Washington County - CA 10-1244 Knoll Infrastructure Gid l a-
CONTRACT AMENDMENT NO. 1
This amendment is made and entered into by and between, City of Tigard (Contractor") and
Washington County, a political subdivision of the State of Oregon ("County").
This amendment modifies that certain contract between the parties, the original contract number
being BCC 0419.
The contract is amended as follows:
Part V. A. Project Description, Scope of Activities and Anticipated Accomplishments is revised
as attached.
Part II. E. Component Activities is revised to reflect $34,769 increase in CDBG funds allocated
to the project.
Part V. Exhibit C. Budget Summary is revised as attached.
Effective Date of Amendment: October 15, 2010 , or upon final signature, whichever is later.
All other terms and conditions of the original contract shall remain in full force and effect.
WASHIN ON COUNTY:
/��/ Robe Massav
V
Si ature Printed Name
IZ��( � Asst,County Administrator
Date Title
CON
Signa Printed Na Ze
Date Title
� ia� su� 1c�-CC ,v 1
Address
D t92
Telephone Number
Revised 4/9/07
PROJECT DESCRIPTION, SCOPE OF ACTIVITIES
AND ANTICIPATED ACCOMPLISHMENTS
2010-2011 CDBG Program Year
1. Proiect Number and Title:
CDBG Project#2128, Tigard, The Knoll Infrastructure Improvements
II. Description of: Project, Activities, Anticipated Accomplishments, Low and
Moderate or Other Target Group Beneficiaries.
A. Nature and Purpose of the Project:
Construction or upgrading of development-required infrastructure
improvements along three streets bordering The Knoll senior housing
project. The project is located in an older area of Tigard that was
developed without sidewalks or storm sewers.
B. Proposed Location or Impact Area(s):
Intersection of SW Hall Blvd. and SW Hunziker Road, Tigard, OR
C. Duration/Timing of the Project:
July 1, 2010 — June 30, 2011
D. Number of Low and Moderate Income or Target Group Beneficiaries:
50 Low to Moderate-income seniors will be served.
E. Component Activities (CDBG vs. Others):
CDBG = $459,769 Others = $217,838
F. Quantitative Projections for CDBG Component Activities (in units, linear
feet, square feet, etc.) for all acquisitions, construction, reconstruction,
rehabilitation, etc.:
Undertake the construction of 552 lineal feet of curbs, sidewalk,
landscape, and drainage adjacent to the proposed 48-unit The Knoll
senior housing development. Construction activities include sidewalk and
associated improvements within the public right-of-way, including the
replacement of two traffic signal poles and various related costs.
EXHIBIT A
S/con10/2128 Tgrd scope
Project No. 2128
Project Year (funded) 2010
BUDGET SUMMARY
Community Development Block Grant
Project Title The Knoll Infrastructure Improvements
Legal Name of Entity City of Tigard
Address 13125 SW Hall Bvd. City Tigard State OR Zip 97223
I. BUDGET LINE ITEMS:
A. PERSONNEL SERVICES:
4. Portion Chargeable to
1. No. of 2. Job Title 3. Total Salary CDBG
Employees
1 Pr 'e t Planner $1,100-00 0.00
5. Subtotal $1,100.00 $0.00
6. Extra Help/Overtime
7. Fringe Benefits
8. TOTAL PERSONNEL COSTS $1,100.00 $0.00
Portion Chargeable to
B. MATERIALS & SERVICES: Materials & Services CDBG
9. Office Supplies $200.00 $0.00
10. Operating Supplies
11. Communications
12. Travel and Training
13. Legal & Public Notices $150.00 $0.00
14. Professional Services $70,905.00
15. Construction Contracts $605.252.00 $459.769.00
16. Other: Specify
17. TOTAL MATERIALS & SERVICES $677,607.00 $459,769.00
S\cdforms\bgtsum.doc
C. CAPITA. OUTLAY: Total Portion Chargeable to
Capital Outlay CDBG
18. Capital Outlay:
Quantity Item $0.00 $0.00
19. Real Property Acquisition: $0.00 $0.00
20. TOTAL CAPITAL OUTLAY $0.00 $0.00
21. Total Project 22. Total CDBG Award
Cost
$677,607.00 $459,769.00
II. SOURCES OF PROJECT FUNDING
1. Federal
2. State 181 2 0
3. Local Cash $35.118.00
4. Count
5. In-Kind Service & Supply 1 10 .
6. Other detail
7. Subtotal $217,838.00
8. Community Development Block Grant $459,769.00 $459,769.00
9. TOTAL PROJECT COST $677 607.00
III. AUTHORIZAT15N
Date Authori �Signature for Project
k J 1-7 I t1
Date Authorized Signature for Project
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - -
COUNTY USE ONLY
Reviewed and approved by Washington County Office of Community Development on
20 _ By
Signature