February 5, 2002
T0108092. CTI
Permit No. BUP2001 -00061
FIELD INSPECTION REPORT FILE COPY
DATES COVERED: January 28, 29, and 31, 2002
PROJECT: Green Office Complex
ADDRESS: 11560 SW 67 Ave — Tigard, OR
INSPECTOR: S. Smith — COP #544, OBOA #327, AWS #95050191
01- 28 -02: As requested, CTI representative was on site for structural steel inspection and the
following was noted.
1) Received samples of bolting, (1) 3 -7/8" diameter A -325 tension control bolting and (3) 1"
diameter A -325 tension control bolts (3 ", 3 % ", 2W). (3) samples of each size received and
transported to lab for Skidmore evaluation. Average shear tab separation on 7/8" diameter
bolts, 42 kips. Average shear .tab separation of 1" diameter, 63 kips. Both values are
satisfactory according to AISC Standards.
2) Performed walkdown of work area. Most steel erected at this time — approximately 50% of
bolting is complete. Reviewed changes in welding provided by contractor from structural
engineer. Welder certifications and WPS were satisfactory.
01- 29 -02: As requested, CTI representative was on site for a structural steel inspection and the
following was noted.
1) Per structural engineer, grid 12/A anchor bolt pattern change is satisfactory "as- built." This
is also true at grids 9/A and 11/A — see attached.
2) Base plate satisfactory at area requiring chipping out to thrust plate (area cleared prior to
column installation).
3) Began monitoring and inspection of welding provided for in supplied approved detail
(Alternative 4,5). Welding is approximately 20% complete. Work appears satisfactory at
this time. Work quality good. No problems to report at this time.
01- 31 -02: As requested, CTI representative was on site for a welding /bolting inspection and the
following was noted.
1) Visual examination was performed on welding per Alternate 4, 5 (revision of A, B, C, D, E,
F, G). Welding appeared to conform to AWS D1.1 Structural Steel Code Standards. WPS
and welder certifications appeared satisfactory.
TO108092.doc
: f 1
1 ,1:',
l 5't �`�//
V
1 {
H�
A
,Y t February 5, 2002
,` " T0108092.CTI
or
Page2of2
2) Visual examination was performed of connections using 7/8 ", as well as 1" diameter, A -325
bolting (tension control bolting). All shear tabs removed with (4) exceptions at C4, 3 grid
frame. (4) bolts required turn -of- the -nut tensioning due to joint geometry and stripped
spline. Bolts now tension satisfactorily.
This concludes structural steel inspection for this project.
Our reports pertain to the materials inspected /tested only. Information contained herein is not to
be reproduced, except in full, without prior authorization from this office.
If there are any further questions regarding this matter, please do not hesitate to contact this
office.
Respectfully submitted,
CARL '1 TESTING, INC.
►. ; W. Leach
C Executive Officer
S' .ab
Attachments
cc: Green Investments
City of Tigard Building Department
Tim Covert Engineering
T0108092.doc
F Main Office Salem Office Bend Office
P.O. Box 23814 4060 Hudson Ave., NE P.O. Box 7918 •
Tigard, Oregon 97281 Salem, OR 97301 Bend, OR 97708
r' rlson " Testing Inc. Phone (503) 684 -3460 Phone (503) 589 -1252 Phone (541) 330 -9155
FAX (503) 684 -0954 FAX (503) 589 -1309 FAX (541) 330 -9163
March 12, 2002
T0108092. CTI
Permit No. BUP2001 -00061
FIELD INSPECTION REPORT
DATES COVERED: March 4, 2002
PROJECT: Green Office Complex
ADDRESS: 11560 SW 67 Ave — Tigard, OR
INSPECTOR: S. Smith — COP#544, OBOA #327, AWS#95050191
03- 04 -02: As requested, CTI representative was on site for a structural steel inspection. Visual
examination of (2) GIu -Lam buckets, top ridge line, north and south, was performed. Work
conformed to direction provided by Tim Covert, structural engineer -of- record, to align buckets
with columns.
Welding appeared to conform to AWS D1.1 Structural Steel Code Standards for weld quality
and workmanship.
***CHECK ONE BOX ONLY*** YES NO
1. This is a preliminary inspection only. — OR — ❑
2. The work inspected conforms to acceptance criteria listed above. If "No," the portions of the
work that are non - conforming items are clearly stated above and will be added to the NCL.
Remaining portions of the work, which are not preliminary in nature, are to be considered as ® ❑
conforming.
Our reports pertain to the materials inspected /tested only. Information contained herein is not to
be reproduced, except in full, without prior authorization from this office.
If there are any further questions regarding this matter, please do not hesitate to contact this
office.
Respectfully submitted,
CARLS e/ 4 TESTING, INC.
Dou as W. Leach
i C ' :• ' Executive Officer
S. sab
cc: Green Investments
City of Tigard Building Department
Tim Covert Engineering
t
rtr
i '. P '* ` 03-04 -02 fr.doc
Main Office . Salem Office Bend Office
P.O. Box 23814 :. 4060 Hudson Ave., NE P.O. Box 7918
/ • Tigard, Oregon 97281 Salem, OR 97301 Bend, OR 97708
arl s on Te s tin , Inc. Phone (503) 684 -3460 Phone (503) 589 -1252 Phone (541 330 -9155
FAX (503) 684 -0954 FAX (503) 589 -1309 FAX (541) 330 -9163
January 30, 2002
T0108092.CTI
Permit No.: BUP2001 -00061 •
SHOP INSPECTION REPORT @ Wshart Welding & General Fabrication
DATES COVERED: January 25, 2002
PROJECT: Green Office Complex
ADDRESS: 11560 SW 67 Ave — Tigard, OR
INSPECTOR: S. Smith — COP#544, OBOA #327, AWS #95050191
01- 25 -02: As requested, a CTI representative was at the shop of Wishart Welding &
General Fabrication this date to witness repairs performed on misfabrication on columns.
Visual examination of fit up as well as monitoring of in- process welding was performed.
•
All work observed this date appeared to conform to AWS D1.1 structural steel code standards
for weld quality and workmanship.
Our reports pertain to the materials inspected /tested only. Information contained herein is not to
be reproduced, except in full, without prior authorization from this office.
If there are any further questions regarding this matter, please do not hesitate to contact this
office.
Respectfully submitted,
CARL ;1 TESTING, INC.
•
Do r W. Leach
C • - • Executive Officer
ck
cc: Green Investments
City of Tigard Building Department
Tim Covert Engineering
T0108092.sr.doc
Main Office Salem Office Bend Office
P.O. Box 23814 4060 Hudson Ave., NE P.O. Box 7918
Tigard, Oregon 97281 Salem, OR 97301 Bend, OR 97708
Carlson 'Vesting Inc. 4� aC • Phone (503) 684 -3460 Phone (503) 589 -1252 Phone (541) 330 -9155
FAX (503) 684 -0954 FAX (503) 589 -1309 FAX (541) 330 -9163
October 9, 2001
T0108092.CTI
Permit No. BUP2001 -00061
SHOP INSPECTION REPORT @ Wishart Welding
DATES COVERED: October 3 and 4, 2001
PROJECT: Green Office Complex
ADDRESS: 11560 SW 67 Avenue — Tigard, OR
INSPECTOR: J. King COP #729, WABO #KIN821850, OBOA#416
10- 03 -01: CTI representative was at the shop of Wishart Welding, at the request of Matt with
Wishart, for continuous inspection of welding on plate to column connections.
Note: The drawings (shop) are unclear as to whether the weld was partial joint penetration or
complete joint penetration double bevel. The structural engineer verified (via phone) depth of
groove is weld size needed (except that 3/8" double bevel on 5/8" plate is not possible), in which
case 5/16" is okay. (The plate is beveled to a point.) Also, the 1 -3/8" plates should have 5/8"
bevels. All plates are beveled to a point though.
Work is in progress on columns 3A x 2 and 2A x 1 at this time by certified welders using WPS's
on specified steel.
10- 04 -01: CTI representative was at the shop of Wishart Welding, at the request of Matt with
Wishart, for continuous inspection of plate to column partial joint penetration and oversized fillet
welding. Welding is being performed within AWS prequalification requirements and WPS's by
certified welders.
Work is in progress on columns 3A x 2 and 2A x 1. This inspector is being' relieved by CTI.
representative S. Smith.
Our reports pertain to the materials inspected /tested only. Information contained herein is not to
be reproduced, except . in full, without prior authorization from this office.
If there are any further questions regarding this matter, please do not hesitate to contact this
office.
Respectfully submitted,
CA RLS TESTING, INC.
J /
Do s W. Leach
Chi; Executive Officer .
J -ab
c Green Investments
City of Tigard Building Dept.
Tim Covert Engineering
Main Office Salem Office Bend Office
P.O. Box 23814 4060 Hudson Ave., NE P.O. Box 7918
�1
Tigard, Oregon 97281 Salem, OR 97301 Bend, OR 97708
Carlson Testing, Inc. Phone (503) 684 -3460 Phone (503) 589 -1252 Phone (541) 330-9155
FAX (503) 684 -0954 FAX (503) 589 -1309 FAX (541) 330 -9163
October 5, 2001
T0108092.CTI
Permit No. BUP2001 -00061
SHOP INSPECTION REPORT @ Wishart Welding
DATES COVERED: October 2, 2001
PROJECT: Green Office Complex
ADDRESS: 11560 SW 67 Avenue — Tigard, OR
INSPECTOR: C. Griffith, COP #731, WABO #GRI72 -9067, OBOA#414
10- 02 -01: CTI representative was at the shop of Wishart Welding for continuous inspection of
welding at complete joint penetration welds and 3/8" fillets per supplied drawings, sheets 1, 2,
and 3 of 13. WPS's and mill certificates were reviewed and on file at office.
Welders: Tim Wishart CTI #1385 Expiration Date: 05 -09 -02
Mike McCollumn CTI #1033 Expiration Date: 07 -24 -02
Cary Hagedorn CTI #1032 Expiration Date: 05 -15 -02
Filler metal = Front Arc 711, E71T -1, .045" and .052 ". Shielding gas = CO at 35 to 40 CFH.
Weld machine settings were monitored with a calibrated volt/amp meter ( #1519):
- Tim Wishart Amps 240 -250 Volts 24-25
Mike McCollumn Amps 240 -255 Volts 24 -25
Cary Hagedorn Amps 220 -235 Volts 25 -26
Reading were within range of WPS. Columns in process are piece mark numbers 3Ax2 and
2Ax1. Fit -ups were inspected and found acceptable. Root passes and backgouging observed.
No columns complete at end of shift.
Our reports pertain to the materials inspected /tested only. Information contained herein is not to
be reproduced, except in full, without prior authorization from this office.
If there are any further questions regarding this matter, please do not hesitate to contact this
• office.
Respectfully submitted,
CARL t TESTING, INC.
/ _
/i�
9 glas W. Leach
ief Executive Officer
.
i G /sab
cc: Green Investments
City of Tigard Building Dept.
Tim Covert Engineering
i , Main Office Salem Office
Bend Office
P.O. Box 23814 4060 Hudson Ave., NE P.O. Box 7918
Tigard, Oregon 97281 Salem, OR 97301 Bend, OR 97708
Carlson Testing Inc. Phone (503) 684-3460 Phone (503) 589 -1252 Phone (541) 330 -9155
9 FAX (503) 684 -0954 FAX (503) 589 -1309 FAX (541) 330 -9163
October 16, 2001
T0108092.CTI
Permit No. BUP2001 -00061
SHOP INSPECTION REPORT @ Wishart Welding
DATES COVERED: October 4, 5, 8, 9, and 11, 2001
PROJECT: Green Office Complex
ADDRESS: 11560 SW 67 Tigard, OR
INSPECTOR: S. Smith COP #544, OBOA #327
J. King COP #729, WABO #KIN821850, OBOA#416
10 -04 -01 (S. Smith): CTI representative was at the shop of Wishart Welding and relieved CTI
representative, J. King, to continue monitoring production of partial penetration welds on
columns. Visual examination was also made of the following beams:
(1) 5B with hanger (2) 7B
(2) 5A - (1) 6B with hanger
(1) 5B with hanger (3) 7A
(1) 6B with hanger (1) 5B
(1) 5A (1) 5A
Visual examination of this work, as well as all work observed on columns, conformed to
approved drawing and AWS D1.1 Structural Steel Code Standards.
10 -05 -01 (S. Smith): CTI representative was at the shop of Wishart Welding and continued
monitoring. All work observed this date appeared to conform to AWS D1.1 Structural Steel
Code Standards for Weld Quality and Workmanship.
10 -08 -01 (S. Smith): CTI representative was at the shop of Wishart Welding this date to
continue monitoring production of partial penetration welds. Visual examination of fit -up, as well
as in- process weld monitoring, was performed. All work observed this date appeared to
conform to AWS D1.1 Structural Steel Code Standards for Weld Quality and Workmanship.
10 -09 -01 (J. King): CTI representative was at the shop of Wishart Welding, at their request, to
observe and monitor the welding of partial joint penetration and oversized fillet welds. Work is
in progress on pieces 1A and 1A opposite by certified welders on specified steel. Another CTI
representative (S. Smith) will be relieving this inspector upon arrival and performing the required
inspections.
10 -09 -01 (S. Smith): CTI representative was at the shop of Wishart Welding, and relieved CTI
representative, J. King, this date to perform monitoring of partial penetration weld production.
The following items were completed at this time:
(2)Mk1A (1)Mk2AOpp
(1) Mk 1A Opp (2) Mk 3A
(1) Mk 2A (1) Mk 3A Opp
l
Y� * T
6
1 ,, 4. M
�n . G 1 p. -
"�
4
r ,n .9
' xv
t�' a 0 -
,l '9 {t'
L
a l ,I exammation disclosed this work to conform to AWS D1.1 Structural Steel Code
xF Standards' Weld Quality and Workmanship.
yh y It E+
yy} .
, �w' 10 11 =01 (S. Smith): CTI representative was at the shop of Wishart Welding this date to
Visual
° = y' exa oftwelding production
wel as interpass weld cleaning, was observed. All w examined
` ,x„',"c; this date appeared to conform to AWS D1.1 Structural Steel Code Standards, as well as
"= :"'L approved drawings. Beams examined are listed below:
° _ ' ' " ,t. (2) 6B with hanger (1) 5B
(2) 7B (4) 6A
(1) 5A
Our reports pertain to the materials inspected /tested only. Information contained herein is not to
be reproduced, except in full, without prior authorization from this office.
If there are any further questions regarding this matter, please do not hesitate to contact this
office.
Respectfully submitted,
CARLSON TESTING, INC.
Douglas W. Leach
Chief Executive Officer
SS /JK/sab
cc: Green Investments
City of Tigard Building Dept.
Tim Covert Engineering
Main Office Salem Office Bend Office
P.O. Box 23814 4060 Hudson Ave., NE P.O. Box 7918
Tigard, Oregon 97281 Salem, OR 97301 Bend, OR 97708
Carlson Testing, Inc • P FAX (503) 684 09540 Phone (503) 589 -1252 Phone (541) 330-9155
FAX (503) 589 -1309 FAX (541) 330 -9163
November 7, 2001
T0108092.CTI
Permit No.: BUP2001 -00061
SHOP INSPECTION REPORT @ Wishart Welding
DATES COVERED: October 16 and 17, 2001
PROJECT: Green Office Complex
ADDRESS: 11560 SW 67 Avenue — Tigard, OR
INSPECTOR: S. Smith — COP#544, OBOA #327, AWS #95050191
10 16 - 01: CTI representative was at the shop of Wishart Welding to examine fit -up of last 5
columns.
Visual examination of bevel preps as well as in process weld monitoring was performed.
All work observed this date appeared to conform to AWS D1.1 structural steel code standards
for weld .quality.
10 17 - 01: CTI representative was at the shop of Wishart Welding and continued monitoring
welding of 3/8" welds on stiffeners, as well as partial penetration welds.
Final examination was performed on columns 3A (opp), 3B, and 2 pcs 3B (opp).
All work examined appeared to conform to AWS D1.1 structural steel code standards.
Our reports pertain to the materials inspected /tested only. Information contained herein is not to
be reproduced, except in full, without prior authorization from this office.
If there are any further questions regarding this matter, please do not hesitate to contact this
office.
Respectfully submitted,
CARLS > TESTING, INC.
14 2 as W. Leach
Chief Executive Officer
SS /ck
cc: Green Investments
City of Tigard Building Department
Tim Covert Engineering
T0108092.FR.doc