Report N
aiasoi°00/t,
Geotechnucal E n ineerin Report
g g p
Proposed AutoZone Store 3756
Tigard, Oregon
Updated April 15, 2010
Project No. 82095068
Prepared for:
AutoZone, Inc.
Memphis, Tennessee
Prepared by:
Terracon Consultants, Inc.
Portland, Oregon
(30p20k -mi (oc .
OFFICE 11111
ail
r acon
r ,..
- ' - x
p
gfficesBNat�a x Established ih 1965 `
Emplo onw , ° terracfl com <
Geotechnical 8 Environmental EIB Construction Materials ® Facilities
April 15, 2010
AutoZone, Inc.
123 South Front Street
Memphis, Tennessee 38103
Attn: Mr. Trey Smallwood
P: 901 - 495 -7956
F: 901 - 495 -8300
Re: Geotechnical Engineering Report - UPDATED
Proposed AutoZone Store 3756
Tigard, Oregon
Terracon Project No. 82095068
Dear Mr. Smallwood:
Terracon Consultants, Inc. (Terracon) has completed the geotechnical engineering services for
the above referenced project. This study was performed in general accordance with our
proposal number P82090096 dated July 22, 2009. This report is an update to our original report
dated August 5, 2009, and is prepared in general accordance with AutoZone Purchase Order No.
62054 dated September 3, 2009, and presents the findings of the subsurface exploration and
provides geotechnical recommendations concerning earthwork and the design and construction of
foundations and floor slabs for the proposed project.
We appreciate the opportunity to be of service to you on this project. If you have; any questions
concerning this report, or if we may be of further service, please contact us. <z's'a. ";_''
Sincerely, f a r
Terracon Consultants, Inc. 1
"• 47: t r � J: y
F°
David A. aB ska, Ph.D., P.E., C.E.G. Eric J. Lim, PE, GE r = phi/2 to
Senior Consultant Geotechnical Depai men 4 Manager
Enclosures
cc: 2 - Above
1 - File
Terracon Consultants, Inc. 12400 SE Freeman Way, Suite 102 Portland, Oregon 97222
P (503] 659 3281 F [503] 659 1287 terracon.com
�4..; °°n:;- r �,,; -. 4 . 9� - �,°-n. r ,�.,c --.x�w a ly''" - t s ^,{4. °
, G e o t etc nt cta
' 111 a E n�u°fi r4 otn(mre;n t a�I Cidrn o f "r utctt i M ait e9"r2raaal s ; U
'Y 1
TABLE OF CONTENTS
Page
EXECUTIVE SUMMARY
1.0 INTRODUCTION 1
2.0 PROJECT INFORMATION 1
2.1 Project Description 1
2.2 Site Location and Description 2
3.0 SUBSURFACE CONDITIONS 2
3.1 Geology 2
3.2 Typical Profile 3
3.3 Groundwater 3
4.0 RECOMMENDATIONS FOR DESIGN AND CONSTRUCTION 4
4.1 Geotechnical Considerations 4
4.2 Seismic Considerations 4
4.2.1 Design Recommendations 4
4.2.2 Seismic Hazards 5
4.2.3 Liquefaction Analysis 5
4.3 Foundation Support Alternatives 6
4.3.1 Aggregate Pier Ground Improvements 7
4.3.2 Earthquake Drains 8
4.3.3 Rigid Shallow Foundations with Seismic Ties 8
'4.4 Earthwork 9
4.4.1 Compaction Requirements 10
4.4.2 Grading and Drainage 10
4.4.3 Construction Considerations 11
4.5 Floor Slab 12
4.5.1 Design Recommendations 12
4.5.2 Construction Considerations 12
4.6 Pavements 13
4.6.1 Design Recommendations 13
4.6.2 Construction Considerations 14
5.0 GENERAL COMMENTS 15
APPENDIX A — FIELD EXPLORATION
Site and Exploration Plan
Boring and CPT Logs
Field Exploration Description
APPENDIX B — LABORATORY TESTING
Laboratory Test Data
APPENDIX C — SUPPORTING DOCUMENTS
General Notes
Unified Soil Classification
7 i
Geotechnical Engineering Report - UPDATED 1
Proposed AutoZone Store 3756 ® Tigard, Oregon
April 15, 2010 D Terracon Project No. 82095068
EXECUTIVE SUMMARY
A geotechnical engineering report has been completed for the investigation for the proposed
AutoZone Store 3756 proposed at 13405 SW Pacific Highway approximately 500 feet southwest
of the intersection of SW Park Street in Tigard, Oregon. Seven borings, designated B -1 through
B -7, were completed to depths ranging between approximately 111/2 to 24 feet below the existing
ground surface (bgs) within the proposed building area and parking areas locations. One Cone
Penetration Test (CPT), designated CPT -1, was also conducted to a depth of approximately 45
feet bgs within the proposed building area. This report specifically addresses the
recommendations for the proposed building. Based on the information obtained from our
subsurface exploration, the site can be developed for the proposed project. The following
geotechnical considerations were identified:
• Loose, saturated sand and non - plastic silt soils were encountered in the explorations
and these soils are considered susceptible to liquefaction during a seismic event.
Seismic related settlements between 4 and 10 inches are estimated.
The 2006 International Building Code, Table 1613.5.2 IBC seismic design classification
for this site is F.
Deep foundations, ground improvements (such as aggregate piers), or earthquake drains
would be required to reduce seismic related settlements to tolerable amounts.
• If the owner accepts the risks of excessive seismic settlements, the building can be
designed for life- safety only over a rigid shallow foundation with seismic ties. This type of
construction is meant to prevent collapse and may not be operable or repairable after a
significant earthquake.
• On -site native soils consist of fine - grained soils that would only be considered suitable
as general engineered fill during extended periods of dry weather. Imported granular fill
may be required for structural fill placed below the structure.
• The near - surface native soils are typically fill soils consisting of stiff and medium dense
sandy silt. We recommend a minimum 12 -inch thick granular base course be placed below
building slab.
• The existing pavements are not considered suitable for reuse for the new development.
We recommend the new pavement section include a geotextile fabric placed over the fine -
grained subgrade and below the base course.
Close monitoring of the construction operations discussed herein will be critical in
achieving the design subgrade support. Therefore, we recommend that Terracon be
retained to monitor this portion of the work.
This summary should be used in conjunction with the entire report for design purposes. It should
be recognized that details were not included or fully developed in this section, and the report must
be read in its entirety for a comprehensive understanding of the items contained herein. The
section titled GENERAL COMMENTS should be read for an understanding of the report
limitations.
Reliable Responsive El Convenient fa Innovative
1
GEOTECHNICAL ENGINEERING REPORT
PROPOSED AUTOZONE STORE 3756
TIGARD, OREGON
Project No. 82095068
April 15, 2010
1.0 INTRODUCTION
A geotechnical engineering report has been completed for the investigation for the proposed
AutoZone Store 3756 Tigard planned at a site located at 13405 SW Pacific Highway south west
of the intersection of SW Park Street in Tigard, Oregon. Seven borings, designated B -1 through
B -7, were completed to depths ranging between approximately 11%2 to 24 feet below the existing
ground surface (bgs) within the proposed building area and parking areas locations. One Cone
Penetration Test (CPT), designated CPT -1, was also conducted to a depth of approximately 45
feet bgs within the proposed building area. The CPT exploration included collection of shear wave
velocity testing and pore pressure dissipation data. This report specifically addresses the
recommendations for the proposed building. Logs of the borings, CPT plots, along with a Site and
Exploration Plan are included in Appendix A of this report.
The purpose of these services is to provide information and geotechnical engineering
recommendations relative to:
Ea subsurface soil conditions foundation design and construction
groundwater conditions a floor slab design and construction
earthwork ® seismic considerations
pavement design and construction
2.0 PROJECT INFORMATION
2.1 Project Description
ITEM j DESCRIPTION
Site layout See Appendix A, Figure 1: Site and Exploration Plan
Building' 6,786 square foot single story structure.
Masonry (Prototype 65W)
Building construction steel bar joist roof, and
slab -on -grade floor.
Finished floor elevation i Unknown at the time that this report was prepared.
Interior Columns: 37 -75 kips
Maximum Toads Perimeter Columns: 20 -50 kips
Walls: 1.2 - 3.0 klf
Reliable Responsive a Convenient o Innovative 1
Geotechnical Engineering Report lierracon
Proposed AutoZone Store 3756 o Tigard, Oregon
April 15, 2010 in Terracon Project No. 82095068
ITEM DESCRIPTION
Floor Slab: 100 psf
Maximum allowable settlement 1 -inch total settlements, 'A -inch differential settlement (both
related to static settlements)
Grading Not known, maximum cut and fill depths assumed to be on
the order of 2 feet
Cut and fill slopes none anticipated
1. Project information based on AutoZone Geotechnical Design Criteria, Rev. 06 -05 -09
2.2 Site Location and Description
ITEM I DESCRIPTION
The proposed project is planned at 13405 SW Pacific
Location Highway approximately 500 feet southwest of the intersection
of SW Park Street in Tigard, Oregon.
Existing improvements
A vacant restaurant building and surrounding asphalt parking
lot occupy the site.
Existing building with asphalt parking lot. Asphalt pavements
observed to have significant areas of "alligator cracking" in
Current ground cover drive lanes and area of previous asphalt reconstruction
patches. Landscaping islands with concrete curbs are located
along the southwest face of the building and adjacent to SW
Pacific Highway.
Existing topography Site has between 2 and 4 feet of grade changes throughout
existing parking lot to drain stormwater to catch basins.
3.0 SUBSURFACE CONDITIONS
3.1 Geology
The regional geology of the site area was reviewed in the Earthquake- Hazard Geology Maps of
the Portland Metropolitan Area, Oregon: Oregon Department of Geology and Mineral Industries
Open File Report 0- 90 -2 The project site area is located within the Beaverton, Oregon
Quadrangle Map (0r090_2f), and is classified as Qff, fine - grained facies. These deposits are
described as crudely to complexly layered, poorly consolidated medium sand and silt, deposited
by glacial outburst flooding. The map indicates the thickness of these deposits is on the order of
about 30 to 60 feet. The subsurface conditions as disclosed by the borings confirmed the
presence and thickness of silt soils as described on the geologic map.
1 Open File Report 0 -90 -2, Beaverton Quadrangle, Oregon - Washington Co., 7.5 Minute Series
(Topographic), 1984
Reliable o Responsive o Convenient ❑ Innovative 2
' 1
Geotechnical Engineering Report irerracon
Proposed AutoZone Store 3756 ® Tigard, Oregon
April 15, 2010 Terracon Project No. 82095068
3.2 Typical Profile
Based on the results of the borings and cone penetration testing, subsurface conditions on the
project site can be generalized as follows:
Description Approximate Depth to Material Encountered Consistency /Density
Bottom of Stratum (feet)
2 inches to 3 inches
Existing
1 /2 to 1'/ Asphalt over
Pavement N/A
Section 3 to 11 inches Gravel Base
Course
Fill j 1 to 5'/ Sandy Silt and Silty Sand Stiff and Medium Dense
Sandy Silt 7 to 10 feet Sandy Silt to Clayey Silt Soft to Stiff
Silty Sand 30 feet Silty Sand Loose to Very Loose
Clayey Silt 40 feet Clayey Silt to Sandy Silt Very Stiff to Hard'
Sandy Silt >45 feet Sandy Silt to Clayey Silt Very Stiff to Hard'
' Based on CPT to SPT correlations.
Conditions encountered at each exploration location are indicated on the individual exploration
logs. Stratification boundaries on the Togs represent the approximate location of changes in soil
types; in -situ, the transition between materials may be gradual. Details for each of the explorations
can be found on the logs in Appendix A of this report.
3.3 Groundwater
The boreholes were observed while drilling and after completion for the presence and level of
groundwater. In addition, delayed water levels were also obtained in some borings. The water
levels observed are noted on the attached boring logs, and are summarized below.
Boring Number Depth to groundwater Depth to groundwater
while drilling, ft. after boring, ft.
B -1 I 9 12
B -2 j 10 12
B -3 I 11 12
B -4 10'/2 12
B -5 10 10
B -6 1 ( 5
B -7 11 Borehole Caved
Reliable o Responsive ® Convenient Innovative 3
Geotechnical Engineering Report irerracon
Proposed AutoZone Store 3756 a Tigard, Oregon
April 15, 2010 a Terracon Project No. 82095068
Groundwater level fluctuations occur due to seasonal variations in the amount of rainfall, runoff
and other factors not evident at the time the borings were performed. Therefore, groundwater
levels during construction or at other times in the life of the structure may be higher or lower
than the levels indicated on the boring Togs. The possibility of groundwater level fluctuations
should be considered when developing the design and construction plans for the project.
4.0 RECOMMENDATIONS FOR DESIGN AND CONSTRUCTION
4.1 Geotechnical Considerations
The soil exploration data and laboratory test results were evaluated to develop
recommendations for the site preparation and for the design and construction of foundations
and floor slabs for the proposed building. The primary geotechnical consideration for
development of this site is the potential for seismic related settlements to exceed typical design
tolerances due to the presence of potentially liquefiable soils at the site. The 2006 International
Building Code (IBC) requires that liquefaction analyses be completed assuming a substantial
earthquake with associated ground accelerations that are provided in the IBC. The IBC seismic
design is based on life safety with the intent of preventing building collapse during such a design
earthquake. It is not the intent of the IBC to require a building to be in an operable condition
after such event. The Owner should understand that the building may not be in an operational
condition after a design earthquake and significant repair or even demolition and reconstruction
might be required. We recommend the owner and design team develop allowable seismic
settlement criteria for this site based on tolerable settlements that would maintain life safety and
also meet owner expectation for building performance subsequent to a design level seismic
event.
4.2 Seismic Considerations
4.2.1 Design Recommendations
Code Used Site Classification
2006 International Building Code (IBC) F 2.3
Mapped Spectral Acceleration for 0.930
Short Periods, S
Mapped Spectral Acceleration for a
0.336
1- second period, S
Reliable a Responsive a Convenient Innovative 4
t i
Geotechnical Engineering Report ���
Proposed AutoZone Store 3756 a Tigard, Oregon
April 15, 2010 a Terracon Project No. 82095068
Code. Used Site Classification
1. In general accordance with the 2006 International Building Code, Table 1613.5.2.
2. The 2006 International Building Code (IBC) requires a site soil profile determination extending a
depth of 100 feet for seismic site classification. The current scope requested does not include the
required 100 foot soil profile determination. Explorations for the building extended to a maximum
depth of approximately 45 feet.
3. Per 2006 IBC, Table 1613.5.2, any profile containing soils vulnerable to potential failure or collapse
under seismic loading such as liquefiable soils.
As discussed later in this report, the site soils are liquefiable; consequently, the Site Class is F.
However, Section 20.3.1 of ASCE 7 -05 allows site coefficients Fa and Fv to be determined
assuming that liquefaction does not occur for structures with fundamental periods of vibration less
than 0.5 second. Based on the results of the shear wave velocity testing, Site Class D may be
used to determine the values of Fa and Fv in accordance with Section 1613.5.2 of the 2006 IBC.
4.2.2 Seismic Hazards
Seismic hazards resulting from earthquake motions can include slope instability, liquefaction,
and surface rupture due to faulting or lateral spreading. Liquefaction is the phenomenon
wherein soil strength is dramatically reduced when subjected to vibration or shaking.
Liquefaction generally occurs in loose sand or non - plastic silt deposits that are below the water
table. Groundwater was typically encountered in borings at depths ranging from 9 to 12 feet. It
is our opinion, based on the site geology and the subsurface conditions encountered in our
borings, that the risks associated with liquefaction are high. Since the project site is not situated •
in close proximity to free slopes, the risk associated with slope instability and lateral spread is
considered low.
We reviewed the USGS Earthquake Hazards Program Quaternary Faults and Folds Database available
online ( http: // earthquake. usqs. qov /regional /gfaults /usmap.php). The nearest faults to the project
site are the Canby - Molalla fault zone, approximately 3/4 mile southwest of the project site.
According to this source, this fault zone consists of a linear series of northeast trending,
discontinuous aeromagnetic anomalies beneath sediments that fill the northern Willamette River
basin and that are buried by Missoula flood deposits, as encountered in the explorations. These
faults are in the slip rate category of less than 0.2 mm /year. Based on the information described
above, we estimate that the risk associated with surface rupture at the site is low.
4.2.3 Liquefaction Analysis
Liquefaction is the phenomenon where saturated soils develop high pore water pressures
during seismic shaking and lose their strength characteristics. This phenomenon generally
Reliable a Responsive a Convenient a Innovative 5
Geotechnical Engineering Report err
Proposed AutoZone Store 3756 ® Tigard, Oregon
April 15, 2010 0 Terracon Project No. 82095068
occurs in areas of high seismicity, where groundwater is shallow and loose granular soils or
relatively non - plastic fine grained soils are present.
Saturated loose to very loose silty sand soils were encountered in the borings below depths of
about 7A to 10 feet bgs and extended to the bottom of the borings. A supplemental cone
penetrometer test (CPT) with seismic shear wave velocities was performed down to
approximately 45 feet bgs to further evaluate the liquefaction potential of the site.
As part of this geotechnical evaluation, we performed a site- specific liquefaction analysis using
the methods based on empirical methods originally developed by Seed and Idriss and
subsequently modified by others. The latest recommended procedures were presented by
Idriss and Boulanger (2008). In our analysis, the CPT data was used to calculate the
liquefaction resistance of the soils based on correlations presented in the Idriss and Boulanger
monograph. The peak ground acceleration and moment magnitude used in the analysis were
based on IBC derived ground motions for the design earthquake.
Using the 2006 IBC seismic parameters, we computed safety factors against liquefaction for the
various soil layers below the water table encountered at the time of our exploration. For the
groundwater at 12 feet bgs, as encountered in our borings, the potential for liquefaction of the
loose sand and non - plastic site soils from about 12 feet bgs to the maximum explored depth of
about 45 feet is considered to be high and we estimate liquefaction- induced settlements of 4 to
10 inches at the ground surface.
4.3 Foundation Support Alternatives
Potential liquefaction due to a design level seismic event is expected to result in excessive
seismic - related settlements of the structure. The following alternatives could be considered to
support the structure and or mitigate liquefaction at the site.
n Deep pile foundations and structurally support floor slab;
® Aggregate Pier / Stone Column Ground Improvements and conventional shallow
foundations;
• Earthquake Drains with limited overexcavation and replacement for shallow foundations;
Shallow footings and slab -on -grade with rigidly connected footings with seismic ties.
Deep foundations would not address settlements below the floor slab. Therefore, a structural
floor slab would also be necessary to provide positive support for the structure. We anticipate
that this alternative would be the most costly alternative, and we anticipate adequate
performance from the ground improvement alternatives. Therefore, we have not provided
recommendations for pile foundations in this report. Rammed aggregate piers (such as
Geopier®) or stone column ground improvement techniques are also feasible foundation
support alternatives and should provide suitable mitigation of liquefaction- induced settlements
Reliable a Responsive 0 Convenient ® Innovative 6
•
Geotechnical Engineering Report ���
Proposed AutoZone Store 3756 Tigard, Oregon
April 15, 2010 0 Terracon Project No. 82095068
when designed and constructed properly. If the owner is willing to accept the risk of excessive
liquefaction - induced settlements and possible demolition of the building after a significant
earthquake, then the building may be designed for a rigid foundation consisting of shallow
spread footings with seismic ties designed to prevent collapse to satisfy life- safety requirements
of the IBC. This alternative would represent the least cost option.
4.3.1 Aggregate Pier Ground Improvements
Based on the presence of liquefaction susceptible soils encountered in the borings, one
alternative for support of the structure would be ground improvement of the loose granular soils
in order to provide positive support of foundations and floor slabs. Installation of a system of
aggregate piers that extend through loose granular materials could consist of Geopiers® or
stone columns. The seismic related settlements would depend on the depth of improvement and
grid spacing of the aggregate piers.
Geopiers® involves excavating 30- to 36 -inch diameter drilled shafts and backfilling the shafts
with crushed aggregate placed in lifts and compacted. Compaction is performed with a
patented beveled edge ram, which also helps densify the soils surrounding the shaft, creating a
stiffer soil matrix for support of foundations. Typical installations to depths of up to about 20 feet
are common. Based on the depth of the loose sand and non - plastic soils encountered in the
explorations, we anticipate typical Geopier depths would be on the order of 30 or more feet.
Conventional spread footings and reinforced slab -on -grade could then be constructed on top of
the Geopier /soil matrix. Engineering design of Geopiers® is proprietary and is typically done on
a design /build basis by the licensed Geopier® contractor.
Vibro- replacement/compaction stone column construction is accomplished using a down -hole
vibratory probe that typically penetrates the ground under its own weight. Stone columns at this
site would extend through the fill and loose soils and would need to extend to soils stable
against liquefaction. Based on the explorations completed for this project and published
geologic literature, it appears that the stone columns would be on the order of 30 feet or more in
length. When the probe has penetrated to the design depth, gravel is placed in lifts through a
tremie pipe. Each gravel lift is forced into the surrounding soil forming a stone column. Stone
columns are also generally designed and constructed by a qualified design -build contractor
based upon replacement area, densification, liquefaction, and settlement criteria. The
contractor also develops specifications for construction of the stone columns, the diameter and
spacing, products to be used, as well as tolerance and acceptance criteria. Conventional
spread footings could then be constructed on top of the stone column /soil matrix.
Floor slabs are also estimated to settle several inches due to potential liquefaction during a
design level seismic event. Floor slab settlement can be reduced by installing aggregate piers
below slabs. The pier spacing typically ranges from 5 to 10 feet depending on slab reinforcing
and the specified design. With wider spaced piers, a reinforced floor slab may be necessary in
Reliable 12 Responsive 0 Convenient 0 Innovative 7
Geotechnical Engineering Report lierracon
Proposed AutoZone Store 3756 a Tigard, Oregon
April 15, 2010 o Terracon Project No. 82095068
order to span between aggregate pier supports. The slab design and spacing of piers in slab -
on -grade areas should be included in the design -build proposals.
4.3.2 Earthquake Drains
Additional measures could also be considered to improve the subsurface conditions and reduce
potential seismic settlements by either densification of the site soils or providing increased
drainage of site soils. Installation of Earthquake Drains in combination with imported structural
fill supported foundations could be considered to reduce seismic related settlements.
Earthquake drains consist of a high flow capacity prefabricated vertical drain wrapped with a
geotextile fabric that is typically 3 inches in diameter. The drain provides a path for the rapid
dissipation of earthquake- generated excess pore pressures. Vibratory installation of the
earthquake drains can also densify loose sand soils around the drain. The Earthquake Drains
are a proprietary system and the design and installation would be completed by the licensed
contractor.
Earthquake drains alone may not be sufficient to reduce seismic related settlements to tolerable
amounts that would prevent life safety with standard foundation construction (i.e. some ground
improvement discussed above would be necessary in addition). However, installation of these
drains in addition to imported structural fill supported footings could reduce settlements and or
improve the performance of the structure during a seismic event.
4.3.3 Rigid Shallow Foundations with Seismic Ties
We understand that the proposed building will be in the same location as the existing building,
but will have a slightly larger footprint. The borings at the four building corners encountered stiff
silt to sandy silt fill soils from 21 to 51 feet. These soils appear to be suitable for support of the
proposed structure under static conditions. However, liquefaction- induced settlement may
cause displacements of 4 to 10 inches, as previously discussed.
We recommend that all footings for the structure be connected together. No isolated footing
pads should be planned or constructed. In addition, the footings should be designed such that
they would be able to span approximately 8 feet without subgrade support (similar to grade -
beams). The intent of these recommendations is driven by life- safety as required by the IBC
and to help limit differential settlements, but not to prevent total settlements to the magnitudes
discussed previously in this report. In addition, this alternative is not intended to mitigate
potential liquefaction settlements occurring due to the design level earthquake and the structure
may require repair or even reconstruction for operability after a design -level event.
The foundations for this alternative may be designed using the parameters provided in the table
below. Foundation parameters for the other alternatives will need to be provided by the design -
build contractor based on their proposed scope of work.
Reliable 0 Responsive o Convenient o Innovative 8
Geotechnical Engineering Report �����
Proposed AutoZone Store 3756 ® Tigard, Oregon
April 15, 2010 El Terracon Project No. 82095068
DESCRIPTION ` Column j Wall
Net allowable bearing pressure 1 2,000 psf 2,000 psf
Bearing soil 2 I Stiff Silt or two feet of structural fill.
Minimum dimensions 30 inches 24 inches
Approximate total static settlement 3 <1 inch <1 inch
Estimated differential Static settlement due <'/2 inch between <1/2 inch over 40 feet
to static loads columns
1. The recommended net allowable bearing pressure is the pressure in excess of the minimum
surrounding overburden pressure at the footing base elevation.
2. The minimum depth for bottom of footings 18 inches for exterior footings (frost depth) and 12
inches for interior footings.
3. The foundation settlement will depend upon the variations within the subsurface soil profile, the
structural loading conditions, the embedment depth of the footings, the thickness of compacted fill,
and the quality of the earthwork operations. The above settlement estimates have assumed that
the maximum footing size is 5 feet for column footings and 2 feet for continuous footings.
4.4 Earthwork
After removal of the existing structures, the floor slabs, existing foundations and pavements
should be broken up and removed completely. In addition, any existing utilities that interfere
with the proposed construction should be properly abandoned in -place or removed and the
trenches backfilled with granular fill.
It is important that the demolition of existing structures be performed with close observation and
testing. Ground improvements and footing foundations, floor slabs and pavements will be
supported on the new structural fill placed in the demolition excavations. The demolition
contractor should be aware of project requirements for backfilling so that removal of these fill
materials and replacement under controlled conditions is not necessary upon building
construction. Also, any excavations necessary for removal of old structures or utilities should be
carefully planned and executed, especially adjacent to existing retaining walls, streets, sidewalks,
or utilities. Temporary sheeting, shoring or other earth retention systems may be needed to
reduce potential for damage to existing infrastructure.
After demolition, the exposed subgrades should be thoroughly observed and tested prior to
placement of new fill, construction of pavements or slabs. This testing should include
proofrolling the subgrade. Wet or dry material should either be removed or moisture conditioned
and recompacted. Loose, dry and low- density soil should be removed or compacted in -place
prior to placing fill. We recommend that exposed excavation surfaces be, at a minimum,
surface compacted prior to the placement of backfill, additional fill, or structural elements.
Reliable E3 Responsive m Convenient o Innovative 9
Geotechnical Engineering Report ���
Proposed AutoZone Store 3756 Tigard, Oregon
April 15, 2010 a Terracon Project No. 82095068
Engineered fill should meet the following material property requirements:
Fill Type 1 USCS Classification Acceptable Location for Placement
SP, GP
Clean Granular Fill All locations
(P200 <5 %)
SP, SP -SM, GP, GW,
Select Granular Fill SW All locations
(P200 <12 %)
SP, SM, GP, GM, GW All locations and elevations, except where non -frost
Granular Fill
(P200 <50 %) susceptible fill is required
1. Controlled, compacted fill should consist of approved materials that are free of organic matter and
debris. Frozen material should not be used, and fill should not be placed on a frozen subgrade. A
sample of each material type should be submitted to the geotechnical engineer for evaluation.
4.4.1 Compaction Requirements
ITEM DESCRIPTION
9- inches or less in loose thickness when heavy, self-
propelled compaction equipment is used
Fill Lift Thickness 4 to 6 inches in loose thickness when hand - guided
equipment (i.e. jumping jack, plate compactor, etc.) is
used
Compaction Requirements 95% of the materials maximum Proctor dry density
(ASTM D 1557)
Moisture Content Granular Material within ±2 percent of optimum moisture content as
determined by ASTM D 1557
1. We recommend that engineered fill be tested for moisture content and compaction during
placement. Should the results of the in -place density tests indicate the specified moisture or
compaction limits have not been met, the area represented by the test should be reworked and
retested as required until the specified moisture and compaction requirements are achieved.
4.4.2 Grading and Drainage
Final surrounding grades should be sloped away from the structure on all sides to prevent ponding
of water. Gutters and downspouts that drain water a minimum of 5 feet beyond the footprint of
the proposed structure is recommended. This can be accomplished through the use of splash -
blocks, downspout extensions, and flexible pipes that are designed to attach to the end of the
downspout. Flexible pipe should only be used if it is daylighted in such a manner that it gravity -
drains collected water. Splash- blocks should also be considered below hose bibs and water
spigots.
Reliable Responsive a Convenient a Innovative 10
i
Geotechnical Engineering Report lierracon
Proposed AutoZone Store 3756 a Tigard, Oregon
April 15, 2010 a Terracon Project No. 82095068
4.4.3 Construction Considerations
There is existing fill in the building pad area, likely placed as structural fill during construction of
the existing building. The condition of the fill as encountered in the explorations appears to be
suitable for the allowable design bearing capacity recommended. However, variations may
exist in the condition of the fill, especially after disturbed by demolition activities. We
recommend that a qualified owner's representative assess the foundation subgrades at the time
of construction for their suitability to support the foundation Toads. Loose or soft to medium stiff
soils should be removed and replaced with structural fill.
Although the exposed subgrade is anticipated to be relatively stable upon initial exposure,
unstable subgrade conditions could develop during general construction operations, particularly
if the soils are wetted and /or subjected to repetitive construction traffic. Due to the fine - grained
nature of the soil, subgrade disturbance may be reduced by placing a working mat of granular
fill over exposed subgrades.
Upon completion of filling and grading, care should be taken to maintain the subgrade moisture
content prior to construction of floor slabs and pavements. Construction traffic over the
completed subgrade should be avoided to the extent practical. The site should also be graded
to prevent ponding of surface water on the prepared subgrades or in excavations. If the
subgrade should become saturated, frozen, desiccated, or disturbed, the affected material
should be removed or these materials should be scarified, moisture conditioned, and
recompacted prior to floor slab and pavement construction.
As a minimum, all temporary excavations should be sloped or braced as required by
Occupational Health and Safety Administration (OSHA) regulations to provide stability and safe
working conditions. Temporary excavations will probably be required during grading operations.
The grading contractor, by his contract, is usually responsible for designing and constructing
stable, temporary excavations and should shore, slope or bench the sides of the excavations as
required, to maintain stability of both the excavation sides and bottom. All excavations should
comply with applicable local, state and federal safety regulations, including the current OSHA
Excavation and Trench Safety Standards.
The geotechnical engineer and /or their representative should be retained during the
construction phase of the project to observe earthwork and to perform necessary tests and
observations during subgrade preparation; proof - rolling; placement and compaction of
controlled compacted fills; backfilling of excavations into the completed subgrade, and just prior
to construction of building floor slabs.
Reliable a Responsive a Convenient G Innovative 11
Geotechnical Engineering Report 1 rerracon
Proposed AutoZone Store 3756 ® Tigard, Oregon
April 15, 2010 o Terracon Project No. 82095068
4.5 Floor Slab
4.5.1 Design Recommendations
ITEM DESCRIPTION
12 -inch compacted granular fill zone and special
Floor slab support
subgrade preparation, is required
125 pounds per square inch per in (psi /in) for point
Modulus of subgrade reaction j loading conditions
Aggregate base course /capillary break ° 6 inches of free draining granular material, tested
for a capillary rise less than 2 inches.
1. Floor slab subgrade is recommended to consist of Granular Fill.
2. Ground improvement techniques, such as aggregate piers or earthquake drains, may alter the
modulus of subgrade reaction and require additional reinforcement or other requirements per the
design -build contractor.
3. We recommend subgrades be maintained in a relatively moist condition until floor slabs and
pavements are constructed. If the subgrade should become desiccated prior to construction of
floor slabs and pavements, the affected material should be removed or the materials scarified,
moistened, and recompacted. Upon completion of grading operations in the building areas, care
should be taken to maintain the recommended subgrade moisture content and density prior to
construction of the building floor slabs.
4. The floor slab design should include a capillary break, comprised of free - draining, compacted,
granular material, such as ODOT gradation Section 02630 Dense graded aggregates 3/4" - 0, at
least 6 inches thick. Free - draining granular material should have less than 5 percent fines
(material passing the #200 sieve) and be tested for a capillary rise of less than 2 inches.
Where appropriate, saw -cut control joints should be placed in the slab to help control the
location and extent of cracking. For additional recommendations refer to the ACI Design
Manual. Joints or any cracks in pavement areas that develop should be sealed with a water-
proof, non - extruding compressible compound specifically recommended for heavy duty concrete
pavement and wet environments.
4.5.2 Construction Considerations
On most project sites, the site grading is generally accomplished early in the construction phase.
However as construction proceeds, the subgrade may be disturbed due to utility excavations,
construction traffic, desiccation, rainfall, etc. As a result, the floor slab subgrade may not be
suitable for placement of base rock and concrete and corrective action will be required.
We recommend the area underlying the floor slab be rough graded and then thoroughly
proofrolled with a loaded tandem axle dump truck prior to final grading and placement of base
rock. Particular attention should be paid to high traffic areas that were rutted and disturbed earlier
and to areas where backfilled trenches are located. Areas where unsuitable conditions are
Reliable o Responsive r Convenient Innovative 12
Geotechnical Engineering Report ���
Proposed Auto Store 3756 u Tigard, Oregon
April 15, 2010 Terracon Project No. 82095068
located should be repaired by removing and replacing the affected material with properly
compacted fill. All floor slab subgrade areas should be moisture conditioned and properly
compacted to the recommendations in this report immediately prior to placement of the base rock
and concrete.
4.6 Pavements
4.6.1 Design Recommendations
Existing pavements present at the site are not considered suitable for reuse for the new store
development. Significant areas of the existing drive areas are either "alligator cracked" or have
been patched. Although we have not completed an evaluation of the remaining design life of
the existing pavements, we anticipate that the pavements would not meet criteria for a 20 -year
design life. Pavement areas removed for construction or damaged will require proper subgrade
preparation for either reinforced concrete or bituminous pavements. Consideration of concrete
pavements is strongly recommended in truck loading and turn around areas.
The existing fill may be left beneath pavements; however, we recommend that, at a minimum,
the upper 1 foot of the subgrade be scarified, blended, and recompacted prior to the placement
of aggregate base or structures. This risk of unforeseen conditions cannot be eliminated
without completely removing the existing fill, but can be reduced by performing additional testing
and evaluation.
Two levels of traffic were provided to us by AutoZone criteria for new pavements to be
constructed on the site. Traffic criteria provided for flexible pavement thickness designs include
18 -kip equivalent single axle loads (ESAL's) of 11,279 for light duty, and 30,567 for heavy -duty
pavement areas.
Listed below are pavement component thicknesses, which may be used as a guide for
pavement systems at the site for the traffic classifications stated herein. It should be noted that
these systems were derived based on general characterization of the subgrade. No specific
testing (such as CBR, resilient modulus test, etc.) was performed for this project to evaluate the
support characteristics of the subgrade.
Reliable a Responsive a Convenient a Innovative 13
Geotechnical Engineering Report llerracon
Proposed AutoZone Store 3756 o Tigard, Oregon
April 15, 2010 o Terracon Project No. 82095068
RIGID (CONCRETE) PAVEMENT SYSTEM
COMPONENT Material Thickness, Inches
Light Duty Heavy Duty
Reinforced Concrete 5 6
ODOT Aggregate 4 I 4
Base
FLEXIBLE (BITUMINOUS) PAVEMENT SYSTEM
COMPONENT Material Thickness, Inches
Light Duty Heavy Duty
Bituminous 3 1/2 4
Pavement
ODOT Aggregate Base 6 8
For areas subject to concentrated and repetitive loading conditions such as dumpster pads,
truck delivery docks, and ingress /egress aprons, we recommend using a Portland cement
concrete pavement with a thickness of at least 7 inches underlain by at least 4 inches of
crushed stone. Prior to placement of the crushed stone the areas should be thoroughly
proofrolled. For dumpster pads, the concrete pavement area should be large enough to support
the container and tipping axle of the refuse truck. Dumpster areas that are not designed in this
manner often experience localized failures due to large wheel loading imposed during waste
collection.
We recommend that newly constructed pavement sections include a geotextile fabric over the
fine - grained subgrade and below the base course to prevent migration of fines into the base
course layer. We recommend using a fabric such as Mirafi 600X, or equivalent. Geotextile
fabrics, if properly selected and installed, will maintain segregation of the subgrade soil and
base course materials. Decreased pavement support will result if the subgrade soils are
allowed to migrate upwards into the base course. The use of stabilization fabric will not reduce
the necessary base rock thickness, since fabric does not provide structural strength at such
depths.
4.6.2 Construction Considerations
Long term pavement performance will be dependent upon several factors, including maintaining
subgrade moisture levels and providing for preventive maintenance. The following
recommendations should be considered the minimum:
O Site grading at a minimum 2% grade away from the pavements;
Reliable o Responsive r3 Convenient El Innovative 14
Geotechnical Engineering Report lierracon Proposed AutoZone Store 3756 E Tigard, Oregon
April 15, 2010 a Terracon Project No. 82095068
• The subgrade and the pavement surface have a minimum 1/4 inch per foot slope to promote
proper surface drainage.
• Consider appropriate edge drainage and pavement under drain systems,
• Install pavement drainage surrounding areas anticipated for frequent wetting (e.g. wash racks)
• Install joint sealant and seal cracks immediately,
• Seal all landscaped areas in, or adjacent to pavements to minimize or prevent moisture
migration to subgrade soils;
• Placing compacted, low permeability backfill against the exterior side of curb and gutter.
Preventive maintenance should be planned and provided for through an on -going pavement
management program. Preventive maintenance activities are intended to slow the rate of
pavement deterioration, and to preserve the pavement investment. Preventive maintenance
consists of both localized maintenance (e.g. crack and joint sealing and patching) and global
maintenance (e.g. surface sealing). Preventive maintenance is usually the first priority when
implementing a planned pavement maintenance program and provides the highest return on
investment for pavements. Prior to implementing any maintenance, additional engineering
observation is recommended to determine the type and extent of preventive maintenance.
Portland Cement Concrete (PCC) pavements will require properly designed and constructed
joints to provide satisfactory performance. Refer to ACI 330, Guide for Design and Construction
of Concrete Parking Lots for information on design of joints for PCC pavements. Construction
traffic on the new pavements was not considered in developing the recommended minimum
pavement thicknesses. Construction traffic can cause significant damage to partially completed
pavement sections. If the new pavements will be subject to traffic by construction
equipment/vehicles, the pavement thicknesses should be revised to consider the effects of
additional traffic loading.
Related civil design factors such as subgrade drainage, shoulder support, cross sectional
configurations, surface elevations and environmental factors which will significantly affect the
service life must be included in the preparation of the construction drawings and specifications.
The above sections should be considered minimum pavement thicknesses and higher traffic
volumes and heavy trucks may require thicker pavement sections.
5.0 GENERAL COMMENTS
Terracon should be retained to review the final design plans and specifications so comments
can be made regarding interpretation and implementation of our geotechnical recommendations
in the design and specifications. Terracon also should be retained to provide observation and
testing services during grading, excavation, foundation construction and other earth- related
construction phases of the project.
Reliable a Responsive ra Convenient o Innovative 15
J 1
Geotechnical Engineering Report lierracon
Proposed AutoZone Store 3756 o Tigard, Oregon
April 15, 2010 o Terracon Project No. 82095068
The analysis and recommendations presented in this report are based upon the data obtained
from the borings performed at the indicated locations and from other information discussed in
this report. This report does not reflect variations that may occur between borings, across the
site, or due to the modifying effects of construction or weather. The nature and extent of such
variations may not become evident until during or after construction. If variations appear, we
should be immediately notified so that further evaluation and supplemental recommendations
can be provided.
The scope of services for this project does not include either specifically or by implication any
environmental or biological (e.g., mold, fungi, bacteria) assessment of the site or identification or
prevention of pollutants, hazardous materials or conditions. Terracon has been contracted to
perform a Phase I environmental assessment for the project site, and the results of this study
are being submitted under a separate cover.
This report has been prepared for the exclusive use of our client for specific application to the
project discussed and has been prepared in accordance with generally accepted geotechnical
engineering practices. No warranties, either express or implied, are intended or made. Site
safety, excavation support, and dewatering requirements are the responsibility of others. In the
event that changes in the nature, design, or location of the project as outlined in this report are
planned, the conclusions and recommendations contained in this report shall not be considered
valid unless Terracon reviews the changes and either verifies or modifies the conclusions of this
report in writing.
Reliable o Responsive a Convenient o Innovative 16
APPENDIX A
FIELD EXPLORATION
APPROXIMATE
LOCATION AND
EXTENT OF BLDG. TO
BE DEMOLISHED
FF = 103.4'
- -_I - --
PROPOSED BUILDING � �, ( I
60' 10' BACK ENTRANCE TO SW
Id PARK STREET —�
• L 0 1 l''
' �' 1 0
30' 03.0 j r F°
1 /F
i L14__
--
B-5 I ti -
I I A
,� ! 104.5 I 70 I ®i 13-7
I 25' * I I 101.5 A
I CPT -1 I 13-4
ilk ,�� 102
- 13 -3 . I _ . . . .
102:5 k I 75 1 \'‘,Y
I B-6 ` 1 �,
100.5
CB ( l
?a9'
—
---A BENCHMARK
4—_ SW PACIFIC HIGHWAY —..
Legend
ED B-1 Approximate Boring Location
103.5 and Surface Elevation, Feet
CPT -1 Approximate Cone Penetration
Test Location
Base Map: Referenced From AutoZone RFP
. Documents, Proposed Store 3756 Tigard, and
Catch Basin on Pacific Highway Modified by Terracon Consultants
Iil Benchmark – Assigned Elevation = 100.0', Terracon Site Datum
NOT TO SCALE TERRACON PROJECT NO.: 82095068
4, SITE AND EXPLORATION PLAN
1 i/ Proposed AutoZone Store 3756
13405 SW Pacific Highway
Tigard, OR 97223
April 2010
P %
LOG OF BORING NO. B -1 Page 1 of 1
CLIENT
AutoZone, Inc.
SITE 13405 SW Pacific Hwy PROJECT .
Tigard, Oregon Proposed AutoZone Store 3756
SAMPLES TESTS
O p 1 - o n
o DESCRIPTION w ° 1- z __- ce
o >_ o! W C z Z Z 0 m'
1 = fn W > Z (n OC W Z CY V)
0_ ~ CO m W O WZ >- Oct
w F-
w v a 0 a� Q 8 o
0 r
o Approx. Surface Elev.: 103.0 ft o S z L Pa m `i o a E
0.25 3" Asphalt over 6 -8" Gravel Base Course 103 —
1 over 102
;4 ;; FILL: SANDY SILT, brown -gray, stiff, — 1 SS 14 9 26 2500*
•• damp —
' • ' •∎∎, 3 100 — 2 SS 18 9 29 2500*
SILT, WITH SAND, brown, stiff, damp —
• 5 —ML 3 ST 4 32
7.5 95.5
SAND, WITH SILT, brown, loose, moist to _SM 4 SS 15 4 32 LL = 27
wet — PI = 2
- becomes wet 10 _ SM 5 SS 17 5
T.
- brown with black mottling 15 —SM 6 SS 16 7
—
- becomes medium dense 20 _SM 7 SS 16 13 36
:21.5 81.5
BOTTOM OF BORING
i.
m
Boring advanced using solid stem augers.
zb-
i-
0
0
Z
0
0
Q
x
K
W
F
0 The stratification lines represent the approximate boundary lines *Calibrated Hand Penetrometer
between soil and rock types: in -situ, the transition may be gradual. * *140H SPT Cathead
N WATER LEVEL OBSERVATIONS, ft BORING STARTED 7 -26 -09
WL SZ 9 WD 1 12.5 AB lierracon BORING COMPLETED 7-26-09
o
o WL Y 12 1HR RIG B.R. 160 DRILLER DFE
m�WL LOGGED BHS JOB # 82095068
f LOG OF BORING NO. B -2 Page 1 of 1
CLIENT
AutoZone, Inc.
SITE 13405 SW Pacific Hwy PROJECT
Tigard, Oregon Proposed AutoZone Store 3756
SAMPLES TESTS
J V
Q c F d en
DESCRIPTION 2 z = a
F ui
w w > zw aw _z LL a
w Q ~z } 0
a F cn CO w� w
o Approx. Surface Elev.: 103.0 ft o S z LcV can in o o a v~i o
rri 0.16 2" Asphalt over 10 "Gravel Base Course 103 —
„� 1 over 102
•• 1 SS 3 12 9
:•: FILL: SILTY GRAVEL, WITH SAND, —_
;.;.; b rown, medium dense, damp
te 3 100 — 2 SS 11 12 25
•. ❖. FILL: SANDY SILT, TRACE GRAVEL, —
A% brown, stiff, damp
.» 5 98 —
SILT WITH SAND, brown, medium stiff, 5 — ML 3 SS 18 7 28 2000*
damp to moist —
— ML 4 ST 21 33 88 2500* 3000
9.5 93.5
SILTY SAND, brown, loose, wet SZ 10
— SM 5 SS 17 4 37
t —
15 — SM 6 SS 17 7 32
. 20 — SM 7 SS 17 5
:; •:. —
:'. 21.5 81.5
BOTTOM OF BORING
m
Boring advanced using solid stem augers.
0
0
0
z
0
0
Q
K
uJ
W
F
5 The stratification lines represent the approximate boundary lines *Calibrated Hand Penetrometer
between soil and rock types: in -situ, the transition may be gradual. * *140H SPT Cathead
a
WATER LEVEL OBSERVATIONS, ft BORING STARTED 7 -26 -09
WL V- 10 WD 1 12 AB lierracon
BORING COMPLETED 7 -26 -09
Fi WL 51 11 5HR RIG B.R. 160 DRILLER DFE
m(WL LOGGED BHS JOB # 82095068
d .
e
LOG OF BORING NO. B -3 Page 1 of 1
CLIENT
AutoZone, Inc.
SITE 13405 SW Pacific Hwy PROJECT
Tigard, Oregon Proposed AutoZone Store 3756
• SAMPLES TESTS
0 d O-
DESCRIPTION _ F z =
wo
W w w Z Z0 CO
a H fn m w O Z Li) I- >- OO w
o Approx. Surface Elev.: 102.5 ft o S z 'k' Pr, m ' 8 o a r a
MI 0.21 2.5" Asphalt over 6 -7" Gravel Base Course 102.5
• 1 over 101.5
* A e FILL: SILT, WITH SAND, dark brown, stiff, — 1 SS 11 13 16
• + • 2.5 damp 100 —
SILT, WITH SAND, brown, stiff, damp _ ML 2 ST 18 24 93
3500*
_ ML 3 SS 15 10 27
5—
_ ML 4 SS 13 9 33 3000*
• - becomes medium stiff _ ML 5 SS 15 5 30 LL = 36
— PI =13
10 92.5
SILTY SAND, brown, loose, moist to wet 10 _SM 6 SS 17 4 32
SL _
Y _
- becomes wet 15 _ SM 7 SS 16 5
20 _ SM 8 SS 16 4
—
21.5 81
•
BOTTOM OF BORING
Boring advanced using solid stem augers.
F-
0
0 .
0
0
Q
K
CL
W
F
The stratification lines represent the approximate boundary lines *Calibrated Hand Penetrometer
between soil and rock types: in -situ, the transition may be gradual. * *140H SPT Cathead
0
N
N WATER LEVEL OBSERVATIONS, ft BORING STARTED 7 -26 -09
Eg WL V 11 WD T 13 AB 1 r�rr�c ®n BORING COMPLETED 7 -26 -09
o WL 1 12 2HR RIG B.R. 160 DRILLER DFE
w
m LOGGED BHS JOB # 82095068
LOG OF BORING NO. B-4 Page 1 of 1
CLIENT
AutoZone, Inc.
SITE 13405 SW Pacific Hwy PROJECT
Tigard, Oregon Proposed AutoZone Store 3756
SAMPLES TESTS cO
c OC
o DESCRIPTION CO i_ z = o
� W > zd) o w Z Zz w
o Approx. Surface Elev.: 102.0 ft o S z i- l aim ° o a o u
In Z
o o
0.16 2" Asphalt over 6 -7" Gravel Base Course 102 _
_ 1 over 101 — 1 SS 12 9 21
••••• FILL: SILT, TRACE SAND, TRACE
:4• 2 ROOTHAIRS, dark gray, stiff, damp 99 —
; FILL: SANDY SILT, brown -gray, stiff damp — 2 SS 12 22
• •
•;• ••
•�•�•
••• —
•:•:. 5
, ••••• 5.5 96.5 _ ML 3 SS 16 15 27
SILT, TRACE SAND, brown, stiff, damp —
29
_ ML 4 ST 10 32 89 1500*
8.5 93.5
, ;: SILTY SAND, brown, loose, damp to moist _ SM 5 SS 15 6 30
- becomes wet 5Z 10 _ SM 6 SS 18 6 30 44%
1 —
- becomes brown -gray 15 _SM 7 SS 15 7 33 48%
- very loose, wet 20 _ SM 8 SS 11 3 31 22%
o•': _SM 9 SS 15 3
• 78
—
8 BOTTOM OF BORING
0
0
a Boring advanced using solid stem augers.
cc
W
The stratification lines represent the approximate boundary lines `Calibrated Hand Penetrometer
0
between soil and rock types: in -situ, the transition may be gradual. **140H SPT Cathead
N
. E WATER LEVEL OBSERVATIONS, ft BORING STARTED 7 -26 -09
WL V 10.5 WD 1 13 AB 1 Yeast ®n BORING COMPLETED 7 -26 -09
o WL Z 12 4HR X RIG B.R. 160 DRILLER DFE
W
m`WL LOGGED BHS JOB # 82095068
1
LOG OF BORING NO. B -5 Page 1 of 1
CLIENT
AutoZone, Inc.
SITE 13405 SW Pacific Hwy PROJECT
Tigard, Oregon Proposed AutoZone Store 3756
SAMPLES TESTS
-J
o c o F- 0 0-
U DESCRIPTION z
cc
V) w > zu w zz
c m ww O W >- 0
W S z F- a �0 0 a 70)
Approx. Surface Elev.: 104.5 ft o S z wm
0.21 2 1/2" Asphalt over 3" Gravel Base Course 104.5
0.5 over 104 — ML 1 SS 13 8 26
SILT, WITH SAND, brown, medium stiff, —
damp _ ML 2 SS 15 9 28 2000*
- becomes brown -gray —
- becomes brown, damp to moist 5 _ ML 3 SS 15 7 29
97 4 SS 17 4 35
SAND, WITH SILT, brown, loose, moist — SM
- becomes wet 10 _ SM 5 SS 16 4
:11.5 93
BOTTOM OF BORING
Boring advanced using solid stem augers.
•
0
0
Z
0
0
uJ
W
P5 The stratification lines represent the approximate boundary lines `Calibrated Hand Penetrometer
between soil and rock types: in -situ, the transition may be gradual. * *140H SPT Cathead
WATER LEVEL OBSERVATIONS, ft BORING STARTED 7 -26 -09
WL S? 10 WD L 10 o AB lierracon
BORING COMPLETED 7 -26 -09
WL RIG B.R. 160 DRILLER DFE
WL LOGGED BHS JOB # 82095068
I 1
LOG OF BORING NO. B -6 Page 1 of 1
CLIENT
AutoZone, Inc.
SITE 13405 SW Pacific Hwy PROJECT
Tigard, Oregon Proposed AutoZone Store 3756
SAMPLES TESTS
0 o 5 O a
DESCRIPTION g >- z
z W Z z
~ to m W O F z >- w
o Approx. Surface Elev.: 100.5 ft o z r uai m 8 o a S c~n
mg 0.25 3" Asphalt over 11 -12" Gravel base Course 100.5 —
• over S? —
0 ,. t 1.5 99 • SANDY SILT, brown -gray, medium stiff, — ML 1 ST 18 23 103 4000*
wet - 3000`
— ML 2 SS 15 6 29 2000*
5 ML 3 SS 17 8 32 2500*
- becomes brown —
7.5 93
SILTY SAND, brown, loose, wet _SM 4 SS 15 6 34
10 —SM 5 SS 14 6
89
BOTTOM OF BORING
Boring advanced using solid stem augers.
•
0 0
0
N
0
0
Z
O
U
W
F-
The stratification lines represent the approximate boundary lines *Calibrated Hand Penetrometer
o between soil and rock types: in -situ, the transition may be gradual. **140H SPT Cathead
WATER LEVEL OBSERVATIONS, ft BORING STARTED 7 -26 -09
WL �? 1 WD 1 5 3HR ir erseon RIG BORING COMPLETED B.R. 160 DRILLER 7 -26
o WL � �
mo L LOGGED BHS JOB # 82095068
•
LOG OF BORING NO. B -7 Page 1 of 1
CLIENT
AutoZone, Inc.
SITE 13405 SW Pacific Hwy PROJECT
Tigard, Oregon Proposed AutoZone Store 3756
SAMPLES TESTS
0 o .E o H 0
o DESCRIPTION o -
. m F z
_ W w z 1-1- t_9
F (1) m w > i w D Ow
Fz )- U ce
o Ii Approx. Surface Elev.: 101.5 ft o z n w a Q o z
t rn � U a E U
0.25 3" Aphalt over 7" Gravel Base Course over 101.5 _
P. Mk'. 1 100.5
SANDY SILT, gray and brown, stiff, damp _ ML 1. SS 9 10 22
- brown to gray mottled, moist _ ML 2 SS 15 13 24
5 96.5
`: ; ;; SILTY SAND, brown, medium dense, 5 _ SM 3 SS 15 10 28
damp —
loose, damp to moist _SM 4 SS 18 6 31
- very loose, wet 10 _SM 5 SS 18 3
Q —
..'.11.5 90
BOTTOM OF BORING
Boring advanced using solid stem augers.
0
• •
0
0
0
0
0
Q
Lx
Lx
W
F
tt The stratification lines represent the approximate boundary lines *Calibrated Hand Penetrometer
fg 0
between soil and rock types: in -situ, the transition may be gradual. **140H SPT Cathead
N
R, WATER LEVEL OBSERVATIONS, ft BORING STARTED 7 -26 -09
WL Si 11 WD N/E AB lrerracon BORING COMPLETED 7-26-09
o WL Y RIG B.R. 160 DRILLER DFE
W
m LOGGED BHS JOB # 82095068
Subsurface Technologies
Operator: SAM CPT Date/Time: 9/4/2009 10:22:49 AM
Sounding: P -1 (CPT -1) Location: TIGARD AUTO ZONE
Cone Used: DSG0683 Job Number: 82095068
Tip Resistance Local Friction Friction Ratio Pore Pressure Diff PP Ratio Soil Behavior Type*
Qt TSF Fs TSF Fs /Qt ( %) Pw PSI (Pw- Ph) /Qt ( %) Zone: UBC -1983
0 250 0 5 0 10 -20 100 -20 100 0 12
0 IIl I I II
II
II
II
11
2 l
1
e I
5 r - --i — y - t - r - -H -1) rrr- r -i - - +
- r - - +- a:•+ r1ry +r
( iP.
1
111 1 )
10 - - + --- r -- - t - - - - - -- - - 1 - + -r- '-- 1 L1-4 - - + — 1- r - + n�`'e'i - F ry +r
I
1
I i „..,,,
1
3
a0a,. =i I
„,„,_:„„..,
;fa riot
20 — - - H-- 1- - - - - -- 4_1 - + -H_ - 1- :- 1 4 +HH 4
- - H „ - -+- Hi - - +- ' . 1 +1-
,,
\,
mat
Depth • 1 k
(ft) aIi p
98
25 — H
l -_ _ - -_____ -II- -+ -H- 3-11 1-•+i -H- --i 1 -i__ +- _Hi - - + - 1
4-+1 -
1 + 4D ei x
4141: OA
I I I !
30
�f (( 5 ' 1
'
1
11 I
J I
�I 1 E k
-4-1 ■ V
it
L y
I Q e 40 — — , Yxr #
,
�I i
rIT
I
r1 fr { asa p
F (1pr r
J I
> 1 I b,9 is
_ '� J� 1, h�c��r
45 _ —_
Maximum Depth = 44.95 feet Depth Increment = 0.328 feet
El 1 sensitive fine grained 1 4 silty clay to clay 1 7 silty sand to sandy silt 1 10 gravelly sand to sand
2 organic material 5 clayey silt to silty clay ri 8 sand to silty sand rei 11 very stiff fine grained ( *)
® 3 clay 16 sandy silt to clayey silt G 9 sand 1 12 sand to clayey sand ( *)
"Soil behavior type and SPT based on data from UBC -1983
s
Subsurface Technologies
Operator: SAM CPT Date/Time: 9/4/2009 10:22:49 AM
Sounding: P -1 (CPT -1) Location: TIGARD AUTO ZONE
Cone Used: DSG0683 Job Number: 82095068
Tip Resistance Soil Behavior Type* SPT N* Seismic Delay Seismic Velocity
Qt TSF Zone: UBC -1983 60% Hammer (milliseconds) (ft/s)
0 250 0 12 0 50 0 60 0 1200
0
1 1 I 1
I 1 I I
I I 1 I
t I I 1 .
Iiii
L
5 — � - 1-------- r-- - + - - -- - a *,,- i- I- t-r+ +r - r+- t- I -1-1-I - -- — 1- -- -1-t-1- - — r- - -t - + -r-
::zitx H7
11 05 630.0525
l I
RIP
f z 1
10 1________ +____ aria,P ylltrr --1- 1111y___ - - 1 - + - r - - r 1I - r_
,
I
IL 19.0 584.08
II I
sUals
nA
¢l C�, tt rt I
t Z
4
J t 1 30.27 7673 5565r
20 71 -/-i 1- + +r —+ 111 -1 - -- — 1--- - I - + - r — — I --- 1 - + - r —
e p I, fl 1
I
116.9
;ei
Depth -'o ,`
, tin
1
— �
25 -------- r - + - --- + +r �+ 1 1 1 — �--
- -- - i - + - r —
— 1--- 1 = + - r—
39.8 L 1794.8819
/ I
C` 3} � 1 I
I
I
30 4 I + 11 + +r _+ 1-I-I —, 1 + -1-- —�
i
f 9 1 i 1
I
..1 L` r�
I —
47.77 9 36.0236
eitti
6 e
1
35 - - -'�F I - + - - -- _i i +A-I- + + - — I-- 4- + - — I - -I - - t--
WOli
6 6}
, � 0. .. " 54.68 133.924
7 +.
40 _ 1_ L - 1.1 +LI- —A- +44 -I-1 -- —~ -- - "4 -l"— —I-' -- -y -t' 1
i
I
I ti e
g L,7R 1 1
1 n rfi A ifn I i
;i ■ , I
a ,,ti6rr -
i , _11 i
45 �. � � 59.84
Maximum Depth = 44.95 feet Depth Increment = 0.328 feet
0 1 sensitive fine grained E 4 silty clay to clay 0 7 silty sand to sandy silt 0 10 gravelly sand to sand
2 organic material 0 5 clayey silt to silty clay E 8 sand to silty sand El 11 very stiff fine grained ( *)
■ 3 clay • 6 sandy silt to clayey silt - 9 sand II 12 sand to clayey sand ( *)
*Soil behavior type and SPT based on data from UBC -1983
' r
Geotechnical Engineering Report - UPDATED ��
Proposed AutoZone Store 3756 a Tigard, Oregon
April 15, 2010 a Terracon Project No. 82095068
Field Exploration Description
The boring and cone penetration test (CPT) locations were selected by AutoZone and marked in
the field by Terracon personnel. The approximate boring and CPT locations are indicated on the
attached Site and Exploration Plan. Distances from the boring and CPT locations to the
reference features shown on the attached diagram are approximate and were measured with a
tape. Right angles for the boring and CPT location measurements were estimated.
The drill crew obtained the elevations at the boring locations using a surveyor's rod and level.
The elevations were referenced to catch basin rim located on the north side of Pacific Highway,
as shown on the Site and Exploration Plan. For the purposes of this report, we assigned this
benchmark an elevation of 100.0 feet, Terracon site datum. The elevations, rounded to the
nearest 1/2 -foot, are shown on the boring logs and Location Diagram. The locations of the
borings should be considered accurate only to the degree implied by the means and methods
used to define them.
The borings were drilled with a trailer- mounted rotary drill rig using continuous flight solid -stem
augers to advance the boreholes. Samples of the soil encountered in the borings were obtained
using the split barrel sampling procedures, and undisturbed samples were obtained using Shelby
tubes.
In the split - barrel sampling procedure, the number of blows required to advance a standard 2 -inch
O.D. split - barrel sampler the last 12 inches of the typical total 18 -inch penetration by means of a
140 -pound C.M.E. auto - hammer with a free fall of 30 inches, is the standard penetration
resistance value (SPT -N). This value is used to estimate the in -situ relative density of
cohesionless soils and consistency of cohesive soils.
Undisturbed samples were obtained by pushing a 3 -inch outside diameter, seamless steel
Shelby tube into the soil using the hydraulic system on the drill rig in accordance with ASTM:
D1587. Since the thin wall tube is pushed rather than driven, the sample obtained is considered
to be relatively undisturbed. The samples were classified in the field by examining the ends of
the tube prior to sealing with plastic caps. The samples were then transported to our laboratory
where they were extruded for further classification and laboratory testing.
A hammer operated with a cathead and rope SPT hammer was used to advance the split - barrel
sampler in the borings performed on this site. A lower efficiency is achieved with a safety hammer
operated with a cathead and rope hammer compared to an automatic hammer. This lower
efficiency has an appreciable effect on the SPT -N value. The effect of the cathead hammer's
efficiency has been considered in the interpretation and analysis of the subsurface information for
this report.
The samples from the borings were tagged for identification, sealed to reduce moisture loss, and
taken to our laboratory for further examination, testing, and classification. Information provided on
Exhibit A -1
•
the boring logs attached to this report includes soil descriptions, consistency evaluations, boring
depths, sampling intervals, and groundwater conditions. The borings were backfilled with bentonite
per applicable state regulations.
A field log of each boring was prepared by the Field Geotechnical Engineer. These logs included
visual classifications of the materials encountered during drilling as well as the engineers'
interpretation of the subsurface conditions between samples. Final boring logs included with this
report represent the engineer's interpretation of the field logs and include modifications based on
laboratory observation and tests of the samples.
Subsurface Technologies, Inc., an independent firm working under subcontract to Terracon,
performed Cone Penetration Test (CPT) at the site on September 4, 2009. The CPT probes were
advanced using a truck mounted rig. A CPT is completed by pushing a probe (Type DSG0683)
with a conical tip into the soil at a constant rate, and measuring the penetration resistance of the
cone and the friction resistance on a friction sleeve. A continuous log of the probe hole was
obtained. Soil descriptions presented on the CPT log are based on interpretations of the cone
data at specific exploration locations. Pore water pressure dissipation and seismic tests were
performed throughout the depths tested. The probe hole was backfilled with bentonite slurry
after completion. Results of the CPT are presented in this appendix.
a
APPENDIX B
LABORATORY TESTING
n .
Geotechnical Engineering Report - UPDATED 1 r�rr�c ®n
Proposed AutoZone Store 375613 Tigard, Oregon
April 15, 2010 o Terracon Project No. 82095068
Laboratory Testing
As a part of the laboratory testing program, the soil samples were classified in the laboratory
based on visual observation, texture, plasticity, and the limited laboratory testing described
above. The soil descriptions presented on the boring logs for native soils are in accordance
with our enclosed General Notes and Unified Soil Classification System (USCS). The estimated
group symbol for the USCS is also shown on the boring logs, and a brief description of the
Unified System is included in this report. Moisture content tests, Atterberg limits, 200 wash, and
dry unit weights were completed on select thin - walled tube samples in the laboratory. The
unconfined compressive strength of moderately cohesive soil samples were estimated using a
hand penetrometer. Results of the laboratory tests are presented on the boring logs.
• , w
Sheet 1 of 1
Depth Liquid Plastic Plasticity Maximum %< #200 USCS Water Dry Unit Satur- Void
Borehole Size Class- Content Weight ation
ft Limit Limit Index Sieve o o) Ratio
(mm) ification (/o ) (p cf) (/o
B -1 1.0 26.4
B -1 2.5 29.4
B -1 5.0 32.1
B -1 7.5 27 25 2 32.0
B -1 20.0 36.0
B -2 1.0 9.3
B -2 2.5 25.0
B -2 5.0 27.7
B -2 7.5 32.7 88.1
B -2 10.0 36.8
B -2 15.0 31.7
B -3 1.0 16.4
B -3 2.5 23.9 92.9
B -3 4.0 27.0
B -3 5.5 32.8
B -3 7.5 36 23 13 29.6
B -3 10.0 31.9
B-4 1.0 20.6
B-4 2.5 22.2
B-4 5.0 27.1
B-4 6.0 29.1
B-4 7.5 31.9 89.1
B-4 8.5 30.1
B-4 10.0 0.075 44 29.8
B-4 15.0 0.075 48 33.0
B -4 20.0 0.075 22 31.3
B -5 0.5 26.1
B -5 2.0 28.2
B -5 5.0 28.9
B -5 7.0 34.5
B -6 1.5 23.4 103.1
B -6 3.5 29.4
B -6 5.0 32.1
B -6 7.5 33.8
B -7 1.0 21.7
B -7 2.5 23.8
H
B -7 5.0 27.6
z
8 B -7 7.5 31.3
0
0
w
W
N
0 (7
0
N
01
SUMMARY OF LABORATORY RESULTS
Project: Proposed AutoZone Store 3756
1 lrerracon Site: 13405 SW Pacific Hwy Tigard, Oregon
Q Job #: 82095068
J
0 Date: 8 -5 -09
APPENDIX C
SUPPORTING DOCUMENTS
•
GENERAL NOTES
DRILLING & SAMPLING SYMBOLS:
SS: Split Spoon -1 3 /8" I.D., 2" O.D., unless otherwise noted HS: Hollow Stem Auger
ST: Thin - Walled Tube - 2" O.D., unless otherwise noted PA: Power Auger
RS: Ring Sampler - 2.42" I.D., 3" O.D., unless otherwise noted HA: Hand Auger
DB: Diamond Bit Coring - 4 ", N, B RB: Rock Bit
BS: Bulk Sample or Auger Sample WB: Wash Boring or Mud Rotary
The number of blows required to advance a standard 2 -inch O.D. split -spoon sampler (SS) the last 12 inches of the total 18 -inch
penetration with a 140 -pound hammer falling 30 inches is considered the "Standard Penetration" or "N- value ".
WATER LEVEL MEASUREMENT SYMBOLS: •
WL: Water Level WS: While Sampling N /E: Not Encountered
WCI: Wet Cave in WD: While Drilling
DCI: Dry Cave in BCR: Before Casing Removal
AB: After Boring ACR: After Casing Removal
Water levels indicated on the boring logs are the levels measured in the borings at the times indicated. Groundwater levels at other
times and other locations across the site could vary. In pervious soils, the indicated levels may reflect the location of groundwater. In
low permeability soils, the accurate determination of groundwater levels may not be possible with only short -term observations.
DESCRIPTIVE SOIL CLASSIFICATION: Soil classification is based on the Unified Classification System. Coarse Grained Soils have
more than 50% of their dry weight retained on a #200 sieve; their principal descriptors are: boulders, cobbles, gravel or sand. Fine
Grained Soils have less than 50% of their dry weight retained on a #200 sieve; they are principally described as clays if they are plastic,
and silts if they are slightly plastic or non - plastic. Major constituents may be added as modifiers and minor constituents may be added
according to the relative proportions based on grain size. In addition to gradation, coarse- grained soils are defined on the basis of their
in -place relative density and fine- grained soils on the basis of their consistency.
CONSISTENCY OF FINE - GRAINED SOILS RELATIVE DENSITY OF COARSE - GRAINED SOILS
Standard
Unconfined Penetration or Standard Penetration
Compressive N -value (SS) or N -value (SS)
Strength, Qu, psf Blows /Ft. Consistency Blows /Ft. Relative Density
< 500 0 - 1 Very Soft 0 — 3 Very Loose
500 — 1,000 2 - 4 Soft 4 — 9 Loose
1,000 — 2,000 4 - 8 Medium Stiff 10 — 29 Medium Dense
2,000 — 4,000 8 - 15 Stiff 30 — 49 Dense
4,000 — 8,000 15 - 30 Very Stiff > 50 Very Dense
8,000+ > 30 Hard
RELATIVE PROPORTIONS OF SAND AND GRAVEL GRAIN SIZE TERMINOLOGY •
Descriptive Term(s) of other Percent of Major Component
constituents Dry Weight of Sample Particle Size
Trace < 15 Boulders Over 12 in. (300mm)
With 15 — 29 Cobbles 12 in. to 3 in. (300mm to 75 mm)
Modifier > 30 Gravel 3 in. to #4 sieve (75mm to 4.75 mm)
Sand #4 to #200 sieve (4.75mm to 0.075mm)
RELATIVE PROPORTIONS OF FINES Silt or Clay Passing #200 Sieve (0.075mm)
Descriptive Term(s) of other Percent of PLASTICITY DESCRIPTION
constituents Dry Weight
Term Plasticity Index
Trace < 5 Non - plastic 0
With 5 —12 Low 1 -10
Modifiers > 12 Medium 11 -30
High > 30
1[erracon_
.. , y
UNIFIED SOIL CLASSIFICATION SYSTEM
Criteria for Assigning Group Symbols and Group Names Using Laboratory Tests" Soil Classification
Group
Symbol Group Name'
Coarse Grained Soils Gravels Clean Gravels Cu z 4 and 1 5 Cc 5 3 GW Well- graded gravel`
More than 50% retained More than 50% of coarse Less than 5 %fines° Cu < 4 and /or 1 > Cc > 3 GP Poorly graded gravel'
fraction retained on
on No. 200 sieve No. 4 sieve Gravels with Fines More Fines classify as ML or MH GM Silty graver 0 "
than 12 %fines° Fines classify as CL or CH GC Clayey gravel 0H
Sands Clean Sands Cu z 6 and 1 <- Cc <_ 3 SW Well- graded sand'
50% or more of coarse Less than 5% fines° Cu < 6 and /or 1 > Cc > 3 SP Poorly graded sand'
fraction passes
No. 4 sieve Sands with Fines Fines classify as ML or MH SM Silty sand "'
More than 12% fines Fines Classify as CL or CH SC Clayey sands "'
Fine - Grained Soils Silts and Clays inorganic PI > 7 and plots on or above "A" line' CL Lean clay M
50% or more passes the Liquid limit less than 50 PI < 4 or plots below "A" line' ML SIIt
No. 200 sieve
organic Liquid limit - oven dried "
< 0.75 OL Organic clay` M"
Liquid limit - not dried Organic silt
Silts and Clays inorganic PI plots on or above "A" line CH Fat clay - ' M
Liquid limit 50 or more K L,M
PI plots below "A" line MH Elastic Silt
organic Liquid limit - oven dried <0.75 OH Organic clay<LMM'
Liquid limit - not dried Organic siltK.L.M
Highly organic soils Primarily organic matter, dark in color, and organic odor PT Peat
" Based on the material passing the 3 -in. (75 -mm) sieve "If fines are organic, add "with organic fines" to group name.
E If field sample contained cobbles or boulders, or both, add "with cobbles ' If soil contains ? 15% gravel, add "with gravel" to group name.
or boulders, or both" to group name. ' If Atterberg limits plot in shaded area, soil is a CL -ML, silty clay.
C Gravels with 5 to 12% fines require dual symbols: GW -GM well - graded K If soil contains 15 to 29% plus No. 200, add "with sand" or "with
gravel with silt, GW -GC well - graded gravel with clay, GP -GM poorly gravel," whichever is predominant.
graded gravel with silt, GP -GC poorly graded gravel with clay.
L If soil contains >_ 30% plus No. 200 predominantly sand, add
° Sands with 5 to 12% fines require dual symbols: SW -SM well - graded "sandy" to group name.
sand with silt, SW -SC well - graded sand with clay, SP -SM poorly graded nn o
sand with silt, SP -SC poorly graded sand with clay If soil contains ? 30 /° plus No. 200, predominantly gravel, add
"gravelly" to group name.
E CU = 060/D10 Cc = (D30) "PI >_ 4 and plots on or above "A" line.
D10 x D60 ° PI < 4 or plots below "A" line.
F If soil contains >_ 15% sand, add with sand" to group name. P PI plots on or above "A" line.
° If fines classify as CL -ML, use dual symbol GC -GM, or SC -SM. ° PI plots below "A" line.
60 r - i i i — 1 -'
For classification of fine - grained
soils and fine - grained fraction ,
_ of co arse - grained soils __'____^ J am? /_ ` `c e
50 V - --
Equation of "A" - line o-• ,'' I .•P
d Horizontal at PI =4 to LL =25.5. 1 I I
\X
110.-i X 40 !— then PI =0.73 (LL -20) • 0 ~
Ca
ILI Equation of "U" -line `
Vertical at LL =16 to P1=7. ,
Z
30 f then PI =0.9 (LL -8) -' I_ — G - ` -_ I � ,
F I- I I I ,' .,°- ;
Q 20 i- - - - -:- __ G - - -__ ; - - -
1 a '
MH or OH
� _ ... — . _- - - - -� _
7 I
I ML or OL I '
0 10 16 20 . 30 40 50 60 70 80 90 100 110
LIQUID LIMIT (LL)
lrerracon
_
Form 111 -6/98