Building Plan Review Response July 15, 1999
Re: Mountain Pacific Machinery
11705 SW 68th
PC #: 6 -10c
BVP #: 99 -00237
SIT #: 99 -00029
Following are responses and comments to the building and Site Plan Review for the above
referenced project. Comments are as noted:
ACCESSIBILITY
1. The finish surfaces of the walkway edge that adjoins the passenger discharge aisle,
and the passenger discharge aisle are designed to be flush with each other, and to
exclude any requirement for a curb ramp. See 1/A2, 1/SP1.
2. Per the State requirement, the clearance to the bottom of the accessible signage has
been revised from a height of 6' - 0", to a height of 7' - 0". See detail 3 /SP1.
3. The kitchen sink and cabinet area has been modified to comply with OSSC 1108.4.3,
and 1109. See detail No.'s 2/A5, 3/A5
4. Drawing A2 shows three exits from the building. According to:
OSSC 1109.9.1
General: Doors required to be accessible shall comply with section 1004 and
provisions of this section.
OSSC 1004.2.3.2 and 1004.2.3.3
These sections reference OSSC table 10 -A to determine the actual number of
exits required in a given situation.
OSSC table 10-A, for the use of offices, lists a minimum of two means of egress
where the number of occupants is at least 30.
Proposed first floor area: 2360.85 sf.
Table 10 -A occupant load factor: 100 sf.
Actual occupant load: 24 (23.6)
According to this table the occupant load is less than 30 (24), therefore requiring
only one exit from this building floor. The exits from this building floor are as
follows:
DENNIS E. BATKE
ARCHITECT, A RI. B.A
4/25/00 Activities for Case #: BUP1999 -00237
2:17:46 PM
Assigned Hold Updated
Activity Description Date 1 Date 2 Date 3 To Done By Disp. Level By Updated Notes
B UPC705 Foot/Found Insp 12/8/99 12/8/99 12/7/99 TLP PASS No Hold TLP 12/8/99 thickened slab footing for
canopy
B UPC705 Foot/Found Insp 12/8/99 12/8/99 12/7/99 TLP PASS No Hold TLP 12/8/99 this inspection for retaining wall
adjacent to structure
BUPC005 Application received 6/4/99 BON RECD No Hold TLP 12/6/99
BUPC008 Permit created 6/11/99 BON DONE No Hold BON 6/11/99
BUPC010 Check for prd. restrict. 6/11/99 BON DONE No Hold BON 6/11/99 Minor Modification letter
attached.
BUPC012 Plans routed to Plans Examiner 6/11/99 BON DONE No Hold BON 6/11/99
BUPC015 Plan Review Ltr. to Ofc. Svcs. 6/21/99 NOTE No Hold RDP 6/21/99 To typing pool 6/21/99
BUPCO24 Plans Approved by CPE 8/9/99 RDP DONE No Hold RDP 8/9/99
BUPCO22 Plans Approved /Routed to DSTs 8/9/99 RDP DONE No Hold RDP 8/9/99
BUPC520 Mechanical Permit Required 8/9/99 8/9/99 No Hold RDP 8/9/99
BUPC530 Electrical Permit Required 8/9/99 8/9/99 No Hold RDP 8/9/99
BUPC565 Plumbing Permit Required 8/9/99 8/9/99 No Hold RDP 8/9/99
B UPC705 Foot/Found Insp 8/9/99 8/9/99 11/1/99 TP PASS No Hold VT 11/1/99 all foundation work complete
per plans and detail 4/s 5
completed per plans.
BUPC725 Slab Insp 8/9/99 8/9/99 11/4/99 TLP PASS No Hold VT 11/4/99
BUPC740 Framing Insp 8/9/99 8/9/99 1/7/00 TLP PASS No Hold AKJ 1/9/00
BUPC750 Insulation Insp 8/9/99 8/9/99 1/10/00 TLP PASS No Hold AKJ 1/10/00
BUPC757 Shear Wall Insp 8/9/99 8/9/99 12/1/99 TLP PASS No Hold TLP 12/1/99
BUPC760 Gyp Board Insp 8/9/99 8/9/99 1/14/00 RB PART No Hold AKJ 1/18/00 do not cover any location that
has not been insp or app
BUPC762 Susp Ceilng Insp 8/9/99 8/9/99 2/7/00 TLP PASS No Hold AKJ 2/7/00
BUPC802 Final Inspection 8/9/99 8/9/99 3/8/00 TLP FAIL No Hold RB 3/9/00 1. SIT1999 -00029
2. Handrail required on steps
• to storage area AND on
handicap ramp.
3. Outside retaining wall
adjacent to handicap parking
requires a guardrail- (7 foot
drop to next level).
NOTE: ALL OTHER WORK
COMPLETED AND
INSPECTED.
BUPCO29 DST Post Review Completed 8/17/99 BON DONE No Hold BON 8/17/99 Ok to issue per Mark Roberts
this date. Needs signed TIF
payment option form before
issuing.
Page 1 of 2
4/25/00 Activities for Case #: BUP1999 -00237
•
2:17:46 PM
Assigned Hold Updated
Activity Description Date 1 Date 2 Date 3 To Done By Disp. Level By Updated Notes
BUPC090 (F) Ready to issue 8/17/99 BON DONE No Hold BON 8/17/99 Needs signed TIF payment
option form before issuing
permit.
BUPC100 (F) Issue permit 10/5/99 DEB DONE No Hold DEB 10/5/99
BUPC707 Footing Drain 10/26/99 10/26/99 10/26/99 TLP PASS No Hold JS 10/26/99
BUPC742 Roof naiing Insp 12/1/99 12/1/99 No Hold TLP 12/1/99
BUPC742 Roof nailng Insp 12/1/99 12/1/99 12/1/99 TLP PASS No Hold TLP 12/1/99
BUPD706 Foundation Insp 12/6/99 12/6/99 12/3/99 PASS No Hold TLP 12/6/99 footing for retaining wall
BUPC705 Foot/Found Insp 12/17/99 12/17/99 12/16/99 TLP PASS No Hold TLP 12/17/99 per revision to original plans
BUPA620 Foundation lnsp 12/30/99 TLP PASS No Hold AKJ 1/2/00
BUPC760 Gyp Board lnsp 1/18/00 1/18/00 1/14/00 RB PART No Hold AKJ 1/18/00 2nd insp this date
lower storage, drywall gar
header beam, protect struc
members
leave drywall off where plm insp
req, afterwards provide nailing
or fasteners as per. specs
BUPC760 Gyp Board Insp 1/19/00 1/19/00 1/19/00 TLP PASS No Hold AKJ 1/19/00
BUPC740 Framing Insp 2/7/00 2/7/00 2/7/00 TLP PASS No Hold AKJ 2/7/00 canopy ext bldg
BUPA065 HOLD for (note in activity) 2/11/00 JMT DONE No Hold JMT 2/11/00 no final until SITE has been
signed off
BUPA998 Phone call (note in activity) 2/25/00 JMT CALL No Hold JMT 2/25/00 final inspection request denied.
I called Don, 849 -3457
informed him that site,
mechanical and elr needs final
inspections before building final
BUPC802 Final Inspection 4/17/00 TLP PASS No Hold AKJ 4/17/00
BUPA990 (F) Issue Cert. of Occupancy 4/17/00 TLP DONE No Hold JMT 4/21/00
BUPA990 (F) Issue Cert. of Occupancy 4/21/00 JMT DONE No Hold ST 4/25/00 4 /25 /00- mailed to
owner/tenant/TVFD/file
BUPA995 File sent to records 4/25/00 JMT DONE No Hold JMT 4/25/00
BUPA994 Plans sent to records 4/25/00 JMT DONE No Hold JMT 4/25/00 plan in file
Page2of2