D & D Concrete And Utilities, Inc ~ 32500022
ACITY OF TIGARD - CONTRACT SUMMARY & ROUTING FORM
Contract Overview
Contract/Amendment Number: 32500022a1
Contract Start Date: 09/04/2024 Contract End Date: 06/30/2025
Contract Title: 2024 ADA Ramp Improvements
Contractor Name: D & D Concrete and Utilities Inc.
Contract Manager: Nichole George
Department: ENG
Contract Costs
Original Contract Amount: $534,503.00
Total All Previous Amendments: n/a
Total of this Amendment: n/a
Total Contract Amount: $534,503.00
Procurement Authority
Contract Type: Public Improvement
Procurement Type: Formal ITB >$150K
Solicitation Number: 2024-05
LCRB Date: 09/03/2024
Account String: Fund-Division-Account Work Order – Activity Type Amount
FY 25 4608000-56005 CP95066-CONS $534,503.00
FY
Contracts & Purchasing Approval
Purchasing Signature:
Comments: Extend Substantial completion date
DocuSign Routing
Route for Signature Name Email Address
Contractor Don Nienke don@ddcui.com
City of Tigard Brian Rager brianr@tigard-or.gov
Final Distribution
Contractor Don Nienke don@ddcui.com
Project Manager Nichole George nicholeg@tigard-or.gov
Project Manager Shauna Large shaunal@tigard-or.gov
Buyer Toni Riccardi tonir@tigard.or.gov