Loading...
Report (670) R k. vG R7— Bend Office (541) 330 -9155 Carlson Testing, Inc ■ Eugene em Office i Office (503) 601 -8250 Eugene Office (541) 345 -0289 (503) 589 -1252 Tigard Office (503) 684-3460 March 24, 2010 T1001923 Permit N° BUP2009 -00208 PO N° P18677 FIELD INSPECTION REPORT DATES COVERED: March 8, 2010 PROJECT: Tualatin Valley Fire & Rescue — Command & Business Operations Center (CBOC) ADDRESS: 11945 SW 70 Avenue — Tigard, OR INSPECTOR: J. Hietpas, COP #343; WABO #HIE522831; ICBO #0873046- 88,- 86, -84; OBOA #205 1 03 -08 -10 - Compression Tests I As requested, CTI representative was on site to test (3) cores for compression strength. Cores were submitted by Jim P. with Howard S. Wright and tested on 03/08/10. PSI Corrected Core ID Length Diameter Area Load Factor PSI East 1 2.83 2.74 5.9 30103 0.88 4490 Middle 2 2.89 2.74 5.9 32805 0.88 4890 West 3 2.98 _ 2.74 5.9 38493 0.89 5800 Our reports pertain to the material tested /inspected only. Information contained herein is not to be reproduced, except in full, without prior authorization from this office. Under all circumstances, the information contained in this report is provided subject to all terms and conditions of CTI's General Conditions in effect at the time this report is prepared. No party other than those to whom CTI has distributed this report shall be entitled to use or rely upon the information contained in this document. If there are any further questions regarding this matter, please do not hesitate to contact this office. Respectfully submitted, CARL / IN TESTING, INC. J. �- F. Hietpas P • • ect Manager ' /ck c Tualatin Valley Fire & Rescue — Siobhan Kirk siobhan.kirk @tvfr.com City of Tigard Building Division KPFF — Ian Eikanas i an.eikanas @kpff.com PSE Architects — Hans Ettlin hans @psearch.com Howard S Wright Constructors — Jason Chupp chuppj @hswc.com Tualatin Valley Fire & Rescue — Greg Perry greg.perry@tvfr.com 03 -08 -10 ft.doc Upd'd 03124/10 r Consulting Engineers SITE VISIT REPORT NO.: 01 Page 1 of 4 PROJECT NAME TVF &R CBOC Owner TVF &R Location: 11945 SW 70th Ave Client: Boora Architects Tigard, OR 97223 Job No.: 209115 Contractor: Howard S. Wright Site Visit Date: Tuesday, March 2, 2010 Weather: Cloudy and Cool Present At Site: Jim Pickering - HSW Nathan Junkert — PSE Ian Eikanas — KPFF Those present walked the project site to review portions of the current construction. Work was ongoing throughout the building. The following was noted: 1. Shoring posts had been installed at the first floor north retaining wall, in preparation for existing brace removal, and they appeared to be in conformance with the phasing plan. See Picture 1. 2. In preparation for installing the shotcrete walls, braces and gusset plates were being removed from the existing braced frames on Grids 2.7, 3, and 5. See Picture 2. 3. Existing braced frame base plate connections to concrete footings were observed at Grid locations C -7, C -8, and C -9. See Picture 3. It was observed that some anchor bolts were missing nuts, and some base plate holes were without anchor bolts. Braced frame gusset plates are receiving new anchorages that have been designed to resist the entire load demand; therefore, new nuts /bolts are not required to fill the absence of the existing missing nuts /bolts. 4. Multiple areas in the third floor composite concrete over metal deck had been chipped or cored to expose wire mesh reinforcement and welded headed studs. See Pictures 4 and 5. At both chipped locations, the wire mesh was found to be near the bottom of the topping slab, located within 1 /2" from the top flute of the metal deck. Mesh located this low in the topping slab will reduce the reinforcement's ability to minimize cracking at the surface of the concrete, and this may be one explanation as to the increased amounts of cracking in the elevated slab. Also, Kyle of HSW, who performed the concrete chipping, explained that the concrete was relatively easy to chip out compared to previous experience with concrete chipping. This indicates that the concrete strength may not be very high; therefore, it may be beneficial to verify the in -place concrete strength by taking concrete cores and having them tested. Action Items 1. HSW will contact Carlson Testing to obtain information about concrete coring /testing. Picture 1: Retaining Wall Shoring Posts per Phasing Plan / �5 • r 2 Picture 2: Removed Brace and Gusset Plate at Existing Braced Frame at Grid 5 TVF &R CBOC 2 of 4 209115 Site Visit Report No. 01 March 2, 2010 4 - a • c1 Picture 3: Existing Braced Frame Base Plate Connection at Grids C -9 r r<` r .z sues- �� ; r � fi - Picture 4: Exposed Wire Mesh Reinforcement at Third Floor Composite Deck TVF &R CBOC 3 of 4 209115 Site Visit Report No. 01 March 2, 2010 gib ` f r- n a r • C 4 .; .._ N & ij Picture 5: Exposed Welded Headed Stud at Third Floor Composite Deck The purpose of this visit was to evaluate portions of the current construction with respect to the design intent. This report is based on a visual observation of construction readily accessible to view. Concealed conditions and items, which were not described in this report, were not included in this review. Respectfully submitted, Ian K. Eikanas cc: Hans Ettlin, PSE Nathan Junkert, PSE Jim Pickering, HSW Sarah Thorson, HSW TVF &R CBOC 4 of 4 209115 Site Visit Report No. 01 March 2, 2010