FIELD INSPECTION REPORT
N
DATES COVERED: August 24, 2010
PROJECT: TV &R — Command & Business Operations Center (Phase III)
ADDRESS: 11945 SW 70 Avenue — Tigard, OR
INSPECTOR: G. Fleming, OBOA #814, ICC #5318962- 86/ -S1
08/24/10: As requested by Ty with A -Pro Fire, CTI representative was on site for fire - sprinkler branch line
seismic restraint inspection. Prior to arrival, 1 1 /2" 0 sprinkler line was secured to structural elements. Observed
use of 12 -ga wire wrapped twice around pipe, secured to upper chord of truss with 4 twists, placed every 43'
per sheet EQ1. Contractor also had 06/22/10 certificate of compliance for seismic wire. Area observed was 3rd
floor, grid lines A -E, 1 -11.
***CHECK ONE BOX ONLY * ** YES NO
1. This is a preliminary inspection only. — OR — ❑
2. The work inspected conforms to acceptance criteria listed above. If "No," the portions of the work that
are non - conforming items are clearly stated above and will be added to the NCL. Remaining portions ® ❑
of the work, which are not preliminary in nature, are to be considered as conforming.
Our reports pertain to the material tested /inspected only. Information contained herein is not to be reproduced,
except in full, without prior authorization from this office. Under all circumstances, the information contained in
this report is provided subject to all terms and conditions of CTI's General Conditions in effect at the time this
report is prepared. No party other than those to whom CTI has distributed this report shall be entitled to use or
rely upon the information contained in this document.
If there are any further questions regarding this matter, please do not hesitate to contact this office.
Respectful y submitted,
CARLS• TESTING, INC.
Ja e C . Hietpas
Pro :.ct Manager
e. /ck
,•c: Tualatin Valley Fire & Rescue — Siobhan Kirk mail / siobhan.kirk @tvfr.com
City of Tigard Building Division ian.eikanas @kpff.com
KPFF — Ian Eikanas
PSE Architects — Nathan Junked nathan@psearchs.com
Howard S Wright Constructors — Jason Chupp chuppj @hswc.com
Tualatin Valley Fire & Rescue — Greg Perry greg.perry @tvfr.com
Tualatin Valley Fire & Rescue — Nancy Collins nancy.collins @tvfr.com
08 -24 -10 fr 618 doc