Report GEODESIGN, INC.
GEOTECHNICAL, ENVIRONMENTAL, AND GEOLOGICAL CONSULTANTS
/35 - 5 N5- 791
REPORT OF
GEOTECHNICAL ENGINEERING SERVICES
72n Avenue Office Buildings
Tigard, Oregon
GDI Project: PNWP -18
For
Pacific Northwest Properties
17400 SW Upper Boones Ferry Rd., Suite 230 • Portland, Oregon 97224 • Phone (503) 968 -8787 • Fax (503) 968 -3068
GEODESIGN, INC.
GEOTECHNICAL, ENVIRONMENTAL, AND GEOLOGICAL CONSULTANTS
October 26, 1999
Pacific Northwest Properties
9665 SW Allen Boulevard, Suite 115
Beaverton, Oregon 97005
Attention: Mr. Paul Gram
Report of Geotechnical Engineering Services
72n Avenue Office Buildings
Tigard, Oregon
GDI Project: PNWP -18
GeoDesign, Inc. is pleased to submit four copies of our "Report of Geotechnical
Engineering Services" for the proposed 72" Avenue Office Buildings to be constructed in
Tigard, Oregon. Our services for this project were conducted in accordance with our
August 20, 1999 proposal.
We appreciate the opportunity to be of service to Pacific Northwest Properties. Please call
if you have questions regarding this report.
Sincerely,
GeoDesign, Inc.
A e_6 1 ),„..5 4 w - �
George Saunders, P.E.
Principal
cc: Mr. Gene Mildren, Mildren Design Group, P.C. (3 bound & 1 unbound copies)
Mr. Brian DeHaas, WRG Design, Inc. (1 bound copy)
RKW:GPS:kt Attachments
Document ID: PNWP -18 -geor Four copies submitted
17400 SW Upper Boones Ferry Rd., Suite 230 • Portland, Oregon 97224 • Phone (503) 968 -8787 • Fax (503) 968 -3068
Table of Contents Page No.
INTRODUCTION 1
PURPOSE AND SCOPE 1
SITE CONDITIONS 2
Surface Conditions 2
Subsurface Conditions 2
CONCLUSIONS AND RECOMMENDATIONS 3
General 3
Site Preparation and Erosion Control 3
Construction Considerations 4
Structural Fill 4
Cement Amendment 5
Permanent Slopes 5
Shallow Foundations 6
Floor Slabs 6
Pavement Recommendations 7
Utility Trenches 8
Retaining Structures 8
Site Drainage 9
Seismic Design 10
OBSERVATION OF CONSTRUCTION 10
LIMITATIONS 10
FIGURES
Vicinity Map Figure 1
Site Plan Figure 2
APPENDIX A
Field Explorations A -1
Laboratory Testing A -1
Key to Test Pit and Boring Log Symbols Table A -1
Soil Classification System and Guidelines Table A -2
Logs of Test Pits Figure A -1
GeoDesign, Inc. i PNWP- 18:102699
Report of Geotechnical Engineering Services
Proposed 72 Avenue Office Buildings
Tigard, Oregon
INTRODUCTION
This report presents the results of GeoDesign's geotechnical engineering evaluation of the
site of the proposed 72n Avenue Office Buildings. The approximately 2.6 -acre site is
located at the northwest corner of SW Cherry Drive and SW 72n Avenue in Tigard,
Oregon. The general location of the site relative to surrounding physical features is shown
in Figure 1.
We understand that the project will consist of constructing two (2) one -story, concrete tilt -
up buildings with slab -on -grade floors, and appurtenant paving and utilities. We have
assumed that column Toads will be less than about 150 kips and wall loads will be Tess than
about 4.5 kips per linear foot, which is typical for concrete tilt -up construction. Sustained
floor slab live loads will be less than about 300 pounds per square foot (psf).
PURPOSE AND SCOPE
The purpose of our services was to explore the subsurface conditions at the site to provide
the basis for geotechnical recommendations for site development. Our specific scope of
work included the following:
• Coordinate and manage the field investigation, including site access authorizations and
scheduling of subcontractors and GeoDesign field staff.
• Explore subsurface conditions by excavating 11 test pits to depths of up to 14.0 feet or
to refusal using a conventional rubber -tired backhoe.
• Obtain soil samples at select depths in the test pit excavations.
• Classify the materials encountered in the test pits. Maintain a detailed log of each
exploration. Observe groundwater conditions in the explorations.
• Determine the natural moisture content and density of select samples obtained from the
explorations.
• Provide recommendations for site preparation, grading and drainage, stripping depths,
fill type for imported materials, compaction criteria, trench excavation and backfill, use
of on -site soils, and wet/dry weather earthwork.
• Provide recommendations for design and construction of shallow spread foundations,
including allowable design bearing pressure and minimum footing depth and width.
• Provide recommendations for preparation of floor slab subgrade.
• Recommend design criteria for retaining walls, including lateral earth pressures,
backfill, compaction, and drainage.
• Provide recommendations for the management of identified groundwater conditions
that may affect the performance of structures or pavement.
GeoDesign, Inc. 1 PNWP- 18:102699
• Provide recommendations for construction of asphalt pavements for on -site access
roads and parking areas, including subbase, base course, and asphalt paving
thickness.
• Provide recommendations for subsurface drainage of foundations and roadways, as
necessary.
• Provide a written report summarizing the results of our geotechnical evaluation.
SITE CONDITIONS
SURFACE CONDITIONS
The approximately 2.6 -acre site is located '/4 mile south of Highway 217 at the northwest
corner of SW Cherry Drive and SW 72' Avenue in Tigard, Oregon. The site slopes down
about 14 feet to the west from SW 72n Avenue and approximately 24 feet down to SW
Cherry Street to the south. There are currently two houses and two detached garages in
the northeast portion of the site. A house previously located at the southeast comer of the
site has been demolished with signs of the foundation still visible. The remainder of the
site is covered with grass. Large deciduous and evergreen trees are present around the
house at the north end of the site and occasionally in other areas.
SUBSURFACE CONDITIONS
We explored subsurface conditions at the site by excavating 11 test pits (TP -1 through
11) to depths of up to 14.0 feet below the existing ground surface. The approximate
locations of the test pit excavations are shown in Figure 2.
We tested selected soil samples from the explorations to determine the natural moisture
content and dry density of the soils. Descriptions of the field explorations, exploration Togs,
and laboratory procedures are included in Appendix A.
We encountered relatively consistent subsurface conditions in the explorations.
Subsurface materials at the site consist of 8 to 12 feet of stiff to very stiff silt underlain by
medium dense to dense sand with varying amounts of silt. In Test Pits TP -1 to TP -5 we
encountered a Tens of weak siltstone and partially cemented sand. However, this material
was easily excavated with the backhoe. In addition, we observed between 3 and 5 feet of
silt and gravel fill in Test Pits TP-4 and TP -5. We met practical refusal in TP -10 when we
encountered a large boulder at approximately 11 feet.
We observed slow groundwater seepage at depths of approximately 11.5 to 14 feet in Test
Pits TP -1, TP-4, TP -6, and TP -9. Groundwater seepage was not observed in the
remaining explorations. Slight caving was observed in Test Pit TP -1 below 10.0 feet.
GeoDesign. Inc. 2 PNWP- 18:102699
CONCLUSIONS AND RECOMMENDATIONS
GENERAL
Based on the results of our explorations, laboratory testing, and analyses, it is our opinion
that the proposed structures, with the building Toads as previously stated, can be supported
on shallow footings bearing on the medium stiff to stiff silts, or on structural fill that is
properly installed during construction. The following paragraphs present specific
geotechnical recommendations for design and construction of the proposed development.
SITE PREPARATION AND EROSION CONTROL •
Based on our site plan, the existing structures will need to be removed prior to developing
the site. All demolition debris and foundation elements, including those associated with the
previously demolished dwells, should be removed prior to site grading. A member of our
geotechnical staff should observe the exposed subgrade to determine if there are areas of
unsuitable soil that may require overexcavation. Basement cavities (if present) and
excavations formed by removal of unsuitable material, should be backfilled with structural
fill.
Trees should be removed from all building and paved areas. In addition, root balls should
be grubbed out to the depth of the roots, which could exceed 2 feet below the ground
surface. Depending on the methods used to remove the root balls, considerable
disturbance and loosening of the subgrade could occur during site grubbing. We
recommend that soil disturbed during grubbing operations be removed to expose firm
undisturbed subgrade. The resulting excavations should be backfilled with structural fill. If
grubbing activities disturb less than a 12 -inch depth of soil and the earthwork is being
completed in the drier summer period, the material can be scarified, moisture - conditioned,
and compacted in place.
The existing topsoil, where it exists, and the thick root zone should be stripped and
removed from the site in all proposed building and pavement areas and for a 5 -foot margin
around such areas. Based on our explorations, the depth of stripping will be approximately
4 to 6 inches, although greater stripping depths may be required to remove localized zones
of loose or organic soil. Greater stripping depths should be expected in the eastern third of
the site and areas of the site that are heavily treed. Actual stripping depths should be
based on field observations at the time of construction. Stripped material should be
transported off -site for disposal or used in landscaped areas.
After demolition, stripping and required site cutting have been completed, we recommend
proofrolling the subgrade with a fully - loaded dump truck or similar -size, rubber -tire
construction equipment to identify areas of excessive yielding. A member of our
geotechnical staff, who will evaluate the subgrade, should observe the proofrolling. If areas
of excessive yielding are identified, the material should be excavated and replaced with
structural fill. Areas that appear to be too wet and soft to support proofrolling equipment
should be prepared in accordance with the recommendations for wet weather construction.
GeoDesign, Inc. 3 PNWP- 18:102699
The test pit excavations were backfilled using the relatively minimal compactive effort of the
backhoe bucket and soft spots can be expected at these locations. In pavement and floor
slab areas, we recommend that a minimum of 3 feet of the backfilled material be removed
and the resulting excavation backfilled with structural fill. We recommend that the full depth
of the backfill be removed and replaced with structural fill if the test pit is located within 2
feet of a footing.
Silt fences, hay bales, buffer zones of natural growth, sedimentation ponds, and granular
haul roads should be used as required to reduce sediment transport during construction to
acceptable levels. Measures to reduce erosion should be implemented in accordance with
Oregon Administrative Rules 340-41 -006 and 340 - 41-455 the City of Tigard and
Washington County regulations regarding erosion control.
CONSTRUCTION CONSIDERATIONS
Trafficability of the silty areas of the site will be difficult during or after extended wet
periods. When wet, the silty surficial soils are easily disturbed and will not provide adequate
support for construction equipment. Proofrolling of the subgrade should not be performed
during wet weather or if wet ground conditions exist. Instead, the subgrade should be
evaluated by probing. Soils that have been disturbed during site preparation activities, or
soft or loose zones identified during probing, should be removed and replaced with
compacted structural fill.
Haul roads subject to repeated construction traffic will require a minimum of 18 inches of
imported granular material or 16 inches of cement amended soil (see "Cement
Amendment" section of this report) overlain by a crushed rock wearing course. For Tight
staging areas 12 inches of imported granular material should be sufficient. The imported
granular material should consist of crushed rock that is well- graded and has less than 8
percent by weight passing the U.S. Standard No. 200 Sieve. A geosynthetic should be
placed in the haul roads below the granular material and should have a minimum Mullen
burst strength of 250 pounds per square inch (psi) for puncture resistance and an apparent
opening size (AOS) between an U.S. Standard No. 70 and No. 100 Sieve.
We recommend that 3 to 4 inches of imported granular material be placed in the bottom of
footing excavations in wet weather conditions. The granular material reduces subgrade
disturbance, prevents water softening of the upper surface, and provides a clean
environment for reinforcing steel.
STRUCTURAL FILL
On -site Materials
The on -site soils are suitable for use as structural fill. However, the silty soils at the site are
sensitive to small changes in moisture content and are highly susceptible to disturbance
when wet. Laboratory testing indicates that the moisture content of the on -site silt is
greater than the anticipated optimum moisture content required for satisfactory compaction.
Therefore, moisture conditioning will be required to achieve adequate compaction. We
recommend using imported granular material for structural fill if the on -site materials cannot
be properly moisture - conditioned. As an altemative, use of the on -site silt for structural fill
GeoDesign. Inc. 4 PNWP- 18:102699
may be acceptable if it is properly amended with portland cement or lime. When used as
structural fill, the on -site silty material should be placed in lifts with a maximum
uncompacted thickness of 6 to 8 inches. The silt should be compacted to not less than 92
percent of the maximum dry density, as determined by American Society for Testing and
Materials (ASTM) D 1557.
If construction is planned for the wet season then careful consideration of the construction
methods and schedule should be made to reduce overexcavation of disturbed site soils,
and the project budget should reflect the recommendations for wet weather construction
contained in this report.
Imported Granular Material
If imported granular material is used as structural fill, this material should consist of pit or
quarry run rock, crushed rock, or crushed gravel and sand that is fairly well- graded
between coarse and fine, contains no organic matter or other deleterious materials, has a
maximum particle size of 3 inches, and has less than 5 percent passing the U.S. Standard
No. 200 Sieve. The percentage of fines can be increased to 12 percent of the material
passing the U.S. Standard No. 200 Sieve if placed during dry weather. Imported granular
material should be moisture - conditioned to the approximate optimum moisture content,
placed in 12- inch -thick lifts, and compacted to not less than 95 percent of maximum dry
density as determined by ASTM D 1557.
CEMENT AMENDMENT
As an alternative to the use of imported granular material for structural fill, working
blankets, and haul roads, an experienced contractor may be able to amend the on -site soils
with portland cement to obtain suitable support for fill operations and /or support of
construction equipment. Based on the moisture contents, soil type, and processing speed,
cement amendment would be more suitable at this site than lime amendment.
Successful use of soil amendment depends on use of correct techniques and equipment,
soil moisture content, and the amount of portland cement added to the soil.
Recommended cement percentages are based on soil moisture contents at the time of
placing the structural fill. Based on our tests and experience, about 4 percent by dry
weight of soil can generally be used when the soil moisture content does not exceed
approximately 25 percent. If the soil moisture content is in the range of 25 to 35 percent,
we recommend 5 to 6 percent cement by weight of dry soil. It is difficult to accurately
predict field performance due to the variability in soil response to portland cement
amendment. The percentage of cement may need to be adjusted based on field
observations and performance. For preliminary design purposes, we recommend a
minimum of 5 percent cement and a treatment depth of 12 inches. At this site, 5 percent
cement would correspond to about 4.8 pounds of cement per square foot, for a 12 -inch
treatment depth.
PERMANENT SLOPES
Permanent cut and fill slopes should not exceed 2H:1V (horizontal to vertical). Buildings,
access roads, and pavements should be located at least 5 feet from the top of cut and fill
GeoDesign. Inc. 5 PNWP- 18:102699
slopes. The slopes should be planted with appropriate vegetation to provide protection
against erosion as soon as possible after grading. Surface water runoff should be collected
and directed away from slopes to prevent water from running down the face of the slope.
SHALLOW FOUNDATIONS
We recommend that spread footings bear on the very stiff silt, or structural fill that is
properly installed during construction and underlain by undisturbed native materials.
Spread footings should have a minimum width of 24 inches, with the base of the footings
founded at least 12 and 18 inches below the lowest adjacent grade for interior and exterior
footings, respectively. Continuous wall footings should have a minimum width Of 18 inches,
and be founded a minimum of 18 inches below the lowest adjacent grade.
Bearing Pressure and Settlement
Footings with the preceding loads and founded as recommended should be proportioned
for a maximum allowable soil bearing pressure of 2,500 psf. This bearing pressure is a net
bearing pressure and applies to the total of dead and long -term live loads and may be
increased by 1/3 when considering earthquake or wind loads. The weight of the footing
and overlying backfill can be ignored in calculating footing loads.
For a 2,500 psf design bearing pressure, total settlement of footings is anticipated to be
less than about 1 -inch for the building loads discussed above. Differential settlements
should not exceed 'h -inch.
Lateral Capacity
We recommend using a passive pressure of 250 pounds per cubic foot (pcf) for design
purposes for footings confined by native silt or structural fill. In order to develop this
capacity, concrete must be poured neat in excavations or the adjacent confining structural
fill must consist of granular soils compacted to 95 percent relative to ASTM D 1557.
Adjacent floor slabs, pavements, or the upper 12 -inch depth of adjacent, unpaved areas
should not be considered when calculating passive resistance.
A coefficient of friction equal to 0.35 may be used when calculating resistance to sliding on
silt subgrades.
FLOOR SLABS
Satisfactory subgrade support for building floor slabs supporting up to 300 psf areal loading
can be obtained from the stiff native silt, or from structural fill, when prepared in
accordance with the recommendations presented in the "Site Preparation" and "Structural
Fill" sections of this report. A minimum 6- inch -thick layer of base rock should be placed
over the prepared subgrade to assist as a capillary break. A subgrade modulus of 250
pounds per cubic inch can be used for the design of the floor slab. Floor slabs constructed
as recommended will likely settle less than 'A -inch.
GeoDesign, Inc. 6 PNWP- 18:102699
Vapor barriers are often required by flooring manufacturers to protect flooring and flooring
adhesives. Many flooring manufacturers will warrant their product only if a vapor barrier is
installed according to their recommendations. Selection and design of an appropriate
vapor barrier, if needed, should be based on discussions among members of the design
team. We can provide additional information to assist you with your decision.
Floor Slab Base
Floor slab base rock should consist of crushed rock that is fairly well - graded between
coarse and fine, contains no organic matter or other deleterious materials, has a maximum
particle size of 1'% inches, and has less than 5 percent passing the U.S. Standard No. 200
Sieve. The floor slab base rock should be placed in one lift and compacted to not Tess than
95 percent of maximum dry density, as determined by ASTM D 1557.
PAVEMENT RECOMMENDATIONS
General
The pavement subgrade should be prepared in accordance with the previously described
site preparation, wet weather construction, and structural fill recommendations. Our
pavement recommendations assume that paving will be conducted in an extended period
of dry weather. Wet weather construction could require an increased thickness of
aggregate base.
We do not have specific information on the frequency and type of vehicles that will use the
area; however, we have assumed that traffic conditions will consist of fewer than 20, 18 -kip
Equivalent Single Axle Loads (ESAL's) per day. We should reevaluate these thicknesses if
traffic exceeds this assumption. We used a subgrade resilient modulus of 6,000 psi in our
analyses.
We recommend a section consisting of 3.0 inches of asphalt concrete (AC) over 10.0
inches of aggregate base in areas where truck traffic is expected. If parking areas are
limited to passenger automobiles only, the pavement section can be reduced to 2.5 inches
of AC over 8.0 inches of crushed rock. If the subgrade is amended with portland cement,
the pavement section can be reduced to 2.5 inches of AC over 6.0 inches of aggregate
base for both truck and passenger car traffic areas. This recommendation is based on a
minimum mixing depth of 12 inches and a minimum 7 -day unconfined compressive
strength of 100 psi.
The AC pavement should conform to Section 00745 for standard- and heavy -duty asphalt
pavements of the Supplemental Standard Specifications for Highway Construction, Oregon
Department of Transportation, 1996 Edition. The crushed rock base should conform to
Section 02630 of Standard Specifications for Highway Construction, Oregon Department of
Transportation, 1996 Edition and have less than 5 percent passing the U.S. No. 200 Sieve.
Crushed rock base should be placed in a single lift and compacted to not less than
95 percent of the maximum dry density, as determined by ASTM D 1557.
GeoDesign, Inc. 7 PNWP- 18:102699
•
UTILITY TRENCHES
Utility Trench Excavation
Trench cuts should stand vertical to a depth of approximately 4 feet, provided no
groundwater seepage is observed in the trench walls. Open excavation techniques may be
used to excavate trenches with depths between 4 and 8 feet, provided the walls of the
excavation are cut at a slope of 1 H:1 V, groundwater seepage is not present and with the
understanding that some sloughing may occur. The trenches should be flattened to
1 %H:1 V if excessive sloughing occurs.
Additionally, trench dewatering may be required to maintain dry working conditions if the
invert elevations of the proposed utilities are below the groundwater level. Pumping from
sumps located within the trench will likely be effective in removing water resulting from
seepage.
While we have described certain approaches to the trench excavation, it is the contractors
responsibility to select the excavation and dewatering methods, to monitor the trench
excavations for safety and to provide any shoring required to protect personnel and
adjacent improvements. All trench excavations should be in accordance with applicable
OSHA and state regulations.
Trench Backfill Material
Trench backfill for the utility pipe base and pipe zone should consist of well - graded granular
material containing no organic material or other deleterious material, have a maximum
particle size of 3 h -inch, and have less than 8 percent passing the U.S. Standard No. 200
Sieve.
Backfill for the pipe base and within the pipe zone should be placed in maximum 12 -inch-
thick lifts and compacted to not less than 90 percent of the maximum dry density, as
determined by ASTM D 1557 or as recommended by the pipe manufacturer. Backfill above
the pipe zone should be placed in maximum 12- inch -thick lifts and compacted to not less
than 90 percent of the maximum dry density, as determined by ASTM D 1557. Trench
backfill located within 2 feet of finish subgrade elevation should be placed in maximum
12- inch -thick lifts and compacted to not less than 95 percent of the maximum dry density,
as determined by ASTM D 1557.
RETAINING STRUCTURES
The following design recommendations are based on the assumptions that: (1) the walls
consist of conventional cantilevered retaining walls or embedded building walls, (2) the
walls are less than 10 feet in height, (3) the backfill is level and drained and consists of SQ
imported granular materials, and (4) no surcharges are imposed behind the wall. °/�
Reevaluation of our recommendations will be required if the retaining wall design criteria for
the project vary from these assumptions.
For walls not restrained from rotation, we recommend using an equivalent fluid pressure of
38 pcf for design. We recommend using an equivalent fluid pressure of 55 pcf for design of
walls restrained from rotation. When computing resistance to lateral loads, a base friction
GeoDesign, Inc. 8 PNWP- 18:102699
coefficient of 0.35 and a passive resistance of a 250 pcf fluid can be used. Footings for the
retaining walls should be designed in accordance with the recommendations given for
shallow spread footings.
As stated above, our recommendations are based on the assumption of drained conditions.
Drains that consist of a 6- to 8- inch - diameter perforated drainpipe should be installed
behind all retaining structures. The pipe should be embedded in a minimum 3- foot -wide
zone of drain rock and sloped to drain (minimum slope of 1 /2 percent) toward a suitable
discharge. The drain rock should be wrapped in a geotextile. Backfill material placed
behind the wall and extending a horizontal distance of 1H, where H is the height of the
retaining wall, should consist of the well - graded gravel, with not more than 5 percent by
weight passing the U.S. Standard No. 200 Sieve. Alternatively, the on -site soils can be
used as backfill material provided a minimum 2- foot -wide column of drain rock wrapped in
a geotextile is placed against the wall. The rock column should extend from the foundation
drains to within approximately 1 -foot of the ground surface.
The geotextile should have an AOS between the U.S. Standard No. 70 and 100 Sieve and
a water permittivity greater than 1.5 sec'. The drain rock should be uniformly graded, have
a maximum particle size of 3 inches, and have less than 2 percent passing the U.S.
Standard No. 200 Sieve (washed analysis).
Backfill should be placed and compacted as recommended for structural fill, with the
exception of backfill placed immediately adjacent to walls. Backfill adjacent to walls should
be compacted to a lesser standard to reduce the potential for generation of excessive
pressure on the walls. Backfill located within a horizontal distance of 3 feet from the
retaining walls should be compacted to approximately 90 percent of the maximum dry
density, as determined by ASTM D 1557. Backfill placed within 3 feet of the wall should be
compacted in lifts less than 6 inches thick using hand - operated tamping equipment (such
as jumping jack or vibratory plate compactors). If flat work (slabs, sidewalk, or pavement)
will be placed adjacent to the wall, we recommend that the upper 2 feet of fill be compacted
to 95 percent of the maximum dry density, as determined by ASTM D 1557. Settlements of
up to 1 percent of the wall height commonly occur immediately adjacent to the wall as the
wall rotates and develops active lateral earth pressures. Consequently, we recommend
that construction of flat work adjacent to retaining walls be postponed at least four weeks
after construction, unless survey data indicates that settlement is complete prior to that
time.
SITE DRAINAGE
We recommend that subsurface drains be connected to a tightline leading to the storm
drain. Pavement surfaces and open space areas should be sloped such that the surface
water runoff is collected and routed to suitable discharge points. We recommend that the
ground and paved surfaces adjacent to the building be sloped to drain away from the
building.
GeoDesign, Inc. 9 PNWP- 18:102699
SEISMIC DESIGN
We recommend that the building be designed using the applicable provisions of the State
of Oregon Structural Specialty Code for Zone 3. Site conditions correspond to a soil profile
type of So and Uniform Building Code 1997 seismic coefficient of C = 0.36.
OBSERVATION OF CONSTRUCTION
Satisfactory foundation and earthwork performance depends to a large degree on quality of
construction. Sufficient monitoring of the contractor's activities is a key part of determining
that the work is completed in accordance with the construction drawings and specifications.
Subsurface conditions observed during construction should be compared with those
encountered during the subsurface exploration. Recognition of changed conditions often
requires experience; therefore, qualified personnel should visit the site with sufficient
frequency to detect whether subsurface conditions change significantly from those
anticipated.
We recommend that GeoDesign be retained to monitor construction at the site to confirm
that subsurface conditions are consistent with the site explorations and to confirm that the
intent of project plans and specifications relating to earthwork and foundation construction
are being met.
LIMITATIONS
We have prepared this report for use by Pacific Northwest Properties and its design team
in the proposed development of the proposed 72' Avenue Office Buildings in Tigard,
Oregon. The data and report can be used for bidding or estimating purposes, but our
report, conclusions, and interpretations should not be construed as a warranty of the
subsurface conditions and are not applicable to other sites.
Test pit excavations indicate soil conditions only at specific locations and only to the depths
penetrated. They do not necessarily reflect soil strata or water level variations that may
exist between exploration locations. If subsurface conditions differing from those described
are noted during the course of excavation and construction, reevaluation will be necessary.
The site development plans and design details were preliminary at the time this report was
prepared. When the design has been finalized and if there are changes in the site grades
or location, configuration, design loads, or type of construction for the building, the
conclusions and recommendations presented may not be applicable. If design changes
are made, we should be retained to review our conclusions and recommendations and to
provide a written evaluation or modification.
The scope of our services does not include services related to construction safety
precautions, and our recommendations are not intended to direct the contractor's methods,
GeoDesign, Inc. 10 PNWP- 18:102699
techniques, sequences or procedures, except as specifically described in our report for
consideration in design.
Within the limitations of scope, schedule and budget, our services have been executed in
accordance with the generally accepted practices in this area at the time this report was
prepared. No warranty or other conditions, express or implied, should be understood.
♦♦
We appreciate the opportunity to be of continued service to you. Please call. if you have
questions concerning this report or if we can provide additional services.
Sincerely,
GeoDesign, Inc.
Ryan K. White, E.I.T.
Geotechnical Staff .<4' 0IiV d :p
ALe-"cbb a 18.025
L AGON c
George Saunders, P.E. PO -GAY 25.1 c�°i,�
Principal Qty P. SA V E
�•ao
GeoDesign, Inc. 11 PNWP- 18:102699
, .I'i V' ii // r• ,-' v 3`° /V° 1•-'-n rl. �' n I II '1 -- \r
. Cr l ' i/ • !.,' 1 t— C ._ r ___ s . '• _2 \ \ . \ •\\ '‘,03 M
o
mv • • - .
Li1&
l 0 •a " I I'I e:.
' - - -- as
`_ - - - -' ' I. 11 I' Y• • r I • • v , ?� I v I` • : °/ r _ 7 a0 •
Z
\ i56 _i / - .-'9C .. _ , IE'I \\% , aN '1 »rew,N S `1. H •
• i Y " e .') /' ;) z:� I ' _ �I _ c o • • Z O • .��- _— .. .+ ; : y 2 , ..- , y;;' a m! . Iri 1 Z F:_ p ipril.
♦ rt ' • •� \` '•' \�, 'll -� y ill.. 0 rl I V�
_ - _ 3N V5' . u � � Ir i, I \� L3fQY L
' • ® , : a.
am' � �'ll i <,.. - • —
�i( 1 iiP ���?;:�
l'I • ,...1:, • • I. • � d / ;Y /I {?i r.d 13 .0 .OL. •
; I ✓ ` �'r �.' - ii ` J i 3n . oL U J � i ..� • ...II \ . ' r J
-- 3 \ 1 ° n. . ` 9 . : f ' + S IP . ;�I ° . ;- - - 74 : - Ay .
r \ ,,' ., •••••• . `CO ga_ .. ,, , • = =. .1.. ..• • ,. • . "' Il , .0._
:.... .
..,_..4.1-0„..s.i.,•. \5u, "...'y �_ .n\c\< r i.l :. ' : � `. :.•. :. 00 /.; 0 \ g 0 \ 1- •, I: J • 1 .� -160 — •• \ ' • `I r ,p U
.• n • .._. . G • r3nV l .... . •
� J - -- --- 111 . 1,- --- 111 . 1,- ' ).le, . I i '',...Y•••••••• \ �" • y \, 1 . .- : i !o l ' ' +v_: tsl % - `: I • �r_ • ' — •
I p • � • i \ � tt �*�' •. \ F-' • ` /� . l i - 1 0 ',\,,,,' , I i• i; l � / / • . • 1 , Z
• . / � � - . .. i M 0 ",i. co i \∎ - I— — I I —__ — .. ••
1 1;1 1 • ® .\ i T; I % - , II • II r --I--j. l lCy , )\ ,: 9 Ii \. •1 -fi S
. r k ir• �� L . ;. I'. a - 002 0 !m N W
�l %� %� ". % ! . ; 'iii " --� N V d o
I % `: •• \ ' I� _ i d •
�:®,O � I 4 ' , �) a (� X 1 1 1! • • : I W �\ 'u `;y. r d O
r :v 1 'I'.; • O ) ' a �gG ^y,l� _ Z Lu Lu
0
1e • • ~ '• 7.'• • • • \ r�'..9,r - 4 - , ,— . - .-. • S n:
• •• .a'i5.� :•;-.,‘..\ •• \' ) � J ] W
• ;s III • ::--- • c''''/ ... '' , .41 % .% \ i: . ; ' - i y ..- 1./ ]L
`� \� ]K / \ .moo . e � s, 41 .�> ` j � ' '. � i , s . r ; (,./•• ; _. ' :•I. !I' , 3nv� : �B M a3 • ' 'i; l .r�s' ..v r,t ! ••I ei : :a' :•\ ` ; - ;.'' 11. , `I •' 1 l ' .
1 i
1
I
1
I
f 1
1'
i
,,
1 ', ■ * (T) ji* I , . . TP_:7 . __.1 IL-2-.7.-7-.1=J I
- -- TP -9 ° - - , - TP- 8 1 . 0 0
___ _„, . e I , , , ______ ( --7------* A'
i I PROPOSED BUILDING : i I
° j .1
* L. . 0 _______
_.I. -1 1
1 ) C 1
I I r I
i
. .. -i : i I
i
w' TP-
I
z
Lu
r l TP -5 w III w
I TP -10 - -- iJ _ Q
I
N.
I` Z
h I TP -3� H cv
• - -- I
--
- 1 .- TP -4 I
j gi
l
( J PROPOSED BUILDING
I
0 •I 1
) • 1)
___ --- -- �- i� , , : . ; 1 o T P -1� ,,
, TP -11 I I 1 i : r ---
I TP -2 J
Ci)-leri 1
SW CHERRY DRIVE
---*** i
/ 6 \
N
EXPLANATION: 0 50 1 + 0 FT
TP -1
S TEST PIT
SITE PLAN FROM DRAWING PROVIDED
BY MILDREN DESIGN GROUP, P.C.
G EODESIGN, INC. SITE PLAN
PNWP -18 OCTOBER 1999 FIGURE:
I
APPENDIX A
FIELD EXPLORATIONS
We explored subsurface conditions at the site by excavating 11 test pits (TP -1 through TP-
11) at the approximate locations shown in Figure 2. Gordon Van Domelen Excavating
excavated the test pits using a rubber -tired backhoe to depths of between 7 and 14 feet on
September 1, 1999.
We chose the test pit locations based on a site plan provided to our office by Mildren
Design Group. We determined the exploration locations in the field from existing site
features. The locations shown on Figure 2 should be considered approximate. A qualified
member of GeoDesign's staff observed and documented all field activities.
We obtained representative samples of the various soils encountered for geotechnical
laboratory testing. Classifications and sampling intervals are shown on the Togs included in
this appendix.
We classified the materials in the field in accordance with the "Key to Test Pit and Boring
Log Symbols" (Table A -1) and "Soil Classification System and Guidelines" (Table A -2),
copies of which are included in this appendix. The test pit logs indicate the depths at which
the soils or their characteristics change, although the change actually may be gradual. If
the change occurred between sample locations, the depth was interpreted.
LABORATORY TESTING
We classified soil samples in the laboratory to confirm field classifications. The laboratory
classifications are included in the test pit logs if those classifications differed from the field
classifications.
We tested the natural moisture content of selected soil samples in general accordance with
guidelines presented in ASTM D 2216. The moisture contents are included in the test pit
logs in this appendix.
GeoDesign, Inc. A -1 PNWP- 18:091099
KEY TO TEST PIT AND BORING LOG SYMBOLS
SYMBOL SAMPLE DESCRIPTION
LOCATION OF SAMPLE OBTAINED IN GENERAL ACCORDANCE WITH ASTM D 1586
STANDARD PENETRATION TEST
LOCATION OF SPT SAMPLING ATTEMPT WITH NO SAMPLE RECOVERY
LOCATION OF SAMPLE OBTAINED USING THIN WALL, SHELBY TUBE, OR GEOPROBE SAMPLER IN
GENERAL ACCORDANCE WITH ASTM D 1587
LOCATION OF THIN WALL, SHELBY TUBE, OR GEOPROBE SAMPLING ATTEMPT WLTH NO SAMPLE
RECOVERY
LOCATION OF SAMPLE OBTAINED USING DAMES AND MOORE SAMPLER AND 300 POUND HAMMER
OR PUSHED
LOCATION OF DAMES AND MOORE SAMPLING ATTEMPT (300 POUND HAMMER OR PUSHED) WITH NO
SAMPLE RECOVERY
LOCATION OF GRAB SAMPLE
WATER LEVEL
GEOTECHNICAL TESTING EXPLANATIONS
PP POCKET PENETROMETER LL LIQUID LIMIT
TOR TORVANE PI PLASTICITY INDEX
CONSOL CONSOLIDATION PCF POUNDS PER CUBIC FOOT
DS DIRECT SHEAR PSF POUNDS PER SQUARE FOOT
P200 PERCENT PASSING U.S. NO. 200 SIEVE TSF TONS PER SQUARE FOOT
W MOISTURE CONTENT P PUSHED SAMPLE
DD DRY DENSITY OC ORGANIC CONTENT
ENVIRONMENTAL TESTING EXPLANATIONS
CA SAMPLE SUBMITTED FOR CHEMICAL ND NOT DETECTED
ANALYSIS
NS NO VISIBLE SHEEN
PID PHOTOIONIZATION DETECTOR HEADSPACE
ANALYSIS SS SLIGHT SHEEN
PPM PARTS PER MILLION MS MODERATE SHEEN
MG /KG MILLIGRAMS PER KILOGRAM HS HEAVY SHEEN
P PUSHED SAMPLE
KEY TO TEST PIT AND
GEODESIGN, INC. BORING LOG SYMBOLS
TABLE A -1
SOIL CLASSIFICATION SYSTEM
MAJOR DIVISIONS SYMBOL NAME
GRAVEL GW Well graded, fine 10 coarse gravel
CLEAN GRAVEL
More than 50% of GP Poorly graded gravel
coarse fraction
COARSE GRAINED retained on GM Silty gravel
No. 4 Si GRAVEL WITH FINES
o. Sieve SOILS GC Clayey grovel
More than 50% retained on SW Well graded, fine to coarse sand
No. 200 Sieve SAND CLEAN SAND SP Poorly graded sand
More than 50% of
coarse fraction passes SM Silty sand
No. 4 Sieve SAND WITH FINES
SC Clayey sand
ML Low plasticity silt
SILT AND CLAY INORGANIC
Liquid Limit CL Low plasticity clay
FINE GRAINED SOILS less than 50%
ORGANIC OL Organic silt, organic clay
More than 50% passes MH High plasticity silt
No. 200 Sieve SILT AND CLAY INORGANIC
Liquid Limit CH High plasticity clay, fat day
greater than 50% ORGANIC OH Organic clay, organic silt
HIGHLY ORGANIC SOILS PT Peat
SOIL CLASSIFICATION GUIDELINES
GRANULAR SOILS COHESIVE SOILS
STANDARD STANDARD UNCONFINED
RELATIVE DENSITY PENETRATION CONSISTENCY PENETRATION COMPRESSIVE
RESISTANCE RESISTANCE STRENGTH (TSF)
Very Loose 0 - 4 Very Soft Less than 2 Less than 0.25
Loose 4 - 10 Soft 2 - 4 0.25 - 0.50
Medium Dense 10 - 30 Medium Stiff 4 - 8 0.50 - 1.0
Dense 30 - 50 Stiff 8 - 15 1.0 - 2.0
Very Dense More than 50 Very Stiff 15 - 30 2.0 - 4.0
Hard More than 30 More than 4.0
GRAIN SIZE CLASSIFICATION
Boulders 12 - 36 inches SUBCLASSIFICATIONS
Cobbles 3 - 12 inches Percentage of other material in sample
Gravel % - 3 inches (coarse) Clean 0 - 2
% -' /. inches (fine) Trace 2 - 10
Sand No. 10 - No. 4 Sieve (coarse) Some 10 - 30
No. 10 - No. 40 Sieve (medium) Sandy, Silty, Clayey, etc. 30 - 50
No. 40 - No. 200 Sieve (fine)
Dry = very law moisture. dry to the touch; Moist = damp. without visible moisture; Wet = saturated, with visible free water.
SOIL CLASSIFICATION SYSTEM
GEODESIGN, INC. AND GUIDELINES
TABLE A -2
DEPTH /FT MATERIAL DESCRIPTION TESTING
TP -1
0-
ML Hard, orange and gray mottled, brown SILT with trace sand; dry to moist (4 -inch thick root
I - zone).
2 -
3 -
4 - becomes medium stiff to stiff at 4.0 feet W = 28%
5-
6-
7-
8- becomes soft; wet at 8.0 feet
9-
10-
11-
12-
with siltstone lens at 12.5 feet
13- becomes gray with trace to some sand at 13.0 feet
W =37%
14 Test pit completed at 14.0 feet on September 1, 1999.
15- Disturbed samples obtained at 1.0, 4.0 and 14.0 feet.
Slow groundwater seepage observed at 14.0 feet.
Slight caving observed below 10.0 feet
TP -2
0-
ML -FILL Hard, brown SILT FILL with some angular cobbles; moist (4 -inch thick root zone).
2 - ML Very stiff, orange mottled, brown SILT; moist.
3 - W =203%
4 -
5
6 -
7-
8 - with siltstone lens at 8.0 feet
9-
10 -
11 W = 36%
Test pit completed at 11.0 feet on September 1, 1999.
12 - Disturbed samples obtained at 3.0, 8.0 and 11.0 feet.
No groundwater seepage or caving observed to the depth explored.
13-
14-
15-
TEST PIT LOGS
GEODESIGN, INC.
PNWP -18 OCTOBER 1999 FIG. A -1
•
I DEPTH /FT MATERIAL DESCRIPTION TESTING
TP -3
0-
ML Hard, brown SILT with trace fine sand; dry to moist (5 -inch thick root zone).
1 -
2 -
3 -
4 - becomes stiff to very stiff at 4.0 feet W = 25%
5 -
6 -
7 - becomes hard and partially cemented at 7.0 feet
8J /
SP Medium dense, brown SAND with some silt; moist.
9-
W =33%
10-
11
Test pit completed at 11.0 feet on September 1, 1999.
12- Disturbed samples obtained at 4.0 and 10.0 feet.
No groundwater seepage observed to the depth explored.
13- No caving observed to the depth explored.
14-
15-
TP-4
0-
ML -FILL Dense, brown, silty GRAVEL FILL (4 -inch thick root zone).
1-
2 W = 10%
3
ML Medium stiff to stiff, dark brown SILT; moist.
4-
W = 1 7%
5-
6 grades to with trace fine sand at 6.0 feet
7-
8-
9-
10 SP Hard, brown, partially cemented SAND; moist.
11_ SP Medium dense, brown SAND with trace to some silt; moist. W = 32%
12- Test pit completed at 11.5 feet on September 1, 1999.
Disturbed samples obtained at 2.0, 4.5 and 11.5 feet.
13 - Slow groundwater seepage observed at 11.5 feet.
14 - No caving observed to the depth explored.
15-
TEST PIT LOGS
GEODESIGN, INC.
PNWP -18 I OCTOBER 1999 FIG. A -2
•
DEPTH /FT MATERIAL DESCRIPTION TESTING
TP -5
0- GW -FILL Dense, gray rounded to subrounded GRAVEL ALL; dry.
1- ML -FILL Very stiff, brown SILT FILL with occasional gravel; moist. W = 22%
2 ML -FILL Soft to medium stiff, orange mottled, dark brown SILT FILL with trace fine sand and debris
3- (bumf wood). moist
4 - W = 26%
5
6 - ML Medium stiff, brown SILT with some fine sand; moist.
8 J
SM Dense, brown and black, partially cemented, silty SAND; moist.
9-
10 W = 35%
11 - Test pit completed at 10.0 feet on September 1, 1999.
Disturbed samples obtained at 1.0, 4.0 and 10.0 feet.
12- No groundwater seepage or caving observed to the depth explored.
13-
14-
15
TP -6
0-
ML Hard, desiccated, orange and gray mottled, brown SILT; dry to moist; moist (3 -inch thick
1- root zone).
W =9%
2-
becomes very stiff at 2.5 feet
3 -
4-
W = 32%
5- becomes medium stiff to stiff at 5.0 feet
6-
7-
8-
9 -
10 _ ML Soft, brown SILT with some fine sand; moist.
11-
12-
13- Test pit completed at 12.5 feet on September 1, 1999.
14 - Disturbed samples obtained at 2.0, 5.0 and 10.5 feet.
Slow groundwater seepage observed at 12.5 feet.
15 - No caving observed to the depth explored.
TEST PIT LOGS
GEODESIGN, INC.
PNWP -18 1 OCTOBER 1999 I FIG. A -3
• DEPTH /FT MATERIAL DESCRIPTION TESTING
TP -7
0-
MI Hard, desiccated, brown SILT; dry 10 moist (5 -inch thick root zone).
1-
2 -
3 -
4 - becomes very stiff at 4.0 feet W = 28%
5 -
6-
7_
8 SM Medium dense, brown, silty SAND; moist.
9-
10-
11 W = 31%
Test pit completed at 11.0 feet on September 1, 1999.
12 - Disturbed samples obtained at 4.0 and 11.0 feet.
No groundwater seepage or caving observed to the depth explored.
13
14-
15-
TP -8
0-
1 " ML Hard, desiccated, orange mottled, brown SILT with trace fine sand; dry to moist W = 11%
2 (6 -inch thick root zone).
3-
4
5 - becomes very stiff at 5.0 feet W = 31%
6 -
7
Test pit completed at 7.0 feet on September 1, 1999.
8 - Disturbed samples obtained at 1.0 and 5.0 feet.
No groundwater seepage or caving observed to the depth explored.
9-
10-
11-
12-
13-
14-
15-
GEODESIGN, INC. TEST PIT LOGS
PNWP -18 OCTOBER 1999 FIG. A -4
DEPTH /FT MATERIAL DESCRIPTION TESTING
TP -9
0-
ML Hard, desiccated, orange and gray mottled, brown SILT; dry to moist (4 -inch thick root
1 - zone).
2-
3-
W =13%
4- becomes very stiff with trace fine sand at 4.0 feet
5-
6 -
7- •
8-
9-
10-
boulder encountered at 10.0 feet
11-
W= 28%
12- Test pit completed at 11.5 feet on September 1, 1999.
Disturbed samples obtained at 3.0 and 11.5 feet.
13 - Slow groundwater seepage observed 0 1 1 1 . 5 feet.
t 4 - No caving observed to the depth explored.
15-
TP-10
0-
ML Hard, desiccated, orange mottled, brown SILT; moist (6 -inch thick root zone).
-
W =14%
2-
3 -
4 -
5- becomes stiff to very stiff at 5.0 feet W = 31%
6-
7 -
8 -
9-
10-
1 large boulder encountered at 11.0 feet
12- Test pit completed 0 1 1 1 . 0 feet due to practical refusal on September 1, 1999.
Disturbed samples obtained at 2.0 and 5.0 feet.
13- No groundwater seepage or caving observed to the depth explored.
14-
15-
GEODESIGN, INC. TEST PIT LOGS
PNWP -18 OCTOBER 1999 I FIG. A -5
DEPTH /FT MATERIAL DESCRIPTION TESTING
TP -11
0-
ML Very stiff, orange and brown mottled SILT; moist (5 -inch thick root zone).
1 - W =10%
2-
3 -
4-
5 - becomes stiff at 5.0 feet W = 31%
6-
DD = 90 PCF
W = 32%
8 -
9
10
SM Medium dense, brown, silty, fine SAND; moist.
11-
W = 36%
12
Test pit completed at 12.0 feet on September 1, 1999.
13- Relatively undisturbed sample obtained from 5.0 to 7.0 feet.
14- Disturbed samples obtained at 1.5, 5.0 and 1 1.5 feet.
No groundwater seepage or caving observed to the depth explored.
15-
GEODESIGN, INC. TEST PIT LOGS
PNWP -18 OCTOBER 1999 FIG. A -6