Tigard Street (Fanno Creek) Bridge Replacement
Comprehensive Plan Amendment, Sensitive Lands Review, Minor Modification
CPA2024-0001/SLR2024-00002/MMD2024-0002
Tigard Planning Commission
February 3rd, 2025
1
Applicant Team Introductions
Applicant – City of Tigard Public Works
Applicant’s Consultant – DOWL
2
Land Use Request Summary
Type III-Modified Comprehensive Plan Amendment for proposed impacts to designated significant wetlands and Fanno Creek vegetated corridors identified on Tigard’s “Wetland and Stream
Corridors Map
Sensitive Lands Review for work occurring within the regulated floodway and special flood hazard area (100-year floodplain)
Minor Modification to the Dirksen Nature Park CUP (CUP 2013-00001) in order to construct a new stormwater bioretention facility within the park’s boundary.
3
Purpose and Need
Existing bridge was constructed in 1958 and was identified for replacement based ODOT’s 2016 bi-annual bridge inspection report.
Existing bridge’s road surface is prone to flooding and is structurally deficient. Emergency repairs were completed in 2017 with the understanding the bridge would be replaced.
Proposed bridge structure is seismically resilient and is above the 100-year floodplain.
Provides safer conditions for vehicles, cyclists and pedestrians.
Project is identified on Tigard’s Capital Improvements Plan (CIP) as project #95060
4
Future Condition
5
Next Steps and Timeline
6
Questions?