DIR1991-00003 DATE: 4/1/1991
CODE SECTIONS: 18.160.050 `i I - 3'
1,- TQPIC1 Subdivision: Phased Development Plat Recording Timelines
* City Attorney's Office Interpretation
INTERPRETATION: Regarding TMC 18.160.050, you have asked me to respond to the questions of what time
limits, if any, exist for filing of the final plat for Phase III, what does the applicant need to do
to record the final plat, and what arrangements can be made for the required security
deposit for public improvements if the applicant is not the owner of the project at the time
the final plat is filed?
The Tigard code contains no specific provisions which determine the answer to the
question concerning the time of filing the final plat. The appropriate thing for the hearings
officer to have done in attaching the condition concerning the phased development, was to
include as a part of that condition, a time schedule for developing the subdivision in
phases. In the absence of such time schedule, my suggestion is that you look to other
relevant provisions of the code relating to the time period required for filing a final plat and
make a reasonable interpretation as applied to this set of facts.
One such interpretation is as follows: TMC 18.160.040(a)(1) requires that a final plat be
filed within one year and six months of the date of the preliminary plat approval or that
preliminary plat approval will lapse. TMC 18.160.140, however, requires that the final plat
be filed within one year of the date of the preliminary plat approval. These sections directly
conflict, both indicate that the sections were amended by Ordinance 89 -06, and I find
nothing in the code to direct how this conflict should be reconciled.
Using either the one year or one and one -half year requirement and starting with the
preliminary approval date of May of 1987, you could "stack" the time limits for the filing of
the preliminary plat of each phase, allowing the maximum time allowed by the referenced
code sections. Using that approach, the final plat for Phase I would need to have been
filed, using the year and one -half requirement, by November of 1988. The final plat for
Phase II would need to have been filed by May of 1990. The final plat for Phase III would
need to have been filed by November of 1991. Using a one (1) year period, the final plat
for Phase I would need to have been filed by May of 1988, Phase II, May of 1989, and
Phase III, May of 1990.
An alternative approach to allowing the maximum time allowed by the code, would be to
run the filing periods from the date of the filing of the final plat of the preceding phase. I do
not have the final plat filing dates for Phases I and II, so I cannot project the specific
dates. However, assuming that the final plat for Phase I was filed on January 1, 1988, the
filing of the final plat for Phase II would occur either one, or one and one -half years later.
The filing date for the final plat filing for Phase III would occur either one, or one and one -
half years from the actual date of filing of the final plat for Phase II.
TMC 18.32.250(0(3) requires that a condition of approval which contains no time limit for
completion must be fulfilled within one year of the date of approval. The approach outlined
above is consistent with that requirement if the phasing requirement is deemed satisfied by
the filing of the final plat for the first phase.
During our discussion on the phone, you suggested an alternative approach which would
require the filing of the final plats for all phases to have occurred simultaneously. That is a
possible interpretation of the language of the code and is perhaps as reasonable as what I
have set forth above. One thought came to mind after our discussion which may impact
your choice of approaches and concerns the requirement of the posting of security for
public improvements prior to the filing of the final plat. If one of the purposes of phasing a
development is to spread out the financial commitment of the applicant over a period of
time allowing for the development and the sale of lots in phases, then an interpretation
which required the posting of security for public improvements of all phases at one time
and required all construction to be completed within two years, pursuant to TMC
18.160.050, would seem to run counter to one of the primary purposes of phasing a
development. The sequential interpretation which I have suggested above is consistent
with the financial impact objective of phasing developments.
I suggest that you review the referenced sections of the code and make an interpretation,
in writing, which takes into account the various sections of the code plus the condition of
approval, and reconciles those provisions in a rational manner. If you determined that the
time period for filing the final plat for Phase III has passed, I would suggest that you look at
the possibility of having the developer file for an extension of that time period pursuant to
TMC 18.160.040(b), although that remedy may not be available due to the lapsing of the
preliminary approval.
Your second question concerns what requirements need to be met in order to file the final
plat for Phase III. TMC 18.160.140, .150, .160, .170, .190, and .200 provide the
procedural requirements for the filing of a final plat. The applicant will need to follow the
procedures and meet the requirements of those sections. If the person with whom you are
dealing on this matter is not the record owner of the property, that person must present in
writing the authorization of the record owner for the person to act as the agent of the owner
in the filing of the final plat. TMC 18.160.030(a).
The last question concerns the filing of security in conjunction with the filing of the final
plat. The applicant has requested that the City accept, as security, retaining physical
possession of the permits allowing development until after the City is provided with a
satisfactory set aside letter or bonding after the final plat has been filed. The City code
requires the posting of security prior to the City signing off its approval of the final plat,
which is a prerequisite before filing.
If the City chooses to, it may, but is not required to, enter into an agreement with the
developer containing the following characteristics; 1) The City would sign the final plat
indicating its approval, 2) The City would hold development permits until after appropriate
security has been posted, 3) The City would receive the actual security documents,
executed by the appropriate parties, and hold them essentially in escrow until authorization
from the surety indicating that the forms have become effective, and 4) The City would
receive from the applicant an executed application for vacation of the plat to be filed only in
the case of the failure of the applicant to complete its obligations regarding the posting of
security in conjunction with this subdivision. If the City chooses to follow this approach,
would be glad to work with you on the form that would be appropriate.
O'DONNELL, RAMIS, CREW & CORRIGAN
ATTORNEYS AT LAW
BALLOW & WRIGHT BUILDING
1727 N.W. Hoyt Street
Portland, Oregon 97209
TELEPHONE: (503) 222 -4402
FAX: (503) 243 -2944
DATE: April 1, 1991
TO: Jerry Offer, Tigard Community Development
City of Tigard
FROM: James M. ColemaQ, City Attorney's Office
RE: Morning HilKSubdivision Procedural Ouestion
This memo is a follow -up to the phone conversation we had on March
29, concerning the processing of the request for filing of a final
plat for Phase III of the referenced subdivision. You informed me
that in May of 1987, the Morning Hill Subdivision received
preliminary plat approval with a condition of approval specifically
authorizing phased develop ' ent pur ant_to._TMC- 111- 16D,_()_50 . The
condition of atrov , by e' t in a time schedule_
s__
a_ree 1U x'ed__ L.y th,�t a r ten_. Phase I of e sub ' v was
S ..
commenced within one year of the approval. Phase II was commenced
at some later period of time and the request now is for the filing
of the final plat of Phase III.
You have informed me that Keith Liden has given the applicant the
opinion that the final plat for Phase III must be filed by May 11,
1991. That opinion was based upon Keith's inter re ation of the
two year construction limit language in TM- 18.160.05 . have
aske m- to respond to the_questions of what • emits, if any,
exist for the f i 1 i ng_oL the final plat for Phase III, what t does the
plic
4pant need_to..do to record the final plat, and what
arrangements can be made for the required security deposit for
public improvements if the applicant is not the owner of the
project at the time the final plat is filed. The Tigard code contains no specific provisions which determine the
answer to ,the question concerning the time of filing the final
plat. The appropriate thing for the hearings officer to have done
in attaching the condition concerning the phase development, was
to include as a part of that condition a time schedule for
developing the subdivision in phases. In the absence of such time
schedule, my suggestion is that you look to other relevant
provisions of the code relating to the time period required for
filing a final plat and make a reasonable interpretation as applied
to this set of facts.
O'DONNELL, RAMIS, CREW & CORRIGAN
Memo re: Morning Hill Subdivision Procedural Questions
April 1, 1991
Page 2
One such interpretation is as follows: TMC 18.160.040(a)(1)
requires that a final plat be filed within one year and six months
of the date of the preliminary plat approval or that preliminary
plat approval will lapse. TMC 18.160.140, however, requires that
the final plat be filed within one year of the date of the
preliminary plat approval. These sections directly conflict, both
indicate that the sections were amended by Ordinance 89 -06 and I
find nothing in the code to direct how this conflict should be
reconciled.
Using either the one year or one and one -half year requirement and
starting with the preliminary approval date of May of 1987, you
could "stack" the time limits for the filing of the preliminary
plat of each phase, allowing the maximum time allowed by the
referenced code sections. Using that approach, the final plat for
Phase I would need to have been filed, using the year and one -half
requirement, by November of 1988. The final plat for Phase II
would need to have been filed by May of 1990. The final plat for
Phase III would need to have been filed by November of 1991. Using
a one (1) year period, the final plat for Phase I would need to
have been filed by May of 1988, Phase II, May of 1989, and Phase
III, May of 1990.
An alternative approach to allowing the maximum time allowed by
code would be to run the filing periods from the date of the filing
of the final plat of the preceding phase. I do not have the final
plat filing dates for Phases I and II so I cannot project the
specific dates. However, assuming that the final plat for Phase
I was filed on January 1, 1988, the filing of the final plat for
Phase II would occur either one or one and one -half years later.
The filing date for the final plat filing for Phase III would occur
either one or one and one -half years from the actual date of filing
of the final plat for Phase II.
TMC 18.32.250(f)(3) requires that a condition of approval which
contains no time limit for completion must be fulfilled within one
year of the date of the approval. The approach outlined above is
consistent with that requirement if the phasing requirement is
deemed satisfied by the filing of the final plat for the first
phase.
During our discussion on the phone, you suggested an alternative
approach which would require the filing of the final plats for all
phases to have occurred simultaneously. That is a possible
interpretation of the language of the code and is perhaps as
`O'DOk ELL, RAMIS, CREW & CORRIGAN
Memo re: Morning Hill Subdivision Procedural Questions
April 1, 1991
Page 3
reasonable as what I have set forth above. One thought came to
mind after our discussion which may impact your choice of
approaches and concerns the requirement of the posting of security
for public improvements prior to the filing of the final plat. If
one of the purposes of phasing a development is to spread out the
financial commitment of the applicant over a period of time
allowing for the development and the sale of lots in phases, then
an interpretation which required the posting of security for public
improvements of all phases at one time and required all
construction to be completed within two years, pursuant to TMC
18.160.050, would seem to run counter to one of the primary
purposes of phasing a development. The sequential interpretation
which I have suggested above is consistent with the financial
impact objective of phasing developments.
I suggest that you review the referenced sections of the code and
make an interpretation, in writing, which takes into account the
various sections of the code plus the condition of approval, and
reconciles those provisions in a rational manner. If you
determined that the time period for filing the final plat for Phase
III has passed, I would suggest that you look at the possibility
of having the developer file for an extension of that time period
pursuant to TMC 18.160.040(b), although that remedy may not be
available due to the lapsing of the preliminary approval.
Your second question concerns what requirements need to be met in
order to file the final plat for Phase III. TMC 18.160.140, .150,
.160, .170, .190, and .200 provide the procedural requirements for
the filing of a final plat. The applicant will need to follow'the
procedures and meet the requirements of those sections. If the
person with whom you are dealing on this matter is not the record
owner of the property, that person must present in writing the
authorization of the record owner for the person to act as the
agent of the owner in the filing of the final plat. TMC 18.160.030
(a) .
The last question concerns the filing of security in conjunction
with the filing of the final plat. The applicant has requested
that the City accept, as security, retaining physical possession
of the permits allowing development until after the City is
provided with a satisfactory set aside letter or bonding after the
final plat has been filed. The City code requires the posting of
security prior to the City signing off its approval of the final
plat, which is a prerequisite before filing.
'O'DONNELL, RAMIS, CREW & CORRIGAN
Memo re: Morning Hill Subdivision Procedural Questions
April 1, 1991
Page 4
If the City chooses to it may, but is not required to, enter into
aN agreement with the developer containing the following
characteristics: 1) The City would sign the final plat indicating
its approval, 2) The City would hold development permits until
after appropriate security has been posted, 3) The City would
receive the actual security documents, executed by the appropriate
parties, and hold them essentially in escrow until authorization
from the surety indicating that the forms have become effective,
and 4) The City would receive from the applicant an executed
application for vacation of the plat to be filed only in the case
of the failure of the applicant to complete its obligations
regarding the posting of security in conjunction with this
subdivision. If the City chooses to follow this approach, I would
be glad to work with you on the form that would be appropriate.
If you have any questions concerning this memo, please give me a
call.
Original Memorandum to: Jerry Offer, Tigard Community Development
Copy to: City of Tigard /Community Development File
JMC:dd
4/1/91
jmc \tigard\900244