Capital Improvement Program FY2008-2013 "� 7717'
+ I STOP:: t
i
P -
City of Tigard
Ca ital Im rovement Program p p
Fiscal Years 2008 -2013
Ca ital Im rovement Program P P
2008 -2013
Prepared by CIP Project Team
Tom Coffee, Community Development Director
Gus Duenas, City Engineer
Dennis Koellermeier, Public Works Director
Vannie Nguyen, Engineering Manager
Carissa Coffins, Senior Management Analyst
Joseph Barrett, Senior Management Analyst
Jaime Marshall, Management Analyst
Marissa Daniels, Editor
T able of ontents
:6 .1 Facilities System 7
Parks System 25
Sanitary Sewer System 45
Storm Drainage System 57
Street System 79
Water System 113
1 1 7 , Urban Renewal District 137
F aci li ties - _ r,„,
Page Projected
Number Project 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
9 90130- Senior Center Seismic Upgrade 757,000 258,459 1,015,459
10 90160- Library Site Monitoring 30,000 30,000
11 95030 -New Public Works Facility 5,100,000 3,750,000 3,750,000 12,600,000
12 94040 -New Police Facilities 1,000,000 10,000,000 11,000,000
13 95050 - Library RFID Technology 750,000 750,000
14 96120 -Police Dept. Carpet Replacement 15,000 15,000
15 96140 - Parking Lot R &M - Cook Park 14,350 14,350
16 96150 - Parking Lot R &M - Library 3,840 3,840
17 96160 -HVAC Control Upgrade - Niche 5,000 5,000
18 96170 -PD Locker Rooms Re -Vinyl 13,000 13,000
19 96180- Parking Lot Expansion - PC /CH 100,000 100,000
20 96230 - Repair /Repaint CH /PD /PC 1,000,000 500,000 1,500,000
21 96470- Parking Lot R &M - Ash Street 780 780
22 96480- Parking Lot R &M - PD /CH /PC 6,537 6,537
23 96490 - Parking Lot R &M - Senior Center 5,355 5,355
24 96500 - Parking Lot R &M - Public Works 130,000 130,000
Total Facilities System 757,000 569,321 6,100,000 5,250,000 14,513,000 - 27,189,321
90130- Senior Center Seismic Upgrade
Remodel /expand Senior Center to meet increased service demands from the senior community in Tigard. Contingency has been included in total
construction costs. The remodel of the facility will be conducted in two phases with the first phase being completed in FY 2007 -08, and the second phase
during FY 2009 -09.
Location
8815 SW O'Mara Street
Project Manager(s)
Dan Plaza, Parks
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Rollover from Springbrook
Design and Engineering 37,350 37,350
Construction 757,000 757,000 221,109 978,109
Project Total 757,000 757,000 258,459 1,015,459
Project by Funding Source
Facilities Fund 757,000 757,000 258,459 1,015,459
Project Total 757,000 757,000 258,459 1,015,459
Tigard Capital Improvement Plan FY 2008 - 2013 9
90160- Library Site Monitoring
The on -going evaluation, monitoring, and remediation of contamination to the surrounding property.
Location
Tigard Library
Project Manager(s)
Gus Duenas, Capital Construction & Transportation
No Photo Available Mike McCarthy, Capital Construction & Transportation
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Rollover from Springbrook
Environmental 30,000 30,000
Project Total 30,000 30,000
Project by Funding Source
Facilities Fund 30,000 30,000
Project Total 30,000 30,000
Tigard Capital Improvement Plan FY 2008 -2013 10
95030- New Public Works Facility
The City of Tigard Public Works Department Facility Needs Analysis, dated March 29, 2006, indicated the Public Works Department would need a site
size of approximately 8.0 acres. The department is currently located on two separate sites: The Water Building site at 8777 SW Burnham Street and the
Public Works Operations yard, located at 12800 SW Ash Avenue. Neither site is of sufficient size to consolidate the department. In addition, the Opera-
tions yard site is flagged for future development related to the downtown improvements, which points toward the need to find a new site for the depart-
ment. This project will also include funds for locating and purchasing an appropriate site, as well as funds for design and construction.
Location
To be determined
Project Manager(s)
Brian Rager, Public Works
F _ s
Funding Status
Unfunded
•
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land/Right of Way Acquisition 4,000,000 4,000,000
Design and Engineering 1,100,000 1,100,000
Construction 3,750,000 3,750,000 7,500,000
Project Total 5,100,000 3,750,000 3,750,000 12,600,000
Project by Funding Source
Unfunded 5,100,000 3,750,000 3,750,000 12,600,000
Project Total 5,100,000 3,750,000 3,750,000 12,600,000
Tigard Capital Improvement Plan FY 2008 -2013 11
95040- New Police Facilities
The Tigard Police Department's facility is too small and the situation will continue to deteriorate as we expand our staff to meet the needs of the com-
munity. The current police facility was occupied in 1986 with 5300 sq. ft. It was expanded in 1996, adding 3000 sq. ft. At the time of the expansion, the
facility was projected to be sufficient for the Police Department's needs until 2005. The projection was accurate; the building is no longer sufficient to
meet our needs and has not met them for the past five years. At the time of our 1996 expansion the PD had 61 FTEs. There are now 80 FTEs, eight part-
time employees, up to seventeen volunteers and frequently one intern. Because we have outgrown our current facility we are storing more equipment and
evidence offsite. We also have filled a modular building behind the PD with eight workspaces, equipment and files we are required to maintain. Due to
overcrowding, the Police Department uses shared workspaces for sergeants, background investigators, patrol officers and others whenever possible. In
addition, due to lack of space, we are renting three offsite storage units at approximately $25,000 per year. The last ten years has cost the City of Tigard
over $250,000 in rental fees. As stated above, the PD is currently a facility that does not meet our needs and the usefulness of the current space will only
deteriorate as we add additional staffing and the space /storage needs. Now is the time to plan for a new facility.
t Location
To be determined
R ' ,, Project Manager(s)
Dennis Koellermeier, Public Works
M MN' roucE ., ''' ...- Funding Status
"# Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 1,000,000 1,000,000
Construction 10,000,000 10,000,000
Project Total 1,000,000 10,000,000 11,000,000
Project by Funding Source
Unfunded 1,000,000 10,000,000 11,000,000
Project Total 1,000,000 10,000,000 11,000,000
Tigard Capital Improvement Plan FY 2008 -2013 12
95050- Library RFID Technology
The RFD Technology is an automated materials handling system that will be used by Circulation staff within the City's Library. This system is designed
to improve the efficiency of the return of Library materials.
Location
Tigard Library
Project Manager(s)
Margaret Barnes, Library
No Photo Available
Funding Status
Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 750,000 750,000
Project Total 750,000 750,000
Project by Funding Source
Unfunded 750,000 750,000
Project Total 750,000 750,000
Tigard Capital Improvement Plan FY 2008 -2013 13
96120- Police Dept. Carpet Replacement
Install new carpet in the Police Department (3285 square feet).
Location
13125 SW Hall Blvd.
Project Manager(s)
Nick Nissen, Facilities Coordinator
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 15,000 15,000
Project Total 15,000 15,000
Project by Funding Source
Facilities Fund 15,000 15,000
Project Total 15,000 15,000
Tigard Capital Improvement Plan FY 2008 -2013 14
96140- Parking Lot R &M - Cook Park
Repair and maintenance to various City facility parking lots to include sealing, striping, saw cutting, patching and overlays.
-....- wri Location
n Cook Park
Project Manager(s)
- - Nick Nissen, Facilities Coordinator
0 10._
Vance Walker, Streets Supervisor
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 14,350 14,350
Project Total 14,350 14,350
Project by Funding Source
Facilities Fund 14,350 14,350
Project Total 14,350 14,350
Tigard Capital Improvement Plan FY 2008 - 2013 15
96150- Parking Lot R &M - Library
Repair and maintenance to various City facility parking lots to include sealing, striping, saw cutting, patching and overlays.
Location
Tigard Library 13500 SW Hall Blvd
%-_ 4 7___* , 4 * - 7 ---- j -- +
maw
Project Manager(s)
Nick Nissen, Facilities Coordinator
Vance Walker, Streets Supervisor
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 3,840 3,840
Project Total 3,840 3,840
Project by Funding Source
Facilities Fund 3,840 3,840
Project Total 3,840 3,840
Tigard Capital Improvement Plan FY 2008 -2013 16
96160- HVAC Control Upgrade - Niche
Install new HVAC control system at the Niche that will enable it to be controlled by computer.
���_ Location
Niche
h Project Manager(s)
_ \
f,�
®w " -� I A Nick Nissen, Facilities Coordinator
--T Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 5,000 5,000
Project Total 5,000 5,000
Project by Funding Source
Facilities Fund 5,000 5,000
Project Total 5,000 5,000
Tigard Capital Improvement Plan FY 2008 -2013 17
96170- PD Locker Rooms Re -Vinyl
Install new vinyl floor surface in the Men's and Women's locker rooms at the Police Department (approx. 2354 sq.ft.)
Ill 51 Location
13125 SW Hall Blvd.
Project Manager(s)
Nick Nissen, Facilities Coordinator
Funding Status
- Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 13,000 13,000
Project Total 13,000 13,000
Project by Funding Source
Facilities Fund 13,000 13,000
Project Total 13,000 13,000
Tigard Capital Improvement Plan FY 2008 -2013 18
96180- Parking Lot Expansion - PC /CH
Addition of 20 to 25 spaces to the City Hall /Permit Center parking lot to compensate for those spaces lost to skate park construction.
Location
lor
13125 SW Hall Blvd.
Project Manager(s)
Steve Martin, Parks & Facilities Manager
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 100,000 100,000
Project Total 100,000 100,000
Project by Funding Source
Park System Development Charge 100,000 100,000
Project Total 100,000 100,000
Tigard Capital Improvement Plan FY 2008 - 2013 19
96230- Repair/Repaint CH /PD/PC
This project comes as a recommendation by Cascade Inspections Northwest as a result of a facility inspection. It will remove the existing Exterior Insulation
Finishing System (EIFS) from the Police Department, Permit Center and City Hall and replace it with a new Portland Cement Stucco system. This new sys-
tem will stop water infiltration and prevent mold build up. Repairs will be made to all the wet spots and painting of the new stucco will complete the project.
This project will be completed in two phases with Phase One being the Permit Center and Phase Two being City Hall and the Police Department.
t ti Location
.: a 13125 SW Hall Blvd
I I L ' Project Manager(s)
, ; Steve Martin Parks & Facilities Manager
t
lit
T -
• 1 Funding Status
Partially Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 1,000 500 1,500,000
Project Total 1,000,000 500,000 1,500,000
Project by Funding Source
Facilities Fund 500,000 500,000 1,000,000
Unfunded 500,000 500,000
Project Total 1,000,000 500,000 1,500,000
Tigard Capital Improvement Plan FY 2008 -2013 20
96470- Parking Lot R &M - Ash Street
Repair and maintenance to various City facility parking lots to include sealing, striping, saw cutting, patching and overlays.
Location
P r , F. 1 12800 SW Ash Avenue
� _ Project Manager(s)
Nick Nissen, Facilities Coordinator
/41-111, 7 _�- -i ` Vance Walker, Streets Supervisor
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 780 780
Project Total 780 780
Project by Funding Source
Facilities Fund 780 780
Project Total 780 780
Tigard Capital Improvement Plan FY 2008 -2013 21
96480- Parking Lot R &M - PD /CH/PC
Repair and maintenance to various City facility parking lots to include sealing, striping, saw cutting, patching and overlays.
. ' Location
.A.t. fi ..,, g • _ � P 13125 SW Hall Blvd
}_ - 4- s
i_ -'/°
Project Manager(s)
Nick Nissen, Facilities Coordinator
Vance Walker, Streets Supervisor
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 6,537 6,537
Project Total 6,537 6,537
Project by Funding Source
Facilities Fund 6,537 6,537
Project Total 6,537 6,537
Tigard Capital Improvement Plan FY 2008 -2013 22
96490- Parking Lot R &M - Senior Center
Repair and maintenance to various City facility parking lots to include sealing, striping, saw cutting, patching and overlays.
= Location
8815 SW O'Mara Street
Project Manager(s)
Nick Nissen, Facilities Coordinator
Vance Walker, Streets Supervisor
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 5,355 5,355
Project Total 5,355 5,355
Project by Funding Source
Facilities Fund 5,355 5,355
Project Total 5,355 5,355
Tigard Capital Improvement Plan FY 2008 -2013 23
96500- Parking Lot R &M - Public Works
Repair and maintenance to various City facility parking lots to include sealing, striping, saw cutting, patching and overlays.
' '''- 'I!'s w'" Location
' " 8777 SW Burnham St
Project Manager(s)
Nick Nissen, Facilities Coordinator
- Vance Walker, Streets Supervisor
1
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 130,000 130,000
Project Total 130,000 130,000
Project by Funding Source
Facilities Fund 130,000 130,000
Project Total 130,000 130,000
Tigard Capital Improvement Plan FY 2008 -2013 24
,*- -- 7, 7 " \ N' -: __, , , . .A"`"' "i , - _-<-
P arks k
Page Projected
Number Project 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
27 90950 -Fanno Cr. Trail (Hall /Fanno) 275,350 275,350
28 91020 -Clute Property - Demolition 300,000 300,000
29 91070 - Washington Sq. Regional Center Trail 20,000 410,020 430,020
30 95060 -Brown Property Trail Construction 25,000 225,000 250,000
31 95070 -Cach Park Development 265,000 265,000
32 95080 - Canterbury Park 140,000 540,000 140,000 140,000 140,000 1,100,000
33 95090 - Entryway Monuments 95,000 95,000 95,000 95,000 380,000
34 95100 -Cook Park Restroom Shelter 70,000 70,000
35 95110 - Elizabeth Price Park Development 351,000 351,000
36 95120 Jack Park Extension 25,000 616,000 641,000
37 95140 -Park System Master Plan Update 50,000 50,000 100,000
38 96130 -Clute Property House Demolition 30,000 30,000
39 96190 -Skate Park Restroom 75,000 75,000
40 96200 -Fanno Cr. Trail (74 /Cook) 650,000 650,000
41 96210 -Senn Park Trailhead 149,500 149,500
42 96510- Loucks /Burton House Demolition 30,000 30,000
43 96520 -Parks SDC Update 20,000 20,000
44 96530 - Schaltz Property Improvements 135,000 135,000
Total Parks System 305,000 2,280,870 1,076,000 535,000 1,055,000 - 5,251,870
90950- Fanno Creek Trail (HalUFanno)
The new trail will begin on the east side of Hall Boulevard, then southward to just north of Fanno Creek. A wood pedestrian bridge will be installed in
conjunction with this project to connect this trail and the existing trail behind the Library. The final alignment of the new trail is contingent upon the
level of impact to the sensitive lands located in the trail's vicinity. Bridge materials have been purchased by the City and installation of the new bridge
awaits final determination of the trail alignment. Funding provided for this project is for design and construction of the trail and the bridge abutments.
T; 4 ; t .-Jay-71 t . ,- :. Location
' East of Hall Blvd. & North of Fanno Creek
k r h t ; t
Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
4 i`
,
ri �� t :
F pi s r , ; ` - Funding Status
r. , ,+ 1 y ,,� I— ; t , , „7,-. Fully Funded
�' " . ;' r � ; a 1 :1,„,.,.;# i �'`,.. - i, AC.
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 156,000 275,350 275,350
Project Total 156,000 275,350 275,350
Project by Funding Source
General Fund 119,350 119,350
Parks Capital Fund 156,000 120,120 120,120
Park System Development Charge 35,880 35,880
Project Total 156,000 275,350 275,350
Tigard Capital Improvement Plan FY 2008 -2013 27
91020- Clute Property- Demolition
This park development project will include a playground structure, picnic shelter, basketball court, portable restroom, picnic tables, benches, garbage cans,
and soft and hard surface trails.
Location
Bull Mountain
Project Manager(s)
■ is ,
. f Dan Plaza, Parks
Funding Status
� � ' Fully Funded
' lwN ✓P
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 300,000 300,000
Project Total 300,000 300,000
Project by Funding Source
General Fund 180,000 180,000
Park System Development Charge 120,000 120,000
Project Total 300,000 300,000
Tigard Capital Improvement Plan FY 2008 -2013 28
91070- Washington Square Regional Center Trail
This project provides funding for right -of -way acquisition and construction of a trail on the south side of Ash Creek between 95th Avenue and Hall
Boulevard. The trail will be approximately 3,000 feet long by 10 feet wide and will be a multi -use bicycle and pedestrian path.
The project is funded through Washington County's MSTIP 3 Bike /Ped funds in the amount of $250,671, and through the Metropolitan Transportation
Improvement Program (MTIP) in the amount of $179,349. The County's MSTIP 3 funding ($250,671) will be used for design and right -of -way
acquisition and the MTIP funds ($179,349) will be used to construct the project. The total project budget from both sources is $430,020. In FY 2007 -08,
$20,000 was utilized for environmental assessment and preliminary design. Wetland permitting, final design and right -of -way acquisition are scheduled
to be completed in FY 2008 -09.
Location
'it 1 Between 95th Avenue & Hall Blvd.
Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
Funding Status
rt Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Rollover from Springbrook
Land/Right of Way Acquisition 172,008 180,671 180,671
Design and Engineering 70,000 20,000 50,000 70,000
Construction 188,012 179,349 179,349
Project Total 430,020 20,000 410,020 430,020
Project by Funding Source
Parks Capital Fund 430,020 20,000 410,020 430,020
Project Total 430,020 20,000 410,020 430,020
Tigard Capital Improvement Plan FY 2008 - 2013 29
95060- Brown Property Trail Construction
This will be a 1500 foot segment of the Fanno Creek Trail connecting the Tigard Library to Bonita Park. It will be a 10 foot wide, concrete trail and will
include one bridge to cross Fanno Creek.
Location
Tigard Library to Bonita Park
x � r
Project Manager(s)
Dan Plaza, Parks
u _ Funding Status
Fully Funded
y ` v #
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Pre - Design 25,000 25,000
Design and Engineering 32,500 32,500
Construction
Project Total 25,000 32,500 57,500
Project by Funding Source
Parks Capital Fund 192,500 192,500
Park System Development Charge 25,000 32,500 57,500
Project Total 25,000 225,000 250,000
Tigard Capital Improvement Plan FY 2008 -2013 30
95070- Cach Park Development
This park, located on Sunrise Lane on Bull Mountain, will contain playgrounds, swing sets, basketball court, picnic shelter, pathways, and open play fields,
restrooms, drinking fountains, and benches.
Location
Sunrise Lane
Project Manager(s)
Dan Plaza, Parks
Funding Status
Fully Funded
kflig
..,� Via.
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 15,000 15,000
Construction 250,000 250,000
Project Total 265,000 265,000
Project by Funding Source
Park System Development Charge 265,000 265,000
Project Total 265,000 265,000
Tigard Capital Improvement Plan FY 2008 -2013 31
95080- Canterbury Park
The City will purchase a portion of the Tigard Water District reservoir property to develop a neighborhood park. Park development will include a
playground structure, picnic shelter, basketball court, portable restroom, picnic tables, benches, garbage cans, and soft and hard surface trails. This site is
located at the intersection of 103rd Avenue and Canterbury Lane.
Location
103rd Avenue & Canterbury Lane
}'fit
4 Project Manager(s)
�M Dan Plaza, Parks
k s, ,.�
, Funding Status
i F k _ - ». Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land/Right of Way Acquisition 1,000,000 140,000 140,000 140,000 140,000 140,000 700,000
Pre - Design 15,000
Construction 85,000 400,000 400,000
Project Total 1,100,000 140,000 540,000 140,000 140,000 140,000 1,100,000
Project by Funding Source
General Fund 322,600 322,600
Parks Capital Fund 1,100,000 140,000 82,600 82,600 82,600 387,800
Park System Development Charge 217,400 57,400 57,400 57,400 389,600
Project Total 1,100,000 140,000 540,000 140,000 140,000 140,000 1,100,000
Tigard Capital Improvement Plan FY 2008 -2013 32
95090- Entryway Monuments
This project ties with a Council goal to establish custom entryway monument signs at key entry points into the City. A landscape architect was hired to
develop detailed designs for these monuments and signs, and it is anticipated that for the next two fiscal years, two monuments will be installed per year.
Location
� TIGARD Various Locations
A P�o�, Hom
=V—E ° Project Manager(s)
Dennis Kocllermeier, Public Works
+ ". r Funding Status
IGARD Partially Funded
=WP 6n000
cmn mww ma+q mwt nry m m mcwa Ana .rone om.. wp., a cM d rgwa weo
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 95,000 95,000 95,000 95,000 95,000 380,000
Project Total 95,000 95,000 95,000 95,000 95,000 380,000
Project by Funding Source
Not Applicable
Parks Capital Fund 95,000 95,000 95,000 190,000
Unfunded 95,000 95,000 190,000
Project Total 95,000 95,000 95,000 95,000 95,000 380,000
Tigard Capital Improvement Plan FY 2008 -2013 33
95100- Cook Park Restroom Shelter
Replace bathroom and rehabilitate shelter #1 at Cook Park. These facilities are approximately 15 years old and are in very poor shape. The old
restrooms will be replaced and the present shelter will be rehabilitated. Both share the same building structure. This project will separate the two
facilities.
Location
,, n
" + Cook Park
t:1� ' I e l
*9 „ :
fri. Project Manager(s)
Dan Plaza, Parks
r
t
.;' - ? --- Funding Status
----"I'1.- Fully Fully Funded
- 7.--_
z-
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 70,000 70,000
Project Total 70,000 70,000
Project by Funding Source
General Fund 70,000 70,000
Project Total 70,000 70,000
Tigard Capital Improvement Plan FY 2008 -2013 34
95110- Elizabeth Price Park Development
This park, located on Bull Mountain Road across the street from Alberta Rider School, will contain a tot lot, climbing structure, pathways, drinking
fountains, benches, and picnic tables.
Location
Bull Mountain Road
AIR
B I'il
t Project Manager(s)
Dan Plaza, Parks
oti 111
No Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 351,000 351,000
Project Total 351,000 351,000
Project by Funding Source
Park System Development Charge 351,000 351,000
Project Total 351,000 351,000
Tigard Capital Improvement Plan FY 2008 -2013 35
95120- Jack Park Extension
Purchase and develop approximately 2 -acres on Walnut Street adjacent to Jack Park. This project is in conjunction with the new TVF &R fire station.
This park will continue to serve the residents living in the vicinity of Jack Park. The development to occur on the 2 -acre site consists of turf areas,
parking, playground structure, trail, and a bridge to cross the creek.
0 , A '.iV ," Location
1Gr, 4 " a Near 12420 SW 127th Avenue
E ' a
f • • . . F r � "Eat. ' � �.
1,,,, Ja i ' " Project Manager(s)
, � t may , ; =a " Dan Plaza, Parks .tsay.,,,,,...4.,70r.
ik7Q d e��, !,
14 4- 4 4
•t Te Funding Status
' Fully Funded
l ag
' _, , k . 114 . . s ..
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land /Right of Way Acquisition 600,000 343,500 343,500
Design and Engineering 25,000 10,000 35,000
Construction 262,500 262,500
Project Total 600,000 25,000 616,000 641,000
Project by Funding Source
General Fund 15,000 369,600 384,600
Parks Capital Fund 600,000
Park System Development Charge 10,000 246,400 256,400
Project Total 600,000 25,000 616,000 641,000
Tigard Capital Improvement Plan FY 2008 -2013 36
95140- Park System Master Plan Update
The current Park System Master Plan was approved in 1999. Although only 8 years have passed since it was approved, it is staffs belief that an update
at this time is in the City's best interest because it will coincide with the City's Comprehensive Plan process currently underway. The plan will address
land acquisition and park development projects for the next ten years.
Location
N/A
Project Manager(s)
No Photo Available Dan Plaza, Parks
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 50,000 50,000 50,000 100,000
Project Total 50,000 50,000 50,000 100,000
Project by Funding Source
Parks Capital Fund 50,000 50,000 50,000
Park System Development Charge 50,000 50,000
Project Total 50,000 50,000 50,000 100,000
Tigard Capital Improvement Plan FY 2008 - 2013 37
96130- Clute Property House Demolition
Demolish and remove house debris from the Clute property.
'i t°Ii"fa /R' �. Location
' ` 13230 SW 154th Avenue
� s o a ✓ M�` � � s_ �
0� �
Project Manage
: ^ u
' rr a -i * � Manager(s)
._
��. et. � � Steve Martin, Parks & Facilities Manager
ficbtox‘ .,., ,, ,:,..,,,- - ,I i ' � ,, Funding Status
�" reelrit`:.:% i A Fully Funded
i t' - , t 4 f ir
s
hlteAllik 4''' 4.146011x
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 30,000 30,000
Project Total 30,000 30,000
Project by Funding Source
Parks Capital Fund 30,000 30,000
Project Total 30,000 30,000
Tigard Capital Improvement Plan FY 2008 - 2013 3 8
96190- Skate Park Restroom
An ADA accessible, unisex restroom will be constructed near the skate park. A drinking fountain will also be installed.
Location
13125 SW Ha11 Blvd.
is
" + Project Manager(s)
_ `.. - Gus Duenas, Capital Construction & Transportation
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 25,000 25,000
Construction 50,000 50,000
Project Total 75,000 75,000
Project by Funding Source
Park System Development Charge 75,000 75,000
Project Total 75,000 75,000
Tigard Capital Improvement Plan FY 2008 - 2013 39
96200- Fanno Creek Trail (74 /Cook)
Acquire property, right -of -way, and easement to install a half mile of hard surface trail from Cook Park to and along 74th St.
int * r „ ,;; ;. . �° Location
74th St. to Cook Park
>.y F
Project Manager(s)
Steve Martin, Parks & Facilities Manager
Funding Status
_ Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land/Right of Way Acquisition 100,000 100,000
Design and Engineering 50,000 50,000
Construction 500,000 500,000
Project Total 650,000 650,000
Project by Funding Source
General Fund 390,000 390,000
Park System Development Charge 260,000 260,000
Project Total 650,000 650,000
Tigard Capital Improvement Plan FY 2008 -2013 40
96210- Senn Park Trailhead
The development of Senn Park will include a small play structure, interpretive trails, viewing area, drinking fountain, climbing structures, and
landscaping.
Location
- E 9852 SW 74th Avenue
f 4'p''
t . Project Manager(s)
: ti Steve Martin, Parks
i xea r 1
7 , t, Funding Status
"� Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 149,500 149,500
Project Total 149,500 149,500
Project by Funding Source
General Fund 115,000 115,000
Parks Capital Fund
Park System Development Charge 34,500 34,500
Project Total 149,500 149,500
Tigard Capital Improvement Plan FY 2008 - 2013 41
96510- Loucks /Burton House Demolition
Once property is purchased the demolition phase will begin. The entire house and other structures, patios, landscaping, etc. will be removed. Grading
and minor landscaping will be completed after demolition.
Location
c ., 13337 SW Hall Blvd.
'E t Q
Project Manager(s)
Gus Duenas, Capital Construction & Transportation
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 30,000 30,000
Project Total 30,000 30,000
Project by Funding Source
Parks Capital Fund 30,000 30,000
Project Total 30,000 30,000
Tigard Capital Improvement Plan FY 2008 -2013 42
96520- Parks SDC Update
In the winter /spring of 2009 the Parks Systems Development Charges (SDC) methodology will be updated. The update will be conducted by a
consultant. The process will determine how SDC's are applied and new SDC rates may be established.
Location
N/A
Project Manager(s)
Gus Duenas, Capital Construction & Transportation
No Photo Available
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 20,000 20,000
Project Total 20,000 20,000
Project by Funding Source
Park System Development Charge 20,000 20,000
Project Total 20,000 20,000
Tigard Capital Improvement Plan FY 2008 -2013 43
96530- Schaltz Property Improvements
After a feasibility study is completed decisions will be made on the type and extent of improvements to be completed at the site. Improvements may
include: structural and engineering improvements to the house; landscape design and installation, additional parking, environmental studies, possible
trail extension, etc.
Location
13335 SW Hall Blvd.
Project Manager(s)
Steve Martin, Parks & Facilities Manager
Gu Funding Status
Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 135,000 135,000
Project Total 135,000 135,000
Project by Funding Source
General Fund 135,000 135,000
Unfunded
Project Total 135,000 135,000
Tigard Capital Improvement Plan FY 2008 -2013 44
S anitary Sewer .. ,
___
Page Projected
Number Project 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
47 90270 -Red Rock Creek Repair 8,000 75,000 83,000
48 90280 - Sanitary Sewer Master Plan 85,000 70,000 155,000
49 95150 -Pipe Removal (Bonita /Fanno Cr.) 2,000 35,000 37,000
50 95160 - Sanitary Sewer Extension Program 1,500,000 1,200,000 750,000 750,000 4,200,000
51 95180- Sanitary Sewer Upgrade (Hwy 217) 500,000 500,000
52 95190 - Sanitary Sewer Upgrade (Hunziker) 500,000 500,000
53 95210- Sanitary Sewer Major Maintenance 75,000 50,000 50,000 50,000 50,000 50,000 325,000
54 96570 - Sanitary Sewer Repair (Hwy 217 /Kruse Way) 60,000 60,000
55 96580 - Sanitary Sewer Repair (Milton Ct.) 75,000 75,000
Total Sanitary Sewer System 1,670,000 1,565,000 1,300,000 1,300,000 50,000 50,000 5,935,000
90270- Red Rock Creek Repair
Red Rock Creek north of Atlanta Street has caused erosion resulting in exposed sewer pipe. The creek will be relocated to a rebuilt historic channel.
The stream channel that is within the sewer alignment will be repaired and a berm will be constructed to direct flow from the sewer.
cataiNf - Location
�.a 6900 SW Atlanta Street
ti, ) i f I Project Manager(s)
Greg Berry, Capital Construction & Transportation
1
Funding Status
Fully Funded
? f
- i
r
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Rollover from Springbrook
Construction 100,000 8,000 75,000 83,000
Project Total 100,000 8,000 75,000 83,000
Project by Funding Source
Sanitary Sewer 100,000 8,000 75,000 83,000
Project Total 100,000 8,000 75,000 83,000
Tigard Capital Improvement Plan FY 2008 -2013 47
90280- Sanitary Sewer Master Plan
The master plan will recommend rehabilitation, expansion and replacement projects over the next 20 years that will guide the preparation of the 5 -year
Capital Improvement Program and identify projects for the subsequent 15 years. It will be a separate plan prepared by a consultant hired by CWS to
update the 2000 Sewer Master Plan Update, which is the current basin -wide plan. The 2000 Sewer Master Plan Update identified nine City sewers with
suspected sewer capacity deficiencies. In addition, City staff has identified three other areas that may also have inadequate capacity. CWS will install
flow monitoring stations at all of these locations and record sewer flows to determine the extent of the capacity deficiencies. The consultant will use the
results of the flow monitoring to develop a plan to correct the deficiencies.
Location
N/A
Project Manager(s)
Greg Berry, Capital Construction & Transportation
No Photo Available
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 70,000 85,000 70,000 155,000
Project Total 70,000 85,000 70,000 155,000
Project by Funding Source
Sanitary Sewer 70,000 85,000 70,000 155,000
Project Total 70,000 85,000 70,000 155,000
Tigard Capital Improvement Plan FY 2008 -2013 48
95150- Pipe Removal (Bonita/Fanno Creek)
A portion of Fanno Creek north of Bonita Rd. will be restored by removing an exposed abandoned sewer pipe crossing the creek. The pipe obstructs the
creek creating a fish barrier and maintenance problems. The surrounding creek bank will be restored with native plantings.
, 3w Location
r i_ '
? , West of Bonita Road/Milton Court intersection
r\
,,, ' , x Project Manager(s)
Brian Rager, Public Works
i
x
. ?q Y N? {. - Funding Status
-- r Fully Funded
= ,,
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 20,000 2,000 35,000 37,000
Project Total 20,000 2,000 35,000 37,000
Project by Funding Source
Sanitary Sewer 20,000 2,000 35,000 37,000
Project Total 20,000 2,000 35,000 37,000
Tigard Capital Improvement Plan FY 2008 -2013 49
95160- Sanitary Sewer Extension Program
The Citywide Sanitary Sewer Extension Program began in FY 2001 -02, to extend sewers to all developed but un- served residential areas Citywide. The
City uses the formation of reimbursement districts to construct the sewers. The program has been extended due to the number of districts that can be
constructed each fiscal year. The Commercial Area Sewer Extension Program is also funded from the Sanitary Sewer Fund and offers commercial
entities the opportunity to participate in reimbursement districts for extension of sewer service to commercial areas. The current incentive programs for
early connection in residential neighborhoods are not offered to the commercial sector. Funding is provided to accommodate potential projects that may
surface during the fiscal year from the commercial sector.
Pit ''`° Location
Various locations
,rte's � � Project Manager(s)
0 pH , � M ,-
3- a _ ,! Vannie Nguyen, Capital Construction & Transportation
1 Greg Berry, Capital Construction & Transportation
z
i iik,
-' Funding Status
j ~ Fully Funded
At
e
�I 5 $
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 200,000 200,000 150,000 75,000 75,000 500,000
Construction 1,800,000 1,300,000 1,050,000 675,000 675,000 3,700,000
Project Total 2,000,000 1,500,000 1,200,000 750,000 750,000 4,200,000
Project by Funding Source
Sanitary Sewer 2,000,000 1,500,000 1,200,000 750,000 750,000 4,200,000
Project Total 2,000,000 1,500,000 1,200,000 750,000 750,000 4,200,000
Tigard Capital Improvement Plan FY 2008 - 2013 50
95180- Sanitary /Sewer Upgrade (Hwy 217)
There is an existing 8 -inch sanitary sewer line that carries flow from the area near the intersection of 72nd Avenue /Hampton Street westerly toward
Highway 217, then north along Highway 217 to a point where the line increases in size and crosses under the freeway. The 8 -inch section shows signs of
reaching capacity and with further development taking place in the Tigard Triangle, the City anticipates a need to upsize this section to at least 12 inches.
The City is working with Clean Water Services (CWS) toward a Sanitary Sewer Master Plan that will analyze these kinds of issues throughout the City.
Staff anticipates the Master Plan will confirm that the line should be upsized, and estimates this large project will be designed and constructed in FY
09/10. The length of sewer line to replace is approximately 2,250 feet. Methods of replacement will need to be reviewed during the design phase, but
could include in -place pipe bursting.
Location
72nd Ave. /Hampton West toward Hwy 217
4
Project Manager(s)
‘; Brian Rager, Public Works
' COL_ Funding Status
- $ 71 Fully Funded
� B7
♦ � `
� �° � r i� 1i o'± r
R _ J.
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 75,000 75,000
Construction 425,000 425,000
Project Total 500,000 500,000
Project by Funding Source
Sanitary Sewer 500,000 500,000
Project Total 500,000 500,000
Tigard Capital Improvement Plan FY 2008 - 2013 51
95190- Sanitary /Sewer Upgrade (Hunziker)
This project will upgrade the existing sanitary sewer line that is expected to be over capacity due to the additional development planned for the Tigard
Triangle.
V' •,1 'i ' - I Location
l ' 7920 to 8001 Hunziker St.
-7/f v.
: _ ,� `6 Project Manager(s)
r Dennis Koellermeier, Public Works
Funding Status
V. 04, i ' - �' Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 500,000 500,000
Project Total 500,000 500,000
Project by Funding Source
Sanitary Sewer 500,000 500,000
Project Total 500,000 500,000
Tigard Capital Improvement Plan FY 2008 -2013 52
95210- Sanitary Sewer Major Maintenance
The Sanitary Sewer Fund will be used to contract out sewer repair projects that are beyond the repair capabilities of the City's Public Works Department.
This program is intended to be a continuing program of preventative maintenance. This program will avoid restoration costs that could be several times
higher. The Sanitary Sewer Major Maintenance Program will include sewer repair projects located at various locations in the City.
Location
Various locations
j Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 100,000 75,000 50,000 50,000 50,000 50,000 50,000 325,000
Project Total 100,000 75,000 50,000 50,000 50,000 50,000 50,000 325,000
Project by Funding Source
Sanitary Sewer 100,000 75,000 50,000 50,000 50,000 50,000 50,000 325,000
Project Total 100,000 75,000 50,000 50,000 50,000 50,000 50,000 325,000
Tigard Capital Improvement Plan FY 2008 - 2013 53
96570- Sanitary Sewer Repair - Hwy 217 /Kruse Way
There is a section of 8 -inch sanitary sewer line that appears to have been damaged near the footing of the Hwy 217/Kruse Way overpass. This project
will replace the whole section of pipe using a combination of open trench and pipe bursting methods due to the close proximity of the pipe to the existing
footing.
Location
Hwy 217 & Kruse Way
1 " ' Project Manager(s)
,...., Vannie Nguyen, Capital Construction & Transportation
�< - Funding Status
1 b
-„,, Fully Funded
1 �' J
3 t xf h
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 60,000 60,000
Project Total 60,000 60,000
Project by Funding Source
Sanitary Sewer 60,000 60,000
Project Total 60,000 60,000
Tigard Capital Improvement Plan FY 2008 -2013 54
96580- Sanitary Sewer Repair - MiltonCt.
This project will include realigning 187 feet of sanitary sewer to replace a section of leaking dislocated pipe. This section crosses the top bank of Fanno
Creek. Necessary easements will need to be obtained for the construction. Environmental permits and final design were completed in FY 2007 -08. This
project will be constructed in FY 2008 -09.
Location
d; jo sus Milton Court
Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
I �
' : , , Funding Status
F, " y � i �` Fully Funded
t,
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 75, 75,000
Project Total 75,000 75,000
Project by Funding Source
Sanitary Sewer 75,000 75,000
Project Total 75,000 75,000
Tigard Capital Improvement Plan FY 2008 -2013 55
1M P _ E' r - ,114' _.1` -
_ -- � ,. ,,om rl / /
S torm D rainage . , ��� � � � � �� � � �
Page Projected
Number Project 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
59 90350 -Storm Drain Rehabilitation 50,000 50,000 50,000 50,000 50,000 50,000 300,000
60 90430 -Water Quality Enhancement 25,000 180,000 25,000 25,000 25,000 25,000 305,000
61 95220- Culvert Replacement (72nd /Dartmouth) 20,000 25,000 45,000
62 95230 - Regional Detention Facility (Commercial St.) 50,000 225,000 275,000
63 95240 - Community Tree Planting 40,000 40,000 35,000 20,000 20,000 155,000
64 95250 - Culvert Replacement 100,000 100,000 200,000
65 95280- Stream Bank Stabilization (Durham /108th) 50,000 100,000 50,000 200,000
66 95290- Riparian Restoration & Enhancement 10,000 10,000 10,000 10,000 30,000 70,000
67 95300 -Storm Water Outfall Retrofits 90,000 90,000
68 95310 -Slope Stabilization (Derry Dell Cr. @ 118th) 100,000 150,000 250,000
69 95330 -Storm Drain Improvements (Greensway) 150,000 150,000
70 95420 - Pedestrian /Bicycle Paths 50,000 50,000 50,000 50,000 50,000 50,000 300,000
71 96330 -Storm Improvements - Greenburg Rd. @ Shady Ln. 150,000 150,000
72 96340 -Storm Drain Installation (100th Ave.) 150,000 150,000
73 96350 - Hiteon Cr. Riparian Enhancement (Downstream) 185,000 185,000
74 96360- Summer & Ascension Cr. Tree Planting 45,000 45,000
75 96440- Community Tree Planting - Capital Maintenance 55,000 60,000 70,000 75,000 70,000 330,000
76 96450 - Culvert & Outfall Improvements (In -House 40,000 25,000 25,000 25,000 25,000 140,000
Construction)
77 96590 -Slope Erosion Repair - Waverly Dr. 20,000 20,000
78 96730 - Culvert Improvements - Walnut St. (Derry Dell Cr./ 75,000 75,000
Fanno Cr.)
Total Storm System 355,000 1,325,000 535,000 265,000 615,000 340,000 3,435,000
90350- Storm Drain Rehabilitation
This yearly program addresses minor storm drainage problems requiring more than normal maintenance effort by the City's Public Works department.
The Storm Drainage Major Maintenance Program includes projects located at various locations in the City.
Location
Various locations
Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
No Photo Available
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 10,000 10,000 10,000 10,000 10,000 10,000 10,000 60,000
Construction 40,000 40,000 40,000 40,000 40,000 40,000 40,000 240,000
Project Total 50,000 50,000 50,000 50,000 50,000 50,000 50,000 300,000
Project by Funding Source
Storm Water 50,000 50,000 50,000 50,000 50,000 50,000 50,000 300,000
Project Total 50,000 50,000 50,000 50,000 50,000 50,000 50,000 300,000
Tigard Capital Improvement Plan FY 2008 -2013 59
90430- Water Quality Enhancement
The projects under this program are focused on systematically upgrading existing water quality facilities that have deteriorated over the years. The
funding will be from the non -SDC portion of the Water Quality /Quantity Fund. The amount allocated for each fiscal year should be able to address one
or more projects annually. Some of the projects that have been identified for implementation during the 5 -year plan period are as follows:
Water Quality Facility #030 (SW Steve St.) This unnamed tributary to Ash Creek at this location is severely incised and threatening abutting properties.
The project installs 150 feet of pipe in the most severely eroded areas and improves remaining area by regrading and replanting as a storm w quality
Swale. Necessary permits and final design are underway. Construction of the project will occur between July and October 2008 to meet the in -water
work window requirement.
r : Location
SW Steve Street, SW Greensward, SW Walnut & 135th
Project Manager(s)
Brian Rager, Public Works
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Rollover from Springbrook
Construction 25,000 25,000 180,000 25,000 25,000 25,000 25,000 305,000
Project Total 25,000 25,000 180,000 25,000 25,000 25,000 25,000 305,000
Project by Funding Source
Traffic Impact Fee
Water Quality /Quantity 25,000 25,000 180,000 25,000 25,000 25,000 25,000 305,000
Project Total 25,000 25,000 180,000 25,000 25,000 25,000 25,000 305,000
Tigard Capital Improvement Plan FY 2008 - 2013 60
95220- Culvert Replacement (72nd/Dartmouth)
The project upgrades an existing culvert located at the 72nd Avenue/ Dartmouth Street intersection to provide additional culvert capacity to relieve
flooding. Implementation of the project also addresses the culvert replacement goal of the Healthy Streams Plan initiated by Clean Water Services. The
design of the upgrade will be combined with the 72nd Avenue/ Dartmouth intersection design already budgeted.
� ,P, Location
.-W _ \,.. \; r -` 72nd Avenue & Dartmouth Streets
i e \ <�1 r
� r / • � di/pa � � Project Manager(s)
' G � & ,� 1 ° Vannie Nguyen, Capital Construction & Transportation
\ �' ) Carla Staedter, Public Works
- -,,,, p ,. - - 44 -
aN- ':1.1410,941:y7-4;R.4, � � Funding Status
, -- *V-
e -, -' _ Full Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 20,000 20,000 25,000 45,000
Project Total 20,000 20,000 25,000 45,000
Project by Funding Source
Water Quality /Quantity 20,000 20,000 25,000 45,000
Project Total 20,000 20,000 25,000 45,000
Tigard Capital Improvement Plan FY 2008 -2013 61
95230- Regional Detention Facility(Commercial Street)
This project constructs a regional storm water detention facility that would treat approximately 40 acres of storm water in and around the downtown Tigard
area. Project design has been completed as part of the design for the Commercial St. improvements. The project will accomplish the outfall retrofit goal of
the Healthy Streams Plan initiated by Clean Water Services.
t � 11F'lii,, ►,d4 Location
1640Y1 Commercial St.
Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
Carla Staedter, Public Works
Funding Status
•' Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 150,000 50,000 225,000 275,000
Project Total 150,000 50,000 225,000 275,000
Project by Funding Source
Water Quality /Quantity 150,000 50,000 225,000 275,000
Project Total 150,000 50,000 225,000 275,000
Tigard Capital Improvement Plan FY 2008 - 2013 62
95240- Community Tree Planting
The City of Tigard will plant native trees and shrubs along creeks and streams in the city to meet the Community Tree Planting goals identified in the
Healthy Streams Plan.
- k.. ..- ,;,^ ," _ - Location
t _ Various locations
t o
j ,, Project Manager(s)
; , it ��: '. Carla Staedter, Public Works
e0 '�- -:= .� Funding Status
? "4 : �s�� Fully Funded
a
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 40,000 40,000 35,000 20,000 20,000 155,000
Project Total 40,000 40,000 35,000 20,000 20,000 155,000
Project by Funding Source
Water Quality /Quantity 40,000 40,000 35,000 20,000 20,000 155,000
Project Total 40,000 40,000 35,000 20,000 20,000 155,000
Tigard Capital Improvement Plan FY 2008 -2013 63
95250- Culvert Replacement
This project will accomplish the culvert replacement goals identified in Clean Water Services Healthy Streams Plan which requires the replacement of 3
culverts per year in both FY 11/12 and FY 12/13. The City will replace problem culverts based on funding availability.
7.‘ PM', ' t " ' 7th Location
�,� a `�` *� ` To be determined
. ' ¢ r ; Project Manager(s)
,. Vannie Nguyen, Capital Construction & Transportation
r - . Carla Staedter, Public Works
a. F.
� 1
'` Funding Status
Fully Funded
1
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 100,000 100,000
Construction 100,000 100,000
Project Total 100,000 100,000 200,000
Project by Funding Source
Water Quality /Quantity 100,000 100,000 200,000
Project Total 100,000 100,000 200,000
Tigard Capital Improvement Plan FY 2008 - 2013 64
95280- Stream Bank Stabilization (Durham /108th)
The creek bank and a portion of the segmental -block retaining wall south of Durham Road have been eroded and undermined due to high stream flow
out falling from a 36 -inch culvert crossing the street. The contributing factors to the problems are a large boulder, which was placed in the middle of the
stream, and the culvert alignment, which does not line up with the creek. The original scope of work proposed in FY 2006 -07, which included
restoration of a portion of the retaining wall and extension of the culvert for proper alignment with the creek, has been revised to add bank stabilization.
Necessary easements have been obtained for the construction. Environmental permits and final design are scheduled to be completed in FY 2007 -08.
Construction will take place between July 1 through September 30, 2008 to comply with the in -water work window requirement.
R Location
Durham Road & 108th Avenue
{
Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 50,000 50,000
Construction 150,000 100,000 50,000 150,000
Project Total 150,000 50,000 100,000 50,000 200,000
Project by Funding Source
Storm Water 150,000 50,000 100,000 50,000 200,000
Project Total 150,000 50,000 100,000 50,000 200,000
Tigard Capital Improvement Plan FY 2008 - 2013 65
95290- Riparian Restoration & Enhancement
This fund will be available for urban forestry projects within riparian corridors. The fund will also support any supplemental planting or site work
needed in the event of an unforeseen failure to past riparian restoration projects.
9 : .ri i x" .- , , t ' �` `+` Location
" , P yr , . ..
Various locations to be determined
r.
X11
Project Manager(s)
h '' Carla Staedter, Public Works
. I 1 I N .
� .. Funding Status
A `"' ` " Fully Funded
i _, , . :.,,,..41.''-.. '-'' .--',"`";:' -
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 10,000 10,000 10,000 10,000 10,000 30,000 70,000
Project Total 10,000 10,000 10,000 10,000 10,000 30,000 70,000
Project by Funding Source
Water Quality /Quantity 10,000 10,000 10,000 10,000 10,000 30,000 70,000
Project Total 10,000 10,000 10,000 10,000 10,000 30,000 70,000
Tigard Capital Improvement Plan FY 2008 - 2013 66
95300- Storm Water Outfall Retrofits
The funding will be used to conduct a geotechnical study to determine the recommended repair method for each outfall retrofit project and to perform the
repairs. The retrofits will be established as an annual program to address the outfall retrofit goals identified in Clean Water Services Healthy Streams Plan.
Location
N/A
Project Manager(s)
4 Brian Rager, Public Works
Funding Status
,,; Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 90,000 90,000
Project Total 90,000 90,000
Project by Funding Source
Water Quality /Quantity 90,000 90,000
Project Total 90,000 90,000
Tigard Capital Improvement Plan FY 2008 - 2013 67
95310- Slope Stabilization (Derry Dell Creek at 118th)
In September 2006, the City discovered slope erosion and bank stability- related issues occurring at two locations in the vicinity of Derry Dell Creek and
118th Avenue. A geotechnical study has been conducted to determine reasons for the erosion and recommend slope stabilization techniques that would
prevent the slope from continuing to erode. Secured plastic sheeting has been placed at one location that appeared to be potentially unstable in December
2006. The funding provided is utilized for final design and repair of the problem at this location. Mitigation of the erosion at the second location is
proposed for FY 2008 -09.
,r- Location
' , 118th Court
vv v 3
o i l
� Project Manager(s)
- i ` '' k '$, �' Vannie Nguyen, Capital Construction & Transportation
T • 4{'4 �:-*'
�_ t
1 , r -t .
Funding Status
t t �= v _ ' Fully Funded
0 —
r-t ° 7 dig . tea
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 20,000 20,000 20,000
Construction 80,000 80,000 150,000 230,000
Project Total 100,000 100,000 150,000 250,000
Project by Funding Source
Storm Water 100,000 100,000 150,000 250,000
Project Total 100,000 100,000 150,000 250,000
Tigard Capital Improvement Plan FY 2008 -2013 68
95330- Storm Drain Improvements (Greensway)
This project will install approximately 900 feet of Polyvinyl Chloride (PVC) pipe, five manholes and seven catch basins between Highland and
Summerfield Drive. The existing aluminized steel pipe has been gradually corroding which has resulted in increased maintenance costs. The existing
pipe will be abandoned in place to avoid extensive roadway excavation and protect the structure integrity of the street. The new pipe is expected to have
a longer service life and adequate capacity to serve the neighborhood.
Location
Highland & Summerfield Drive
Project Manager(s)
Vannie Nguyen, C apital Construction & Transportation
Funding Status
- Fully Funded
„p
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 150,000 150,000
Project Total 150,000 150,000
Project by Funding Source
Storm Water 150,000 150,000
Project Total 150,000 150,000
Tigard Capital Improvement Plan FY 2008 - 2013 69
95420- Pedestrian /Bicycle Paths
This project constructs pathways to improve pedestrian safety and access between bus stops, schools and adjacent residential developments. Pathways
can either be concrete sidewalks or paved/gravel paths. Landscaped strips are not included in the scope of work as the need for the improvement is to
fill in gaps between existing sidewalks within limited rights -of -ways or to enhance pedestrian access to transit stops.
Paved /gravel pathways may also be off - street (but within the street right -of -way) to be used by pedestrians and bicyclists. To construct the pathways,
existing ditches that convey storm water will be replaced with pipes and backfilled with clean rock. Locations of the improvements will be at various
locations in the City.
The fund may be used to prepare, in partnership with the school district, a master plan for sidewalk, bicycle and traffic safety related improvements
within two miles of schools in Tigard. Improvements identified in the master plan will be used to request for grants from federal and state programs.
Grants, if obtainable, will help to expand local funding sources to make school routes safe for children to walk and bike.
Location
Various
Project Manager(s)
oistlek Vannie Nguyen, Capital Construction & Transportation
_
' Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 60,000 50,000 50,000 50,000 50,000 50,000 250,000
Project Total 60,000 50,000 50,000 50,000 50,000 50,000 250,000
Project by Funding Source
Storm Water 60,000 50,000 50,000 50,000 50,000 50,000 250,000
Project Total 60,000 50,000 50,000 50,000 50,000 50,000 2.50,000
Tigard Capital Improvement Plan FY 2008 -2013 70
96330- Storm Improvements - Greensburg Rd at Shady Lane
A damaged drainage pipe will be replaced and a manhole will be installed.
pm -...- ,..-,%.,. _:i1:-.01wir--_,41 Location
Greenburg Rd at Shady Lane
'1H' i` , , P roject Manager(s)
0 '�' ;� Gus Duenas, Capital Construction & Transportation
f , ,, -, 4 ,' -- '.,' Carla Staedter, Public Works
Funding Status
/ � Fully Funded
w ,
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 150,000 150,000
Project Total 150,000 150,000
Project by Funding Source
Storm Water 150,000 150,000
Project Total 150,000 150,000
Tigard Capital Improvement Plan FY 2008 - 2013 71
96340- Storm Drain Installation 100th
This project provides funding for installation of new storm pipes on 100th Ave from Sattler Road to Murdock Street. The pipes will be constructed concur-
rently with the roadway improvements, which will include backfilling the existing narrow ditch at about 6 feet deep, widening the roadway and installing
sidewalks. The completed projects will not only provide a safe walk for pedestrians but also improve the capacity of the storm drainage system.
its' , Location
y , I k Sattler Road to Murdock Street
'' ' .,� . Project Manager(s)
Ito 1 s Vannie Nguyen, Capital Construction & Transportation
' #4* r w 1 #, �' . :7 w '
d
Funding Status
�� � �iC _ Fully Funded
litt ' — 7, X11. 4 ea 4 .
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 150,000 150,000
Project Total 150,000 150,000
Project by Funding Source
Storm Water 150,000 150,000
Project Total 150,000 150,000
Tigard Capital Improvement Plan FY 2008 -2013 72
96350- Hiteon Cr. Riparian Enhancement (downstream)
This project constructs riparian enhancement features, including modifications of riparian buffer areas, to promote the treatment of high flows. It also
includes removal of culverts and repair of stream channel associated with an asphalt pedestrian path. In FY 2006 -07 permitting was completed from the
project. The proposed funding is to complete construction of the project. The project will accomplish culvert replacement, outfall retrofit, and
community tree planting goals identified in Clean Water Services Healthy Streams Plan.
' . a 9a�p.. Location
" wr Downstream of Springwood Dr.
r k V
� a
"p gy s 7�` i a? s ,, ;I Project Manager(s)
IC . gi ' c s 5 4 � Carla Staedter, Public Works
n: �
' "` I ..' `` Funding Status
''. �, Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 35,000 35,000
Project Total 35,000 35,000
Project by Funding Source
Storm Water 35,000 35,000
Water Quality /Quantity 150,000 150,000
Project Total 185,000 185,000
Tigard Capital Improvement Plan FY 2008 -2013 73
96360- Summer & Ascension Creek TreePlanting
This project includes site preparation and installation of 11,000 native trees and shrubs on 5.1 acres of riparian corridor along Summer Creek between 121st
Ave. and 116th St. The project also includes the removal of non - native vegetation and planting of 1,000 native trees and shrubs along Ascension Creek,
a separate site, located in a city -owned greenbelt between Ascension Dr. and Fern St. These planting projects will meet a Community Tree Planting goal
identified in the Healthy Streams Plan.
Location
Between 121st Ave. & 116th St.
Project Manager(s)
Carla Staedter, Public Works
No Photo Available
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 41,250 41,250
Contingency 3,750 3,750
Project Total 45,000 45,000
Project by Funding Source
Water Quality /Quantity 45,000 45,000
Project Total 45,000 45,000
Tigard Capital Improvement Plan FY 2008 -2013 74
96440- Community Tree Planting - Capital Maintenance
This project plans and implements maintenance activities for three years following planting of Healthy Streams projects. Maintenance activities include
management of non - native plant species, mowing, and light herbicide application as needed to establish plantings. These maintenance projects will
ensure that plantings installed to meet Community Tree Planting goals, identified in the Healthy Streams Plan, become established and survive.
Location
To be determined
Project Manager(s)
Gus Duenas, Capital Construction & Transportation
No Photo Available
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 55,000 60,000 70,000 75,000 70,000 330,000
Project Total 55,000 60,000 70,000 75,000 70,000 330,000
Project by Funding Source
Water Quality /Quantity 55,000 60,000 70,000 75,000 70,000 330,000
Project Total 55,000 60,000 70,000 75,000 70,000 330,000
Tigard Capital Improvement Plan FY 2008 -2013 75
96450- Culvert & Outfall Improvements (In House Construction)
This project provides funding to complete culvert and outfall retrofitting using on -call consultants to assist with design and permitting and using our
stormwater crews to complete construction of the projects. Projects to be completed in FY 2008 -09 include removal of a culvert on Derry Dell Creek
upstream of Eden Court and repair of an outfall to Derry Dell Creek upstream of 118th. Projects for subsequent years will be identified and completed as
crew time allows and based on prioritization discussed in the Healthy Streams Plan. This project meets the goals of the Healthy Streams Plan.
Location
Derry Dell Cr. Upstream of 118th
Project Manager(s)
Gus Duenas, Capital Construction & Transportation
No Photo Available Carla Staedter, Public Works
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 24,000 15,000 15,000 15,000 15,000 84,000
Construction 16,000 10,000 10,000 10,000 10,000 56,000
Project Total 40,000 25,000 25,000 25,000 25,000 140,000
Project by Funding Source
Water Quality /Quantity 40,000 25,000 25,000 25,000 25,000 140,000
Project Total 40,000 25,000 25,000 25,000 25,000 140,000
Tigard Capital Improvement Plan FY 2008 -2013 76
96590- Slope Erosion Repair - Waverley Drive
Erosion caused by a storm drain outfall between two houses will be repaired. An outfall structure to prevent further erosion will be constructed and the
surrounding area will be planted with native vegetation.
- Location
Waverly Drive
i Project Manager(s)
- Greg Berry, Capital Construction & Transportation
. _ , _
`r Funding Status
• ," ,pRLv � t Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 20,000 20,000
Project Total 20,000 20,000
Project by Funding Source
Water Quality /Quantity 20,000 20,000
Project Total 20,000 20,000
Tigard Capital Improvement Plan FY 2008 -2013 77
96730- Culvert Improvements - Walnut St. (Derry Dell Cr./Fanno Cr.)
This project will construct upgrades to the existing Derry Dell Creek culverts at Fanno Creek and Walnut St. The existing culvert will be removed to in-
crease capacity and provide fish passage. The project will also accomplish the culvert replacement goal identified in Clean Water Services' Healthy Streams
Plan. The project was initiated in FY 06/07 and also included the culvert under Walnut Street. The Walnut street culvert will be improved in conjunction
with road improvements in FY 10 /11. The City of Tigard is currently negotiating with Clean Water Services and a private landowner to realign Derry Dell
Creek to protect sewer lines in the vicinity. If this partnership is successfully negotiated, the funds from this project will be diverted to be used to design the
larger project of stream re- alignment.
., ;�a : Location
� �� $, Walnut Street @ Pathfmder Street
Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
•
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 75,000 75,000
Project Total 75,000 75,000
Project by Funding Source
Water Quality /Quantity 75,000 75,000
Project Total 75,000 75,000
Tigard Capital Improvement Plan FY 2008 -2013 78
� �9 ' __ -- - rte. „,,_,,
S treets
fir
m
Page Projected
Number Project 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
81 90440- Pavement Major Maintenance Program 824,679 935,511 1,150,000 1,150,000 1,150,000 1,150,000 6,360,190
82 90560 -Ash Ave. Extension (Burnham to RR) 578,920 400,000 978,920
83 90660 -Hall Blvd. Half - Street Improvements 200,000 75,000 275,000
84 90770 - Greenburg Rd / 99W Intersection 360,000 1,165,300 3,149,596 255,000 640,000 5,569,896
86 95350 -110th Ave. Improvements (Sattler to Murdock St.) 75,000 300,000 375,00()
87 95370 - Collector & Arterial ROW Enhancement 5,000 35,000 35,000 35,000 35,000 145,000
88 95410 - Street Improvements - 72nd Ave. (Dartmouth to 99W) 400,000 400,000 1,448,000 1,650,000 3,898,000
89 95430 -Ash Ave. Extension (Fanno Cr. / Scoffins) 200,000 500,000 1,000,000 1,700,000
90 95450 - Street Improvements- 121st (Walnut to N. Dakota) 200,000 300,000 650,000 1,150,000
91 95460 - Street Improvements - 121st (Whistler to Tippit) 400,000 1,350,000 2,000,000 3,750,000
92 95470 - Street Improvements - 72nd Ave. (Bonita to Hunziker) 450,000 450,000
93 95480 - Street Improvements - 72nd Ave. (Hunziker to Dartmouth) 400,000 400,000 400,000 1,200,000
94 95490 - Sidewalk - 92nd Ave. (Durham Rd. to Cook Park) 100,000 450,000 550,000
95 95500 - Street Improvements - Dartmouth Rd. (72nd to 68th) 300,000 500,000 800,000
96 95520 -Right Turn Lane Widening (Hall Blvd. at McDonald) 350,000 50,000 400,000
97 95530- Street Improvements - Murdock (103rd to 97th) 75,000 400,000 475,000
98 95540- Pedestrian Bridge (N. Dakota) 300,000 100,000 400,000
99 95550- Street Improvements - N. Dakota (Greenburg to 95th) 50,000 50,000
100 95560 - Street Improvements - Walnut St. (116th to Tiedeman) 127,000 1,043,000 2,500,000 697,000 4,367,000
101 95910 - Crosswalks (Hall / Fanno Cr.) 20,000 80,000 100,000
102 95920- Traffic Light (Main / Tigard) 175,000 175,000
103 95950- Gateway Treatment (SE Corner Main St.) 225,000 225,000
Continued on next page
Page Projected
Number Project, ctd. 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
104 95980- Tigard Triangle LID #1 155,500 2,200,000 2,355,500
105 96250 - Former St. / 115th Guardrail 25,000 25,000
106 96260 - School Zone Flashing Beacons 160,000 160,000
107 96280 - Sidewalk - Hall Blvd. (Bonita Rd. / 600'N) 336,566 336,566
108 96290- Pedestrian Bridge Repair (Tigard St.) 40,000 40,000
109 96380- Traffic Median Modification (Dartmouth to 99W) 15,000 15,000
110 96400- Street Improvements - Greenburg Rd. (N. Dakota to Shady 400,000 1,000,000 1,400,000
111 96710- Crosswalk & Lighting System (Durham Rd. / Tigard H.S.) 60,000 60,000
Total Street System 155,500 2,836,566 - - 400,000 1,000,000 4,392,066
90440- Pavement Major Maintenance Program
The funding will provide for improvements of the areas outside the existing edges of pavement if needed (i.e. Widening a narrow travel lane, paving a
gravel shoulder, etc.). Rehabilitation of streets, including reconstruction if necessary, within the existing edges of pavement will be funded through the
Street Maintenance Fee Fund.
Location
A I Various locations
*4 Project Manager(s)
Gus Duenas, Capital Construction & Transportation
Mike McCarthy, Capital Construction & Transportation
- - Funding Status
- = Partially Funded
mr- Jar
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Rollover from Springbrook
Construction 824,679 824,679 935,511 1,150,000 1,150,000 1,150,000 1,150,000 6,360,190
Project Total 824,679 824,679 935,511 1,150,000 1,150,000 1,150,000 1,150,000 6,360,190
Project by Funding Source
Gas Tax 24,679 24,679 125,000 149,679
Street Maintenance Fee 800,000 800,000 810,511 692,629 692,478 692,413 693,700 4,381,731
Unfunded 457,371 457,522 457,587 456,300 1,828,780
Project Total 824,679 824,679 935,511 1,150,000 1,150,000 1,150,000 1,150,000 6,360,190
Tigard Capital Improvement Plan FY 2008 -2013 81
90560- Ash Ave Ext (Burnham to RR)
The project includes construction of a 24 -foot wide paved section to provide two travel lanes and a 5 -foot wide sidewalk on the west side. Streetlights,
storm drain and sanitary sewer pipes are also included in the project. The new street connects the future Burnham /Ash Ave intersection to the new Park
and Ride parking lot constructed by the Commuter Rail project.
VR T' + i' Location
Burnham Street to railroad tracks
Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Rollover from Springbrook
Land /Right of Way Acquisition 378,920 578,920 400,000 978,920
Design and Engineering
Construction
Project Total 378,920 578,920 400,000 978,920
Project by Funding Source
Gas Tax 378,920 578,920 400,000 978,920
Project Total 378,920 578,920 400,000 978,920
Tigard Capital Improvement Plan FY 2008 -2013 82
90660- Hall Blvd Half Street Improvements
Hall Blvd is a state -owned highway and is classified as arterial, which consists of five travel lanes with bike lanes and sidewalks on both sides. This
project widens Hall Blvd on the east side of the street from the existing Fanno Creek Bridge to approximately 450 feet north. The current northbound
travel lane, which is less than 12 feet, will be widened to 12 feet. The narrow roadway shoulder will be widened to provide space for a 6 -foot bike lane.
The new sidewalk will be placed at the ultimate location where it can be retained for future street improvements. Mitigation of the storm water generated
by the additional impervious area will also be addressed in the design. The existing bridge will not be widened as part of this project.
Location
Fanno Creek to 450 feet north
Project Manager(s)
z : Vannie Nguyen, Capital Construction & Transportation
• Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Pre - Design
Construction 200,000 75,000 275,000
Project Total 200,000 75,000 275,000
Project by Funding Source
Traffic Impact Fee 200,000 75,000 275,000
Unfunded
Project Total 200,000 75,000 275,000
Tigard Capital Improvement Plan FY 2008 - 2013 83
90770- Greenburg Rd /99W Intersection
The existing intersection of Highway 99W with Greenburg Road and Main Street and the Highway 99W intersection with Hall Boulevard are the most
highly congested intersections in the City. Capacity improvements to the Highway 99W/ Hall Boulevard intersection are funded through Washington
County's MSTIP 3 program and the project is in the design stage for construction sometime in 2008. The improvements to the Hall Boulevard/ 99W
intersection will not be fully effective in improving circulation and relieving traffic congestion as long as the bottleneck at the Greenburg Road intersection
remains. A corresponding improvement to the Greenberg Road intersection is needed to complement the Hall/ 99W project and improve traffic circulation
across and along Highway 99W north of the viaduct to the Highway 217 interchange. The specific capacity improvement will include:
• Separating the through and left -turn movements by adding dedicated left -turn lanes on Greenburg Road and Main Street;
• Providing dedicated through movements across the intersection from both side streets and retain the dedicated right -turn lanes on both streets; and
• Constructing an additional eastbound through lane on Highway 99W from the viaduct east through the intersection to connect to the new
eastbound through lane planned for the Highway 99W/ Hall Boulevard intersection.
Location
Greenburg Road/Highway 99W/Main Street
Project Manager(s)
im P Gus Duenas, Capital Construction & Transportation
Mike McCarthy, Capital Construction & Transportation
Funding Status
Partially Funded
—.00-
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land /Right of Way Acquisition 1,000,000 1,000,000
Design and Engineering 500,000 360,000 15,000 375,000
Construction 150,000 3,149,596 255,000 640,000 4,194,596
Environmental 300 300
Project Total 500,000 360,000 1,165,300 3,149,596 255,000 640,000 5,569,896
Project by Funding Source
Water Fund 15,300 15,300
City Gas Tax 500,000 360,000 1,150,000 1,855,404 3,365,404
Tigard Capital Improvement Plan FY 2008 -2013 84
Unfunded 1,294,192 255,000 640,000 2,189,192
Project Total 500,000 360,000 1,165,300 3,149,596 255,000 640,000 5,569,896
Tigard Capital Improvement Plan FY 2008 -2013 85
95350 -100th Ave. Improvements (Sattler to Murdock St.)
100th Avenue between Sattler and Murdock Street is approximately 20 feet wide and is drained by deep ditches along the west side of the street. The two
travel lanes of 10 feet each take up all street space leaving no area for roadway shoulders. This condition creates a risk for motorists traveling the street espe-
cially at night. The proposed improvements, which include backfilling the ditches for street widening, and installing storm drain pipes and curbs, will provide
wider travel lanes (up to 12 feet wide) and some spaces on the street for emergency parking if feasible.
. - Location
to N:, , ' Sattler to Murdock St.
x� °i urf
' � 'fix ri
Project Manager(s)
— r Vannie Nguyen, Capital Construction & Transportation
Funding Status
F - Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 75,000 75,000
Construction 300,000 300,000
Project Total 75,000 300,000 375,000
Project by Funding Source
Unfunded 75,000 300,000 375,000
Project Total 75,000 300,000 375,000
Tigard Capital Improvement Plan FY 2008 - 2013 86
95370- Collector & Arterial ROW Enhancement
This is an annual effort to retrofit and upgrade landscaping in the collector and arterial rights of way.
hR \\ Location
_ 1'' Various locations to be determined
• N. 1p „-., ,, , qii
- _- �� _,
- - •,,,-.- , ,,,,,, = � � i Project Manager(s)
Dennis Koellermeier, Public Works
47
Funding Status
Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 5,000 5,000 35,000 35,000 35,000 35,000 145,000
Project Total 5,000 5,000 35,000 35,000 35,000 35,000 145,000
Project by Funding Source
Gas Tax 5,000 5,000 5,000
Unfunded 35,000 35,000 35,000 35,000 140,000
Project Total 5,000 5,000 35,000 35,000 35,000 35,000 145,000
Tigard Capital Improvement Plan FY 2008 - 2013 87
95410- Street Improvements (72nd Ave., Dartmouth to 99W)
The vertical alignment of 72nd Avenue between Dartmouth Street and Highway 99W requires corrections to meet sight distance standards. In addition,
the street is narrow and the pavement surface is in poor condition. This project widens the street, corrects the vertical sight distance, upgrades the
existing storm drain, extends the sanitary sewer, and undergrounds the existing utilities to provide a three -lane roadway section with bike lanes and
sidewalks both sides. Rights -of -way will be obtained as part of the project for the ultimate street cross section of five lanes.
Location
72nd Avenue between Dartmouth Street & Hwy 99W
Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
) . -
8
II
_!' 1 Funding Status
// ■e Partially Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land/Right of Way Acquisition 400,000 400,000 800,000
Design and Engineering 400,000 400,000
Construction 1,048,000 1,650,000 2,698,000
Project Total 400,000 400,000 1,448,000 1,650,000 3,898,000
Project by Funding Source
Underground Utility 150,000 150,000
Unfunded 400,000 400,000 1,448,000 1,500,000 3,748,000
Project Total 400,000 400,000 1,448,000 1,650,000 3,898,000
Tigard Capital Improvement Plan FY 2008 -2013 88
95430- Ash Avenue Extension (Fanno Creek/Scoffins St.)
A corridor study was completed to determine a feasible alignment for Ash Avenue extension between Fanno Creek and Scoffms Street. This project
proposes to design and acquire necessary rights -of -way for future construction of the extension. The design will incorporate improvement concepts
developed by the Downtown Comprehensive Streetscape plan.
Location
Fanno Creek and Scoffms Street
_ Project Manager(s)
Gus Duenas, Capital Construction & Transportation
Funding Status
j
Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land /Right of Way Acquisition 500,000 500,000
Design and Engineering 200,000 200,000
Construction 1,000,000 1,000,000
Project Total 200,000 500,000 1,000,000 1,700,000
Project by Funding Source
Unfunded 200,000 500,000 1,000,000 1,700,000
Project Total 200,000 500,000 1,000,000 1,700,000
Tigard Capital Improvement Plan FY 2008 - 2013 89
95450- Street Improvements -121st (Walnut to N. Dakota)
This project widens 121st Avenue between Walnut and North Dakota Street to a three -lane roadway with bike lanes and sidewalks on both sides. Planter
strips are also installed wherever feasible. Water, storm drainage, and sanitary sewer improvements and utility under- grounding are also included in the
project. Replacement of the existing bridge on this street will be done under a separate project as costs associated with the replacement may be substantial
and could possibly be funded through different funding sources (i.e. federal grants).
' � •, 'I Location
, ,�. ' Between Walnut St. & N. Dakota
i
� Project Manager(s)
.-, Vannie Nguyen, Capital Construction & Transportation
,
( f\h. -----
— i Funding Status
— Partially Funded
I
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land/Right of Way Acquisition 200,000 200,000
Construction 300,000 650,000 950,000
Project Total 200,000 300,000 650,000 1,150,000
Project by Funding Source
Underground Utility 150,000 150,000
Unfunded 200,000 300,000 500,000 1,000,000
Project Total 200,000 300,000 650,000 1,150,000
Tigard Capital Improvement Plan FY 2008 -2013 90
95460- Street Improvements (121/Whistler /Tippit)
The design for the project, which began in FY 2001 -02, consists of roadway, storm drainage, water, streetlight improvements and utility underground.
The design was completed in FY 2003 -04 and partial right -of -way has been acquired from two properties. Remaining rights -of -way are programmed for
FY 2009 -10 and the construction is scheduled to begin in FY 2010 -11. Upon completion of the construction, the street will have a paved width of 44
feet, which consists of two travel lanes, a center -turn lane and two bike lanes. Sidewalks will also be provided.
'' - > Location
: -.+ ' _ '`� ! ± 121st Avenue
\ ''Z' Project Manager(s)
a r F Vannie Nguyen, Capital Construction & Transportation
_,
_ Funding Status
1'
Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land/Right of Way Acquisition 215,000 215,000
Construction 185,000 1,350,000 2,000,000 3,535,000
Project Total 400,000 1,350,000 2,000,000 3,750,000
Project by Funding Source
Unfunded 400,000 1,350,000 2,000,000 3,750,000
Project Total 400,000 1,350,000 2,000,000 3,750,000
Tigard Capital Improvement Plan FY 2008 - 2013 91
95470- Street Improvements (72nd/Bonita-Hunziker)
This project continues the improvements for 72nd Avenue from south of the 72nd Ave /Dartmouth Street intersection to Hunziker Street. The
improvements involve street widening, utility underground, storm drainage and sanitary sewer upgrades. One travel lane will be provided in each
direction. A center -turn lane will also be added to allow for safe left turn movements. Full -width sidewalks and bike lanes will also be installed as part of
the improvements.
�y � ,i Location
, Re 72nd Ave. (Bonita to Hunziker)
AP
• , - Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
7 - ______ Funding Status
Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 450,000 450,000
Project Total 450,000 450,000
Project by Funding Source
Unfunded 450,000 450,000
Project Total 450,000 450,000
Tigard Capital Improvement Plan FY 2008 -2013 92
95480- Street Improvements (72nd Ave - Hunziker to Dartmouth)
This project widens 72nd Avenue to a three -lane roadway, which includes a center -turn lane and one travel lane in each direction. Sidewalk will be
installed at a location where it can be retained for the ultimate improvements for a five -lane roadway section as specified by the Tigard Transportation
System plan. Right -of -way acquisition is included in the project.
fi Location
," 72nd Ave. (Hunziker to Dartmouth)
x
' Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
Funding Status
Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land /Right of Way Acquisition 400,000 400,000 800,000
Design and Engineering 400,000 400,000
Project Total 400,000 400,000 400,000 1,200,000
Project by Funding Source
Unfunded 400,000 400,000 400,000 1,200,000
Project Total 400,000 400,000 400,000 1,200,000
Tigard Capital Improvement Plan FY 2008 - 2013 93
95490- Sidewalk -92nd Ave (Durham Road to Cook Park)
This project will rebuild existing street sections and add curbs, drainage facilities and sidewalks adjacent to Cook Park to provide a safe pedestrian travel
during the Balloon Festival and other regional activities at Cook Park.
Location
Durham Road to Cook Park
Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
Funding Status
Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land/Right of Way Acquisition 50,000 50,000
Design and Engineering 10,000 10,000
Construction 90,000 400,000 490,000
Project Total 100,000 450,000 550,000
Project by Funding Source
Unfunded 100,000 450,000 550,000
Project Total 100,000 450,000 550,000
Tigard Capital Improvement Plan FY 2008 -2013 94
95500- Street Improvements (Dartmouth /72nd Ave -68th Ave)
This project proposes to reconstruct Dartmouth Street between 72nd and 68th Avenue. The street from east of Highway 99W to 72nd Avenue has been
improved by the City and surrounding developments in the past few years. The intersection of Dartmouth Street and 72nd Avenue is under design for
installation of a traffic signal at the intersection. This project expands the improvements from east of the intersection to 68th Avenue. The street section
after construction will have two travel lanes, one in each direction, a center -turn lane and bike lanes and sidewalks on both sides.
1L r Location
Dartmouth (72nd to 68th)
4F h'4 � T
r
1 ,
Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
,
I %hi Funding Status
Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land/Right of Way Acquisition 500,000 500,000
Design and Engineering 300,000 300,000
Project Total 300,000 500,000 800,000
Project by Funding Source
Unfunded 300,000 500,000 800,000
Project Total 300,000 500,000 800,000
Tigard Capital Improvement Plan FY 2008 - 2013 95
95520 - Right Turn Lane Widening (Hall at McDonald)
This project involves the design, acquisition of necessary right -of -way and construction of a southbound right -turn lane on Hall Boulevard at McDonald
Street. In addition to the turn-lane, curb and sidewalk will also be installed to improve pedestrian safety and the existing signal timing at the intersection
will be modified to improve traffic circulation at the intersection.
1 '..i' Location
- 1 Hall Blvd. and McDonald Street
filli4 RI
Project Manager(s)
■ 1,4 ' ,e Vannie Nguyen, Capital Construction & Transportation
;' r
Funding Status
- Fully Funded
- ifir
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land /Right of Way Acquisition 100,000 100,000
Construction 250,000 50,000 300,000
Project Total 350,000 50,000 400,000
Project by Funding Source
Traffic Impact Fee 350,000 50,000 400,000
Project Total 350,000 50,000 400,000
Tigard Capital Improvement Plan FY 2008 -2013 96
95530- Street Improvements (Murdock -103rd to 97th)
Children walking to Twality Jr. High School and James Templeton School are forced to walk along the edges of Murdock Street as the street is narrow
and has no shoulders. The proposed improvements include backfilling existing ditches to provide space for street widening, installing storm drain pipes,
and constructing curbs and sidewalks at least on one side of the street. Acquisition of right -of -way may be required for the widening.
w.7.0011 Location
te' 103rd Avenue to 97th Avenue
Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
Funding Status
Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 75,000 75,000
Construction 400,000 400,000
Project Total 75,000 400,000 475,000
Project by Funding Source
Unfunded 75,000 400,000 475,000
Project Total 75,000 400,000 475,000
Tigard Capital Improvement Plan FY 2008 -2013 97
95540- Pedestrian Bridge (North Dakota Street)
The North Dakota Street Bridge is too narrow to safely pass pedestrian and vehicular traffic simultaneously. A feasibility study for installation of a
pedestrian bridge was conducted by a bridge consultant in 2005. The study presents an option to build the bridge in two phases: the first phase is to build
a separated 8 -foot wide pre -cast pre- stressed concrete bridge on the south side of the existing bridge. The second phase is to salvage the bridge and
widen it to a full width to be used by pedestrians, bicyclists and vehicular traffic. This project addresses work for the first phase.
it
9 1
7 �` Location
,,,,
y ( North Dakota Street
> ,� - /
s
'..r. ' 7--,,\
Project Manager(s)
J g ()
I Vannie Nguyen, Capital Construction & Transportation
°
- Funding Status
- Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 150,000 150,000
Construction 150,000 100,000 250,000
Project Total 300,000 100,000 400,000
Project by Funding Source
Unfunded 300,000 100,000 400,000
Project Total 300,000 100,000 400,000
Tigard Capital Improvement Plan FY 2008 -2013 98
95550- Street Improvements (North Dakota- Greenburg to 95th)
North Dakota Street between Greenburg Road and 95th Avenue is currently unimproved. The existing drainage system is under capacity and a major
portion of the street is narrow and does not have curb and sidewalk. Improvements of the street will be in accordance with the design standards required
for a Neighborhood route, which include one travel lane in each direction and parking on both sides of the street. Curbs and sidewalks will also be
included.
Location
Greenburg Road to 95th Avenue
Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
Funding Status
Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 50,000 50,000
Project Total 50,000 50,000
Project by Funding Source
Unfunded 50,000 50,000
Project Total 50,000 50,000
Tigard Capital Improvement Plan FY 2008 -2013 99
95560- Street Improvements (Walnut St/116th to Tiedeman)
The design of Walnut Street between 116th and Tiedeman Avenue was completed in 2001. Rights -of -way needed for the widening have been purchased.
Construction of the improvements has been tentatively proposed for FY 2009 -10. However, due to funding limitations, the proposed schedule may be
revised.
Location
E 1 ! 116th Avenue to Tiedeman Avenue
Eto Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
Funding Status
Partially Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 22,000 22,000
Construction 105,000 1,043,000 2,500,000 697,000 4,345,000
Project Total 127,000 1,043,000 2,500,000 697,000 4,367,000
Project by Funding Source
Water Fund 127,000 43,000 170,000
Traffic Impact Fee 1,000,000 697,000 1,697,000
Unfunded 1,000,000 1,500,000 2,500,000
Project Total 127,000 1,043,000 2,500,000 697,000 4,367,000
Tigard Capital Improvement Plan FY 2008 -2013 100
95910- Crosswalks (Hall /Fanno Creek)
This project is carried over from FY 2007 -08 for installation of a crosswalk on Hall Blvd to provide a mid -block crossing for Fanno Creek Trail users.
Since Hall Boulevard is a state route, location of the crosswalk requires approval from the Oregon Department of Transportation (ODOT). Upon
completion of the project, the crosswalk will provide a mid -block crossing on a heavily - traveled, two -lane state route with a posted speed limit of 40
mph. Flashing beacons will be installed at and prior to the crossing to alert the on- coming two -way traffic of pedestrians crossing the street.
Location
_._ • At Fanno Creek pathway
• • { 3.
1:10114 '
Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Pre - Design 16,192 5,000 5,000
Construction 64,771 15,000 80,000 95,000
Project Total 80,963 20,000 80,000 100,000
Project by Funding Source
Gas Tax 80,963 20,000 80,000 100,000
Project Total 80,963 20,000 80,000 100,000
Tigard Capital Improvement Plan FY 2008 - 2013 101
95920- Traffic Light (Main /Tigard)
A traffic analysis performed by in -house staff indicates that the intersection barely meets one of the traffic signal warrants. Installation of a traffic signal
at this intersection is not fully justified at this point. Another traffic analysis will be performed after the Commuter Rail begins operation and stabilizes.
Funding is provided under FY 2009 -10 to design the signal system if the analysis indicates that a signal should be installed. The design will be
coordinated with the signalized crossing gates for the Main Street railroad crossing. If the analysis at that time clearly indicates that a signal is not
warranted, the funds provided under this project can be redirected to the Walnut Street /135th intersection, which is clearly in need of improvement and
signalization at this time.
.- ° i Location
' i. Main & Tigard Streets intersection
``_ " k , , Project Managers)
POTENTIAL )\ N "> Vannie Nguyen, Capital Construction & Transportation
TRAFFIC j• s , -
SIGNAL ,,
\ «' ' � Funding Status
010. r s, Unfunded
Ib' , ,‘ N> Al ? - ,i:
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land/Right of Way Acquisition
Design and Engineering
Construction 175,000 175,000
Project Total 175,000 175,000
Project by Funding Source
Traffic Impact Fee
Unfunded 175,000 175,000
Project Total 175,000 175,000
Tigard Capital Improvement Plan FY 2008 -2013 102
95950- Gateway Treatment (SE Corner Main Street)
This project includes design and construction of a key gateway to the Downtown area at the south end of Main Street at its intersection with Highway
99W (across from Johnson Street), including site demolition, and entryway features such as monuments, landscaping, lighting, signage, and furnishings.
T.
I Location
Main Street
IT Project Manager(s)
d � -- Gus Duenas, Capital Construction & Transportation
/lb Funding Status
AWill ' Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 225,000 225,000
Project Total 225,000 225,000
Project by Funding Source
Unfunded 225,000 225,000
Project Total 225,000 225,000
Tigard Capital Improvement Plan FY 2008 - 2013 103
95980- Tigard Triangle LID #1
On February 26, 2008, City Council established Tigard Triangle LID No. 1 to improve streets within the Tigard Triangle. SW 69th Avenue between
SW Dartmouth Street and about 100 feet south of Baylor and SW Clinton Street between SW 68th Parkway and SW 70th Avenue will be fully
improved with curbs, sidewalks, street trees and street lighting. The north side of Dartmouth Street from 68th Parkway to SW 70th Avenue will also be
improved with curbs, sidewalks, street trees and street lighting. The west side of SW 68th Parkway from SW Dartmouth Street to approximately 350
feet north of Clinton Street will be improved with sidewalk, street trees and street lighting.
In addition, sidewalks, ramps, curbs, signing and striping will be installed for a proposed traffic signal at SW 68th Avenue and Dartmouth Street. A
sanitary sewer in SW 69th Avenue will be extended to provide sewer service to all properties within the District.
To V 777.'' Y Y .,, } , .z. 1 Location
`∎: , 4 ' 4 SW 69th Avenue and SW Clinton
i , l rar . IF. , I
} Project Manager(s)
t F — Gus Duenas, Capital Construction & Transportation
r
o' k � ..� d ok :;.
:I.-7 ° Funding Status
a , 1
' ' Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 22,598 155,500 155,500
Construction 2,200,000 2,200,000
Project Total 22,598 155,500 2,200,000 2,355,500
Project by Funding Source
Gas Tax 22,598 155,500 155,500
Tigard Triangle LID #1 2,200,000 2,200,000
Project Total 22,598 155,500 2,200,000 2,355,500
Tigard Capital Improvement Plan FY 2008 -2013 104
96250- Fonner St /115th Guardrail
Fonner Street is a narrow, two -lane roadway classified as a Neighborhood Route in accordance with the Tigard Transportation System Plan. The street has
no curb, sidewalk and shoulder. The intersection of Fonner Street and 115th Ave is too sharp for traveling speeds. Some vehicles have missed the corner and
driven into the yard of an adjacent house. The installation of a guard rail including markers on the outside of the curve would draw attention from motorists
and keep vehicles within the travel lane.
or Location
ir ADO GUARD Fonner St/115th Avenue
PONNER STREET
...,, u . ,..,„ pri 1 Project Manager(s)
illri r t " IPOLtFi' . .... ..., '' , ,,,, ,¢ ,- Vannie Nguyen, Capital Construction & Transportation
tre
•- dawn , ,\ � ` � Funding Status
Fully Funded
KV 4,4A - , ‘,
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 25,000 25,000
Project Total 25,000 25,000
Project by Funding Source
Gas Tax 25,000 25,000
Project Total 25,000 25,000
Tigard Capital Improvement Plan FY 2008 -2013 105
96260- School Zone Flashing Beacons
Traffic conditions near schools can seriously affect the safety of school children. Although by law, school zones have a 20 mile per hour speed limit
when children are present, the posted limits alone don't always ensure the safety of children as they are crossing streets. School Zone Flashing Beacons
(also called flashers or flashing lights) consist of a pair of yellow lights typically installed with signs that say Speed Limit 20 When Flashing. The
purpose of the flashing beacons is to draw motorists attention to the reduced speed limit of 20 miles per hour. When flashing lights are activated, the
speed is enforced in the school zone. The projects will integrate electronic speed signs to further enhance safety by showing motorists actual speeds as
they travel through the school zones.
The following locations were selected for installation of flashing beacons and electronic speed signs because of the locations of the schools and the
traffic volumes on the streets:
- Locust Street at Metzger School
- Gaarde Street at Gaarde Christian School
- Bull Mountain Road at Alberta Rider School
- Walnut/Tiedeman Street at Fowler School
Location
' f '> ' Various
4 +:
Project Manager(s)
, I Mike McCarthy, Community Development
Funding Status
- - Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 160,000 160,000
Project Total 160,000 160,000
Project by Funding Source
Gas Tax 160,000 160,000
Project Total 160,000 160,000
Tigard Capital Improvement Plan FY 2008 -2013 106
96280- Sidewalk (Hall Blvd/Bonita Road to 600' N)
This project is located on the east side of Hall Blvd and north of Bonita Road. There are gaps in the sidewalks at this location where a new bus stop is
proposed to be installed. One of the gaps includes a narrow shoulder and steep slope, which create safety concern for pedestrians and bicyclists. Traffic
turning right onto Hall Boulevard from Bonita Road at this location also put pedestrians waiting for stop lights at the corner at risk.
In addition to installing a new sidewalk at this location, a retaining wall will be constructed to support the infill placed for the sidewalk. Installation of a
new sidewalk at this location will significantly improve pedestrian safety and enhance transit accessibility.
This project is funded in the amount of $270,566 through the State Pedestrian/Bicycle Improvement grant. The City provides a local share of $66,000
funded through the Gas Tax Fund. Engineering and construction management will be performed by the City as additional local match.
Location
Hall Blvd/Bonita Rd
Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 336,566 336,566
Project Total 336,566 336,566
Project by Funding Source
Gas Tax 336,566 336,566
Project Total 336,566 336,566
Tigard Capital Improvement Plan FY 2008 -2013 107
96290- Pedestrian Bridge Repair - Tigard St.
City staff inspected the bridge and determined that most of the wood associated with the pedestrian section is rotten and is in need of replacement. This
bridge has been closed to pedestrian traffic due to safety concern.
This project removes and replaces the existing joists, railings, handrails and decking. No work is anticipated to occur in Fanno Creek. The work area will
be covered and the debris and lumber will be hauled off site to protect the creek from contamination during construction.
Location
Tigard Street
Project Manager(s)
47 . " Vannie Nguyen, Capital Construction & Transportation
r
Funding Status
_ - Fully Funded
r �.
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 10,000 10,000
Construction 30,000 30,000
Project Total 40,000 40,000
Project by Funding Source
Gas Tax 40,000 40,000
Project Total 40,000 40,000
Tigard Capital Improvement Plan FY 2008 - 2013 108
96380- Traffic Median Modification (Dartmouth /99W)
On Dartmouth Street, traffic going onto Highway 99W and 78th Avenue is directed through a left turn lane, a combined left and through traffic lane, and a
combined right turn and traffic through lane. The issue is as the outside left turn lane is filled up by vehicles approaching Highway 99W from Dartmouth
Street, it blocks the short inside left turn lade and makes the lane unusable. This project provides funding to realign the concrete median and re- stripe
Dartmouth at this location. The modification will provide additional space for left - turning vehicles and as a result will enhance traffic movements at the
Dartmouth /Highway 99W intersection.
Ii r-' IP Location
} ` Dartmouth Street and Highway 99W
�
\ %
�1
I N),z.
• N . a �. Project Manager(s)
■ •
, � ' ' y • r Vannie Nguyen, Capital Construction & Transportation
t < `s �_1
•4 Funding Status
a VII
ria A 1 ' F ��
Fully Funded
Rj 1 I a� s
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 15,000 15,000
Project Total 15,000 15,000
Project by Funding Source
Traffic Impact Fee 15,000 15,000
Project Total 15,000 15,000
Tigard Capital Improvement Plan FY 2008 -2013 109
96400- Street Improvements (Greenburg- North Dakota to Shady)
This project will widen the existing 3 lanes on Greenburg Road from North Dakota Street to Shady Lane to provide a 5 -lane facility with bike lanes and
sidewalks on both sides. The street will be reconstructed as necessary for proper vertical alignment, and the signal systems at Cascade Blvd and Tiedeman
Ave will be modified to conform to the widened roadway. Appropriate transitions will be built at both ends of the street as well as at the intersecting streets.
The existing bridge will also be replaced to allow for the expanded roadway. Construction of the project is not scheduled at this time.
Location
North Dakota to Shady Ln.
• Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
_ `,:-
/ - Funding Status
Unfunded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land /Right of Way Acquisition 1,000,000 1,000,000
Design and Engineering 400,000 400,000
Project Total 400,000 1,000,000 1,400,000
Project by Funding Source
Unfunded 400,000 1,000,000 1,400,000
Project Total 400,000 1,000,000 1,400,000
Tigard Capital Improvement Plan FY 2008 -2013 110
96710- Crosswalk & Lighting System - Durham Rd @ Tigard HS
An evaluation of the need for a marked crosswalk on Durham Road at Tigard High School midway between the signalized intersections of 92nd Avenue
and Hall Boulevard concluded that a marked crosswalk is warranted at that location. This project will design and install a marked crosswalk with
crosswalk lighting system and advance warning signs. It will also include an electronic speed sign on the north side of Durham Road on the westbound
approach to match the existing electronic sign located on the south side of the street. Funds for that sign will be budgeted under the project to install
flashing beacons and signs at selected school locations.
1,., . # d, 16 8 - - 5 Location
k L ' '. 4. t f Z iU t 92nd Avenue and Durham Road
""�' . J I' 't -' 'I '� p " Project Manager(s)
' s T 1 93 Vannie Nguyen, Capital Construction & Transportation
+' ,,x. : Funding Status
IV , - - 6 ? r Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 60,000 60,000
Project Total 60,000 60,000
Project by Funding Source
Gas Tax 60,000 60,000
Project Total 60,000 60,000
Tigard Capital Improvement Plan FY 2008 -2013 111
ear
e
W ater i,'
: ,: F AL
Page Projected
Number Project 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
115 91160 -Water Meter Replacements 50,000 77,000 54,000 56,300 58,500 60,800 356,600
116 91170 -Meter Installations 60,000 50,000 45,000 40,000 35,000 35,000 265,000
117 95570 -10MG Transfer Pump Station Upgrade 50,000 3,050,000 700,000 3,800,000
118 95590- Waterline Extension (Ash Ave.) 80,000 80,000
119 95600 -ASR 1 Rehabilitation 500,000 500,000
120 95610 -ASR Expansion Studies 810,000 50,000 850,000 850,000 2,560,000
121 95660 - Reservoir Seismic Upgrades 70,000 450,000 187,000 707,000
122 95680 -Water Conservation Demonstration Garden 26,500 125,000 151,500
123 95690 -Water Main Oversizing 75,000 125,000 75,000 275,000
124 95700 -Water Main Replacements 50,000 75,000 54,000 56,300 80,000 80,000 395,300
125 95710 -Water Service Installations 5,000 10,400 10,800 11,300 11,700 12,000 61,200
126 95720 -Water Site Security Upgrades 50,000 52,000 54,000 56,500 58,500 60,800 331,800
127 95730 -550 Zone Reservoir No. 2 & Supply Piping 4,400,000 3,000,000 7,400,000
128 95740 -ASR 3 300,000 1,500,000 300,000 2,100,000
129 95770 -550' Reservoir No. 1 200,000 200,000
130 95780 -550 Zone 12 Inch Canterbury Loop 789,000 50,000 839,000
131 95790 -550 Zone 18 Inch Canterbury Supply Line 1,750,000 100,000 1,850,000
132 96110 - Menlor Tank Re- Circulation System 45,000 45,000
133 96220 -High Tor Pump Station Rebuild 150,000 1,000,000 1,150,000
134 96540 - Defective Water Meter Replacements 77,000 77,000
135 96550 -Long Term Water 3,031,579 3,971,930 6,972,632 14,470,175 13,894,737 42,341,053
Total Water System 5,646,500 10,597,979 7,576,730 11,882,032 15,363,875 14,418,337 65,485,453
91160- Water Meter Replacements
This has been one of the long -term projects for the Public Works Depaitment. The meter replacement program covers two size ranges of meters. First,
the program covers systematic testing, repair and /or replacement of all 1 inch and larger water meters. Meters of this size have developed problems
where actual water flows are inaccurately measured; most of the time, the volume of water is under - reported. The result is that water customers could
be using more water than they are being assessed. Testing and or replacement of these water meters have proven to make financial sense in that the
investment is recouped by the additional revenues received due to accurate meters.
The second part of the program covers meters of less than 1 1/2 -inch in size. These are replaced as needed when problems are noted.
'gill% Location
Various locations
Project Manager(s)
Sam Morrison, Public Works
r
il 4 I! ` ,i
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Rollover from Springbrook
Construction 50,000 50,000 77,000 54,000 56,300 58,500 60,800 356,600
Project Total 50,000 50,000 77,000 54,000 56,300 58,500 60,800 356,600
Project by Funding Source
Water Fund 50,000 50,000 77,000 54,000 56,300 58,500 60,800 356,600
Project Total 50,000 50,000 77,000 54,000 56,300 58,500 60,800 356,600
Tigard Capital Improvement Plan FY 2008 -2013 115
91170- Meter Installations
This on -going program ties in with the Water Service Installations program. When new water customers, or existing customers who need an additional
water service, apply for a new service, Public Works staff install the service line and will set the new meter.
. , 'W ' ' :; 4 Location
,;" ; / 3 %' + - ; : Various locations
*
;vc; Project Manager(s)
-` _, °, Sam Morrison, Public Works
a T:
. ,. i -_F . . °� ' Funding Status
- . -F. ..
y, P Fully Funded
„,
...
51 .. ' A fl[ifr.1 in
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Rollover from Springbrook
Construction 60,000 60,000 50,000 45,000 40,000 35,000 35,000 265,000
Project Total 60,000 60,000 50,000 45,000 40,000 35,000 35,000 265,000
Project by Funding Source
Water Fund 60,000 60,000 50,000 45,000 40,000 35,000 35,000 265,000
Project Total 60,000 60,000 50,000 45,000 40,000 35,000 35,000 265,000
Tigard Capital Improvement Plan FY 2008 -2013 1 16
95570- 10MG Transfer Pump Station Upgrade
The existing transfer pump station, located on the 10 MG reservoir site at Bull Mountain Road /125th Avenue, serves both the 550 -foot and 713 -foot
service zones. The Water Distribution System Hydraulic Study identified a need to replace this pump station with one that would provide a higher
pumping capacity to both service zones. Construction of this improvement increases pumping capacity from 2,000 gpm to 3,300 gpm for the 713 -foot
service zone. The pump station will also provide 3,900 gpm to the 550 -foot zone Reservoir No. 2. Along with the piping improvements, the existing
pump station at the Canterbury site (Pump Station No. 1) will be abandoned.
Location
Bull Mountain Road & 125th Avenue
• 1.
Project Manager(s) Ailliar
r CSI Rob Murchison, Public Works
• Funding Status
Fully Funded
. .:. :7 — ----_-
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 50,000 50,000 300,000 350,000
Construction 2,750,000 700,000 3,450,000
Project Total 50,000 50,000 3,050,000 700,000 3,800,000
Project by Funding Source
Water CIP 50,000 50,000 3,050,000 700,000 3,800,000
Project Total 50,000 50,000 3,050,000 700,000 3,800,000
Tigard Capital Improvement Plan FY 2008 -2013 117
95590- Waterline Extension (Ash Ave)
This project is in conjunction with the Ash Ave. extension from Burnham to the railroad tracks. Since this would be a new extension of a public street, it is
anticipated that a new 8 -inch public water line would be needed. Funds for the water system would include design and construction costs.
Location
Re Burnham St. to Railroad Tracks
Aitreer
"
Project Manager(s)
Vannie Nguyen, Capital Construction & Transportation
Rob Murchison, Public Works
11116 Funding Status
Fully Funded
/ rte
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 6,000
Construction 80,000 80,000
Project Total 6,000 80,000 80,000
Project by Funding Source
Water SDC 6,000 40,000 40,000
Water CIP 40,000 40,000
Project Total 6,000 80,000 80,000
Tigard Capital Improvement Plan FY 2008 -2013 118
95600- ASR 1 Rehabilitation
Rehabilitation of ASR wells is recommended every six years. Typical work involved may include removal of the pump and reconditioning of the well. In
the case of ASR 1, it is also anticipated that a down -hole control valve will be installed, which will likely help eliminate air entrapment in the well due to
the cascade effect during the recharge period.
Location
To be determined
i 1 wil Clitift
is Project Manager(s)
} ,, + { �1111 u Rob Murchison, Public Works
` i
-_,t -, f IT An
ET 'r 6 _ Funding Status
■ 1 Fully Funded
6iiiimin_-- .1% : ' —
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 50,000 50,000
Construction 450,000 450,000
Project Total 500,000 500,000
Project by Funding Source
Water SDC 500,000 500,000
Project Total 500,000 500,000
Tigard Capital Improvement Plan FY 2008 -2013 119
95610- ASR Expansion Studies
The City's hydrogeologist of record will assist Staff in locating potential sites for additional aquifer storage and recovery (ASR) wells. In addition, test
wells must be drilled by a qualified well driller in order for the hydrogeologist to determine suitability of the well for ASR purposes. Therefore, these
studies will include both consulting services and drilling services.
Location
To be determined
Project Manager(s)
Rob Murchison, Public Works
Brian Rager, Public Works
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 100,000 100,000 70,000 70,000 240,000
Construction 710,000 710,000 50,000 780,000 780,000 2,320,000
Project Total 810,000 810,000 50,000 850,000 850,000 2,560,000
Project by Funding Source
Water CIP 810,000 810,000 50,000 850,000 850,000 2,560,000
Project Total 810,000 810,000 50,000 850,000 850,000 2,560,000
Tigard Capital Improvement Plan FY 2008 -2013 120
95660- Reservoir Seismic Upgrades
In FY 07/08, a Reservoir Seismic Upgrade Evaluation will be completed to determine what upgrades should be completed at existing reservoirs. Staff
anticipates the actual improvements will need to be constructed over a three -year period, beginning FY 08/09.
Location
To be determined
Project Manager(s)
Rob Murchison, Public Works
No Photo Available
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 70,000 70,000 70,000
Construction 450,000 187,000 637,000
Project Total 70,000 70,000 450,000 187,000 707,000
Project by Funding Source
Water Fund 70,000 70,000 70,000
Water CIP 450,000 187,000 637,000
Project Total 70,000 70,000 450,000 187,000 707,000
Tigard Capital Improvement Plan FY 2008 -2013 121
95680- Water Conservation Demonstration Garden
The project will be located at the Public Works Building, located at the northwest corner of Burnham Street /Hall Boulevard. The adjacent street
intersection is also a location designated as a downtown entryway. As Tigard continues to support regional water conservation efforts, one way of
providing public education is in the area of landscaping. Tigard currently provides incentives to customers who demonstrate they have installed
water - saving elements into their irrigation design.
Another excellent way of providing education to customers is by establishing a demonstration garden that would incorporate a variety of water- saving
irrigation features, creative plant selection and layout. Such a demonstration garden located at this City building would provide good access to
pedestrians who will be visiting the downtown area.
T X I'� Y , - ,r, Location
r'� +1� * ,
• � To be determined
4 i Y
_ �, ° ' � � Project Manager(s)
C '*. F ' . " ,1` Rob Murchison, Public Works
' sr. "� � ;, { , - ; Funding Status
i � �" a mr � w ��
l ,� :. � r k . ? Fully Funded
� y .
,_ r .e' A, 'aim
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 6,500 6,500 6,500
Construction 43,500 20,000 125,000 145,000
Project Total 50,000 26,500 125,000 151,500
Project by Funding Source
Water CIP 50,000 26,500 125,000 151,500
Project Total 50,000 26,500 125,000 151,500
Tigard Capital Improvement Plan FY 2008 -2013 122
95690- Water Main Oversizing
During the course of the year the City may find the need to upsize a planned pipeline through a new development, thus accomplishing an identified
capital improvement as listed in the Water Distribution System Hydraulic Study dated May 2000.
, .1"
� � * 3 Location
max , , 1 #4,; :, , ,
N/A
_ Project Manager(s)
_ Rob Murchison, Public Works
c0 Funding Status
1 s =‘,,,,,...
Fully Funded
z
x
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 125,000 75,000 125,000 75,000 275,000
Project Total 125,000 75,000 125,000 75,000 275,000
Project by Funding Source
Water SDC 125,000 75,000 125,000 75,000 275,000
Project Total 125,000 75,000 125,000 75,000 275,000
Tigard Capital Improvement Plan FY 2008 -2013 123
95700- Water Main Replacements
This on -going program is based on the needs identified in the Water Distribution System Hydraulic Study May 2000, and is for the routine replacement
of leaking, damaged and older water mains throughout the water system. In most cases the existing mains have adequate capacity and will be replaced
with the same diameter water mains. This program is also for the completion of loops in the system to maintain hydraulic efficiencies.
NOTE: Larger amounts shown in FY 08/09 and 11/12 due to anticipated main replacements related to the proposed Main Street reconstruction projects.
= ` Location
Various locations to be determined
Project Manager(s)
Sam Morrison, Public Works
T 0 r 0 <. P
s • +
' le e;;° Funding Status
b
a �
r� f � x Fully Funded
4 r
i ..
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 50,000 50,000 75,000 54,000 56,300 80,000 80,000 395,300
Project Total 50,000 50,000 75,000 54,000 56,300 80,000 80,000 395,300
Project by Funding Source
Water Fund 50,000 50,000 75,000 54,000 56,300 80,000 80,000 395,300
Project Total 50,000 50,000 75,000 54,000 56,300 80,000 80,000 395,300
Tigard Capital Improvement Plan FY 2008 -2013 124
95710- Water Service Installations
This is a long -term program for the department. Each year the City adds new customers to the system through individual building permits or additional
water services. Customers apply for a new water service, and Public Works staff installs the service line and will set the meter (see Meter Installations
line item).
Location
Various
" Project Manager(s)
"r-- - y Sam Morrison, Public Works
° % A ii
li, Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 10,000 5,000 10,400 10,800 11,300 11,700 12,000 61,200
Project Total 10,000 5,000 10,400 10,800 11,300 11,700 12,000 61,200
Project by Funding Source
Water Fund 10,000 5,000 10,400 10,800 11,300 11,700 12,000 61,200
Project Total 10,000 5,000 10,400 10,800 11,300 11,700 12,000 61,200
Tigard Capital Improvement Plan FY 2008 -2013 125
95720- Water Site Security Upgrades
This project will accomplish the water site security upgrades that were identified in the PW Vulnerability Assessment and Emergency Response Plan.
The security upgrades will include improvements to such things as access, fencing, intrusion alarms, and monitoring. The implementation of these
improvements is estimated to take place over a 20 -year period.
7,. *
Location
A. Various locations to be determined
, �, 4 - Project Manager(s)
- John Goodrich, Public Works
; Y 4+nMip .
ail 14 1Y if
VV . Funding Status
Fully Funded
II
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 50,000 50,000 52,000 54,000 56,500 58,500 60,800 331,800
Project Total 50,000 50,000 52,000 54,000 56,500 58,500 60,800 331,800
Project by Funding Source
Water Fund 50,000 50,000 52,000 54,000 56,500 58,500 60,800 331,800
Project Total 50,000 50,000 52,000 54,000 56,500 58,500 60,800 331,800
Tigard Capital Improvement Plan FY 2008 -2013 126
95730- 550 Zone Reservoir No. 2 & Supply Piping
This reservoir will be located on Bull Mountain and will serve the south and eastern portions of the 550 -foot pressure zone. Constructing this reservoir
will eliminate some of the demand currently supplied by the 713 -Foot pressure zone. Supply to the reservoir will be provided through the transfer pump
station upgrade. This project will also include the supply piping necessary between the transfer pump station and the new reservoir, as well as the supply
piping from the reservoir to the existing 550 -foot pressure zone to the south.
Location
4 .' Bull Mountain
e- p s ttR :ate
4 * �y� y' '" '* Project Manager(s)
/,/' , . � �
>s' ' �..:' Rob Murchison, Public Works
4 wei:
zw.„,vo r
.
l r
Funding Status
�r }`�� . �/, ���' A` Fully Funded
�/ . § Ski'" 1EC 42
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 400,000 400,000 400,000
Construction 4,000,000 4,000,000 3,000,000 7,000,000
Project Total 4,400,000 4,400,000 3,000,000 7,400,000
Project by Funding Source
Water CIP 4,400,000 4,400,000 3,000,000 7,400,000
Project Total 4,400,000 4,400,000 3,000,000 7,400,000
Tigard Capital Improvement Plan FY 2008 -2013 127
95740- ASR 3
The City will continue to expand its aquifer storage and recovery well system. It is anticipated that a production well will be drilled and well head
improvements installed at a location where testing has occurred and have proven positive.
lipir ' , ,K Location
r Bull Mountain Road & 125th Avenue
" Project Manager(s)
1 `
Rob Murchison. Public Works
�� it ' t i� • i '
I ∎A \CI i ° y'�� \��'. '; Funding Status
0 ,amp W y < .• ;° r," , `` t Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 300,000 300,000 300,000
Construction 1,500,000 300,000 1,800,000
Project Total 300,000 300,000 1,500,000 300,000 2,100,000
Project by Funding Source
Water CIP 300,000 300,000 1,500,000 300,000 2,100,000
Project Total 300,000 300,000 1,500,000 300,000 2,100,000
Tigard Capital Improvement Plan FY 2008 -2013 128
95770- 550' Reservoir No. 1
The City's Water System Hydraulic Master Plan calls for a 550' Zone Reservoir located on the north side of Bull Mountain to serve that section of the
pressure zone.
Location
North side of Bull Mountain
Project Manager(s)
. 4 Rob Murchison, Public Works
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 200,000 200,000
Project Total 200,000 200,000
Project by Funding Source
Water CIP 200,000 200,000
Project Total 200,000 200,000
Tigard Capital Improvement Plan FY 2008 - 2013 129
95780- 550 Zone 12 Inch Canterbury Loop
This project will involve upsizing of existing water lines to a 12" supply line to feed the Canterbury Hill Neighborhood in the 550' zone.
♦♦1 .• 1 CG-q = ii�d u.►i ♦• 11 r- Location
����1 �, �� � ••11��.: Canterbury Hill Neighborhood
:,! ..J ® R l`0 ■ , n oI , C 4 ' �', ■ ,Li
qmiliii �sr' E ra■.. +�■ ■ , — , A Project Manager(s)
, . 4 . 1 .—o. i I � 1 t I�t Rob Murchison, Public Works
3 aiNiki ' r4 4110 1 rani 1
De f ow I � �� lg � Funding Status
��` " \,�.. • r...:::rr Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 100,000 100,000
Construction 689,000 50,000 739,000
Project Total 789,000 50,000 839,000
Project by Funding Source
Water CIP 789,000 50,000 839,
Project Total 789,000 50,000 839,000
Tigard Capital Improvement Plan FY 2008 -2013 130
95790 550 Zone 18 Inch Canterbury Supply Line
This project will construct a transmission line from the 10 MG Transfer Pump Station area to the 550' zone around Canterbury Hill and will involve cross-
ing Highway 99W.
` 07 • 1 :,wi�s=yams -_ - rn7th'W Location
Imo'.: ►,. : %.....aMilli" .l ! '1.'; ;MII- - : Canterbury Hill Neighborhood
!I is % ! R .. g . 1 . 1 0 1
i t,•;L;m1 l� "r"'r� ■..� +I:;,i 7 Project Manager(s)
. ..■ e
Dennis Koellermeier, Public Works
le : .1 p m aa�L pp' - — ' nm n1
.: , 3
ii C aninn Mr 1 i t fl y,r Funding Status
Lilt f'3 � r �� , Fully Funded
0101 ill ..01W .. Atli,
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 175,000 175,000
Construction 1,575,000 100,000 1,675,000
Project Total 1,750,000 100,000 1,850,000
Project by Funding Source
Water CIP 1,750,000 100,000 1,850,000
Project Total 1,750,000 100,000 1,850,000
Tigard Capital Improvement Plan FY 2008 -2013 131
96110- Menlor Tank Re- Circulation System
This project will increase water quality by re- circulating water movement within the 3.5 mg storage reservoir. Initially this project was to use a convention-
al recirculation pump and piping. This was tabled to investigate new technology. Staff recommends the installation of a solar powered battery assist stand-
alone Solar Bee recirculation pump system. Grant monies may be available to assist with funding, however at this time the project would be fully funded
through the Water Fund. This project meets the City Council goal regarding "green" energy efficient technologies.
Location
13425 SW 154th Ave.
y am..
Project Manager(s)
Rob Murchison, Public Works
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 36,000 36,000
Contingency 9,000 9,000
Project Total 45,000 45,000
Project by Funding Source
Water CIP 45,000 45,000
Project Total 45,000 45,000
Tigard Capital Improvement Plan FY 2008 -2013 132
96220- High Tor Pump Station Rebuild
The existing facility is 25 years old and is underground. It has flooded twice in the past five years due to mechanical failure. This project will replace
the underground facility with a modern, above ground facility to provide a constant flow source to the surrounding neighborhood and because it is above
ground, it will be protected from future flooding damage.
Location
14255 SW High Tor Dr.
P
Project Manager(s)
t
Dennis Koellermeier, Public Works
, %. - f-.� I. ,"
Funding Status
Fully Funded
a. ---
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 150,000 150,000
Construction 1,000,000 1,000,000
Project Total 150,000 1,000,000 1,150,000
Project by Funding Source
Water CIP 150,000 1,000,000 1,150,000
Project Total 150,000 1,000,000 1,150,000
Tigard Capital Improvement Plan FY 2008 -2013 133
96540- Defective Water Meter Replacements
This has been one of the long -term projects for the Public Works Department. The meter replacement program covers two size ranges of meters. First,
the program covers systematic testing, repair and /or replacement of all 1 inch and larger water meters. Meters of this size have developed problems
where actual water flows are inaccurately measured; most of the time, the volume of water is under - reported. The result is that water customers could
be using more water than they are being assessed. Testing and or replacement of these water meters have proven to make financial sense in that the
investment is recouped by the additional revenues received due to accurate meters.
The second part of the program covers meters of less than 1 1/2 -inch in size. These are replaced as needed when problems are noted.
Location
Various
Project Manager(s)
John Goodrich, Public Works
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 77,000 77,000
Project Total 77,000 77,000
Project by Funding Source
Water Fund 77,000 77,000
Project Total 77,000 77,000
Tigard Capital Improvement Plan FY 2008 -2013 134
96550- Long Term Water
The Tigard Water Service Area (TWSA) continues to evaluate participation in and development of a long term domestic water supply. Four options or
combinations of options exist, which include development of major water facilities on the Clackamas, Tualatin, or Willamette systems, as well as
continuing a wholesale water purchase arrangement with the City of Portland. Projects and decisions in FY 2008 -09 should, at minimum, reduce the
various choices to two, or optimistically, select one source as the preferred alternative and begin development activities of that source.
Location
To be determined
Project Manager(s)
Dennis Koellermeier, Public Works
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 3,031,579 3,971,930 6,972,632 14,470,175 13,894,737 42,341,053
Project Total 3,031,579 3,971,930 6,972,632 14,470,175 13,894,737 42,341,053
Project by Funding Source
Water CIP 3,031,579 3,971,930 6,972,632 14,470,175 13,894,737 42,341,053
Project Total 3,031,579 3,971,930 6,972,632 14,470,175 13,894,737 42,341,053
Tigard Capital Improvement Plan FY 2008 -2013 135
� j am ..
U r b an Renewa 1r .. Y
Page Projected
Number Project 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
139 90650 -Hall Blvd at Hwy 99W Gateway 75,000 75,000
140 90720- Burnham St. Reconstruction 715,000 5,250,000 1,300,000 7,265,000
141 95130 -Park Land Acquisition 1,626,859 1,183,816 1,000,000 3,810,675
142 95810- Commuter Rail Enhancements 100,000 100,000
143 95830 - Commercial St. Improvements 26,648 120,000 850,000 996,648
145 95860 -Fanno Cr. Park Gateway at Main St. 150,000 692,109 842,109
146 95870 -Fanno Cr. Trail (Main to Grant) 115,000 115,000 230,000
147 95900 -Fanno Creek Plaza 1,650,000 320,000 2,109,905 4,079,905
148 95930 -Main St. / Green St. Retrofit 284,999 334,999 2,420,002 3,040,000
149 95960- Street Realignment (Scoffins /Hall/Hunziker) 400,000 1,500,000 1,900,000
150 96560 -Ash Street Site Valuation Study 25,000 25,000
151 96620- Commuter Rail Entryway Enhancements 20,000 20,000
152 96630 -Fanno Cr. Lower Park 385,000 790,000 940,000 2,115,000
153 96640 - Festival Street 123,000 820,680 943,680
154 96650 -Upland Park 150,000 976,081 1,126,081
155 96660- Street Trees (Main St.) 45,000 45,000
156 96670 -Main St. Green Street Retrofit (Phase 2) 400,000 2,500,000 2,900,000
Total Urban Renewal System 2,483,507 7,603,815 4,924,999 3,830,002 4,158,986 6,512,789 29,514,098
90650- Hall Blvd @ Hwy 99W Gateway
This project designs and constructs landscape improvements at the intersection of Highway 99W and Hall Boulevard. The improvements will incorporate
the design concept established by the Downtown Comprehensive Streetscape Plan and will coordinate with the MSTIP 3 Hall Boulevard at Highway 99W
right turn lane widening project managed by Washington county. The funding provided in FY 2008 -09 will be used to purchase right of way needed to
'accommodate the proposed gateway enhancement.
11 — 3191111110„ 4 . 1 4itiff Location
Hwy 99W & Hall Blvd. . .
i I Project Manager(s)
yM J , " Gus Duenas, Capital Construction & Transportation
Funding Status
W ` Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land/Right of Way Acquisition 75,000 75,000
Project Total 75,000 75,000
Project by Funding Source
Gas Tax 75,000 75,000
Project Total 75,000 75,000
Tigard Capital Improvement Plan FY 2008 - 2013 139
90720- Burnham Street Reconstruction
The construction of Burnham Street improvements incorporates design concepts recommended by the Tigard Downtown Comprehensive Streetscape
plan. These concepts include widening Burnham Street between Main Street and Ash Avenue to a paved width of 38 feet and between Ash Avenue and
Hall Boulevard to 50 feet. Sidewalks, landscaped medians, pedestrian crossings and on- street parking will be provided as part of the widening. In
addition, a traditional four -way intersection will be installed at the intersection of Hall Boulevard and Ash Avenue, and greenstreet stormwater
management concepts will be applied for water quality enhancement. Construction is scheduled to begin in late summer or fall of 2008.
lr , _, Location
I p n4 ; n SW Burnham Street e. a [ Project Manager(s)
l� - p Kim McMillan, Development Engineering
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Rollover from Springbrook
Land/Right of Way Acquisition 615,000 468,000 1,300,000 1,768,000
Design and Engineering 100,000 247,000 95,000 342,000
Construction 650,000 3,855,000 1,300,000 5,155,000
Project Total 1,365,000 715,000 5,250,000 1,300,000 7,265,000
Project by Funding Source
Gas Tax 1,800,000 1,300,000 3,100,000
Water Fund 350,000
Traffic Impact Fee 715,000 715,000 2,350,000 3,065,000
Underground Utility 300,000 300,000 300,000
Water CIP 450,000 450,000
Urban Renewal Fund 350,000 350,000
Project Total 1,365,000 715,000 5,250,000 1,300,000 7,265,000
Tigard Capital Improvement Plan FY 2008 -2013 140
95130- Park Land Acquisition
This project includes appraisal and acquisition of floodplain properties adjacent to Fanno Creek Park for park expansion. The expansion of the park area
is critical to the reconstruction and restoration of Fanno Creek itself which is anticipated to occur on one of two parcels. The other parcel is important for
full use of the park and its eventual connection to a public plaza.
Location
: . Various locations to be determined
Project Manager(s)
Phil Nachbar, Downtown Redevelopment
rix
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land/Right of Way Acquisition 329,000 1,626,859 1,108,816 1,000,000 3,735,675
Design and Engineering 75,000 75,000
Project Total 329,000 1,626,859 1,183,816 1,000,000 3,810,675
Project by Funding Source
Parks Capital Fund 329,000 1,626,859 808,816 2,435,675
Park System Development Charge 375,000 1,000,000 1,375,000
Project Total 329,000 1,626,859 1,183,816 1,000,000 3,810,675
Tigard Capital Improvement Plan FY 2008 -2013 141
95810- Commuter Rail Enhancements
This project upgrades the Commuter Rail Shelter from the revised design provided by Tri -Met to their original and more traditional shelter design. The
upgrade also includes two additional foundations for expansion of the shelter of up to 24 feet.
9 Location
Commercial St. & Main St. Intersection
,, --' Project Manager(s)
. Phil Nachbar, Downtown Redevelopment
I. -
-- + Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 105,000 100,000 100,000
Project Total 105,000 100,000 100,000
Project by Funding Source
Facilities Fund 105,000 100,000 100,000
Project Total 105,000 100,000 100,000
Tigard Capital Improvement Plan FY 2008 -2013 142
95830- Commercial St. Improvements
Commercial Street is located in the downtown area of Tigard. The improvements involve re- construction of the existing pavement and base construction
of a sidewalk on the north side of the street to provide a safe walk for the neighborhood to the Commuter Rail Station, bus stops and businesses on Main
Street. The total paved width of Commercial Street after completion is 28 feet, which will accommodate two travel lanes, one in each direction. Parking
on the street will be permitted between the Highway 99W over - crossing and Main Street. Streetscape improvements for the project will incorporate de-
sign concepts recommended in the Tigard Downtown Comprehensive Streetscape Plan. The construction was originally scheduled for the spring of 2006.
However, this schedule has been postponed due to funding limitations. Completion of the project will provide a safe and convenient pedestrian route to
downtown services and the Commuter Rail Station.
.ti; ,9 Location
> Lincoln Avenue to Main Street
0. s GTE ��
ti �' a ��
.>
4.,;‘` � .. '' - 4� / i► Project Manager(s)
,, 4 . r %0' / ` Vannie Nguyen, Capital Construction & Transportation
•"
fog 414 \, • :s Funding Status
"), Partially Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 27,648 27,648 27,648
Construction 211,300 120,000 850,000 970,000
Project Total 238,948 27,648 120,000 850,000 997,648
Tigard Capital Improvement Plan FY 2008 - 2013 143
Project by Funding Source
Gas Tax 27,648 27,648 27,648
Water Fund 120,000 120,000
Water Quality /Quantity 120,000
Unfunded 850,000 850,000
Project Total 238,948 27,648 120,000 850,000 997,648
Tigard Capital Improvement Plan FY 2008 -2013 144
95860- Fanno Creek Park Gateway at Main St
A formal, public entryway into Fanno Creek Park from Main Street including a cantilevered deck / overlook and pathway into the park. Specific
improvements include hard - scaped pathway, lighting, deck and railing for overlook, signage, bollards, and decorative monuments on the bridge.
Location
0 . gob Main Street
Project Manager(s)
Phil Nachbar, Downtown Redevelopment
r
o;. Funding Status
Partially Funded
u ►n
I
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 150,000 150,000
Construction 692,109 692,
Project Total 150,000 692,109 842,109
Project by Funding Source
Urban Renewal Fund 150,000 322,109 472,109
Unfunded 370,000 370,000
Project Total 150,000 692,109 842,109
Tigard Capital Improvement Plan FY 2008 -2013 145
95870- Fanno Creek Trail Main Street to Grant Street
Project includes the installation of a trail from Main Street to Grant Street. This trail is a key part of the larger Fanno Creek Regional Trail System from
Portland to Tualatin, and will connect with the trail into Fanno Creek Park, and the future Downtown Plaza.
Location
Main Street to Grant Street
Project Manager(s)
�° Phil Nachbar, Downtown Redevelopment
ii _
, ;, , c 41" / % % Funding Status
t ' - .4
. . - Fully Funded ,.,„„, ,
-4, . 4..•' 4
. .-- - . s .„ . .i,,
, . .. ..,: N
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 115,000 115,000 115,000 230,000
Project Total 115,000 115,000 115,000 230,000
Project by Funding Source
General Fund 88,895 88,895
Parks Capital Fund 115,000 115,000 115,000
Park System Development Charge 26,105 26,
Project Total 115,000 115,000 115,000 230,000
Tigard Capital Improvement Plan FY 2008 -2013 146
95900- Fanno Creek Plaza
This project is the central public gathering space for the community, and a catalyst project intended to stimulate new investment in Downtown. The Fanno
Creek Plaza project was designed in concept and adopted as part of the Fanno Creek Park & Downtown Plaza Master Plan (February, 2008). The plaza will
have a uniquely lighted connection to Main Street to the west, and Fanno Creek Park to the south. The plaza will include a fountain, pavilion, cafe seating,
and surrounding park improvements. The intention is the plaza will be constructed as part of joint redevelopment with adjoining properties.
N
V Location
� � Vicinity of Main & Burnham Streets
1,06k , ` oO, Project Manager(s)
Phil Nachbar, Downtown Redevelopment
y , Mhl• ion Area
Funding Status
Y , cny Partially Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land/Right of Way Acquisition 1,650,000 1,650,000
Design and Engineering 320,000 320,000
Construction 2,109,905 2,109,905
Project Total 1,650,000 320,000 2,109,905 4,079,905
Project by Funding Source
Park System Development Charge
Urban Renewal Fund 147,200 1,854,905 2,002,105
Unfunded 1,650,000 172,800 255,000 2,077,800
Project Total 1,650,000 320,000 2,109,905 4,079,905
Tigard Capital Improvement Plan FY 2008 - 2013 147
95930- Main St /Green St Retrofit
The Main Street project is multi -year and includes comprehensive redesign and construction of the full length of Main Street. This phase of the project
(MTIP Grant proposal) is to reconstruct the street in accordance with Green Street Standards for 1400 lineal feet of Main Street, from the Commuter
Rail entrance to the south entrance at 99W. It encompasses the entire, public right -of -way (ROW) and includes streets, curbs, sidewalks, landscape, and
drainage improvements. Design will be based on concept plans as approved in the Downtown Streetscape Plan. The project is divided into 2 phases:
Phase 1 starts at the railroad tracks south to Highway 99W and Phase 2 from the railroad tracks north to Greenburg Road.
Location
Main Street
I Project Manager(s)
Kim McMillan, Development Engineering
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land/Right of Way Acquisition 79,269 79,269
Design and Engineering 284,999 255,730 540,729
Construction 2,420,002 2,420,002
Project Total 284,999 334,999 2,420,002 3,040,000
Project by Funding Source
Gas Tax 255,730 300,595 1,983,675 2,540,000
Urban Renewal Fund 29,269 34,404 436,327 500,000
Project Total 284,999 334,999 2,420,002 3,040,000
Tigard Capital Improvement Plan FY 2008 -2013 148
95960- Street Realignment (Scoffins /Hall/Hunziker)
This project corrects the unusual four -leg intersection of Hall Blvd /Scoffins /Hunziker Street. Hunziker and Scoffins Street intersect Hall Boulevard at an
acute angle and at two separate locations creating inadequate corner sight distance at four quadrants. The closely spaced offset between the two intersect-
ing streets creates a sub - standard queue- storage distance on Hall Blvd, one of the most heavily traveled streets in Tigard. The proposed funding, if avail-
able, is for preparation of a traffic study including alternative resolutions of the problems, conceptual design, final design, right -of -way acquisition and
construction.
, Location
ilk '� Scoffins /Hall /Hunziker
S ' /64
% , u "w" s Project Manager(s) A , ,,,,„,* ^r Phil Nachbar, Downtown Redevelopment
Funding Status
* Unfunded it
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Land/Right of Way Acquisition 1,500,000 1,500,000
Design and Engineering 400,000 400,000
Project Total 400,000 1,500,000 1,900,000
Project by Funding Source
Unfunded 400,000 1,500,000 1,900,000
Project Total 400,000 1,500,000 1,900,000
Tigard Capital Improvement Plan FY 2008 -2013 149
96560- Ash Street Site Valuation Study
The City Public Works site will be evaluated for redevelopment as part of the Departments future facility planning. The study will determine the sites
development capacity, financial feasibility, and how Fanno Creek Park may be integrated with development to maximize its value. An estimate of the
market value of the site will be made for facility planning.
Location
12800 SW Ash Avenue
Project Manager(s)
Phil Nachbar, Downtown Redevelopment
No Photo Available
Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 25,000 25,000
Project Total 25,000 25,000
Project by Funding Source
General Fund 25,000 25,000
Project Total 25,000 25,000
Tigard Capital Improvement Plan FY 2008 -2013 150
96620- Commuter Rail Entryway Enhancements
The commuter rail will be operating in Fall 2008. The Commuter Rail Entryway Project will identify improvements that will have visual impact on
passengers as they arrive at the Tigard Station. Options include signage, art installations, and landscape improvements from Hall Blvd to Main St. and at
the station platform. The project will provide design, and installation prior to the opening of Commuter Rail anticipated in October 2008.
Location
Hall Blvd. to Main St.
I ,,
Project Manager(s)
Station Elevation
Gus Duenas, Capital Construction & Transportation
Funding Status
Fully Funded
Station Bench Trash Receptacle Station Light Fixture
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction 20,000 20,000
Project Total 20,000 20,000
Project by Funding Source
General Fund 20,000 20,000
Project Total 20,000 20,000
Tigard Capital Improvement Plan FY 2008 - 2013 151
96630- Fanno Creek Lower Park
Construction of Lower Fanno Creek Park, as defined in the new master plan for Fanno Creek Park & Plaza (Feb 2008), is from Hall Blvd to Main St.
neighborhoods to the south and the southern edge of properties along Burnham Street to the north. The Lower Park will be improved to include new
trails, boardwalks, bridges, restoration, and creek alignment / stabilization.
It will abut the Upper Park which includes the Plaza and surrounding area as defined in the master plan.
Ak Location
Ate ��, � �0 Hall Blvd. to Main St.
\� „ , . a Project Manager(s)
Phil Nachbar, Downtown Redevelopment
�q R 9 I
, ` 4 mio� LJ ,O mow vo "�
Funding Status
Partially Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 260,000 260,000
Construction 125,000 790,000 940,000 1,855,000
Project Total 385,000 790,000 940,000 2,115,000
Project by Funding Source
Park System Development Charge 385,000 385,000
Unfunded 790,000 940,000 1,730,000
Project Total 385,000 790,000 940,000 2,115,000
Tigard Capital Improvement Plan FY 2008 -2013 152
96640- Festival Street
Festival Street is a planned, new street adjoining the Downtown Plaza, from Burnham Street south to Ash Avenue. The street will function to provide
vehicular access to Fanno Upland Park, and can be closed off to provide a place for the Tigard Farmers market. The street is part of the adopted Fanno
Creek Park & Plaza Master Plan, adopted in February 2008.
- - it y Location i.
Burnham St. South to Ash Ave.
—I 46,r, • Piz 7
'�`� Project Manager(s)
ree
Phil Nachbar, Downtown Redevelopment
.\\.\
�`° , ' '�� Funding Status
Fully Funded
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 123,000 123,000
Construction 820,680 820,680
Project Total 123,000 820,680 943,680
Project by Funding Source
Urban Renewal Fund 123,000 820,680 943,680
Project Total 123,000 820,680 943,680
Tigard Capital Improvement Plan FY 2008 - 2013 153
96650- Upland Park
The Upland Park portion of Fanno Creek Park surrounds the Fanno Creek Plaza and is intended to serve as a formal park. It includes a Great Lawn for
casual and programmed events, the Urban Creek, a man -made creek channeling urban run -off, an Overlook, an open deck looking towards the lower
park, a childrens play area adjacent to the Great Lawn, and various walkways connected to the Plaza, the Festival Street, and Lower Fanno Creek Park.
o
Location
„�,,� / T' ^ 4 Part of Fanno Cr. Park
� =' ! Housing �'
e , - w , Play Area
Overlook Pier
� �,m� Project Manager(s)
- Festival Stree[
\ Phil Nachbar, Downtown Redevelopment
��: \ \ Funding Status
�
\ Partially Funded
A
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 150,000 150,000
Construction 976,081 976,081
Project Total 150,000 976,081 1,126,081
Project by Funding Source
Park System Development Charge 81,000 81,000
Urban Renewal Fund 69,000 448,997 517,997
Unfunded 527,084 527,084
Project Total 150,000 976,081 1,126,081
Tigard Capital Improvement Plan FY 2008 -2013 154
96660- Street Trees- Main Street
One of the strategies to improve Main Street in Downtown before major street redesign and construction takes place is to install new street trees. Street
trees beautify the street, create shade, and convey positive change. A significant number of new trees will be added to Main Street, with the primary
focus from the railroad track north to the Greenberg Road intersection. Trees will be planted with the intent to relocate them if possible when
reconstruction takes place. The southern section of Main St. from the railroad tracks south to 99W is undergoing redesign and tree planting will be kept
to a minimum since reconstruction will occur in FY 2011 - 12.
Location
Main St.
II � h [ Project Manager(s)
- - Phil Nachbar, Downtown Redevelopment
–� Funding Status
1111%!.'71. — Fully Funded
w� =
f _
Actual Revised
Through Budget Projected Adopted
2006 -07 2007 -08 2007 -08 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Construction
Project Total
Project by Funding Source
General Fund
Tree Replacement Fund 45,000 45,000
Project Total 45,000 45,000
Tigard Capital Improvement Plan FY 2008 - 2013 155
96670- Main St. Green Street Retrofit (Phase 2)
The Main Street project is multi -year and includes comprehensive redesign and construction of the full length of Main Street. This phase of the project
(MTIP Grant proposal) is to reconstruct the street in accordance with Green Street Standards for 1400 lineal feet of Main Street, from the Commuter Rail
entrance to the south entrance at 99W. It encompasses the entire, public right -of -way (ROW) and includes streets, curbs, sidewalks, landscape, and drain-
age improvements. Design will be based on concept plans as approved in the Downtown Streetscape Plan. Phase 1 of the project starts at the railroad tracks
south to Highway 99W and Phase 2 from the railroad tracks north to Greenburg Road.
Location
Main St.
61 _ — N o Project Manager
; ,r . `-, Gus Duenas, Capital Construction & Transportation
° 2 Y
! is Funding Status
Unfunded
Actual Revised
Through Budget Projected
2006 -07 2007 -08 2008 -09 2008 -09 2009 -10 2010 -11 2011 -12 2012 -13 Total
Project by Category
Design and Engineering 400,000 400,000
Construction 2,500,000 2,500,000
Project Total 400,000 2,500,000 2,900,000
Project Funding Source
Unfunded 400,000 2,500,000 2,900,000
Project Total 400,000 2,500,000 2,900,000
Tigard Capital Improvement Plan FY 2008 -2013 156