Correspondence (38) 5// February 11, 1999
CITY OF TIGARD
Sconzo /Hallstrom Architects
Vince Loftus OREGON
919 124th Avenue NE #101
Bellevue, WA 98005
RE: Eagle Hardware Site Plan Review
12615 SW 72nd Avenue
PC #: 11-43c SIT #: 98 -0048
We have completed review of your response to our December 4,1998 site plan review letter. Thank you for
responding so thoroughly. There are just a few corrections or additions needed before processing the
application further.
I SITE WORK
Ite 1 - Copy of the recorded legal description.
Item #5 - Soil special inspection form. c•/' « R ef a t
l � c tJoe�c Slit
Iig 0 -A. -- �c
(ACCESSIBILITY
D tjtem #3 - Correct detail A1.02(3) to read 7 feet above finish grade. I apologize for the typo.
(STRUCTURAL
.) 4t1
Ite #2
Item - Sheet C9/9.
n addition, the structural design and specifications for the monument and CMU wall /trellis shall be included in
the site civil drawings and stamped by J.U.B. Engineers, Inc.
A. Submit the engineering for the cmu /steel trellis design. ', Pte '' °
B. A special inspection will be required for the welding. nlrf' Pte-
Please submit three copies of revised submittal documents and a letter indicating your response to the above
comments for review. Please call me at (503) 639 -4171 if you have any questions.
Since e ,
Jim Funk
PLANS EXAMINER
13125 SW Hall Blvd., Tigard, OR 97223 (503) 639 -4171 TDD (503) 684 -2772
.d.-...._____
r ..„..
. ..
. ,
• % .•
,,
. . .. .
. . . .
__ ,,„„,„„,,,,,,,,,,,,,,,
ir,,,,,,„
....„..34.,,,,..a.,:,
December 4, 1998 CITY OF TM)
OREGON
Sconzo /Hallstrom Arch.
Vince Loftus
919 124th Avenue NE #101
Bellevue, WA 98005 -
RE: Eagle Hardware Site Plan Review
12615 SW 72nd Ave
PC#: 11-43c SIT #: 98 -0048
Submittal documents for the above referenced project have been reviewed for conformance with
the applicable 1996 Oregon Specialty Codes and other applicable codes and standards. The
following comments are noted:
17 /III 1 I SITE WORK ' -
5 ,.... � 1 The proposed project site consists of more than one parcel of land. There shall be no
underlying land divisions unless the buildings are designed for location to property lines.
Provide a true copy of the recorded document describing the site as one parcel.
Provide the total square footage of impervious area. Include roofs, sidewalks, parking lot
and gravel areas. Subtract existing impervious areas. ) 9 Z,3 f,
3/ Provide the total cubic yards of each of the following:
,
A. Excavation 7 f vi
B. Fill [structural and non - structural] / 3 V, 6 3
Water Quality Facility observation by Engineer of record.
The owner shall employ the Engineer of record, responsible for the design and
fr,
specifications of the Water Quality Facility, to perform construction and visual observation
of the Water Quality Facility for compliance of the design and specifications, at significant
I I stages, and at completion of the construction.
C1
Prior to final occupancy approval of the construction under permit for the site, the
Engineer of record shall provide the City of Tigard, "Attention Plans Examiner" and
.), "Supevising Inspector" with written confirmation that the Water Quality Facility is in
y ' compliance with the design and specifications of same. I
�, 4 b S � Complete the enclosed Soils Special Inspection form des " it :.: - n Approved Testing , 7'
G i
1 Laboratory [Line B] and signed by the owner of the project • . ‘ r f
^� A. The completed form must be returned to this office before a Site permit can be ety\
issued.
13125 SW Hall Blvd., Tigard, OR 97223 (503) 639 -4171 TDD (503) 684 -2772