint fittings vary slightly with different manufacturers. Install the particular fittings
furnished in accordance with the manufacturer's recommendations. In general, the procedure
shall be as hereinafter specified. Clean the ends of the fittings of all dirt, mud, and foreign
matter by washing with water and scrubbing with a wire brush, after which. Slip the gland and
gasket on the plain end of the pipe. If necessary, lubricate the end of the pipe to facilitate
sliding the gasket in place. Then guide the fitting onto the spigot of the pipe previously laid.
I. Pipelines intended to be straight shall not deviate from the straight line at any joint in excess of
one inch horizontally or vertically. Wherever it is necessary to deflect pipe from a straight line
either in a vertical or horizontal plane, to avoid obstructions, or where long radius curves are
permitted, the amount of deflection allowed shall not exceed 5 degrees per joint.
J. Provide reaction or thrust blocking, as shown, or as directed. The concrete mix shall have a
compressive strength of not less than 3,000 pounds per square inch. Place blocking between the
undisturbed ground and the fitting to be anchored. The bearing surface shall be as shown on
Detail No. 20. Place the blocking so that the pipe and fitting joints will be accessible for
repairs, unless otherwise shown.
K. Install valves, fittings, hydrants, and thrust blocking in accordance with AWWA C 600. '
L. Where water lines cross over or under sanitary sewer lines, a minimum clearance between pipes
of 18" shall be maintained.
3.3 PIPE TEST
A. Notify owner, local plumbing inspector and public works inspector two days before tests. 1
B. Test water mains and water service lines in accordance with the requirements of AWWA C 600
for hydrostatic testing. Test ductile -iron pipelines with mechanical joints shall not exceed the
amounts given in AWWA C 600. The amount of leakage on ductile -iron pipe with mechanical
joints shall be exceed the amounts given in AWWA C 600; no leakage will be allowed at joints
made by any other method.
3.4 CHLORINATION
A. General: Upon completion of all tests and necessary replacements, all domestic water piping
shall be disinfected as required.
B. Method: After thoroughly flushing the system with water to remove sediment, the system shall
be disinfected according to AWWA C 651.
END OF SECTION
•
1
1
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02510 -6
Primed 04/21/04
SECTION 02620
FOUNDATION DRAINAGE
i
PART 1 GENERAL
1 1.1 GENERAL REQUIREMENTS
A. Drawings and general provisions of the Contract, including General and other Conditions and
Division 1 — General Requirements sections, apply to the work specified in this section.
1.2 WORK INCLUDED
' A. System shall include foundation and subdrainage drainage lines and connections to existing
downspouts and drainage lines as detailed.
1.3 RELATED WORK
A. Section 02315 - Earthwork
B. Section 02316 - Trenching, Backfilling, and Compaction
' 1.4 REFERENCES
A. The publications listed below form a part of this specification to the extent referenced. The
publications are referred to in the text by the basic designation only. Latest editions.
' B. American Society for Testing and Materials (ASTM) Publications
1. ASTM C 478 Precast Reinforced Concrete Manhole Sections
2. ASTM C 913 Precast Concrete Water Wastewater Structures
' 3. ASTM D3034 Type PSM Poly (Vinyl Chloride) (PVC) Sewer Pipe and Fittings
4. ASTM D3212 Joints for Drain and Sewer Plastic Pipes Using Flexible Elastomeric
' Seals
5. ASTM F 477 Elastomeric Seals (Gaskets) for Joining Plastic Pipe
' C. Uni -Bell Plastic Pipe Association (UNI) Publication
1. Installation of Polyvinyl Chloride (PVC) Sewer Pipe
' 1.5 DEFINITIONS
A. Not used in this section.
1.6 SUBMITTALS
' A. Manufacturer's Data: Submit manufacturer's standard drawings or catalog cuts of the following
items:
1 1. Fittings
2. Joints and couplings
02054 TIGARD HIGH SCHOOL ADDITION I REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02620 -1
Printed 04/20/04
SECTION 02620
• FOUNDATION DRAINAGE
i
3. Precast drainage structures
4. Pipe '
1.7 QUALITY ASSURANCE
A. Codes and Regulations '
1. Whenever indicated materials, workmanship, arrangements or construction is of higher
quality or capacity than that required by the above codes, the drawings and/or
specifications shall govern.
2. Should there be any direct conflict between the state or local codes, laws or regulations
and the drawings and/or specifications, the state or local codes, laws or regulations shall
govern.
B. Permits and Inspections 1
1. Unless otherwise distinctly hereinafter specified, this contractor shall apply and pay for
all necessary permits, fees and inspections required by any public authority having
jurisdiction.
C. Drawings '
1. The working drawings are generally diagrammatic. They do not show every offset, bend
or elbow required for installation in the space provided. They do not show every
dimension, component piece, section, joint or fitting required to complete the project.
All locations for work shall be checked and coordinated with existing conditions in the
field before beginning construction under this section or any other section. Contractor is
responsible for providing a complete operating system. ,
1.8 DELIVERY, STORAGE AND HANDLING
A. Inspect materials delivered to site for damage: store with minimum of handling. Store materials ,
on site in enclosures or under protective coverings. Do not store materials directly on the
ground. Keep inside of pipes and fittings free of dirt and debris.
B. Handle pipe, fittings, and other accessories in such a manner as to ensure delivery to the trench
in sound undamaged condition. Take special care not to injure coating on pipe and fittings; if
damaged, make satisfactory repairs. Carry pipe to trench; do not drag it. When rubber gaskets
and plastic piping are not to be installed immediately, do not leave them exposed to sunlight, but
store under cover out of direct sunlight.
1.9 SCHEDULING AND SEQUENCING I
A. Not used in this section.
PART 2 PRODUCTS
2.1 GENERAL
A. Materials for underground utilities to bid as specified below. If upon field identification,
existing utilities are of different material than specified below, notify owner.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD- TUALATIN SCHOOL DISTRICT 23J 02620 -2
Printed 04/20/04
' SECTION 02620
FOUNDATION DRAINAGE
2.2 PIPING
A. PVC Pipe: Perforated PVC pipe conforming to ASTM D3034 and SDR 35. The perforations
' shall consist of two rows of two inch slots. The slots shall be transverse to the axis of the pipe.
The two rows of slots shall be 120 degrees on centers. Slot size shall be 0.4 inches.
' 2.3 JOINTING MATERIALS
A. Use only lubricants for jointing materials approved by the manufacturer.
' B. PVC Pipe: Use rubber gaskets for PVC pipe conforming to ASTM F477.
2.4 SUBDRAINAGE FILTERS
' A. Subdrainage geotextile fabric: See Section 02350.
PART 3 EXECUTION
3.1 TRENCHING
A. General: Perform all necessary excavation and backfill required for the installation of work.
Any piping or other work damaged by the contractor's operations shall be repaired at
contractor's expense.
B. Water: Keep all excavations free of standing water. Excavations damaged or softened by water
or frost shall be re- excavated and filled back to original level with material by the contractor at
his own expense.
C. Trench Excavation: Excavate site trenches to the necessary depth and width, removing rocks,
unstable soil (muck, peat, etc.), roots and stumps. Cost of additional excavation to facilitate
' utility crossovers, additional offsets, extra bedding connections to existing utilities, connections
to plumbing fixtures, etc., shall be borne by the contractor. Excavation material is unclassified.
Width of trench shall be adequate for proper installation of piping or conduit.
3.2 GENERAL
A. Install all piping and appurtenances in accordance with vendor's recommendation.
' B. All field joints made in joining of sections of pipe to form culverts and sewers, and to connect to
structures in special sections to be closely fitted, tight, providing a smooth and uniform interior
surface.
C. Inspect all pipe prior to placement in the trench and if necessary clean any material tending to
plug pipe.
D. Provide proper tools, labor, and equipment for efficient execution of the work. All pipe and
fittings to be carefully lowered into the trench to avoid contamination.
E. Connections to Existing Lines: Make connections to existing lines in an approved manner.
Conduct work so that there is minimum interruption of service on existing line.
END OF SECTION
i
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02620 -3
Primed 04n0iO4
SECTION 02630
STORM DRAINAGE SYSTEM
PART 1 GENERAL
' 1.1 GENERAL REQUIREMENTS
A. Drawings and general provisions of the Contract, including General and other Conditions and
Division 1 — General Requirements sections, apply to the work specified in this section.
1 1.2 WORK INCLUDED
' A. System shall include storm drainage lines and branches, catch basins, trench drains, and
connection to existing downspouts and drainage lines. Provide and relocate drainage lines and
structures as noted:
1 1. Storm drainage piping.
2. Precast concrete manholes.
1 3. Standard catch basins.
4. Culverts.
' 5. Clean -outs.
' 6. Connections to existing system.
7. Water quality catch basins.
1.3 RELATED WORK
A. Section 02315 — Earthwork
' B. Section 02316 - Trenching, Backfilling, and Compaction
' 1.4 REFERENCES
A. The publications listed below form a part of this specification to the extent referenced. The
publications are referred to in the text by the basic designation only.
B. American Society for Testing and Materials (ASTM) Publications
1. ASTM A 536 Ductile Iron Castings
2. ASTM A 615 Standard Specification for Deformed and Plain Steel Bars for Concrete
' Reinforcement
3. ASTM A 746 Ductile Iron Gravity Sewer Pipe
4. ASTM C 478 Precast Reinforced Concrete Manhole Sections
5. ASTM C 564 Rubber Gaskets for Cast Iron Soil Pipe and Fittings
1 6. ASTM C 913 Precast Concrete Water Wastewater Structures
7. ASTM C 923 Standard Specification for Resilient Connectors Between Reinforced
Concrete Manhole Structures
'
02054
APR 04 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
TIGARD - TUALATIN SCHOOL DISTRICT 23J 02630 -1
Primed 04/20/04
SECTION 02630
STORM DRAINAGE SYSTEM
1
8. ASTM D 2729 Poly (Vinyl Chloride) (PVC) Sewer Pipe and Fittings
9. ASTM D 3034 Type PSM Poly (Vinyl Chloride) (PVC) Sewer Pipe and Fittings '
10. ASTM D 3212 Joints for Drain and Sewer Plastic Pipes Using Flexible Elastomeric
Seals I
11. ASTM F 477 Elastomeric Seals (Gaskets) for Joining Plastic Pipe
C. American Water Works Association ,
1. AWWA C 104 Cement - Mortar Lining for Ductile -Iron Pipe and Fittings for Water
2. AWWA C 110 Ductile Iron and Gray -Iron Fittings 3" 48 for Water and Other
Liquids
3. AWWA C 153 Ductile -Iron Compact Fittings 3" - 16" for Water and Other Liquids '
4. AWWA C 600 Installation of Ductile Iron Mains
D. Uni -Bell Plastic Pipe Association (UNI) Publication
1. Installation of Polyvinyl Chloride (PVC) Sewer Pipe ,
1.5 DEFINITIONS
A. Not used in this section.
1.6 SUBMITTALS
A. Manufacturer's Data: Submit manufacturer's standard drawings or catalog cuts of the following
items:
1. Fittings '
2. Joints and couplings
3. Precast drainage structures and manholes
4. Pipe I
5. Catch basins
6. Stormwater management filter catch basins ,
B. Manufacturer's Certificates of Conformance: Submit manufacturer's certificates of conformance
or compliance for each of the following materials which are specified to conform to publications
referenced under paragraph, "Materials," in this section:
1. Pipe and fittings, including factory- applied linings
2. Pipe joint materials
3. Cast -iron or welded steel frames, covers, and gratings '
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02630 -2
Printed 04/20/04
SECTION 02630
STORM DRAINAGE SYSTEM
4. Manholes and pipe penetration seals
C. All tests performed by each applicable referenced publication shall have been performed,
whether specified in that publication to be mandatory or otherwise. For tests which are not
specified in the referenced publications to be performed at definite intervals during
' manufacture, the tests shall have been performed within three years of the date of submittal of
certificates on the same type, class, grade, and size of material as is being provided for the
project.
' D. Field/Installation Testing: Submit test results for each of the following installation tests:
1. Hydrostatic testing of gravity lines.
2. Deflection testing for flexible pipe.
' E. Operations & Maintenance Manual: Submit complete O &M manual for stormwater
management filter catch basin
F. Maintenance Training: Stormwater Management, Inc., shall provide a training session to
' Templeton Elementary School maintenance staff regarding proper procedures for care and
maintenance of storm filter catch basins.
' 1.7 QUALITY ASSURANCE
A. Codes and Regulations
1111 1. All work and materials shall conform to City of Tigard requirements.
2. Whenever indicated materials, workmanship, arrangements or construction is of higher
' quality or capacity than that required by the above codes, the drawings and/or
specifications shall govern.
3. Should there be any direct conflict between the state or local codes, laws or regulations
' and the drawings and/or specifications, the state or local codes, laws or regulations shall
govern.
' B. Permits and Inspections
1. Unless otherwise distinctly hereinafter specified, this contractor shall apply and pay for
' all necessary permits, fees and inspections required by any public authority having
jurisdiction.
C. Drawings
1. The working drawings are generally diagrammatic. They do not show every offset, bend
or elbow required for installation in the space provided. They do not show every
dimension, component piece, section, joint or fitting required to complete the project.
All locations for work shall be checked and coordinated with existing conditions in the
field before beginning construction under this section or any other section. Contractor is
' responsible for providing a complete operating system.
2. Existing underground utilities lying within the limits of excavation under this section
shall be verified as to condition, size and location by uncovering, providing such is
permitted by local public authorities with jurisdiction, before beginning construction
' 02054
APR 04 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
TIGARD - TUALATIN SCHOOL DISTRICT 23J 02630 -3
Printed 04 /20/04
SECTION 02630 '
STORM DRAINAGE SYSTEM
under this section or any other section. '
1.8 DELIVERY, STORAGE AND HANDLING
A. Piping: Inspect materials delivered to site for damage: store with minimum of handling. Store '
materials on site in enclosures or under protective coverings. Do not store materials directly on
the ground. Keep inside of pipes and fittings free of dirt and debris.
B. Precast Concrete: Handle precast sections with care to avoid chipping and breakage; store as
directed. Protect precast concrete from contact with the soil and exposure to weather; keep dry
until used. Use of precast concrete containing frost will not be permitted.
C. Metal Items (Except Concrete Reinforcement): Check upon arrival; identify and s egregate as to
types, functions, and sizes. Store in a manner affording easy accessibility and not causing
excessive rusting or coating with grease or other objectionable materials.
D. Handling: Handle pipe, fittings, and other accessories in such a manner as to ensure delivery to
the trench in sound undamaged condition. Take special care not to injure coating on pipe and
fittings; if damaged, make satisfactory repairs. Carry pipe to trench; do not drag it. When
rubber gaskets and plastic piping are not to be installed immediately, do not leave them exposed
to sunlight, but store under cover out of direct sunlight. '
1.9 SCHEDULING AND SEQUENCING
A. Not used in this section. ,
PART 2 PRODUCTS
2.1 GENERAL
A. Materials for underground utilities to bid as specified below. If upon field identification,
existing utilities are of different material than specified below, notify owner.
2.2 PIPING
A. Ductile Iron Pipe: Use ductile iron pipe conforming to ASTM A 746 Class 52, with Push -on
Joint or Mechanical Joints per AWWA C 110 or AWWA C 153. Ductile iron pipe shall be
lined with cement mortar and seal coated in accordance with ANSI Standard A21.4 and AWWA
C 104.
B. PVC Pipe: Use PVC pipe conforming to ASTM D3034, SDR 35, (4" to 15 ") or ASTM F679,
PS 46, (18" to 27 ").
2.3 JOINTING MATERIALS
A. Use only lubricants for jointing materials approved by the manufacturer.
•
B. Cast Iron and Ductile Iron Pipe: Use rubber gaskets conforming to ANSI A21.11. '
C. PVC Pipe: Use rubber gaskets for PVC pipe conforming to ASTM F477.
2.4 DRAINAGE STRUCTURES ,
A. Precast Concrete Manhole Sections: Precast concrete manhole risers, base sections, and tops
shall conform to ASTM C478. Gaskets for joints between sections shall conform to ASTM ,
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02630 -4
rr;"«d 04/20/04
' SECTION 02630
STORM DRAINAGE SYSTEM
' C443. Resilient connectors for making joints between manhole and pipes entering manhole
shall conform to ASTM C923.
' 2.5 METAL ITEMS
A. Standard Frames, Covings, and Gratings: Frames, covers, and gratings shall be of cast iron per
' ASTM A 48. Frames, covers, and gratings shall be rated for AASHTO H -20 traffic loading.
B. Manhole Steps: Shall conform to ASTM C478 and shall be of zinc coated or polypropylene
' coated steel. Aluminum steps or rungs will not be permitted. Steps are not required in
manholes, curb inlets, or catch basins less than four feet deep.
C. Metal Catch Basins: Shall be 10 gauge steel catch basins specified for AASHTO H -20 highway
' loading. Interior coated with asphalt coating. Manufactured by Lynch Company or approved
equal.
2.6 WATER QUALITY FILTER CATCH BASINS
A. All internal components including PVC piping, filter cartridge(s) and filter media (as specified
in the StormFilter data block) shall be provided by Stormwater Management Inc., 2035 NE
I Columbia Blvd., Portland, OR 97211 (800) 548 -4667.
B. PVC Piping: All internal PVC piping and fittings shall meet ASTM D1785.
' C. Filter Cartridge: Cartridge bottom pan, inner ring, and hood shall be constructed from linear
low- density polyethylene. Cartridge screen shall consist of galvanized 1" x 1/2" welded wire
fabric (16 gauge minimum) with a bonded PVC coating. Internal parts shall consist of PVC or
ABS pipe and fittings. Siphon - priming float shall be constructed from linear low- density
polyethylene. Outer filter fabric shall be 10 x 8.5 clear fiberglass mesh. Inner filter fabric shall
be 10 x 8.5 clear fiberglass mesh over Enkamat 7210 or woven polyethylene with a US Standard
' Sieve #20 opening size. All miscellaneous screws, nuts, and fasteners shall be aluminum or
stainless steel.
' D. An orifice plate shall be supplied with each cartridge to restrict flow rate to 15 gpm maximum.
E. Filter Media: Filter media shall be by Stormwater Management or approved alternate. Filter
media shall consist of perlite media, as specified in the StormFilter data block. Perlite media
' shall be made of natural siliceous volcanic rock free of any debris or foreign matter. The
expanded perlite shall have a bulk density ranging from 6.5 to 8.5 lb/ft3 and particle sizes
ranging from 0.06 to 0.50 inches.
' F. Steel Catch Basin: Catch basin shall be all welded steel construction, fabricated from 1/4 -inch
steel, coated inside and out with asphaltic paint, and rated for 20,000 lb loading.
' G. Catch Basin Grate: Grating shall be ductile iron construction and rated for 20,000 lb loading.
H. Catch Basin Solid Lid: Solid lid shall be diamond -plate construction with 2 -inch angle support,
' all sides coated with asphaltic paint, and rated for 20,000 lb loading.
PART 3 EXECUTION
' 3.1 TRENCHING
A. General: Perform all necessary excavation and backfill required for the installation of work.
Any piping or other work damaged by the contractor's operations shall be repaired at
' 02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02630 -5
Printed 04 /20/04
SECTION 02630 I
STORM DRAINAGE SYSTEM
contractor's expense. ,
B. Water: Keep all excavations free of standing water. Excavations damaged or softened by water
or frost shall be re- excavated and filled back to original level with material by the contractor at
his own expense.
C. Trench Excavation: Excavate site trenches to the necessary depth and width, removing rocks,
unstable soil (muck, peat, etc.), roots and stumps. Cost of additional excavation to facilitate
utility crossovers, additional offsets, extra bedding connections to existing utilities, connections
to plumbing fixtures, etc., shall be borne by the contractor. Excavation material is unclassified.
Width of trench shall be adequate for proper installation of piping or conduit.
D. Increase depth as required to avoid other utilities. Encase piping in areas where depth of cover
over pipe is less than vendor's recommended minimum depth or as required to conform to ,
governmental requirements for crossings. •
E. Obtain owner's approval prior to installing such piping and encasement. '
3.2 GENERAL
A. Install all piping and appurtenances in accordance with vendor's recommendation. '
B. Normally begin pipe laying at the downstream of the pipe line. The lower segment of the pipe
should be in contact with the shaped bedding throughout its full length. Bell or groove ends of
rigid pipe and outside circumferential laps of flexible pipe should be placed facing upstream.
C. All field joints made in joining of sections of pipe to form culverts and sewers, and to connect to
structures in special sections to be closely fitted, tight, providing a smooth and uniform interior
surface.
D. Inspect all pipe prior to placement in the trench and if necessary clean any material tending to
plug pipe.
E. Provide proper tools, labor, and equipment for efficient execution of the work. All pipe and
fittings to be carefully lowered into the trench to avoid contamination.
F. The work covered by this section shall terminate at a point approximately 5 feet from the
building unless otherwise indicated on the drawings.
G. Connections to Existing Lines: Make connections to existing lines in an approved manner.
Conduct work so that there is minimum interruption of service on existing line. ,
3.3 SPECIAL REQUIREMENTS
A. Cast -Iron and Ductile Iron Soil Piping: Install pipe and fittings in accordance with the general '
requirements for installation of pipelines and with the recommendations of the pipe
manufacturer. Make joints with the rubber gaskets previously specified for joints with this
piping. Assemble joints in accordance with the recommendations of the pipe manufacturer and
AWWA C6
B. PVC Plastic Piping: Install pipe and fittings in accordance with the general requirements for
installation of pipelines and with the requirements of ASTM D2321 for laying and joining pipe
and fittings. Make joints with the gaskets previously specified joints with this piping; assemble
these joints in accordance with the requirements of ASTM D2321 for assemble of joints. Make
joints to other Pipe materials in accordance with the recommendations of the plastic pipe '
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02630 -6
Printed 04 /20/04
' SECTION 02630 -
STORM DRAINAGE SYSTEM
' manufacturer.
3.4 MANHOLES
A. Forming of Gravity Manhole Base and Invert. Form the invert t a half circle before initial set
of the concrete with a smooth transition from inlet to out. Apply final grout coat to the manhole
' base with a sack finish. Apply Portland Cement grout to the joint between the sewer pipe and
the manhole wall inside and out to insure a watertight seal.
B. Place the first manhole riser section before the concrete base has taken its initial set. Bed the
ring into the concrete. Apply Portland Cement grout inside and out to insure a watertight seal.
C. Place the manhole riser and cone sections together using full bed of Portland Joint compound or
I rubber gasket to insure a watertight joint.
D. When using rubber gasket material, prime both ends of manhole cone and risers. Apply primer
' to clean and dry concrete. Install rubber gasket in accordance with manufacturer's
recommendations.
E. Use flat slab top for manholes 5 feet or less in height, and eccentric cone section for manholes
' over 5 feet in height. Height, measured from centerline invert to rim elevation, will be used.
3.5 WATER QUALITY FILTER CATCH BASINS
' A. Backfill: Shall be 3/4 -inch minus rock or as otherwise specified in the general technical
specifications.
B. Catch basin floor shall be set level and plumb.
C. Contractor shall prevent sediment and debris from entering the filter unit during construction.
•
' D. Contractor shall compact sub -base to 95% of maximum density or as otherwise specified by
engineer. Unsuitable material below sub -grade shall be replaced as directed by engineer.
E. If necessary, the inlet chamber may be filled with clean water to assist in preventing flotation
during construction until the structure is backfilled and the concrete collar is poured.
' F. Contractor shall compact backfill to 95% of maximum density or as otherwise specified by
engineer.
G. Catch basin outlet shall be connected to downstream (and upstream, if applicable) piping using
a flexible -type coupling.
H. Concrete perimeter slab shall be constructed I foot wide and 6 inches thick. Slab shall include
two #4 rebar hoops with minimum 6 -inch overlap at closure. Allow 2 -inch vertical spacing
between hoops and minimum 2 -inch clearance from concrete surfaces.
I. Catch Basin Storm Filter shall be provided complete with cartridge(s) and cartridge media
installed.
' J. The project site shall be clean and free of dirt and debris before runoff is allowed to enter the
filter. Site work shall be in a complete condition as approved by the engineer. The project site
includes any surface that contributes storm drainage to the system. The inlet/outlet chamber and
filter chamber(s) shall be free of construction debris and sediment before the system is placed in
' operation. Contractor shall the 4 -inch temporary construction plug(s) between the inlet
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 233 02630 -7
Printed 04/20/04
- SECTION 02630
STORM DRAINAGE SYSTEM
chamber and filter chamber(s) to place the system in operation. The 4 -inch cleanout plug in the
overflow weir wall shall remain in place for proper operation of the system
3.6 TRACER WIRE '
A. Install tracer wire in all trenches for sanitary sewers. Place the tracer wire directly over the pipe
centerline and on top of the pipe zone material. Splice a branch tracer wire at each manhole and
extend a single wire up the outside of the manhole. Drill a 10 mm (3/8 inch) diameter hole
through the manhole wall within 0.5 m (18 inches) of the finish grade of the manhole rim.
Extend the wire through the hole with a 1 m (3 foot) minimum length of coiled wire inside the
manhole. Seal the opening in the manhole wall with silicone sealant. Place a branch tracer wire
over each pipe connected to the main sewer. Make tracer wire splices using a high- pressure
compression type solderless connector to securely join the wires both mechanically and
electrically. Insulate splices to be moisture and waterproof. Splices wrapped with tape will not
be accepted as waterproof. Have all splice kits approved prior to installation. Test all tracer
wire with locating equipment prior to acceptance.
3.7 HYDROSTATIC TESTING (GRAVITY LINES) '
A. Notify Owner, local Plumbing Inspector, and Public Works Inspector two days before tests.
B. Pipe and joints shall sustain losses not exceeding 0.04 gallons per hour per inch diameter per
100 feet when field tested by exfiltration methods, except 0.3 gallons per hour may be used in
arid climate zones if approved by the engineer. '
C. The hydrostatic head for test purposes shall exceed the maximum estimated ground water level
in the section being tested by at least 72 inches and in no case shall be less than 72 inches above
the inside top of the highest section of pipe in the test section, including service connections.
The engineer shall make the final decisions regarding test height for the water in the pipe section
being tested. The length of pipe tested by exfiltration shall be limited so that the pressure on the
invert of the lower end of the section shall not exceed 28 feet of water column. I
D. The pipe test section may be filled 24 hours prior to time of exfiltration testing, if desired, to
permit normal absorption into the pipe walls to take place.
E. All service connection footage shall be taken into account in computing allowable leakage.
3.8 DEFLECTION TESTING FOR FLEXIBLE PIPE '
A. Make a deflection test on entire length of installed plastic pipeline on completion of all work
adjacent to and over the pipeline, including tests, backfilling, placement of fill, grading, paving,
concreting, and any other superimposed loads. Deflection of pipe in the installed pipeline under
all external loads shall not exceed 4.5 percent of the normal inside diameter of pipe. Determine
whether the allowable deflection has been exceeded by use of a pull - through device, or a
deflection measuring device.
B. Measure deflections through each run of installed pipe. If deflection readings in excess of 4.5
percent of normal inside diameter of pipe are obtained, retest pipe. If retest continues to show a
deflection in excess of 4.5 percent of normal diameter of pipe, replace pipe that has excessive
deflection and completely retest in same manner and under same conditions as previously
specified.
3.9 REPAIRS
A. The contractor shall locate and repair any sections failing to pass the required tests and I
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02630 -8
Printed 04/20/04
SECTION 02630
STORM DRAINAGE SYSTEM
inspections and shall then repeat the specified tests and inspections on those sections at no
expense to the owner.
B. Following a successful hydrostatic or air test, visible infiltration of groundwater in any section
shall be considered evidence that the original test was in error or that failure of the section has
occurred. The contractor shall correct such failures, and retest the repaired sections, at no
expense to the owner.
END OF SECTION
. 1
1
1
1
-
1
1
I.
1
i
1
1
1
1 02054
APR 04 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
TIGARD - TUALATIN SCHOOL DISTRICT 23J 02630 -9
Printed 04/20/04
SECTION 02740
ASPHALT CONCRETE PAVING
PART 1 GENERAL
' 1.1 GENERAL REQUIREMENTS
A. Drawings and general provisions of the Contract, including General and other Conditions and
t Division 1 — General Requirements sections, apply to the work specified in this section.
1.2 WORK INCLUDED
A. This specification covers all labor, equipment, and materials required to provide asphalt paving
as shown on the plans including new paving surfaces and restoration of asphalt paving along
pipe trench runs in parking areas and street crossings.
1.3 RELAT WORK
' A. Section 02315 - Earthwork
1.4 REFERENCES (Latest Editions)
' A. Oregon Department of Transportation (ODOT) /American Public Works Association (APWA)
Oregon Chapter.
' 1. OSSC Oregon Standard Specifications for Construction
B. American Association of State Highway and Transportation Officials (AASHTO) Publications:
M l. AASHTO T 102 Spot Test of Asphaltic Materials Quantitative Extraction of Bitumen
From Bituminous Paving Mixtures (Method A)
' C. American Society for Testing and Materials (ASTM) Publications:
1. ASTM C 136 Sieve Analysis of Fine and Coarse Aggregates
' 2. ASTM D 75 Sampling Aggregates
3. ASTM D 140 Sampling Bituminous Materials
4. ASTM D 979 Sampling Bituminous Paving Mixtures
5. ASTM D 1557 Moisture- Density Relations of Soils and Soil- Aggregate Mixtures
Using 10 -lb Rammer and 18 -inch Drop
6. ASTM D 1664 Coating and Stripping of Bitumen from Bituminous Paving Mixtures
7. ASTM D 2172 Quantitative Extraction of Bitumen from Bituminous Paving Mixtures
8. ASTM D 2419 Sand Equivalent Value of Soils and Fine Aggregate
9. ASTM D 2922 Tests for Density of Soil and Soil Aggregate in place by Nuclear
Methods
1.5 DEFINITIONS
A. Not used in this section.
' 02054
APR 04 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
TIGARD- TUALATIN SCHOOL DISTRICT 23J 02740 -1
Printed 04/20/04
SECTION 02740
ASPHALT CONCRETE PAVING
1.6 SUBMITTALS 1
A. Manufacturer's data showing compliance with referenced standards and results of specified
testing.
B. Asphalt job mix formula for each type of hot mixed asphalt concrete (HMAC) material
specified or indicated. The job mix formula (JMF) shall meet the requirements outlined in the
OSSC Section 00745.
1.7 QUALITY ASSURANCE
A. Provide HMAC quality control and mix design verification (MDV) conformin g to the OSSC
Section 00745.
•
B. Owner may employ, at its own expense, a testing and inspection laboratory to perform sampling,
testing and inspection as specified below.
1.8 DELIVERY, STORAGE AND HANDLING '
A. Not used in this section.
1.9 SCHEDULING AND SEQUENCING
•
A. Not used in this section.
1.10 STATE STANDARD SPECIFICATIONS
A. Whenever this specification is referenced, the following is understood:
1. Wherever the term Division occurs, it shall mean Owner. Whenever the term engineer or
project manager occurs, it shall mean the Owner's representative.
2. All references to statistical testing are deleted.
3. Whenever a discrepancy occurs between the standard specifications and this ,
specification, it is understood that this specification governs.
4. All references to measurement and payment are deleted. '
PART 2 PRODUCTS
2.1 MATERIALS I
A. Subbase, Aggregate Base and Leveling Courses: As specified in Section 02315, "Earthwork ".
B. Hot Mixed Asphalt Concrete (HMAC): Provide a hot plant mixed, uniformly coated mixture of
asphalt cement, graded aggregate, and additives conforming to OSSC Section 00745 for all
paved areas in thickness indicated.
1. Level 3 HMAC HMAC for use in applications exposed to moderate truck
traffic. 1
C. Asphalt Cement: Shall conform to Section 00745 of the OSSC Section 00745. The asphalt
cement shall be heated and delivered to the mixer at a temperature recommended by the asphalt
manufacturer for the temperature- viscosity relationship of the cement.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02740 -2
Printed 04/20/04
SECTION 02740 •
ASPHALT CONCRETE PAVING
D. Aggregate: Provide aggregate material for HMAC as specified in OSSC Section 00745.
E. Reclaimed Asphalt Pavement (RAP) Material: Reclaimed HMAC pavement (RAP) material
used in the production of new HMAC is optional. No more than 20% RAP material will be
allowed in the new HMAC pavement. RAP material will not be allowed in open graded HMAC
or Level 4 dense graded HMAC wearing courses.
F. Mix Type and Broadband Limits: Furnish the type(s) of HMAC as indicated. The broadband
limits for each of the mix types are specified in OSSC Section 00745.
1 1. 3/4" Dense Graded Mix (Class "B')
PART 3 EXECUTION
3.1 PREPARATION OF SUBGRADE
A. Requirements for subgrade are specified in Section 02315, "Earthwork ". Prior to construction
of asphaltic concrete, clean previously constructed subgrade of all foreign substances. Inspect
surfaces for the specified compaction and trueness to line and grade as specified below.
3.2 BASE COURSE
A. Place aggregate base as required in accordance with Section 02315, "Earthwork ".
3.3 MAINTENANCE
A. Maintain the base course until the asphaltic pavement is in place. Maintenance shall include
drainage, rolling, shaping, and water as necessary to maintain the course in proper condition.
Maintain sufficient moisture at the surface to prevent a dusty condition by light sprinkling with
' water. Areas of completed base course that are damaged prior to asphalt placement shall be
conditioned, reshaped and recompacted in accordance with the requirements of this
specification at no additional cost.
' 3.4 FINISH SURFACE
A. The finish surface of base course, when tested for uniformity of slope, shall not deviate at any
' point more than 3/8 inch from bottom of a 10 -foot straightedge laid in any direction. When base
course is constructed in more than one layer, specified smoothness requirements shall apply
only to top surface.
' 3.5 PRIME COAT
A. Prior to the application of the asphaltic concrete, apply a prime coat of liquid asphalt at the rate
of .25 gallons per square yard on the prepared compacted base in accordance with the standard
specifications. Apply liquid asphalt by pressure distributors. Allow sufficient time before
placing the asphalt concrete to permit the prime coat asphalt to penetrate the prepared
compacted base.
3.6 ASPHALT CONCRETE
' A. Requirements: The asphalt concrete shall consist of mineral aggregate, uniformly mixed with
bituminous material in a central plant in accordance with the OSSC Section 00745 for HMAC.
The mixing plant and construction equipment shall conform to the requirements of the standard
' specifications.
' 02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02740 -3
Printed 04/20/04
SECTION 02740
ASPHALT CONCRETE PAVING
1
B. Placing: Deliver bituminous mixtures to the roadbed at temperatures specified in the OSSC
Section 00745. Cover all loads with tarpaulin or other material during transportation.
C. Season and Temperature Limitations: Per OSSC Section 00745.
D. Compaction: Initial or breakdown rolling and the final rolling of the uppermost layer of the
asphalt concrete shall be in accordance with OSSC Section 00745. Compaction by vehicular
traffic shall not be permitted.
E. Joining Pavement: Carefully make joints between old and new pavements or between '
successive days' work made in such manner as to insure a continuous bond between old and new
sections of the course. Transverse and longitudinal joints shall be made as specified in OSSC
Section 00745. Paint all joints with a uniform coat of tack coat before the fresh mixture is
placed.
F. Protection of Pavement: After final rolling, no vehicular traffic of any kind shall be permitted on
the pavement until it has cooled and hardened and in no case less than 6 hours.
G. Finishing and Cleaning Up: Pavement smoothness and corrections to pavement roughness shall
conform to tolerances specified in the OSSC Section 00745.
3.7 FIELD TESTS
A. Sampling and Testing_ Owner may direct and reimburse an independent testing laboratory to I
take samples and perform tests for the determination of in -place density of compacted base
course and percent of asphalt content. The contractor shall replace the pavement where samples
are removed. No payment will be made for the areas of pavement deficient in composition,
Ift
density or thickness uritil they are removed and replaced.
1. Perform tests on base course in accordance with Section 02315, "Earthwork ". 1
2. Determine asphalt content in percent by extraction in accordance with AASHTO T164
or ASTM D2172, Method A.
3. Frequency of Tests: Minimum number and type of quality control tests shall be as
follows:
Base Course Tests
a. Maximum density determination Note'
b. In -place density Note
c. Surface tolerance Note
Bituminous Paving ,
a. Extraction test percent asphalt and gradation Note
Notes:
1. One for each different gradation with in place density requirements.
2. One set of three tests for each 2,000 square yards, or fraction thereof.
1
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02740 -4
Printed 04/20/04
' SECTION 02740
ASPHALT CONCRETE PAVING
1
3. Inspection and tests shall be made at the start of the pavement work; one test for each
400 square yards of surface, or fraction thereof.
4. One test for each 100 tons of bituminous material; at least one test per project, for
quantity less than 100 tons.
I
END OF SECTION
1
1 I
I
1
1
1
1
I
1
1
' 02054
APR 04 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
TIGARD- TUALATIN SCHOOL DISTRICT 23J 02740 -5
Printed 04/20/04
t SECTION 02750
SITE CONCRETE
PART 1 GENERAL
' 1.1 GENERAL REQUIREMENTS
A. Drawings and general provisions of the Contract, including General and other Conditions and
Division 1 — General Requirements sections, apply to the work specified in this section.
1.2 WORK INCLUDED
A. This work consists of furnishing, placing and finishing commercial grade concrete curbs,
islands, traffic separators, driveways, walks, monolithic curb and sidewalks, miscellaneous
surfaces, and stairs in close conformity to the lines, grades and dimensions shown or
1 established. These items in this section will be collectively referred to as "structures."
1.3 RELATED WORK
A. Section 02315 - Earthwork
1.4 REFERENCES
A. ACI 211.1 (1991) Selecting Proportions for Normal, Heavyweight, and Mass
Concrete
I
B. ACI 301 (1996) Structural Concrete for Buildings
g
C. AC 1 305R (1991) Hot Weather Concreting
I ' V D. ACI 306.1 (1990) Cold Weather Co
E. ASTM A 184/A 184 M (1990) Fabricated Deformed Steel Bar Mats for Concrete
� Reinforcement
F. ASTM A 185 (1994) Steel Welded Wire Fabric, Plain for Concrete Reinforcement
G. ASTM A 497 (1995) Steel Welded Wire Fabric, Deformed for Concrete
Reinforcement
1 H. ASTM A 615/A 615M (1995; Rev. B) Deformed and Plain Billet -Steel Bars for Concrete
Reinforcement
i I. ASTM A 775/A 775M (1994; Rev. D) Epoxy- Coated Reinforcing Steel Bars
' J. ASTM C 31 (1991) Making and Curing Concrete Test Specimens in the Field
K. ASTM C 31 (1993) Concrete Aggregates
L. ASTM C 94 (1994) Ready -Mixed Concrete
M. ASTM C 143 (1990; Rev. A) Slump of Hydraulic Cement Concrete
N. ASTM C 150 (1995) Portland Cement
O. ASTM C 171 (1995) Sheet Materials for Curing Concrete
APR TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
AP 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02750 -1
Printed 04/20/04
SECTION 02750 ,
SITE CONCRETE
P. ASTM C 172 (1990) Sampling Freshly Mixed Concrete I
Q. ASTM C 231 (1991; Rev. B) Air Content of Freshly Mixed Concrete by the Pressure
Method ,
R. ASTM C 260 (1995) Air - Entraining Admixtures for Concrete
S. ASTM C 309 (1995) Liquid Membrane - Forming Compounds for Curing Concrete
T. ASTM C 494 (1992) Chemical Admixtures for Concrete
U. ASTM C 618 (1995) Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use as
a Mineral Admixture in Portland Cement Concrete
1.5 DEFINITIONS
A. Not used in this section.
1.6 SUBMITTALS
A. General: Submit the following according to the conditions of the contract and Division lof the
specification sections.
B. Product data for proprietary materials and items, including reinforcement and forming
accessories, admixtures, joint systems, curing compounds, dry-shake finish materials, and others
data.
C. Design mixes for each class of concrete. Include revised mix proportions when characteristics
of materials, project conditions, weather, test results, or other circumstances warrant
adjustments.
D. Laboratory test reports for evaluation of concrete materials and mix design tests.
1.7 QUALITY ASSURANCE
A. Concrete Standards: Comply with provisions of the following standards, except where more
stringent requirements are indicated.
1. American Concrete Institute (ACI) 301, "Specifications for Structural Concrete for
Buildings."
2. ACI 318, "Building Code Requirements for Reinforced Concrete." i
3. Concrete Reinforcing Steel Institute (CRSI) "Manual of Standard Practice."
B. Concrete Manufacturer Qualifications: Manufacturer of ready -mixed concrete products
complying with ASTM C 94 requirements for production facilities and equipment.
C. Concrete Testing Service: Engage a qualified independent testing agency to perform materials
evaluation tests and to design concrete mixes.
1.8 DELIVERY, STORAGE AND HANDLING I
A. Not used in this section.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD- TUALATIN SCHOOL DISTRICT 23J 02750 -2
Pnntcd 04/20/04
t SECTION 02750
SITE CONCRETE
' 1.9 SCHEDULING AND SEQUENCING
A. Not used in this section.
' 1.10 PROJECT CONDITIONS
1 A. Traffic Control: Maintain access for vehicular and pedestrian traffic as required for other
construction activities.
' 1. Temperature and Weather Requirements
2. Do not place concrete when temperature or weather will affect performance or
appearance of concrete.
Maximum Wind Velocity: 15 mph
3.
•
1 4. Minimum Ambient Temperature: 40 °F
5. Precipitation: None expected in 8 hours
I B. Substrate Requirements
1. Do not place concrete on muddy or frozen substrate
2. Remove mud, dirt, and ice from formwork surface
PART 2 PRODUCTS
2.1 FORMS
A. Design of the formwork is the contractor's responsibility.
B. Form Materials: Plywood, metal, metal -framed plywood, or other acceptable panel -type
materials to provide full- depth, continuous, straight, smooth exposed surfaces. Use flexible or
' curved forms for curves of a 100 -foot or less radius.
C. Form Release Agent: Provide commercial formulation form- release agent with a maximum of
' 350 g/L volatile organic compounds (VOCs) that will not bond with, stain, or adversely affect
concrete surfaces and will not impair subsequent treatments of concrete surfaces.
D. Forms and Formwork Accessories
1. Exposed Plywood Forms: Plyform, Class I or II
2. Lumber and Steel Forms: Smooth face lumber or steel
3. Chamfer Strip: 1 inch radius
4. Steel Pipe Sleeves: ASTM A 53
' 5. Expansion and Isolation Joint Fillers: Granulated cork, V2 inch thick, ASTM D 1752,
Type II
6. Form Joint Tape: Closed cell PVC foam with pressure sensitive adhesive on one side
1
'
02o54 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD- TUALATIN SCHOOL DISTRICT 23J 02750 -3
Printed 04/20/04
SECTION 02750
SITE CONCRETE
2.2 REINFORCING MATERIALS
A. Reinforcing Bars and Tie Bars: ASTM A 615, Grade 60, deformed. I
B. Joint Dowel Bars: Plain steel bars, ASTM A 615, Grade 60. Cut bars true to length with ends
square and free of burrs.
C. Hook Bolts: ASTM A 307, Grade A bolts, internally and externally threaded. Design hook bolt
joint assembly to hold coupling against pavement form and in position during concreting
operations, and to permit removal without damage to concrete or hook bolt.
D. Supports for Reinforcement: Chairs, spacers, dowel bar supports and other devices for spacing,
supporting, and fastening reinforcing bars, welded wire fabric, and dowels in place. Use wire
bar -type supports complying with CRSI specifications.
1. Use supports with sand plates or horizontal runners where base material will not support
chair legs.
2.3 CONCRETE MATERIALS
A. Portland Cement: ASTM C 150, Type I. Use one brand of cement throughout Project unless 1
otherwise approved in writing by the Owner's representative.
B. Fly Ash: ASTM C 618, Type F. t
• C. Normal- Weight Aggregates: ASTM C 33, Class 4, and as follows. Provide aggregates from a
single source. Maximum aggregate size is 3 /4 inch.
1. Do not use fine or coarse aggregates that contain substances that cause spalling.
D. Water: Potable
2.4 ADMXTURES
A. Provide concrete admixtures that contain not more than 0.1 percent chloride ions.
B. Air- Entraining Admixture: ASTM C 260, certified by manufacturer to be compatible with other
required admixtures.
C. Water - Reducing Admixture: ASTM C 494, Type A. ,
2.5 CURING MATERIALS
A. Absorptive Cover: Burlap cloth made from jute or kenaf, weighing approximately 9 oz per SY,
complying with AASHTO M182, Class 2.
B. Moisture - Retaining Cover: One of the following, complying with ASTM C 171.
1. Waterproof paper.
2. Polyethylene film. 1
3. White burlap- polyethylene sheet.
1
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02750 -4
Printed 04/20 /04
SECTION 02750
SITE CONCRETE
r C. Clear Solvent -Borne Liquid Membrane - Forming Curing Compound: ASTM C 309, Type I,
Class A or B, wax free.
D. Evaporation Control: Monomolecular film- forming compound applied to exposed concrete slab
surfaces for temporary protection from rapid moisture loss.
' 2.6 RELATED MATERIALS
A. Bonding Agent: Acrylic bonding agent ASTM C.
B. Epoxy Adhesive: ASTM C 881, two - component material suitable for dry or damp surfaces.
Provide material type, grade, and class to suit requirements.
C. Patching Compound: Two component cement base and acrylic polymer, with minimum
compressive strength of 5,000 psi in 28 days.
D. Expansion Joints Sealants: Use a one component Polyurethane Sealant with color closely
matching the concrete. Sikaflex lA Aluminum Gray or approved equal. •
' 2.7 CONCRETE MIX
A. Prepare design mixes for each type and strength of normal- weight concrete by either laboratory
trial batch or field experience methods as specified in ACI 301. For the trial batch method, use
a qualified independent testing agency for preparing and reporting proposed mix designs.
1. Do not use the owner's field quality- control testing agency as the independent testing
agency.
B. Proportion mixes according to ACI 211.1 and ACI 301 to provide normal - weight concrete with
the following properties:
1. Compressive Strength (28 -Day): 3,500 psi unless otherwise noted.
1 2. Maximum Course Aggregate Size: inch.
3. Maximum Slump: 4 inches plus V2 to 1 inch.
1 4. Entrained Air: 5 percent ± %2 tol percent
C. Adjustment to Concrete Mixes: Mix design adjustments may be requested by contractor when
' characteristics of materials, project conditions, weather, test results, or other circumstances
warrant.
2.8 CONCRETE MIXING
A. Ready Mixed Concrete: Comply with requirements and with ASTM C 94. When air
temperature is between 85 °F (30 °C) and 90 °F (32 °C), reduce mixing and delivery time from 1-
1/2 hours to 75 minutes; when air temperature is above 90 °F (32 °C), reduce mixing and delivery
time to 60 minutes.
PART 3 EXECUTION
3.1 GENERAL
A. All curb and sidewalk construction shall conform to the City of Tigard Standard Specifications
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02750 -5
Printed 04/20/04
SECTION 02750
SITE CONCRETE
and Details. I
3.2 SURFACE PREPARATION
A. Proof -roll prepare subbase surface to check for unstable areas and verify need for additional
compaction. Do not begin paving work until such conditions have been corrected and are ready
to receive paving.
B. Remove loose material from compacted subbase surface immediately before placing concrete. I
3.3 EDGE FORMS AND SCREED CONSTRUCTION
A. Set, brace, and secure edge forms, bulkheads, and intermediate screed guides for paving to I
•
required lines, grades, and elevations. Install forms to allow continuous progress of work and so
that forms can remain in place at least 24 hours after concrete placement.
B. Check completed formwork and screeds for grade and alignment to following tolerances:
1. Top of Forms: Not more than 1/8 inch in 10 feet. I
2. Vertical Face on Longitudinal Axis: Not more than 1/4 inch in 10 feet.
C. Clean forms after each use and coat with form release agent as required ensuring separation '
from concrete without damage.
3.4 PLACING REINFORCEMENT
A. General: Comply with Concrete Reinforcing Steel Institute's recommended practice for
"Placing Reinforcing Bars" for placing and supporting reinforcement. 1
B. Clean reinforcement of loose rust and mill scale, earth, ice, or other bond - reducing materials.
C. Arrange, space, and securely tie bars and bar supports to hold reinforcement in position during 1
concrete placement. Maintain minimum cover to reinforcement.
D. Install welded wire fabric in lengths as long as practicable. Lap adjoining pieces at least one
full mesh and lace splices with wire. Offset laps of adjoining widths to prevent continuous laps
in either direction.
E. Install fabricated bar mats in lengths as long as practicable. Handle units to keep them flat and
free of distortions. Straighten bends, kinks, and other irregularities or replace units as required
before placement. Set mats for a minimum 2 inch overlap to adjacent mats.
3.5 JOINTS
A. General: Construct contraction, construction, and isolation joints true to line with faces
perpendicular to surface plane of concrete. Construct transverse joints at right angles to the
centerline, unless indicated otherwise.
1. When joining existing paving, place transverse joints to align with previously placed I
joints, unless indicated otherwise.
B. Contraction Joints: Provide weakened -plane contraction joints, sectioning concrete into areas as
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02750 -6
meted 04/20/04
' SECTION 02750
SITE CONCRETE
' shown on Drawings. Construct contraction joints for a depth equal to at least 1/4 of the
concrete thickness, as follows:
1. Tooled Joints: Form contraction joints in fresh concrete by grooving and finishing each
edge of joint with a radiused jointer tool.
1 2. Sawed Joints: Form contraction joints with power saws equipped with shatterproof
abrasive or diamond - rimmed blades. Cut 1/8 inch wide joints into hardened concrete
' when cutting action will not tear, abrade, or otherwise damage surface and before
development of random contraction cracks.
3. Inserts: Form contraction joints by inserting premolded plastic, hardboard, or fiberboard
strips into fresh concrete until top surface of strip is flush with paving surface. Radius
each joint edge with a jointer tool. Carefully remove strips or caps of two -piece
assemblies after concrete has hardened. Clean groove of loose debris.
C. Construction Joints: Set construction joints at side and end terminations of paving and at
locations where paving operations are stopped for more than 1/2 hour, unless paving terminates
at isolation joints.
1. Provide preformed galvanized steel or plastic keyway- section forms or bulkhead forms
with keys, unless indicated otherwise. Embed keys at least 1 -1/2 inches into concrete.
' 2. Continue reinforcement across construction joints unless indicated otherwise. Do not
continue reinforcement through sides of strip paving unless indicated.
3. Provide tie bars at sides of paving strips where indicated.
4. Use bonding agent on existing concrete surfaces that will be joined with fresh concrete.
' D. Isolation Joints: Form isolation joints of preformed joint filler strips abutting concrete curbs,
catch basins, manholes, inlets, structures, walks, other fixed objects, and where indicated.
' 1. Locate expansion joints at intervals of 50 feet, unless indicated otherwise.
2. Extend joint fillers full width and depth of joint, not less than 1/2 inch or more than 1
inch below finished surface where joint sealant is indicated. Place top of joint filler flush
with finished concrete surface when no joint sealant is required.
3. Furnish joint fillers in one -piece lengths for full width being placed wherever possible.
Where more than one length is required, lace or slip joint filler sections together.
4. Protect top edge of joint filler during concrete placement with a metal, plastic, or other
1 temporary preformed cap. Remove protective cap after concrete has been placed on both
sides of joint.
1 E. Install dowel bars and support assemblies at joints where indicated. Lubricate or asphalt -coat
one half of dowel length to prevent concrete bonding to one side of joint.
' 3.6 CONCRETE PLACEMENT
A. Inspection: Before placing concrete, inspect and complete formwork installation, reinforcing .
steel, and items to be embedded or cast in. Notify other trades to permit installation of their
work.
' 02054
APR 04 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
TIGARD - TUALATIN SCHOOL DISTRICT 23J 02750 -7
Printed 04/20/04
SECTION 02750 1
SITE CONCRETE
B. Remove snow, ice, or frost from subbase surface and reinforcing before placing concrete. Do
not place concrete or surfaces that are frozen.
C. Moisten subbase to provide a uniform dampened condition at the time concrete is placed. Do
not place concrete around manholes or other structures until they are at the required finish
elevation and alignment.
D. Comply with requirements and with ACI 304R for measuring, mixing, transporting, and placing
concrete.
E. Deposit and spread concrete in a continuous operation between transverse joints. Do not push
or drag concrete into place or use vibrators to move concrete into place.
1. When concrete placing is interrupted for more than 1/2 hour, place a construction joint. i
F. Use a bonding agent at locations where fresh concrete is placed against hardened or partially 111 hardened concrete surfaces.
G. Consolidate concrete by mechanical vibrating equipment supplemented by hand - spading,
rodding, or tamping. Use equipment and procedures to consolidate concrete complying with
ACI 309R. Consolidate concrete along face of forms and adjacent to transverse joints with an
internal vibrator. Keep vibrator away from joint assemblies, reinforcement, or side forms. Use
only square -faced shovels for hand - spreading and consolidation. Consolidate with care to
prevent dislocating reinforcing, dowels, and joint devices.
H. Screed paved surfaced with a straightedge and strike off. Use bull floats or darbies to form a
smooth surface plane before excess moisture or bleed water appears on the surface. Do not
further disturb concrete surfaces prior to beginning finishing operations.
I. Place concrete in two operations; strike off initial pour for entire width of placement and to the
required depth below finish surface. Lay welded wire fabric or fabricated bar mats immediately
in final position. Place top layer of concrete, strike off, and screed.
J. Curbs and Gutters: When automatic machine placement is used for curb and gutter placement, '
submit revised mix design and laboratory test results that meet or exceed requirements. Produce
curbs and gutters to required cross section, lines, grades, finish, and joining as specified for
formed concrete. If results are not acceptable, remove and replace with formed concrete.
K. Slip -Form Pavers: When automatic machine placement is used for paving, submit revised mix
design and laboratory test results that meet or exceed requirements. Produce paving to required
thickness, lines, grades, finish, and jointing as required for formed paving. Compact subbase
and prepare subgrade of sufficient width to prevent displacement of paver machine during
operations.
L. When adjoining pavement lanes are placed in separate pours, do not operate equipment on
concrete until pavement has attained 85 percent of its 28 -day compressive strength.
M. Cold- Weather Placement: Comply with provisions of ACI 306R and as follows. Protect t
concrete work from physical damage or reduced strength that could be caused by frost, freezing
actions, or low temperatures.
1. When air temperature has fallen to or is expected to fall below 40 °F (4 °C), uniformly
heat water and aggregates before mixing to obtain a concrete mixture temperature of not
less than 50 °F (10 °C) and not more than 80 °F (27 °C) at point of placement.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02750 -8
Printed 04/20/04
I SECTION 02750
SITE CONCRETE
I 2. Do not use frozen materials or materials containin g ice or snow.
I 3. Do not use calcium chloride, salt, or other materials containing antifreeze agents or
chemical accelerators unless otherwise accepted in mix designs.
I N. Hot - Weather Placement: Place concrete complying with ACI 305R and as specified when hot
weather conditions exist.
1 1. Cool ingredients before mixing to maintain concrete temperature at time of placement to
below 90 °F (32 °C). Mixing water may be chilled or chopped ice may be used to control
temperature, provided water equivalent of ice is calculated to total amount of mixing
I water. Using liquid nitrogen to cool concrete is Contractor's option.
2. Cover reinforcing steel with water- soaked burlap if it becomes too hot, so that steel
I temperature will not exceed the ambient air temperature immediately before embedding
in concrete.
3. Fog spray forms, reinforcing steel, and subgrade just before placing concrete. Keep
I subgrade moisture uniform without standing water, soft spots, or dry areas.
3.7 CONCRETE FINISHING
I A. Float Finish: Begin floating when bleed water sheen has disappeared and the concrete surface
has stiffened sufficiently to permit operations. Float surface with power - driven floats, or by
ii hand - floating if area is small or inaccessible to power units.
B. Construct all slabs within ' /<" of established surface grade, cross section, and slope. All finished
surfaces shall be free from humps, sags, or other irregularities. Finish surfaces to true places
I within a tolerance of 1/4 inch in 10 feet as determined by a 10 foot long straightedge placed
anywhere on the surface in any direction. Cut down high spots and fill low spots. Refloat
surface immediately to a uniform granular texture.
I 1. Medium -to -Fine Textured Broom Finish: Draw a soft bristle broom across concrete
surface perpendicular to line of traffic to provide a uniform fine line texture finish.
I C. Final Tooling: Tool edges of paving, gutters, curbs, and joints formed in fresh concrete with a
jointing tool to the following radius. Repeat tooling of edges and joints after applying surface
finishes. Eliminate tool marks on concrete surfaces.
1 1. Radius: 3/8 inch
3.8 FINISHING VERTICAL SURFACES
I
A. Finishing Concealed Vertical Concrete Surfaces
1 1. Provide rough form finish, complying with ACI 301, Paragraph 10.2.1.
2. Remove fins and projections exceed 1/4 inch in height and patch tie holes and surface
I defects.
B. Finishing Exposed Vertical Concrete Surfaces
1 1. Provide smooth form finish complying with ACI 301, Paragraph 10.2.2.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02750 -9
Printed 04/20/04
SECTION 02750 '
SITE CONCRETE
2. Remove fins and projections and patch tie holes and surface defects.
3. Provide smooth rubbed finish for exposed curb and walk edges, complying with ACI
301, Paragraph 10.3.1.
4. Within 24 hours after form removal, wet and rub exposed vertical surfaces with
carborundum brick or other abrasive until uniform color and texture are produced.
•
3.9 CONCRETE PROTECTION AND CURING •
A. General: Protect freshly placed concrete from premature drying and excessive cold or hot
temperatures. Comply with the recommendations of ACI 306R for cold weather protection and
ACI 305R for hot weather protection during curing. ,
B. Evaporation Control: In hot, dry, and windy weather, protect concrete from rapid moisture loss
before and during finishing operations with an evaporation - control material. Apply according to
manufacturer's instructions after screeding and bull floating, but before floating.
C. Begin curing after finishing concrete but not before free water has disappeared from concrete
surface. '
D. Curing Methods: Cure concrete by moisture curing, moisture - retaining -cover curing, curing
compound, or a combination of these as follows:
1. Moisture Curing: Keep surfaces continuously moist for not less than 7 days with the
following materials:
a. Water '
• b. Continuous water -fog spray
c. Absorptive cover, water saturated, and kept continuously wet. Cover concrete
surfaces and edges with a 12 -inch lap over adjacent absorptive covers '
2. Moisture - Retaining -Cover Curing: Cover concrete surfaces with moisture - retaining
cover for curing concrete, placed in widest practicable width, with sides and ends lapped
at least 12 inches, and sealed by waterproof tape or adhesive. Immediately repair any
holes or tears during curing period using cover material and waterproof tape.
3. Curing Compound: Apply uniformly in continuous operation by power spray or roller
according to manufacturer's directions. Recoat areas subjected to heavy rainfall within 3
hours after initial application. Maintain continuity of coating and repair damage during
curing period. ,
3.10 JOINING NEW TO EXISTING CONCRETE
A. Construct suitable connections between new and existing concrete where existing driveways, 1
walks, and other structures are cut back to permit the new construction or where the new
construction abuts the existing concrete. Unless shown or directed otherwise, furnish and place
minimum 12 mm (1/2 inch) thick performed expansion joint filler between new and existing
concrete.
3.11 FIELD QUALITY CONTROL TESTING
A. Employ a qualified independent testing and inspection agency to sample materials, perform
tests, and submit test reports during concrete placement as follows:
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02750 -10
Printed 04/20/04
I SECTION 02750
SITE CONCRETE
I B. The Owner will employ a qualified testing and inspection agency to sample materials, perform
tests, and submit test reports during concrete placement. Sampling and testing for quality
control may include the following:
I 1. Sampling Fresh Concrete: ASTM C 172, except modified for slump to comply with
ASTM C 94.
I 2. Slump: ASTM C 143; one test at point of placement for each compressive- strength test
but no less than one test for each day's pour of each type of concrete. Additional tests
will be required when concrete consistency changes.
I 3. Air Content: ASTM C 231, pressure method; one test for each compressive- strength test
but no less than one test for each day's pour of each type of air - entrained concrete.
1 4. Concrete Temperature: ASTM C 1064. One test hourly when air temperature is 40 °F
(4 °C) and below and when 80 °F (27 °C) and above, and one test for each set of
I compressive - strength specimens.
5. Compression Test Specimens: ASTM C 31. One set of four standard cylinders for each
compressive - strength test, unless directed otherwise. Mold and store cylinders for
1 laboratory-cured test specimens except when field -cured test specimens are required.
6. Compressive - Strength Tests: ASTM C39. One set for each day's pour of each concrete
I class exceeding 5 sq. yd. but less than 25 cu. yd. plus one set for each additional 50 cu.
yd. Test one specimen at 7 days, test two specimens at 28 days, and retain one specimen
in reserve for later testing if required.
is
C. When frequency of testing will provide fewer than five strength tests for a given class of
concrete, conduct testing from at least five randomly selected batches or from each batch if
fewer than five are used.
I D. When total quantity of a given class of concrete is less than 50 cu. yd. Architect may waive
strength testing if adequate evidence of satisfactory strength is provided.
I E. When strength of field -cured cylinders is less than 85% of companion laboratory-cured
cylinders, evaluate current operations and provide corrective procedures for protecting and
curing the in -place concrete.
I F. Strength level of concrete will be considered satisfactory if averages of sets of three consecutive
strength test results equal or exceed specified compressive strength and no individual strength
I test result falls below specified compressive strength by more than 500 psi.
G. Test results will be reported in writing to architect, concrete manufacturer, and Contractor
within 24 hours of testing. Reports of compressive strength tests shall contain the Project
I
identification name and number, date of concrete placement, name of concrete testing agency,
concrete type and class, location of concrete batch in paving, design compressive strength at 28
days, concrete mix proportions and materials, compressive breaking strength, and type of break
I for both 7 -day and 28 -day tests.
H. Additional Tests: The testing agency will make additional tests of the concrete when test results
I indicates lump, air entrainment, concrete strengths, or other requirements have not been met, as
directed by architect. Testing agency may conduct tests to determine adequacy of concrete by
cored cylinders complying with ASTM C 42, or by other methods as directed.
1 3.12 REPAIRS AND PROTECTION
I 02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD- TUALATIN SCHOOL DISTRICT 23J 02750 -11
Printed 04/20/04
•
SECTION 02750
SITE CONCRETE
1
A. Remove and replace concrete paving that is broken, damaged, or defective, or does not meet the
requirements of this section.
B. Drill test cores where directed by Architect when necessary to determine magnitude of cracks or
defective, or does not meet the requirements of this section.
C. Protect concrete from damage. Exclude traffic from paving or at least 14 days after placement.
When construction traffic is permitted, maintain paving as clean as possible by removing
surface stains and spillage of materials as they occur.
D. Maintain concrete avin free of stains, discoloration, dirt, and other foreign
p g gn material. Sweep
concrete paving not more than 2 days prior to date scheduled for Substantial Completion
inspections. '
E. Barricade area containing fresh concrete slabs, stairs, ramps, curbs, and walks for 24 hours
minimum
F. Cover fresh concrete with %2 inch thick, plywood or oriented strand board for 48 hours minimum
where exposed to public, pedestrian, and animal traffic.
G. Protect concrete from shrinkage crack damage until protected by curing procedure.
H. Protect concrete from physical damage or reduced strength caused by air temperatures below
45 °F during curing period, as recommended in ACI 306R.
I. Protect concrete from physical damage or reduced strength caused by air temperatures above
75 °F during curing period, as recommended in ACI 305R.
3.13 REPAIRING EXPOSED VERTICAL CONCRETE SURFACES
A. Clean, dampen, and brush -coat concrete patch areas with acrylic or epoxy bonding agents.
B. Fill honeycomb voids and rock pockets with patching compound.
C. Compact and screed patching compound in place as recommended by patching compound
manufacturer.
D. Finish exposed concrete patches to match adjacent surfaces.
E. Strike off excess patching compound at exposed surface. '
F. If defects in color and texture of concrete surface cannot be repaired, remove and replace the
defective concrete.
END OF SECTION
1
t
1
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE 2
APR 04 TIGARD - TUALATIN SCHOOL DISTRICT 23J 02750 -12
Printed 04/20/04
SECTION 02800
SITE FURNISHINGS
PART 1 GENERAL
1.01 QUALITY ASSURANCE
' A. Manufacturing Standards: Provide each item of equipment as a complete unit produced by a
single manufacturer, including fittings, accessories bases and anchorage devices.
1.02 SUBMITTALS
A. Product Data: Submit to Landscape Architect two sets of manufacturer's technical data and
installation instructions for each item, with list of accessory items. Clearly indicate options of
size, model and finish.
PART 2 PRODUCTS
2.01 TRASH RECEPTACLES:
A. Acceptable Manufacturer and Product: Victor Stanley, Inc. Distributor: Wildwood Playgrounds,
811 E. Burnside, Suite 116, Portland, OR 97214, phone 503/232 -3211. Model: Bethesda Series S-
424 with 32 gallon high density plastic liner and spun steel lid secured by vinyl coated steel cable;
with optional DS -32 steel dome top. Two (2) required.
B. Finish: Powder coat to match bench. Submit color sample. Sample to be approved by Owner's
�, Representative.
' C. Attachment Method: Expansion bolt to pavement, or on concrete footing as per manufacturer's
detail.
' 2.02 BENCHES:
A. Renaissance Series, 2806 -8 bench. Five (5) required. Columbia Cascade Company, 1975 S. W.
Fifth Avenue, Portland Oregon 97201, (503) 223 -1 157.
B. Finish: Powder coat "Evergreen ". Submit color sample. Sample to be approved by Owner's
Representative.
C. Attachment Method: Expansion bolt to pavement, or on concrete footing as per manufacturer's
detail.
PART 3 EXECUTION
3.01 INSPECTION
A. Examine surfaces or conditions where Site Furnishings are to be erected. Notify the Owner's
Representative of any conditions detrimental to the proper and timely completion of the work. Do
not proceed with installation until unsatisfactory conditions have been corrected and are
acceptable to the installer.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02800 -1
Printed 05/03/04
SECTION 02800
SITE FURNISHINGS
3.02 INSTALLATION ,
A. Install work in this Section in accordance with the manufacturer's recommendations and as
approved by the Owner's Representative. All furnishings to be installed plumb and true. '
B. Stake out locations for approval by Owner's Representative approval prior to initiating
installation.
C. Touch up any marred powder coated surfaces with manufacturer- approved compatible paint prior
to final acceptance.
END OF SECTION
1
1
N
I
r
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL 1
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02800 -2
Printed 05/03/04
1
I SECTION 02810
IRRIGATION
I
PART 1 GENERAL '
I
1.01 GENERAL
A. Drawings indicate general location and arrangement of piping systems. Indicated locations and
arrangements were used to size pipe and calculate friction loss, and in other design considerations.
Install piping as indicated, except where deviations to layout are approved on coordination
I drawings.
1.02 WORK INCLUDED
I A. Furnish all labor, material, tools, machinery and equipment necessary to install a complete and
operating automatically controlled irrigation system as indicated on the Drawings.
I B. Work of this Section includes, but is not limited to, landscape irrigation system; automatic controls
and connection to control valves; connection to power and water service; controller programming;
record drawings and maintenance and operating instructions.
I 1.03 QUALITY ASSURANCE
I A. Multiple Units: When two or more units of the same type or class of materials or equipment are
required, provide units produced by one manufacturer.
.. B. System Requirements:
1. The layout of the irrigation system is schematic. Follow as closely as possible. Modify
equipment locations as required to accommodate plant material, utilities, and other
I underground obstructions. Review significant modifications with the Landscape
Architect prior to proceeding.
2. Full and complete coverage is required. Contractor shall, at no additional cost to the
I
Owner, make necessary adjustments to layout and /or nozzles required to achieve full
coverage of irrigated areas without overthrow on sidewalks or buildings.
1.04 SUBMITTALS
A. Provide Data: Submit a list of materials showing manufacturer's name, catalog number, technical
I data, photo or drawing of manufactured materials, and manufacturer's installation instructions for
Landscape Architect's review.
B. Test Reports: Submit copies of field test reports of water pressure at water supply connection and
of irrigation lines prior to backfilling and compacting.
C. Record Set: Keep current record of all documents. Show revisions, if any, to location of irrigation
I main and lateral lines, valves (including, control, gate and drain and quick coupling valves), points
of connection, control wire routing, controller and backflow prevention locations. Control valves
shall be clearly labeled with numbers corresponding to the controller station numbers. Submit
full sized reproducible set of Project Record Documents prior to final acceptance.
I 1.05 PROJECT CONDITIONS
I 02054 TIGARD HIGH SCHOOL ADDITION / REMODEL
DEC 03 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02810 -1
Printed 05/03/04
SECTION 02810
IRRIGATION
A. Existing Site Improvements: Protect existing utility lines, walks, paving and plant root systems
during trenching and backfilling.
B. Weather Requirements: Do not solvent weld polyvinyl chloride pipe when ambient temperature is
below 40 degrees F and falling.
1.06 SCHEDULING
A. Pipe Sleeves: Coordinate placement of pipe sleeves under paving with other trades.
B. Sprinkler Heads: Install sprinkler heads after final grading. '
1.07 WARRANTY
A. Manufacturer's Warranty: Provide equipment manufacturer's standard Warranty for automatic
controllers, valves, quick couplers, and heads.
B. Installer's Warranty: Provide a one year warranty on the complete system.
PART 2 PRODUCTS
2.01 MANUFACTURERS '
A. Sprinkler Heads: As shown on Drawings.
B. Automatic Controllers: Rainbird.
C. Remote Control Valves: Rainbird.
D. Isolation Valves:Nibco.
E. Quick Coupling Valves: Rainbird.
F. Double Check Valve: Febco.
G. PVC Pipe and Fittings: Spears, Lasco, Pacific Western or approved equal.
H. Other Manufacturers: Submit Substitution Request prior to Bid Date.
2.02 MATERIAL
A. Polyvinyl Chloride Pipe, Fittings and Accessories: '
1. Main Lines:
a. Large Diameter Pipe (3" size and larger): ASTM D 2241, PVC 1220, Type 1,
Class 200, NSF approved. Bell and spigot connections.
b. Small Diameter Pipe (2 %2" and smaller): ASTM D 2241, PVC 1220, Type I,
Class 200, NSF approved. Solvent weld connections.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL
DEC 03 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02810 -2
Printed 05/03/04
I SECTION 02810
IRRIGATION
I 2. Lateral Lines: ASTM D 2241, PVC 1220, Type 1, Class 200, NSF approved. Solvent
weld connections.
I 3. Main Line Fittings:
a. Small Diameter Pipe: Schedule 40 PVC.
I b. Large Diameter Pipe:
i. Tees, elbows, reducers: Harco deep bell push on ductile iron fittings
I with gaskets.
ii. Flanges: schedule 80 PVC Van Stone flanges for gate valves, backflow
preventers, flow sensors.
I iii. Saddles: Romac 4lOIN Tap Saddle for control valve and quick coupler
taps, size as required.
I 4. Sleeves: Schedule 40 PVC.
5. PVC Threaded Fittings: ASTM D 1785, Schedule 40, NSF approved.
1 6. Solvent Cement: Weld -on 725.
7. Joint Cleaner: Weld -On C -60.
I 8. Joint Primer: Weld -On P -75.
9. Joint Tape: YZ inch wide teflon tape.
•
1111
10. Trench Marking Tape: Alarmatape or approved equal.
B. Valves, Flow Regulators and Accessories:
I 1. Remote Control Valve: Rainbird PEB Series, size as indicated.
2. Gate Valve: Nibco T1 -8, 200 lb. Brass Gate Valve with Bronze Body, non - rising stem.
I Sizes '/4" through 4 ". Gate valve shall match line size.
3. Manual drain valve: Champion 200 series 3 /4" brass manual angle valve
I 4. Quick Coupling Valve: 44 LRC by Rainbird, or approved equal
a. Stabilizer: Leemco, LS 120 for 3 /4" and 1" valves and LS -150 for 1 -1/2": valves.
I 5. Valve Operating Key: Provide 3 corresponding valve keys with swivel hose ells by the
quick coupler manufacturer.
I 6. Valve Box: Ametek 170106 Standard 12" box with snap lock lid. Extensions as required.
Provide 5 keys.
7. Backflow Preventer: Febco 805Y or 805YD, size as indicated.
I 8. Backflow Preventer Vault: Brooks Products 37 -T or 38 -T or 66 -T series. , or size as
required.
I C. Sprinkler Heads: As shown on drawings.
D. Control Equipment:
I 02054 TIGARD HIGH SCHOOL ADDITION / REMODEL
DEC 03 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02810 -3
Printed 05/03/04
SECTION 02810
IRRIGATION
1. Automatic Controllers: ESP -MC, Series wall mount controller. Size as shown on plans.
2. Control Wire: Single strand, copper, Type UF, UL approved for direct burial in NEC
Class II circuits, minimum AWG size no. 14. Size according to manufacturer's
recommendations. Jacket colors: red for control wires, white for common wire.
3. Electrical Connectors: 3M DBY, Scotch -lock connector sealing pack No. 3576 with
Type R electrical connectors; Rainbird Pen -Tite Wire Connectors 101 through 104 or
approved.
E. Drainage Gravel: 'A" pea gravel with 0% retained on 3/8" sieve.
PART 3 EXECUTION
3.01 EXAMINATION
A. Investigate and determine available water supply water pressure and flow characteristics. Test
pressure at connection point. Notify Architect immediately if results vary from pressure as
indicated on Drawings. Verify that backflow device has been installed and tested before
connecting water supply to irrigation system.
B. Investigate site for improvements and underground utilities. Protect all affected active utilities.
C. Examine substrates, sleeves, wiring and conditions under which irrigation work will be completed.
Do not proceed with irrigation work until unsatisfactory conditions have been corrected.
D. Check and verify the correlation between ground measurements and finish elevations and the
Drawings.
E. Starting work constitutes acceptance of existing conditions.
F. Set flags to identify proposed sprinkler locations and general layout of main lines. Obtain
Landscape Architect's approval before excavation.
3.02 TRENCHING -
A. Trench size as required for installation, inspection and backfill compaction. '
B. Excavate pipe trenches "snaked" slightly, allowing for expansion and contraction of PVC pipes.
C. Trench to sufficient depths to allow for specified cover. '
D. Keep usable topsoil separate from subsoil in a condition similar to that existing before excavation.
3.03 PIPING APPLICATIONS
A. Refer to Part 2 of this Section for detailed specifications for pipe and fittings products listed below.
Use pipe, tube, fittings, and joining methods according to the following applications.
B. Use Class 200 IPS solvent weld PVC pipe for main and lateral lines.
C. Install piping in Schedule 40 PCV sleeves where crossing sidewalks, roadways, and parking lots.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL '
DEC 03 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02810 -4
Printed 05/03/04
1
I SECTION 02810
IRRIGATION
I 3.04 JOINT CONSTRUCTION
A. Threaded Joints: Thread pipes with tapered pipe threads according to ASME BI.20.1, apply tape
I or joint compound, and apply wrench to valve ends into which pipes are being threaded.
B. Polyvinyl Chloride (PVC) Piping Solvent - Cemented Joints: Construct joints according to ASTM
I D 2672 and ASTM D 2855. Comply with procedures in ASTM F 402 for safe handling when
joining plastic pipe and fittings with solvent cements.
C. Dissimilar Materials Piping Joints: Construct joints using adapters that are compatible with both
I piping materials, outside diameters, and system working pressure.
3.05 PIPING INSTALLATION
I A. Install polyvinyl chloride (PVC) plastic pipe according to ASTM D 2774.
I B. Lay piping on solid subbase, uniformly sloped without humps or depressions. When installing two
pipes in a trench, lay pipes side by side with 6" spacing between pipes.
Minimum Cover: Provide following minimum cover over top of buried piping:
I C. 1. Pressure Piping: 18 inches.
I 2. Lateral Piping: 12 inches.
3. Sleeves: 18 inches.
II D. Install all piping under sidewalks and paving in sleeves as shown on plans. Some sleeves locations
may be shown on plans which are to be paved in a later phase of construction. Coordinate work
with other trades.
I E. Install thrust blocks on all tees, crosses and elbows for 3" pipe and larger per detail.
3.06 VALVE INSTALLATION
I A. Remote Control Valves: Install remote control valves in valve boxes in accordance with the
Drawings. Install one valve per box and space valves in manifolds equally with adequate
I clearance (plus or minus 3') for ease of service. Install control valve box flush with finish grade
on bedding of drainage gravel as indicated on Drawings. Compact backfill around valve boxes.
B. Quick Coupling Valves: Install quick coupling valves in accordance with the Drawings.
I C. Gate Valves: Install gate valves in accordance with the Drawings.
1 3.07 BACKFLOW PREVENTER INSTALLATION
A. Install backflow preventers of type, size, and capacity indicated. Include valves and test cocks.
I Install according to plumbing code and health department authorities with jurisdiction.
B. Install backflow preventer, quick coupler for air injection, together in one vault. Install vault per
manufacturer's recommendations. Secure Landscape Architect's approval of location prior to
I
excavation. Top of vault shall be flush with finish grade.
I 02054 TIGARD HIGH SCHOOL ADDITION / REMODEL
DEC 03 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02810 -5
Printed 05/03/04
SECTION 02810
IRRIGATION
3.08 SPRINKLER INSTALLATION
A. Flush circuit piping with full head of water and install sprinklers after hydrostatic test is completed.
Cap risers immediately after flushing for a minimum of 2 minutes.
B. Install sprinklers at manufacturer's recommended heights and as indicated on Drawings. Install
additional heads if required for 100% (head to head) coverage in lawn and shrub areas.
C. .Locate part- circle sprinklers to maintain a maximum distance of 4 inches from walls, curbs and
paving.
3.09 AUTOMATIC CONTROL SYSTEM INSTALLATION
A. Install controllers according to manufacturer's written instructions and in accordance with the
Drawings.
B. Provide reduced scale as -built layout drawing of irrigation system with zone identified by different
colors. Install plastic laminated drawing on inside cover of the controller cabinet.
3.10 CONTROL WIRE
A. Connect common wire and control wires from controllers to each valve.
B. Wire size shall be minumum 14 AWG. Comply with wire sizing chart published by manufacturer
of automatic control valves.
C. Make splices moistureproof using waterproof electrical connectors. Wire splices to be made in
valve boxes only. Do not bury wire splices.
D. Bundle wire together and wrap with electrical tape at five foot intervals.
E. Provide 4 ft. expansion curls every 100 ft. for runs more than 100 ft. in length. Provide 10 inches
of slack at connection to electric control valves.
F. Run control wire in main line trenches at a minimum depth of 18 inches and then in conduit to
controller.
G. Lay wire in trenches under pipe. '
H. Common wire shall be white. Control wires shall be red.
3.11 CONNECTIONS
A. Connect piping to sprinklers, devices, valves, control valves, specialties, and accessories.
B. Connect water supplies to irrigation systems. Include backflow preventers on potable water
supplies.
C. Electrical Connections: Connect to controller to compatible power source according to
manufacturer's instructions and in conformance with all electrical codes having jurisdication over
the project and power company requirements. Ground systems as recommended by manufacturer.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL
DEC 03 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02810 -6
Printed 05/03/04
1
I SECTION 02810
IRRIGATION
t 3.12 FIELD QUALITY CONTROL
A. Testing: Perform hydrostatic test of piping and valves before backfilling trenches. Piping may be
I tested in sections to expedite work. Notify Landscape Architect 48 hours in advance of pressure
test.
1. Cap and subject the piping system to a static water pressure of 100 psi. Isolate test source
and allow to stand for 4 hours. Leaks and loss in test pressure constitute defects that must
be repaired.
I 2. Repair leaks and defects with new materials and retest system or portion thereof until
satisfactory results are obtained.
I 3.13 BACKFILLING
A. After pipe is installed and tested, backfill trench with clean site soil or sand to 2 inches above pipe.
Carefully tamp around and over pipe.
I B. Backfill to finish grade exercising care to maintain established soil profile with topsoil on top.
Remove large aggregate or other material that may damage pipe; wet and tamp earth in layers not
I over 6 inches thick until throughly compacted and settled.
C. Mark all main lines with a continuous trench marker tape placed six inches below finish grade
directly over buried pipe.
I
3.14 CLEANING AND ADJUSTING
i
A. Flush dirt and debris from piping before installing sprinklers and other devices.
YE
B. Adjust automatic control valves to provide flow rate of rated operating pressure required for each
I sprinkler circuit.
C. Carefully adjust lawn sprinklers so they will be flush with, or not more than V2 inch above, finish
grade after completion of landscape work.
I D. Adjust settings of controllers and automatic control valves.
I E. Balance and adjust system to provide complete, uniform coverage and minimum overspray onto
paved areas and adjacent property.
F. Clean -up premises of debris and surplus materials. Clean exposed equipment prior to final
I inspection.
3.15 COMMISSIONING
I A. Starting Procedures: Follow manufacturer's written procedures. if no procedures are prescribed by
manufacturers, proceed as follows:
I 1. Verify that specialty valves and their accessories have been installed correctly and
operate correctly.
2. Verify that specified tests of piping are complete.
3. Check that sprinklers and devices are correct type.
I 02054 TIGARD HIGH SCHOOL ADDITION / REMODEL
DEC 03 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02810 -7
Printed 05/03/04
I
SECTION 02810 1
IRRIGATION
4. Check that damaged sprinklers and devices have been replaced with new materials. i
5. Check that potable water supplies have correct type backflow preventers.
6. Energize circuits to electrical equipment and devices. i
7. Adjust operating controls.
8. Assist Owner in programming system. Supply Owner with as -built information and
information concerning field conditions which may affect programming system including
but not limited to soil conditions, slope, precipitation rates, and establishment and
maintenance procedures.
B. Operational Testing: Perform operational testing of entire system and make adjustments prior to
demonstration to Architect or Owner's maintenance personnel.
3.16 DEMONSTRATION
A. Demonstrate to Architect that system meets coverage requirements and that automatic controls
function properly.
B. Demonstrate to Owner's maintenance personnel operation of equipment, sprinklers, specialties, and
accessories. Review operating and maintenance information.
C. Provide 7 days' written notice in advance of demonstration.
END OF SECTION p
I
t
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL
DEC 03 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02810 -8
Printed 05/03/04
I
SECTION 02920
SOIL PREPARATION
PART 1 GENERAL
1.01 GENERAL REQUIREMENTS
' A. Drawings and general provisions of the Contract, including General and other Conditions and
other Division 1 - General Requirements sections, apply to the work specified in this Section.
1.02 WORK INCLUDED
, A. Topsoil Placement.
I B. Fine Grading.
1.03 QUALITY ASSURANCE
A. Soil Tests: Provide the following soil tests by approved testing lab prior to importing soil material.
Collect soil samples according to procedures recommended by testing lab. Do not begin importing
soil material until soil analysis submittals have been approved.
1. Approved Testing Lab:
a. A & L Western Agricultural Laboratories, (503) 968 -9225 or approved equal.
2. Fertility Analysis: Provide two soil fertility analyses according to approved testing lab
complete analysis soil test package (S3C) with recommendations for the following:
a. Topsoil alone and;
b. Soil mix (topsoil mixed with organic compost at the specified rate)
3. Soil Texture Analysis: Provide a USDA particle size appraisal of topsoil indicating
compliance with specified USDA Soil Class.
B. Contractor shall make allowance for the addition of fertilizers, or trace elements to correct
deficiencies according to testing lab recommendations. Do not add fertilizers to soil mix unless
directed to do so by Landscape Architect.
1.04 SUBMITTALS
A. Quantity Certification: Submit quantities of imported topsoil, and ammendments anticipated to be
used for project prior to beginning work. Submit trucking invoices for certification of quantities of
topsoil and compost purchased.
B. Quality Certification: Submit manufacturer's or vendor's certified analysis of soil amendments.
C. Topsoil Fertility and Soil Texture Analysis.
1.05 DELIVERY, STORAGE AND HANDLING
A. Deliver commercial fertilizer in containers showing weight, analysis and name of manufacturer.
B. Protect soil materials from deterioration during delivery and storage.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 231 02920 -1
Printed 05/03/04
I
SECTION 02920
SOIL PREPARATION
1.06 SITE CONDITIONS ,
A. Seasonal Limitations: Conduct landscape work within the acceptable planting season for each kind
of planting. 1
B. Utility Lines: Stake location of underground utilities and avoid excavation in these areas beyond
safe limits. Hand excavate where required to avoid utility line damage.
PART 2 PRODUCTS
I
2.01 TOPSOIL
A. NEW IMPORTED TOPSOIL: Import topsoil. Do not use site soil. Imported topsoil shall 1
conform to USDA soil texture class "sandy loam" or "loam ". Soil shall be fertile, friable and free
of rubbish, brush, weeds, roots, stones larger than 2 inches in any dimension and other material
harmful to plant growth. Obtain from well drained site.
2.02 SOIL AMENDMENTS
A. LIME: Natural limestone containing not less than 85% of total carbonates, ground so that not less
than 90% passes a 10 mesh sieve and not less than 50% passes a 100 mesh sieve. Dolomite lime,
calcium magnesium carbonate.
B. ORGANIC COMPOST: Nature's Needs Humus; or approved equal.
1. Nature's Needs I
9570 NW 307 Ave.
North Plains, OR 97133
(503) 647-9489 1
www. naturesneeds.com
2. If alternative to above- approved compost is proposed, submit manufacturer's certification
that compost meets all of the following requirements: Compost shall be certified by the
US Composting Council Seal of Testing Assurance (USCC -STA) as derived from the
controlled biological decomposition of organic wastes that have been sanitized through
the generation of heat and processed to further reduce the pathogens as defined by the US
EPA (Code of Federal Regulations Title 40, Part 503, Appendix B, Section B) or
approved equal. Raw material may include items such as food and agricultural redidues,
animal manures, mixed solid waste and biosolids (treated sewage sludge) that meet all
State environmental agency requirements and have been stabilized to the point that is
beneficial to plant growth. The product shall be well composted, free of viable weed
seeds and contain material of a generally hu3nis nature capable of sustaining growth of
vegetation, with no materials toxic to plant growth and meeting the following criteria:
a. PH of the material shall be between 6.7 -8.0
b. Moisture content shall be between 35 % -60%
c. Bulk density shall be no less than 800 lbs /cu. yd. And no more than 1000 lbs. /cu.
yd.
d. Carbon to Nitrogen ratio (C:N) shall be between 20 -25:1
e. Organic Nitrogen content (NH shall be no greater than 1.25 parts per million
f. Potassium content shall be no greater than 5500 parts per million
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02920 -2
Printed 05/03/04
SECTION 02920
SOIL PREPARATION
g. Phosphorous content shall be no greater than 325 parts per million
h. Pesticide residues shall not exceed 0.05 parts per million
i. Heavy Metals (trace) shall not exceed 0.5 parts per million
j. Material shall have been "aged" a minimum of six (6) months prior to delivery to
site
k. The material shall not contain rocks or other inert organic debris larger than 1/4"
and
1. The material shall not contain pieces of plastic, metal glass or other inorganic
materials.
' m. The material shall achieve a species richness diversity index of 7.0 or greater as
certified by BBC Laboratories (1217 N. Stadem Dr. Tempe, AZ 85281, (480)
967 -5931)
' n. The material shall achieve a ration of aerobic microorganisms to anaerobic of
10:1 or greater as certified by BBC Laboratories (1217 N. Stadem Dr. Tempe,
AZ 85281, (480) 967 -5931)
o. The material shall not contain soluble salts (Ecs) exceeding 5.0 ds /m as indicated
by a certified soil testing agency
2.03 MISCELLANEOUS MATERIALS
A. Herbicide: Round -up
1
PART 3 EXECUTION
3.01 PREPARATION
A. Protection of Existing Site: Protect utility lines, storm drainage lines, site improvements, and
underground utilities whether indicated or not.
1 B. Prepare soil mix by adding organic compost to topsoil at rate of one part soil amendment to 5 parts
topsoil by volume. Add fertilizers and trace elements according to soil testing lab
recommendations, if any, and as directed by Landscape Architect. Mix thoroughly.
' C. Apply contact herbicide to all weeds within planting areas in accordance with manufacturer's
instructions. Apply in season when plants are actively growing. Allow at least seven days for
positive kill before continuing work.
' 3.02 PREPARING LAWN AND SHRUB PLANTING AREAS
A. Excavate existing soil and imported construction fill materials to extent necessary to allow for
placement of soil mix to full specified depths in all planting areas. Allow for placement of
specified bark mulch in depth calculations. Remove excess subsoil from site.
B. After excavation, scarify (loosen) highly compacted subgrades an additional 6" and remove all
construction debris, mortar, concrete, asphalt and any other material that may be harmful to plant
life from all planting beds.
C. Do not begin soil mix placement until Owner's representative has inspected and approved of
subgrade.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02920 -3
Printed 05/03/04
SECTION 02920
SOIL PREPARATION
D. Place Soil Mix: Place 12" minimum depth of soil mix in all shrub and groundcover planting areas. 1
Place 6" minimum depth of soil mix in all lawn areas.
E. Grading: Compact prepared topsoil to 80% density and float planting areas to 2 inches below
elevations indicated on Drawings. Slope planting areas with 6 inch crown or 2% minimum slope.
Maintain positive drainage.
F. Bring planting areas to smooth even surface with loose, uniformly fine texture. Remove ridges and
depressions. Maintain positive drainage.
I
END OF SECTION
I
1
1
I
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02920 -4
Printed 05/03/04
SECTION 02930
LAWNS
PART 1 GENERAL
1.01 GENERAL REQUIREMENTS
I A. Drawings and general provisions of the Contract, including General and other Conditions and
other Division 1 - General Requirements sections, apply to the work specified in this Section.
1.02 WORK IN OTHER SECTIONS
A. Topsoil and Soil Amendments: Section 02920 SOIL PREPARATION.
B. Fine Grading: Section 02920 SOIL PREPARATON.
1.03 QUALITY ASSURANCE
A. Certification of Seed Purity and Germination: Comply with standards established by the
Association of Official Seed Certifying Agencies.
•
1.04 SUBMITTALS
A. Maintenance Notification: Notify Owner's Representative in writing 14 days minimum prior to
Owner's assumption of maintenance responsibility for lawn areas. Owner will accept maintenance
-. responsibility for lawn and grass areas after final acceptance of entire project. -
"'s B. Submit certification of seed.
1.05 SITE CONDITIONS
A. Wind Velocity: Apply seed by hydromulching or sowing when wind velocity is less than 5 miles
1 per hour at the Site.
B. Seasonal Requirements: Seed during seeding windows indicated for applicable areas in the Seed
Specification Manual, Golf Courses of North America, published by Seed Research of Oregon,
1996.
1.06 WARRANTY
A. Installer shall guarantee seeding of lawn areas to produce vigorous, healthy and weed free growth
as specified. Installer will replace eroded areas, washouts or bare areas within the period of the
contract at no additional cost. Otherwise conform to the warranty provisions of the General
Requirements.
t
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE II
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 231 02930 -1
Printed 05/03/04
SECTION 02930
LAWNS
PART 2 PRODUCTS '
2.01 MATERIALS '
A. Water: Furnished by Owner.
B. Grass Seed: Grass seed shall be certified. Submit certification. The blend of varieties need not be
certified if the Contractor delivers unopened certified varieties to the site and blends the varieties
onsite prior to planting. Utilize a blend of at least two but not more than three of the following
varieties of perennial ryegrass mixed in equal proportions by weight: Birdie -II, Blazer, Citation II,
Derby, Gator, Manhattan II, Palmer, Prelude, Premier, Repell, Tara BT -1.
C. Hydroseed Mulch: Wood cellulose fiber mulch, containing no growth or germination inhibiting
factors.
D. Tackifier: Acrylamide copolymer (P.A.M.) or organic polysaccharide guar based product.
E. Urea: 46 -0 -0 sulfer coated, slow release
2.02 EQUIPMENT '
A. Hydroseeding Equipment: Hydraulic equipment with continuous mixing and agitating action to
mix water, seed, fertilizer and mulch to form a homogenous slurry, and distribute the mixture on
lawn and other seeded areas.
PART 3 EXECUTION
3.01 LAWN AREAS '
A. Preparation:
1. Do not begin seeding work until finish grades have been approved in writing by Owner's '
representative.
2. Preparation for Seeding: After fine grading has been completed, apply urea at a rate of 2 111 lbs. per 1000 s.f. Do not incorporate into soil.
3. Stabilize by lightly irrigating soil and rolling with a roller. Repeat operation until surface
is stabilized within specified tolerances of finish grade and approved by Owner's
representative.
B. Installation: Apply seed with hydraulic seeding equipment approved by Owner's representative.
Hand or surface seeding is not permissible. Seed at a minimum rate of 6 lbs. per 1000 s.f.
1
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE II
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02930 -2
Printed 05/03/04
1
SECTION 02930
LAWNS
3.02 ADJUSTING AND CLEANING
' A. Adjusting: Repair grades, and reseed lawn areas where soil erosion or poor germination cause
bare areas or "wash- outs ". Contractor is responsible for producing a thick, even turf in lawn areas.
B. Cleaning: At completion of Work in each area, remove debris,equipment and surplus materials.
Wash walks, walls and paving areas adjacent to seeded areas to remove seed, fertilizer, mulch and
soil materials.
C. Provide a 30" minimum height temporary fence of two strands of heavy twine around perimeter of
lawn areas.
' 3.03 MAINTENANCE
A. Lawn Maintenance:
1 1. Irrigate lawn areas to keep moist..
2. Do not walk on lawn areas to irrigate, weed, or replace seed, plugs or sod. When required
use plywood protection boards to reach lawn areas.
3. Apply lawn fertilizer as per manufacturer's recommendations and thoroughly water on
14th day of maintenance period.
4. Maintain lawn areas until final acceptance of entire project.
5. First mowing at 2 -1/2" maximum grass height, cut grass to 1 -1/2 inches and remove
' clippings.
6. Repeat for second mowing two weeks after first mowing and continue mowings weekly or
as needed until final acceptance.
7. Continue lawn care after final acceptance as specified in Section 02491
MAINTENANCE AND WARRANTY
END OF SECTION
I
I
I
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE II
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02930 -3
Printed 05/03/04
SECTION 02950
PLANT MATERIAL
I
PART 1 GENERAL
1.01 GENERAL REQUIREMENTS
A. Drawings and general provisions of the Contract, including General and other Conditions and
other Division 1 - General Requirements sections, apply to the work specified in this Section.
1.02 WORK IN OTHER SECTIONS
A. Warranty and Establishment Operations: Section 02990 LANDSCAPE WARRANTY.
•
B. Prepared Backfill Mix: Section 02920 SOIL PREPARATION.
1.03 SUBMITTALS
A. Certified Confirmed Orders: Certify in writing within 30 days of the award of the bid, confirmed
' orders for plants and provide the quantity, location, phone number and address of the grower who
has agreed to provide plant material.
B. Mulch Sample: Submit samples of bark mulch for review prior to delivery at the Site.
1.04 QUALITY ASSURANCE
' A. Government Inspection: Meet or exceed the specifications of federal, state and county laws
requiring inspection of plants and planting material for plant disease and control.
B. Industry Standards: Quality definitions, grading tolerances, and caliper to height ratios shall be no
less than minimums specified in American Standards for Nursery Stock, published by American
Association of Nurserymen, Inc., ANSI Z60.1- latest edition.
C. Landscape Architect's Inspection: Landscape Architect shall have the right to inspect all plant
material on order at the nursery and reject plant material not meeting specified standards.
Contractor shall locate acceptable plant material and place new orders to replace rejected plant
material at no additional cost to the Owner.
1.05 DELIVERY, STORAGE AND HANDLING
A. Delivery: Notify Landscape Architect of delivery schedule so plant materials may be inspected
upon delivery. Landscape Architect may reject plant materials which do not meet specified
standards. Remove rejected materials from site. Do not deliver more plant materials than can be
planted in one day.
B. Storage and Handling: Protect products against damage or dehydration. Cover plant roots and root
balls with soil or other accepted material upon delivery, if not scheduled for planting within four
hours. Store plant materials in shade and protect against harmful weather.
1
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE II
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02950 -1
' Printed 05/03/04
SECTION 02950
PLANT MATERIAL
PART 2 PRODUCTS
I
2.01 PLANT REQUIREMENTS
A. Nursery Stock: Provide healthy well branched and rooted, full foliaged when in leaf, free of '
disease, injury, insects, weeds and weed roots. Do not use cold storage plants.
B. Large Plant Root Protection: (B &B) Balled and Burlapped with natural ball of size to insure
healthy growth.
C. Small Plant Root Protection: Container - grown, furnished in removable containers or integral peat
pots well rooted to ensure healthy growth. Grown in containers from six months to two years
prior to delivery, with roots filling container but not root bound.
D. Plant Names: Furnish plants true to name and tag one of each bundle or lot with the common and
botanical name. Name and size of plants in accordance with the standards of practice of the
American Association of Nurserymen and shall conform to "Standardized Plant Names." 1942
Edition, published by J. Horace McFarland Company. In all cases, botanical names shall take
precedence over common names.
2.02 MATERIALS
A. Bark Mulch: Free from noxious weeds, seeds and foreign material harmful to plant life. Medium
grind hemlock or fir, maximum size to pass a 3/4" inch mesh screen; or Fine -Comp stuff as
provided by McFarlanes Bark Inc., 13345 SE Johnson Road, Portland OR, 503/659 -4240, or
approved equal.
B. Wood Stakes:
1. Wood Specie and Grade: Douglas Fir, No. 2 or construction grade.
2. Size for evergreen trees: 2" x 2" x 36" nominal
3. Size for deciduous trees: 2" x 2" x 8' -0" nominal.
4. Stake Finish: One coat oil base wood stain, Olympic Redwood Natural Tone #717 or
approved.
C. Guys: Broad belt -type strapping or plastic chain min. 1 1/2" width. Submit sample for approval.
D. Guy Wire and Accessories: 3/32" minimum 5- strand glavanized steel wire rope. Install 18" length
of 3/4" PVC pipe flag on evergreen guys. 5/16" galvanized turnbuckles and eyehooks.
E. Amended Topsoil: See SECTION 02920 SOIL PREPARATION. I
r
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE II
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02950 -2
Printed 05/03/04 ,
SECTION 02950
PLANT MATERIAL
PART 3 EXECUTION
3.01 PREPARATION
A. Protect Existing Site Improvements: Verify location of underground facilities. Protect active
service lines whether indicated or not.
B. Excavate pit to two times diameter of root ball or root system and not less than 6 inches deeper for
shrubs and 12 inches deeper for trees.
3.02 TREE AND SHRUB PLACEMENT
A. Shrub Base: Place shrub directly on undisturbed subgrade. Do not over excavate.
' B. Tree Base: Place tree directly on undisturbed subgrade. Do not over excavate.
C. Plant upright and face to give best appearance or relationship to adjacent plants and structures.
D. Loosen and remove twine binding and burlap from top one half of root balls.
3.03 TREE SUPPORT
A. Guy and stake evergreen trees from three directions as per detail. Securely fasten guy wires to
' stakes with eyehooks and wires to tree with broad belt type or chain plastic tree ties. No wire is
permitted around trunk. Tighten guy wires with turnbuckles. Stake deciduous trees from two
directions as per detail.
' B. Install tree supports prior to backfilling.
' 3.04 BACKFILLING
A. Cut off broken or frayed roots.
B. Place and compact amended imported topsoil. Avoid injury to roots, fill voids.
C. When hole is 4" deep, fill with water and let stand until water is absorbed by soil. Fill to finish
' grade and provide 2" depressed water basin at each shrub and tree.
D. Initial watering -in of trees and shrubs by underground sprinkler system is not permitted
3.05 PLANTING GROUND COVERS
A. Install plants at spacing indicated. Dig holes large enough to allow spreading of roots.
B. Backfill with prepared soil mix, compact to eliminate voids. Slightly dish finish grade at each
plant. Water thoroughly.
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE II
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 231 02950 -3
Printed 05/03/04
SECTION 02950
PLANT MATERIAL
3.06 FIELD PRUNING
A. Prune trees and shrubs to remove damaged or diseased branches. ,
3.07 MULCHING
A. Apply 2" layer of bark mulch over shrub planting beds within two days after planting. Bark shall
also be applied to areas of soil where no lawn or shrubs are indicated.
B. Lift plant foliage above mulch where required.
3.08 ADJUSTING AND CLEANING '
A. Remove and replace plants or materials not meeting specified standards. Remove materials
rejected by the Architect from the site within 24 hours.
B. Reinstall plants not located as indicated on Drawings.
C. Repair damage to service lines or site improvements caused by planting work.
D. Reshape finish grade where directed and remove excess materials from the site.
3.09 ESTABLISHMENT
A. Comply with Section 02990 LANDSCAPE WARRANTY. Begin care of plant materials as soon
as they are planted and continue to the end of the specified period.
END OF SECTION
I
02054
TIGARD HIGH SCHOOL ADDITION / REMODEL — PHASE II
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02950 -4
Printed 05/03/04
SECTION 02990
LANDSCAPE MAINTENANCE AND WARRANTY
1
PART 1 GENERAL
1
1.01 SCOPE OF WORK
1 A. Length of Warranty: One year from the date of substantial completion.
1 1.02 ESTABLISHMENT AND WARRANTY PERIOD REQUIREMENTS
A. PLANT MATERIALS: All plant materials shall be warranted to remain in a healthy condition
I until the end of the Warranty Period. Replace dead and unhealthy plants immediately.
B. IRRIGATION SYSTEM:
' • 1. Scope: Warrant the compete irrigation system. The complete system shall remain fully
operational with head to head coverage, without leaks or settling trenches. Defects, leaks
and settled trenches shall be repaired at no expense to the owner. Pavement which cracks
' due to settlement of trenches shall be replaced. Other damage sustained by trench
settlement shall be repaired at no expense to the Owner.
2. Procedures: When warranty work is needed, the Owner shall inform the Contractor in
' writing to arrange a schedule for repair. If the Contractor does not submit a mutually
acceptable repair schedule within one week of receipt of the request, the Owner shall
have the right have the repairs made by others at normal market rates at the Contractor's
expense. The Owner shall also have the right to make emergency repairs by others at the
Contractor's expense. Emergency repairs shall be defined as repairs necessary to limit
collateral damage such as that caused by a mainline leak or malfunction during hot or dry
weather.
PART 2 PRODUCTS
2.01 PLANT MATERIALS
A. All plant materials and equipment replaced under warranty shall be replaced accordance with all
provisions of the Contract Documents. Equipment shall be of the same manufacturer, model, size
and quantity as originally installed. Plant material shall be of the same variety, size, and quantity
as originally installed. Owner reserves the right to inspect plant materials replaced under warranty
1 and reject those which do not conform to specified standards.
PART 3 EXECUTION
3.01 TURF AREA OPERATIONS
1 A. Fine Mowing: Contractor shall be responsible for the first three mowings after final acceptance.
After the third mowing, the Owner will assume responsibility for mowing, edging and trimming of
' lawns. For all turf areas the contractor shall inspect and police the grounds for litter and debris
prior to each mowing, and dispose of it. Mowing height for all irrigated lawn areas shall be no
less than 1 1/2 ", not to exceed 2 1/2" between mowing operations. At least one week shall pass
between mowings unless the grass exceeds 2 1/2" in height. The turf shall be cut at a uniform
' 02054 TIGARD HIGH SCHOOL ADDITION / REMODEL
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02990-1
Printed 05 /03/04
SECTION 02990
LANDSCAPE MAINTENANCE AND WARRANTY
• height, with reel mowers in open areas and rotaries in closed areas. Scalping and uneven cutting
shall be prevented. Mower blades shall be maintained in a good condition for an even cut. Any
excess clippings shall be dispersed and /or collected to prevent damage to existing lawn areas or if
it causes an unsightly appearance. Contractor shall repair or replace all trees, shrubs and other
plantings and other permanent fixtures that are damaged during Contractor mowing operations.
Mowing equipment will be adjusted and maintained to provide the best possible cut.
B. Edging: All sidewalks, curb lines, concrete slabs, bed edges shall be mechanically edged as
needed to maintain a neat, clean appearance, once every three mowings (minimum).
C. Hand Clipping and Weed Eating: Trimming shall be performed around all road signs, guard posts,
trees, shrubs, utility poles and other obstacles. The grass to be trimmed shall be trimmed no less
than the desired height of cut determined by the mowing operation. To be done with each mowing
operation. 1
D. Sweep /Blow Walks: At the conclusion of each mowing, walks adjacent to work areas are to be
swept or blown clean.
3.02 IRRIGATION SYSTEM
A. The Owner will establish time settings and intervals of irrigation water application for each valve 1
of all irrigation zones. Cooperate with the Owner to make changes when necessary to correspond
to variable watering requirements for all planting areas.
B. Observe operation of all irrigation heads at least twice each operating month until the last mowing.
Check for coverage and plugged or broken heads and leaks; repair leaks, balance system and clean
or replace heads or nozzles as required to maintain system in proper working order. Replacement
heads shall be as originally specified in the Contract Documents.
1
END OF SECTION
1
1
1
1
1
1
02054 TIGARD HIGH SCHOOL ADDITION / REMODEL
MAY 04 TIGARD — TUALATIN SCHOOL DISTRICT 23J 02990 -2
Printed 05/03/04