Plan Check Response
To: Brian Blalock — City of Tigard
From: Michael Peterson, P.E.
Date: 9/5/06
Project: Dartmouth Square
Jurisdiction Permit #: BUP2006 -00299
FCE Job #: 05 -T361
This memorandum is in response to the structural plan check comments by Miller Consulting Engineers
for the City of Tigard. Since the plan check comments the building's structural system has changed
extensively, such that some comments may no longer apply. An entire new set of structural drawings and
calculations have been issued for your review. Please see below for a response to each numbered issue:
1. Pages containing calculations for the trash enclosure have been added to the package. The changes
have been forwarded to the architect so that they can be added to architectural sheet A1.2. In addition the
trash enclosure detail will be shown on the structural drawings as well.
2. We completed these calculations and the architect submitted them to the city with the rest of the
engineering calculations. They probably did not get forwarded to Miller Consulting. Please forward them
for review.
3. A note regarding the frequency of periodic special inspections has been added on sheet S1.1.
4. Veneer is 4" brick as called in the specifications. This allows standard veneer ties to be used per code
as described on S1.1.
5. A page has been added, showing calculations for the self - drilling screws at the exterior walls.
6. The calculations have been revised to show a "d" of 9.5 ".
7. Details have been updated to show a connection between the studs and the track.
8. The calculations have been revised to show a 2" of cover on the toe side and 3" of cover on the soil
side. Details have been revised to show the new wall changes.
9. Calculations have been update for the connection shown in the details.
10. Details have been updated to show the connections between the studs and the track as well as the
connection between the track and the HSS header.
11. Detail has been added to the plans. This detail shows the connection of the floor beam to the
concrete column. Please note that this particular beam is not part of a moment frame. The moment
frame lateral system has been changed to a different braced frame system.
12. Calculation pages have been added which show the mass of the veneer as an included weight in the
seismic calculations. The veneer is treated as a line Toad around the perimeter of the building.
13. Calculation pages have been added to the package showing the connection of the beams to the
columns. Three beams had to be increased in size to allow for the proper number of bolts at the
connections.
14. The detail has been updated to reference the correct detail.
15. Calculation pages have been added that show the method used for transferring load around the large
opening.
16. The moment frame system has been changed to a braced frame system. The drag strut
requirements have changed and are covered in the new calculation package.
17. New braced frame system instead of original moment frame system.
18. Calculation pages have been added to the package showing the uplift condition and checking for
lateral bucking.
19. Details have been updated to show a weld connection between the angle and the HSS.
20. Special inspection testing laboratory will submit reports for the inspected items for review. A final
approval letter will be provided.
21. We will provide structural observation for the listed items throughout the duration of the project.
22. This is a deferred submittal and will be presented prior to construction.
23. This is a deferred submittal and will be presented prior to construction.
24. This is a deferred submittal and will be presented prior to construction.
25. This is a deferred submittal and will be presented prior to construction.
26. This is a deferred submittal and will be presented prior to construction.
27. The proper sets will be presented to the city.
These comments should answer the questions that were listed. If you have further questions or require
more information please call.
Regards,
Michael Peterson, P.E.
Rug 03 06 02:15p Froelich Consulting Eng 503 - 624 -9770 p.l
;: +�'
July 28, 2006
CITY OF TIGARD
OREGON
Froelic Consulting Engineers, Inc.
6969 SW Hampton Street
Portland, OR 97223
RE: STRUCTURAL PLAN REVIEW ONLY
Project Information
Building Permit: BUP2006 -00299 Occupancy Type: B
Project Name: Dartmouth Square Construction Type: IIB
Address: 11945 SW 70 Avenue Occupant Load: NA
Area: 38,380 Sq Ft Stories: 3
To whom it may concern,
Attached is the STRUCTURAL PLAN REVIEW performed by Miller Consulting Engineers,
for the City of Tigard, under the State of Oregon Structural Specialty Code (OSSC) 2004 edition.
• Please provide an item by item response to the review document and 2 copies of any
revised plans, calculations or details.
When submitting revised drawings or additional information, please attach a copy of the
enclosed City of Tigard, Letter of Transmittal. The letter of transmittal assists the City of
Tigard in tracking and processing the documents.
Resp
�� / G
i
f %
/ !aria laloc RECEllVE
Senior P Examiner
L!
JUL 31 2006
Froelich Consulting Engineers for;
6.G : f --rY(- L GQdup /1-FZcy Pre c7-
1 3125 SW Q6p myhxerc elltil ft(503) 639 -4171 TDD (503) 684 -2772
Rug 03 06 02:15p Froelich Consulting Eng 503 - 624 -9770 p.2
DARTMOUTH SQUARE OFFICE BUILDING: CITY OF TIGARD
11945 SW 70 AVENUE 13125 SW HALL BLVD
JULY 25, 2006 TIGARD, OR 97223
SHEET 1 OF 3
Project No. 060841 STRUCTURAL PLAN REVIEW # 1
Plans Dated 6/19/06
Corr. Item Page No. Comments Code Section
Made No.
1 Sheet A1.2 Submit calculations and details for trash 106.1.1
enclosure.
2 Sheets RW1 and RW2 Submit calculations for retaining walls. 106.1.1
3 Sheet S1.1 Submit the frequency of items noted as 1705.2
Special Inspection periodic.
4 Sheet S1.1 Submit calculations and details for metal or 1405.5.2
Masonry/Stone Veneer wire ties.
(4)
5 Sheet S1.1 Submit calculations and details for self drilling 106.1.1
Light Gage Steel screws.
Framing (3)
6 Sheet S2.1 Calculations page 507 note 11.5 inches for 106.1.1
Detail 6/S4.1 °d° on a 12 inch wall. Clarify.
7 Sheet S2.1 Submit calculations and details for track to 106.1.1
Detail 8/S4.1 stud connection.
8 Sheet S2.1 Calculation pages 509 thru 520 note 8.0 106.1.1
Detail 9/S4.1 inches for °d° on a 10 inch wall clarify.
9 Sheet S2.2 and S2.3 Submit calculations and details for brick 106.1.1
Details 15/S5.2, support. Note: Details not per calculation
17/S5.2, 18/S5.2, pages 524 and 525.
19/S5.2, 32/S5.3,
33/S5.3
10 Sheet S2.2 and S2.3 Submit calculations and details for HSS to 106.1.1
Details 15/S5.2, track and track to stud.
17/S5.2, 18/S5.2,
19/S5.2, 32/S5.3,
33/S5.3
11 Sheet S2.2 Submit calculations and details for 106.1.1
Details MF1 /S3.1 connections at grids 2 and A.
12 Sheet S2.2, S2.3, S3.1 Submit calculations and details for seismic 106.1.1
Lateral Calculations loading including brick weight. Note:
pages 555 thru 640 Calculations are not the same as the items
noted on drawings.
13 Sheet S2.2 and S2.3 Submit calculations for W14X, W16 106.1.1
Details 4/S5.1 connection of plate to HSS wail.
Flue 03 06 02:15p Froelich Consulting Eng 503 - 624 -9770 p.3
DARTMOUTH SQUARE OFFICE BUILDING: CITY OF TIGARD
11945 SW 70TH AVENUE 13125 SW HALL BLVD
JULY 25, 2006 TIGARD, OR 97223
SHEET 2 OF 3
Project No. 060841 STRUCTURAL PLAN REVIEW # 1
Plans Dated 6/19106
Corr. Item Page No. Comments Code Section
Made No.
14 Sheet S2.2 and S2.3 Detail notes detail 15/S7.1. Detail 15/S7.1 to 106.1.1
Detail 331S5.3 be submitted.
15 Sheet S2.3 Submit calculations and details for method 106.1.1
used to transfer diaphragm forces around
opening at grid 5 to 6.
16 Sheet S2.2, S2.3 and Submit calculations and details for 106.1.1
S2.4 method used to transfer lateral forces
from diaphragm to special moment
frames.
17 Sheet S2.2 and Submit calculations and details for base 106.1.1
Detail MF7 /S3.1 connection.
18 Sheet S2.5 Submit calculations (page 537) for uplift and 106.1.1
Details 211SS5.2, lateral buckling.
22/S5.2 and 24/S5.2
19 Sheet S3.28, S3.3 Submit calculations and details for 106.1.1
Detail 20/S5.2 connection of angles to HSS.
20 Special Inspection Special inspection is required for concrete, 1704, 1705, 1707,
welding, reinforcing steel, bolting, welded 1708
studs, embed plates, bolts in concrete,
structural steel fabrication and erection,
epoxy anchors and floor and roof metal deck.
21 Structural Observation Structural observation is required for
concrete foundation, steel moment frames,
roof and floor diaphragms and at completion.
22 General Submit one set of reinforced steel shop
drawings, which have been reviewed an
initiated by the project engineer, to be filed
with the City of Tigard before placement.
23 General Submit one set of miscellaneous steel shop
drawings, which have been reviewed an
initiated by the project engineer, to be filed
with the City of Tigard before placement.
24 General Submit one set of light gage steel shop
drawings, which have been reviewed an
initialed by the project engineer, to be filed
with the City of Tigard before placement.
25 General Submit one set of steel decking shop
drawings, which have been reviewed an
initialed by the project engineer, to be filed
with the City of Tigard before placement.
Rug 03 06 02:16p Froelich Consulting Eng 503 - 624 -9770 p.4
DARTMOUTH SQUARE OFFICE BUILDING: CITY OF TIGARD
11945 SW 70 AVENUE 13125 SW HALL BLVD
JULY 25, 2006 TIGARD, OR 97223
SHEET 3 OF 3
Project No. 060841 STRUCTURAL PLAN REVIEW # 1
Plans Dated 6/19/06
Corr. Item Page No. Comments Code Section
Made No.
26 General Submit one set of steel stair framing shop
drawings, which have been reviewed an
initialed by the project engineer, to be filed
with the City of Tigard before placement.
27 General Approved resolution of the above terms shall
be incorporated into submittal plans before a
permit will be issued. Submit (4) sets of the
revised plans to the city of Tigard