MEMORANDUM Portland
TO: Bob Burns via fax (626 - 8903)
FROM: Scott McDevitt and Dave Thiele l
DATE: July 1, 1999
/
FILE: 4217 - 013 -01
SUBJECT: Tigard Triangle Site Filling Issues
This memorandum addresses outstanding issues that remain unresolved during the placement of
structural fill at the Tigard Triangle Site.
• The percentage and size of oversized material being imported on to the site has increased in the last
few days. In our memorandum dated June 14, 1999, we defined unacceptable oversized material as
hard rock pieces greater than 8 inches. Occasional pieces, which can be incorporated into the fill and
surrounded by smaller particles or broken up by compaction equipment, are acceptable. In the first
few days of filling, this was the case. However, based on our observations, fill imported recently and
stockpiled or spread across the areas of Building Pads B and C contain excessive oversized material.
It is especially important that the first lift, which has been placed in the area of Building Pad B be
well graded and free of excessive oversized rock pieces.
• The fill imported within the past few days has higher moisture content. We have observed excessive
deflection of wet, compacted fill under loaded dump trucks. Coffman Excavating is aware of this and
has spread and tilled this material in an attempt to dry it further. As of this morning, the material is
too wet to be placed as structural fill. When the material becomes dry enough and has been
compacted, a proof roll using a loaded dump truck should be performed to determine if adequate
compaction has been achieved.
• Occasional oversized rock pieces have been pushed to the sides of fill areas during filling operations.
The oversized pieces are still present around the perimeter of fill areas and should be removed prior to
placing fill in these areas. Removal of the oversized material in fill margins will require cutting into
the fill to remove the oversized material and expose compacted fill.
• A soft spot in the native subgrade is present at the north end of Building Pad C. The subgrade
became soft due to truck traffic in this area. Coffman Excavating has informed us that the area will
be repaired when truck traffic can be diverted from this area.
These issues have been noted in a running `Outstanding Issues' list that is included with each field report.
Baugh Construction and Coffman Excavating have been made aware of these issues and have indicated
that they will be addressed. -The increased incidence of oversized material and wetter material will
require more site visits from us: In addition, since compaction testing cannot be conducted in this
material, it may be necessary to perform more frequent proof - rolls.
cc: Hand delivered to site and mailed to Project Field Reports Distribution List
d
FIELD REPORT File No.
GeoEngineers Inc. 4 1 - A-17-t9 rj -,
10170S.W.NimbusAvenue,Suite H1 Project: -b6, Ne Date:
1 Portland, Oregon97223
Owner: Report No.
Prepared by: Location: Arrival Time: Page:
Scarf" M.'vvr 1r 11664/42/ oft 0 ,30 / of 4
Purpose of Visit: Weather: Depart. Time: Permit No.
6764S fi--rwn Mot.' (To/a-461 �i� toi i' j 6 S '
.6-12-1(24v6-0 aY um_ Y {�.J� . Ic+ oSSehevE GoNS c 1v/re S_ [ M
e- Le - +tilt ) SST &$ - g2/64-4 6.40 +4a. -1 ) c SIT -
Gc("Fht A-r' Ez 1134.014c-c- u.F.A * trtP, STW! -M ��E. - a— 7de44c4.4 r jj r t- >✓ jc /9r.02[jpro 2
112& C Sri. StM- PLaY+) 3 4 nta25G 'B¢os • co,N,S► 4r. 4-,,v,,Pp -
it I (7 d- of eepcpte Pau_ 6A 12.- b+■9
3 =4' yet _ N01.4 r., .p IN -- 01=4/E pr-•S1 - MSTS 6.; - trtf- Sty
(4.50 46) - r 1 7 0 ) , - ( L 3 ¢ 3 6 614 c - 1 , E 1.47, DeNs.N4F. 'tESr trAtes w h 5m -
t - 4' fig -tcA ut_ Mrvr X9.1 01- MPc-vrtor', Q91 Tesfs FweLeEar a.y
jj () ►nor.
1- Pu >)ull,t4'rIt ac4c)
b- t. * c' u . Nt4,0 - 1:p - So --r► -t ¶ 3-11 u.>t'- 6) P 13 lb
�pt�tn �y wj Sat-r . 2er5 ISr r,( jr4 TF-ro <t Cr Ek -SrivF
moT `TV 4 It,- -. Ti 'isS Aar wtu. Re R t..o
jam 6'-L- INFI 2ME �H' fi - St Lf - 614 . SPQri 7 Du Qo� xr. �cc 8
I>.ocrb� r 1E Ar fr 11elFQ6) 5 fA l' 4v 4se.D Ittisre-to_ C2
eot4. W(u 0x!/12 Pat .04- It> ( FL rt f 6F 4 i kra__
_ Mme{ 6 76-171N�1F.� PLCr(C 4" ; s772,1.tC?1, furl /11 tIlA?ra16 a- t-S
(MPoumx) y 1"-.1^A4 7'YLtnor` / (,rte c„›„Arakor..D
Ns- 1,46 b Gb-r F72S SE c-9 i AA_E-12-- UN 'fiN -"q1 ss t.Ct
12 roll D of f 4 , ( SP-P-At a, 4 Pe-et- 13r 1m k
(A.S sN E 14N 9e-2 A ]>i merecn CIG _ 1 Pf e P -rte -YT l f (t of c iv.4 c ,t et-c.
vvt -s N Ti-n t 442,f-4. Y - Wlf•11 NA SMe)c, _ r ee-0 ?'
SILL S gc F r fct , . ' O - . STS., =_c Pec*E
'fG �_Pr�rs vr% 24 -r\., 3r, . fA 0 tom/ ' iy 6SSf s, - (--ry a C5.1.tot -te4
oh tr 4 o-rf) (S Nd71 Surrat31-- 11 <PP. c aft_
l l�c.r.f J-4-1>c• c cm/ r-FiD 12 t>F e P2f?rr i o 'IN IS( .� eaD
tL t-C4 OF t) lrA- Z f as' l-I> < S`4 €C/24' 0E 2Ayt�,tn,toy¢�i ( � C O o (-l::,
- 1:4; 1344 rt e. A4 t„t g,441 % A ) - 1 SE € v 111,4v.(-p 6M12_ -1- 1-u IS
4.0Q>- t.Jlrhf titt r4 , F -ta1 .ft.s'L- cY' . I - f-'t tit Srf'V 1109
This report presents opinions formed as a result of our observation of activities relating to geotechnical engineering. We rely on the contractor to comply with the plans and specifications
throughout the duration of the project irrespective of the presence of our representative. Our work does not include supervision or direction of the actual work of the contractor, his employees or
agents. Our firm will not be responsible for job or site safety on this project.
Attachments: . Qc.p. -r
Distribution: 0.4 Sit,; Signed: ' k �-.
� -- - Pn_CI AC 07
- Inc. Geo Engineers FIELD REPORT File No.
9� 474 7- 01 3 - 9/
10170S.W. Nimbus Avenue,Suite H1 Project: Date:
Portiand,Oregon97223 _ 6- Le-1-9
Owner: Report No. _
. Prepared by: Location: Arrival Time: Page:
2 ofig 4
Purpose of Visit: Weather: Depart. Time: Permit No.
l4s
"_i r_. .r..: 1 . d 1 • - ✓.ate- A1 ro L • • •t. •[ • d i
M ' r. - t . 0 - or r.» evrvi o c- B H .01 ^ K ed , A 1-64]1 - 8 , P- ticcavarr D - r* ` -
v “�, • •�• , �. A X- '
� ■. •a! '4 ' • � 4-- . 2400 -t k Q f . tV . - r. '(Q� � / � • -
PLJ S1�IZtA'•t& U- wE 3'r - of 6 11� I 4cr
i [MQK•M�V»" Q
Wee41a M4T 411 1 -t o '^ T-- T- 1-1-2=-1 ;f-4 Pc. A I ./ /34-.s t4E . -t.› 1 s S�f Nr.
t ossEeii'.p I f„,,t - fh• t IGI NO") f...p. y I"' DT cc-6s - Gto&r 3G Q.dJ. b- fact7F aPLA-
CC ec4ait�CA IN $i/ liz>1•-1ti ( •, I...,I v1- oc- eAke...rMbeQDv -'. BA-50Q oN M y
h€ ¶t mm,o .J5 F1 w S �r, ,ao IM C P cozuotIc_ wait «.te. I
.GMM wc7 flo - _ 1 l.6' -t Pf i645,
This report presents opinions formed as a result of our observation of activities relating to geotechnical engineering. We rely on the contractor to comply with the plans and specifications
throughout the duration of the project irrespective of the presence of our representative. Our work does not include supervision or direction of the actual work of the contractor, his employees or
agents. Our firm will not be responsible for job or site safety on this project.
Attachments: ,, •
Distribution: Signed: Pf
•
I_cl A-_R7
o -
8 W ti
W 0 1 00 200
E ,
F SCALE IN FEET
E••••
y
O a 0
o �'`�` S S w
_ �� y / y
� � — — — — _ — — — _ - Bounds ..jr
/A lka i ---__ ,
%...e. ,. / I �- Bu ing I I I I 1 0 •
ila 1 I TP A TP -3 , — TP \ — — fr' -r — — — — •"4 — 12
-- 175 ta.s 12
S. W. Oth.N B / s '''----.__.___—
E.
M
6 E.
PI C4C13 T
us Ak9 Sr,2w1
s hk
r.S
co r.1
a. EXPLANATION: 'FIX- p al
O
TP -1 TEST PR c v .N f Ii
c 18 DEPTH TO BOULDERS (IN FEE T) h
? _ BOULDERS NOT ENCOUNTERED) TO
DEPTHS EXPLORED
Note: The locations of all feotures shown are approximate.
in
Reference: Base drawing produced from AutoCAD file Spect2.dwg entitled. 'Tigard Triangle Masterplan." � r 9 SITE PLAN
GeoEngineers
n doted 04/27/98, provided by LRS Architects. It� FIGURE 2
1 1(
SUMMARY OF IN -PLACE NUCLEAR DENSITY AND MOISTURE TESTS
PROJECT: . - fl61t;-(? FILE NO. 4 -013— I SHEET 't OF 4
Feet Probe Field Dry Density Percent
Test Test General Elev. to Soil Type of Depth Moisture % ± (pct) Compaction
Number Date Location (feet) Grade Type Compactor (inches) ( %) OMC Field Maximum Field Spec.
/ 6- �o SinP-M aep -,," — cR. 13v 1 2. - 7 , o I2¢,1 X25.4 99, • y-
2 _ - 6,S iZZ,9 , TS , .. 0
3 - 7, a 124.2 49,o
¢ - 7, 7. 1(9,4 9 2
S .),( f -( -, 2 "i o ► 1 8, 2 54.3
v - z ' t P 9,1 1 /7.3 93 V
d
Percent compaction based on: Soil Type: s = Sandy Type of Compactor. Abbreviations:
Standard Proctor (AASHTO T 99-57, ASTM D698) S = Sand g = Gravelly R = rubber -tire roller OMC = Optimum moisture content
Modred Proctor (AASHTO T 180-57, ASTM D1557) (3 = Gravel sl = Silty V = Vibratory compactor % = percent
Si = Silt c = Clayey S = Sheepsfoot roller pcf = pounds per cubic foot
Testing conducted by: C = Clay GD = Grid roller RT = Retest of an area
CR = Crushed Rock L = Loaded scraper
Attachment to Field Report Number JJ = Jumping jack
BV = Backhoe vibratory plate
VP = Vibratory plate
Document ID: NucD&M HT = Hand tamper
°
GeoEngineers Inc. FIELD REPORT File No.
- u7 - � f 3 - � 1
• 7504 SW Bridgeport Road Project: Date:
Portland, Oregon 97224 S ' t 4t1 T10.09 tat C.--
(503) 624 -9274 Owner: Report No.
Prepared by: Location: Arrival Time: Page:
of
Purpose of Visit: Weather: Depart. Time: Permit No.
cam "S f7isi67 uSsu
• seer b .p3 IN Nemv c-4g6 gz .DE (:) me— wen.l fit-I.) - e Per if S
o 1 .4 ' Cf Sax Plu.. l +-1 S .1D. $ IS "fD✓ "rihct- "n> " Gor to - Or *i
1 .- . . - • . _ - r - �• i - ESQ LVGA - C
O Pr SP'r (( Ntan vG SN 31� R-i• 0 t only gi-42 c F 5-1 I La1NG Poo 4.- 02c,3 d 0
This report presents opinions formed as a result of our observation of activities relating to geotechmcal engineering. We rely on the contractor to comply with the plans and specifications
throughout the duration of the project irrespective of the presence of our representative. Our work does not include supervision or direction of the actual work of the contractor. his employees or
agents. Our firm will not be responsible for job or site safety on this project.
Attachments:
Distribution: Signed:
G E 1 45 -87
L File No. GeoEngineers Inc. FIELD REPORT 4u is q
10170S.W.NimbusAvenue,Suite H1 Project: Date:
Portland, Oregon 97223 SEk _ b Z9' 9
Owner: Report No.
<ctFT 1
Prepared by: Location: Arrival Time: Page:
Scorrr M 6Mvirr Q 945 of 2
Purpose of Visit: Weather: Depart. Time: Permit No.
Ls7f`1St. •- p
vr
MoNrjbii Olrl - 15
A-404vS0 oer e:7D4 1 •85e4e-v LoNSr-9-1.40r)c"4 1S.-e.rvrn , 1 nnP,� JPT�
Cf'.�•�w 8 (4=•r-c-IvLog.L
N 1 N L(
?l-stn► e I 11 PeP S Es 4'1 Sc-- 7ei+rvea•c r,r. 1.1 7 t
m z r e p - dP 8un.D11.& P P. 4,49s n v y We6r of i t - )_ LA, %A/A.5
vmeoareo E=Ni D 1? - cam,'5fb r usir.& b- Cr Dozka-
Lt ri-s )/ CAP r g7 a- t4=*r $ 2s- n rr> poi> 9-01A. ¢
telt.4) rAA olvr1.o a-PP � — ta s �a v�slv�+. wrartre.42- ome- '� caKesac cF
tNL..ga• dg, - rite Po,graa soft W' r 64€4:blvr
1 r � e-e�/ .P,f) eyl w jU.." t�lsi,.l6 d L.04Dgo w ,e, t o)
4; �t4A,41 1 wl r►k c-�.• �v�tt l•FS5 l 4-p4y Tom.
rc1/4.0 t2t Tv S:X% r'i rum, o H 4 fW a - h IN Tk r� u Fr 'rn - ictr 15 Mo rsr -
w>� Io r + DtswNTNt•, c t,1_I NN OF ,/LA:emc/ ?t.9
.143(7. I tet- - fi SrrS Acr le:45 p t
l f F -N 1-6D tMcV tra1.L■4L t n•oST 1 i r_a.fil7 I N THE
6ec.c- v 13 13 14 S l MG 4- r l br I T.0.Qi, w GS tat st't '7U
t V,i 'r" ot% T 1 9 �kfo5 i Nt T- lane- So! L-5
T' fry SoMG o(lit..,s a+-t.D l r.?f G !iC �rre- SHP.c-a-c e
, o , evF.o ar � R � �. 4> � [-rti S� � kA St µ 6 o- wt - 2.-• re.tt ck. So+�tF
Trtz.4 Yz. wa-s .c73 v r 7 t N 1.5oi v, a-P.t%n. s _ u P ro
Sia44i i , fl LA VVI1. 1" *- - ? lo<,IFA is " fig SuBljP...DE_ t ,4F0(2, Se.+c•.4
> (Se- s t4 o4. t 4L-. ti - 'f -ns r5
Pte,,, 9I P & __
1 M Po P.ITp ¥ p-F -Q e rt> tsr, � L�t/F. A bP - n t9;
Su •06 vomit 'Fi In . v'Dj SPQR ] iwd2oS.5 T j &-1 t r�r 114 urys (G` a 2 u ss
& H O Nor \ F - 4 " C r A I ■ p - i(7 .6-S 177 D 1 . A . G , r D J . I Gt"{ r!A WCifl 1 i b ?P
V- I f.t FR 11-41)01 Seri
I t7KS0 F.2 b cilooFPotk. 01%� L.nIr.c ( G �A!MG
t'� X tress iYe. wt or' Y Q 0 A( A� w .P,F 12 o� r� S+-Quc P.4t,
1U_ VS/b6 fgessei -er, D�I,E(A 4 wt>5 vo wt. p..geo?S oi- - The tzs.
kt.wrir t• rcn1 ?Do L- I k M tri , Siif t0t.sD0" &k _ ec'r04 -4
This report presents opinions formed as a result of our observation of activities relating to geotechnical engineering. We rely on the contractor to comply with the plans and specifications
throughout the duration of the project irrespective of the presence of our representative. Our work does not include supervision or direction of the actual work of the contractor, his employees or
agents. Our firm will not be responsible for job or site safety on this project.
Attachments: S t (
Distribution: vnr frk Signed: ' � ` I l
" IWCU,tt7 S SoGT 64fiDS hb1`FA tNt 1i R rIcI .G_Q7
r W
0 41
W
In E-4 W
En C4 W 0 100 200
RI ( SCALE IN FEE T
n
N
- Uj
- -- -- -- TP�1? I/ – — [ouna - W th - - —
— - -- — // —_ ____ — •-- rte— / i
— 125__ Prop ed ` — 1 " ' Pro osed� / _ T P - 1 -54 i 71/1
----- � �� ,R -- , / j P r o posed
• 12.5 wilding - p - TP_14
�--�_. _�� \ M M _ - - - Build I)'� 1 1.
• • T -19; , ! �P'`v Tt % _� %� p' . TP -12 —
; �.TP i 11.5 I '
/ ._,1 l 1 ---1 i
. _
( \ ' 13.5 i — . `� _ . ..,,
�— •\ ��� -� Tp / TP -10 P -13 �� • 250__.. _. \ .,, , . • , . . 7 , , ,
. . ...,
, \, .. • , 4. ,-, ( i' ,I /I'
/------- �� — • �TP - — TP - _-- \ TP - _ _ • X3.5 _ 12 — -- ._ _ �1 • j \ 17 18.5 12 �.� -- — —
S.W. /Oth AME E – -
f I a. (' -- . W i
i;
u)
rzl
co
0
Cg
EXPLANATION:
0
in
TP - i i j TEST PIT
18.5 Uj
o DEPTH TO BOULDERS (IN FEET)
0
Q
__ BOULDERS NOT ENCOUNTERED TO
o
DEPTHS EXPLORED
o° Note: The locations of all features shown are approximate.
I
rn
° �� SITE PLAN
Reference: Base drawing produced from AutoCAD file Spect2.dwg entitled, "Tigard Triangle Masterplan," Geo ineers
dated 04/27/98, provided by LRS Architects. ` �/ FIGURE 2
FIELD REPORT File No.
GeoEngineers Inc. _ 4-z17-0 (-4r)
7504 SW Bridgeport Road Project: Date:
y Portland, Oregon 97224 SPeU•(f -- n 4p-e47 11240-4E
(503) 624 -9274 Owner: Report No.
Prepared by: Location: Arrival Time: Page:
of
Purpose of Visit: Weather: Depart. Time: Permit No.
p Uri r.iG? ESsu Iv S
►:TC, mss i
▪ n 4 .� •. r .. _ ¢ , es. A . e - two - f-._ 5
O r _ LV G-2.6 .
.1 _. i Sd-V?
4 - - •L� =u a.a y � �a : •a �tr aisi�lCl!ISG� =Sr�7�Yc�f�i - i 4
• .
• eXeLP Onor4 TUtCtf 1 0G6F/a NOT ,. SPeCs (WOO' °"i(
•
•
This report presents opinions formed as a result of our observation of activities relating to geotechnical engineering. We rely on the contractor to comply with the plans and specifications
throughout the duration of the proreet impactive of the presence of our representative. Our work does not include supervision or direction Of the actual work of the contractor. his employees or
agents. Our firm will not be responsible for lob or site safety on this etolect.
Attachments: Signed:
Distribution: •
G E 145 -87
•