Loading...
HomeMy WebLinkAboutKittelson & Associates ~ 32500039 CITY OF TIGARD - CONTRACT SUMMARY & ROUTING FORM Contract Overview Contract/Amendment Number: 32500039 Contract Start Date: 01/03/2025 Contract End Date: 02/28/2026 Contract Title: McDonald Street Engineering Services Contractor Name: Kittelson & Associates Contract Manager: Courtney Furman Department: ENG Contract Costs Original Contract Amount: $1,559,099.00 Total All Previous Amendments: n/a Total of this Amendment: n/a Total Contract Amount: $1,559,099.00 Procurement Authority Contract Type: Personal Services Procurement Type: Formal RFP >$150K Solicitation Number: 2024-25 LCRB Date: 12/10/2024 Account String: Fund-Division-Account Work Order – Activity Type Amount FY 25 4608000 56006-95074 $500,000.00 FY 26 4608000 56006-95074 $1,059,099.00 FY Contracts & Purchasing Approval Purchasing Signature: Comments: New contract DocuSign Routing Route for Signature Name Email Address Contractor Anthony Yi ayi@kittelson.com City of Tigard Steve Rymer stever@tigard-or.gov Final Distribution Contractor Anthony Yi ayi@kittelson.com Project Manager Courtney Furman courtneyf@tigard-or.gov Project Manager Shauna Large Shaunal@tigard-or.gov Buyer Toni Riccardi tonir@tigard-or.gov City of Tigard | 13125 SW Hall Blvd., Tigard, OR 97223 | (503) 639-4171 | www.tigard-or.gov City of Tigard Qualification – Based Request for Proposal (RFP) MCDONALD STREET ENGINEERING SERVICES RFP 2025-08 Proposals Due: Tuesday, October 8, 2024 – 10:00 a.m. local time Proposer must submit one (1) electronic copy in portable document format (pdf). Submit Proposals To: ContractsPurchasing@tigard-or.gov Direct Questions To: Toni Riccardi Phone: (503) 718-2518 Email: tonir@tigard-or.gov Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 2 ATTACHMENT C CITY OF TIGARD, OREGON PERSONAL SERVICES CONTRACT MCDONALD STREET ENGINEERING SERVICES THIS AGREEMENT made and entered into this 11th day of December, 2024 by and between the City of Tigard, a municipal corporation of the State of Oregon, hereinafter called City, and Kittelson & Associates, hereinafter called Contractor. RECITALS WHEREAS, the City’s 2025-2026 fiscal year budget provides for services related to engineering services; and WHEREAS, City has need for the services of a company with a particular training, ability, knowledge, and experience possessed by Contractor, and WHEREAS, City has determined that Contractor is qualified and capable of performing the professional services as City does hereinafter require, under those terms and conditions set forth, THEREFORE, the Parties agree as follows: 1. SERVICES TO BE PROVIDED Contractor will initiate services immediately upon receipt of City’s notice to proceed together with an executed copy of this Agreement. Contractor agrees to complete work that is detailed in Exhibit A, incorporated herein by reference. 2. EFFECTIVE DATE AND DURATION This Agreement is effective upon the date of execution and expires on February 28, 2026, unless otherwise terminated or extended. All work under this Agreement must be completed prior to the expiration of this Agreement. 3. COMPENSATION The City agrees to pay Contractor in accordance with the fee schedule outlined in Exhibit A. The total amount paid to the Contractor by the City may not exceed One Million Five Hundred Fifty-Nine Ninety-Nine and No/100 Dollars ($1,559,099.00). Payments made to Contractor will be based upon the following applicable terms: A. Payment by City to Contractor for performance of services under this Agreement includes all expenses incurred by Contractor, with the exception of expenses, if any, identified in this Agreement as separately reimbursable. B. Payment will be made in installments based on Contractor’s invoice, subject to the approval of the City Manager, or designee, and not more frequently than monthly. Unless otherwise agreed, payment will be made only for work actually completed as of the date of invoice. C. Payment by City releases City from any further obligation for payment to Contractor for services performed or expenses incurred as of the date of the invoice. Payment may not be considered acceptance or approval of any work or waiver of any defects therein. Contract Number 32500039 Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 3 D. Contractor must make payments promptly, as due, to all persons supplying labor or materials for the performance of the work provided for in this Agreement. E. Contractor may not permit any lien or claim to be filed or prosecuted against the City on any account of any labor or material furnished. F. Contractor will pay to the Department of Revenue all sums withheld from employees pursuant to ORS 316.167. G. Contractor will pay all contributions or amounts due the Industrial Accident Fund from the contractor or any subcontractor. H. If Contractor fails, neglects, or refuses to make prompt payment of any claim for labor or services furnished to Contractor or a subcontractor by any person as such claim becomes due, City’s Finance Director may pay such claim and charge the amount of the payment against funds due or to become due the Contractor. The payment of the claim in this manner does not relieve Contractor or their surety from obligation with respect to any unpaid claims. I. Contractor will promptly, as due, make payment to any person, co-partnership, association, or corporation, furnishing medical, surgical, and hospital care or other needed care and attention, incident to sickness or injury, to the employees of Contractor, of all sums that Contractor agrees to pay for the services and all moneys and sums that Contractor collected or deducted from the wages of employees pursuant to any law, contract, or agreement for the purpose of providing or paying for services. J. Contractor and its employees, if any, are not active members of the Oregon Public Employees Retirement System and are not employed for a total of 600 hours or more in the calendar year by any public employer participating in the Retirement System. K. Contractor must obtain, prior to the execution of any performance under this Agreement, a City of Tigard Business License. The Tigard Business License is based on a calendar year with a December 31st expiration date. New businesses operating in Tigard after June 30th of the current year will pay a pro-rated fee though the end of the calendar year. L. The City certifies that sufficient funds are available and authorized for this Agreement during the current fiscal year. Funding during future fiscal years is subject to budget approval by Tigard’s City Council. 4. OWNERSHIP OF WORK PRODUCT City is the owner of and is entitled to possession of any and all work products of Contractor which result from this Agreement, including any computations, plans, correspondence, or pertinent data and information gathered by or computed by Contractor prior to termination of this Agreement by Contractor or upon completion of the work pursuant to this Agreement. Contractor shall have no liability should its work product be revised by others without its consent or utilized for any other purpose than that contemplated under this Agreement. 5. ASSIGNMENT/DELEGATION Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 4 6. 7. 8. Neither party may assign, sublet or transfer any interest in or duty under this Agreement without the written consent of the other and no assignment has any force or effect unless and until the other party has consented. If City agrees to assignment of tasks to a subcontract, Contractor is fully responsible for the acts or omissions of any subcontractors and of all persons employed by them. Neither the approval by City of any subcontractor nor anything contained herein creates any contractual relation between the subcontractor and City. The provisions of this Agreement are binding upon and will inure to the benefit of the parties to the Agreement and their respective successors and assigns. STATUS OF CONTRACTOR AS INDEPENDENT CONTRACTOR Contractor certifies that: A.Contractor acknowledges that for all purposes related to this Agreement, Contractor is an independent contractor as defined by ORS 670.600 and not an employee of City. Contractor is not entitled to benefits of any kind to which an employee of City is entitled and is solely responsible for all payments and taxes required by law. Furthermore, in the event that Contractor is found by a court of law or any administrative agency to be an employee of City for any purpose, City is entitled to offset compensation due, or to demand repayment of any amounts paid to Contractor under the terms of this Agreement, to the full extent of any benefits or other remuneration Contractor receives (from City or third party) as a result of said finding and to the full extent of any payments that City is required to make (to Contractor or to a third party) as a result of said finding. B. Contractor is not an officer, employee, or agent of the City as those terms are used in ORS 30.265. CONFLICT OF INTEREST The undersigned Contractor hereby represents that no employee of the City, or any partnership or corporation in which a City employee has an interest, has or will receive any remuneration of any description from Contractor, either directly or indirectly, in connection with the letting or performance of this Agreement, except as specifically declared in writing. If this payment is to be charged against Federal funds, Contractor certifies that he/she is not currently employed by the Federal Government and the amount charged does not exceed their normal charge for the type of service provided. INDEMNIFICATION City has relied upon the professional ability and training of Contractor as a material inducement to enter into this Agreement. Contractor represents that all of its work will be performed in accordance with generally accepted professional practices and standards as well as the requirements of applicable federal, state, and local laws, it being understood that acceptance of a Contractor’s work by City will not operate as a waiver or release. To the extent allowed by law, Contractor agrees to indemnify and defend the City, its officers, employees, agents, and representatives and hold them harmless from any and all liability, claims, losses, and damages, that may be asserted by any person or entity to the extent such liability, claims, losses, and damages arise from the fault of Contractor. Relative to professional services, Contractor’s duty to defend is limited to reimbursement of reasonable legal costs should Contractor be found liable by adjudication or alternative dispute resolution or otherwise resolve by settlement agreement. In no Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 5 event shall defense costs charged to the Contractor exceed Contractor’s proportionate percentage of fault. Such indemnification will also cover claims brought against the City under state or federal worker’s compensation laws. If any aspect of this indemnity is found to be illegal or invalid for any reason whatsoever, such illegality or invalidity does not affect the validity of the remainder of this indemnification. 9. INSURANCE Contractor and its subcontractors must maintain insurance acceptable to City in full force and effect throughout the term of this contract. Such insurance must cover risks arising directly or indirectly out of Contractor's activities or work hereunder, including the operations of its subcontractors of any tier. The policy or policies of insurance maintained by the Contractor must provide at least the following limits and coverages: A. Commercial General Liability Insurance Contractor will obtain, at Contractor’s expense, and keep in effect during the term of this contract, Comprehensive General Liability Insurance covering Bodily Injury and Property Damage on an “occurrence” form (CG 2010 1185 or equivalent). This coverage must include Contractual Liability insurance for the indemnity provided under this contract. The following insurance will be carried: Coverage Limit General Aggregate $5,000,000 Products-Completed Operations Aggregate $5,000,000 Personal & Advertising Injury $1,000,000 Each Occurrence $5,000,000 Fire Damage (Any one fire) $50,000 B. Professional Liability Engineer shall obtain, at Engineer’s expense, and keep in effect during the term of this contract, Professional Liability Insurance covering any damages caused by an error, omission or any negligent acts. Combined single limit per claim shall not be less than $5,000,000, or the equivalent. Annual aggregate limit shall not be less than $5,000,000 and filed on a “claims-made” form. C. Commercial Automobile Insurance Contractor must also obtain, at Contractor’s expense, and keep in effect during the term of the contract, Commercial Automobile Liability coverage including coverage for all owned, hired, and non-owned vehicles on an “occurrence” form. The Combined Single Limit per occurrence may not be less than $2,000,000. If Contractor uses a personally-owned vehicle for business use under this contract, the Contractor will obtain, at Contractor’s expense, and keep in effect during the term of the contract, business automobile liability coverage for all owned vehicles on an “occurrence” form. The Combined Single Limit per occurrence may not be less than $2,000,000. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 6 D. Workers’ Compensation Insurance The Contractor, its subcontractors, if any, and all employers providing work, labor, or materials under this Contract that are subject employers under the Oregon Workers' Compensation Law must comply with ORS 656.017, which requires them to provide workers' compensation coverage that satisfies Oregon law for all their subject workers. Out-of-state employers must provide Oregon workers' compensation coverage for their workers who work at a single location within Oregon for more than 30 days in a calendar year. Contractors who perform work without the assistance or labor of any employee need not obtain workers’ compensation coverage. All non- exempt employers must provide Employer's Liability Insurance with coverage limits of not less than $1,000,000 each accident. E. Additional Insured Provision All required insurance policies, other than Workers’ Compensation and Professional Liability, must name the City its officers, employees, agents, and representatives as additional insureds with respect to this Agreement. F. Insurance Carrier Rating Coverages provided by the Contractor must be underwritten by an insurance company deemed acceptable by the City. All policies of insurance must be written by companies having an A.M. Best rating of "A-VII" or better, or equivalent. The City reserves the right to reject all or any insurance carrier(s) with an unacceptable financial rating. G. Self-Insurance The City understands that some contractors may self-insure for business risks and the City will consider whether such self-insurance is acceptable if it meets the minimum insurance requirements for the type of coverage required. If Contractor is self-insured for commercial general liability or automobile liability insurance, Contractor must provide evidence of such self-insurance. Contractor must provide a Certificate of Insurance showing evidence of the coverage amounts on a form acceptable to the City. The City reserves the right in its sole discretion to determine whether self-insurance is adequate. H. Certificates of Insurance As evidence of the insurance coverage required by the contract, Contractor will furnish a Certificate of Insurance to the City. No contract is effective until the required Certificates of Insurance have been received and approved by the City. The certificate will specify and document all provisions within this contract and include a copy of Additional Insured Endorsement. A renewal certificate will be sent to the below address prior to coverage expiration. I. Primary Coverage Clarification The parties agree that Contractor’s coverage is primary to the extent permitted by law. The parties further agree that other insurance maintained by the City is excess and not contributory insurance with the insurance required in this section. J. Cross-Liability Clause A cross-liability clause or separation of insureds clause will be included in all general liability policies required by this Agreement. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 7 A certificate in form satisfactory to the City certifying to the issuance of such insurance will be forwarded to: City of Tigard Attn: Contracts and Purchasing Office contractspurchasing@tigard-or.gov At the discretion of the City, a copy of each insurance policy, certified as a true copy by an authorized representative of the issuing insurance company, may be required to be forwarded to the above address. Such policies or certificates must be delivered prior to commencement of the work. The procuring of such required insurance will not be construed to limit Contractor’s liability hereunder. Notwithstanding said insurance, Contractor is obligated for the total amount of any damage, injury, or loss caused by negligence or neglect connected with this Agreement. 10. METHOD & PLACE OF SUBMITTING NOTICE, BILLS AND PAYMENTS All notices, bills and payments will be made in writing and may be given by personal delivery, mail, or by fax. Payments may be made by personal delivery, mail, or electronic transfer. The following addresses will be used to transmit notices, bills, payments, and other information: CITY OF TIGARD KITTELSON & ASSOCIATES Attn: Courtney Furman Attn: Anthony Yi Address: 13125 SW Hall Blvd Tigard, OR 97223 Address: 851 SW 6th Ave, Ste 600 Portland, OR 97204 Phone: (503) 718-2442 Phone: (503) 535-7407 Email: Courtney.furman@tigard-or.gov Email: ayi@kittelson.com Notice will be deemed given upon deposit in the United States mail, postage prepaid, or when so faxed, upon successful fax. In all other instances, notices, bills and payments will be deemed given at the time of actual delivery. Changes may be made in the names and addresses of the person to who notices, bills, and payments are to be given by giving written notice pursuant to this paragraph. 11. SURVIVAL The terms, conditions, representations, and warranties contained in this Agreement survive the termination or expiration of this Agreement. 12. MERGER This writing is intended both as a final expression of the Agreement between the parties with respect to the included terms and as a complete and exclusive statement of the terms of the Agreement. No modification of this Agreement will be effective unless and until it is made in writing and signed by both parties. 13. TERMINATION WITHOUT CAUSE At any time and without cause, City has the right in its sole discretion to terminate this Agreement by giving notice to Contractor. If City terminates this Agreement pursuant to this paragraph, City will pay Contractor for services rendered to the date of termination. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 8 14. TERMINATION WITH CAUSE A. City may terminate this Agreement effective upon delivery of written notice to Contractor, or at such later date as may be established by City, under any of the following conditions: 1) If City funding from federal, state, local, or other sources is not obtained and continued at levels sufficient to allow for the purchase of the indicated quantity of services. This Agreement may be modified to accommodate a reduction in funds. 2) If federal or state regulations or guidelines are modified, changed, or interpreted in such a way that the services are no longer allowable or appropriate for purchase under this Agreement. 3) If any license or certificate required by law or regulation to be held by Contractor, its subcontractors, agents, and employees to provide the services required by this Agreement is for any reason denied, revoked, or not renewed. 4) If Contractor becomes insolvent, if voluntary or involuntary petition in bankruptcy is filed by or against Contractor, if a receiver or trustee is appointed for Contractor, or if there is an assignment for the benefit of creditors of Contractor. Any such termination of this agreement under paragraph (A) will be without prejudice to any obligations or liabilities of either party already accrued prior to such termination. B. City, by written notice of default (including breach of contract) to Contractor, may terminate the whole or any part of this Agreement: 1) If Contractor fails to provide services called for by this Agreement within the time specified, or 2) If Contractor fails to perform any of the other provisions of this Agreement, or fails to pursue the work as to endanger performance of this Agreement in accordance with its terms, and after receipt of written notice from City, fails to correct such failures within ten (10) days or such other period as City may authorize. The rights and remedies of City provided above related to defaults (including breach of contract) by Contractor are not exclusive and are in addition to any other rights and remedies provided by law or under this Agreement. If City terminates this Agreement under paragraph (B), Contractor will be entitled to receive as full payment for all services satisfactorily rendered and expenses incurred, provided, that the City may deduct the amount of damages, if any, sustained by City due to breach of contract by Contractor. Damages for breach of contract include those allowed by Oregon law, reasonable and necessary attorney fees, and other costs of litigation at trial and upon appeal. 15. ACCESS TO RECORDS City will have access to such books, documents, papers and records of Contractor as are directly pertinent to this Agreement for the purpose of making audit, examination, excerpts and transcripts. 16. HAZARDOUS MATERIALS Contractor will comply with all federal Occupational Safety and Health Administration (OSHA) requirements and all Oregon safety and health requirements. In accordance with OSHA and Oregon OSHA Hazard Communication Rules, if any goods or services provided under this Agreement may Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 9 release, or otherwise result in an exposure to, a hazardous chemical under normal conditions of use (for example, employees of a construction contractor working on-site), it is the responsibility of Contractor to provide the City with the following information: all applicable Safety Data Sheets, the identity of the chemical/s, how Contractor will inform employees about any precautions necessary, an explanation of any labeling system, and the safe work practices to prevent exposure. In addition, Contractor must label, tag, or mark such goods. 17. FORCE MAJEURE Neither City nor Contractor will be considered in default because of any delays in completion and responsibilities hereunder due to causes beyond the control and without fault or negligence on the part of the parties so disenabled, including but not restricted to, an act of God or of a public enemy, civil unrest, volcano, earthquake, fire, flood, epidemic, quarantine restriction, area-wide strike, freight embargo, unusually severe weather or delay of subcontractor or supplies due to such cause; provided that the parties so disenabled will within ten (10) days from the beginning of such delay, notify the other party in writing of the cause of delay and its probable extent. Such notification will not be the basis for a claim for additional compensation. Each party will, however, make all reasonable efforts to remove or eliminate such a cause of delay or default and will, upon cessation of the cause, diligently pursue performance of its obligation under the Agreement. 18. NON-WAIVER The failure of City to insist upon or enforce strict performance by Contractor of any of the terms of this Agreement or to exercise any rights hereunder should not be construed as a waiver or relinquishment to any extent of its rights to assert or rely upon such terms or rights on any future occasion. 19. HOURS OF LABOR, PAY EQUITY In accordance with ORS 279B.235, the following are hereby incorporated in full by this reference: A. Contractor may not employ an individual for more than 10 hours in any one day, or 40 hours in any one week, except as provided by law. For contracts for personal services, as defined in ORS 279A.055, Contractor must pay employees at least time and a half pay for all overtime the employees work in excess of 40 hours in any one week, except for employees who are excluded under ORS 653.010 to 653.261 or under 29 U.S.C. 201 to 209 from receiving overtime. B. Contractor must give notice in writing to employees who work on a public contract, either at the time of hire or before commencement of work on the contract, or by positing a notice in a location frequented by employees, of the number of hours per day and days per week that the employees may be required to work. C. Contractor may not prohibit any of Contractor’s employees from discussing the employee’s rate of wage, salary, benefits or other compensation with another employee or another person and may not retaliate against an employee who discusses the employee’s rate of wage, salary, benefits or other compensation with another employee or another person. D. Contractor must comply with the pay equity provisions in ORS 652.220. Compliance is a material element of this Agreement and failure to comply will be deemed a breach that entitles City to terminate this Agreement for cause. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 10 20. NON-DISCRIMINATION Contractor will comply with all federal, state, and local laws, codes, regulations, and ordinances applicable to the provision of services under this Agreement, including, without limitation: A. Title VI of the Civil Rights Act of 1964; B. Section V of the Rehabilitation Act of 1973; C. The Americans with Disabilities Act of 1990, as amended by the ADA Amendments Act (ADAAA) of 2008 (Pub L No 101- 336); and D. ORS 659A.142, including all amendments of and regulations and administrative rules, and all other applicable requirements of federal and state civil rights and rehabilitation statutes, rules and regulations. 21. ERRORS Contractor will perform such additional work as may be necessary to correct errors in the work required under this Agreement without undue delays and without additional cost. 22. EXTRA (CHANGES) WORK Only the City’s Project Manager for this Agreement may change or authorize additional work. Failure of Contractor to secure authorization for extra work constitutes a waiver of all right to adjust the contract price or contract time due to such unauthorized extra work and Contractor will not be entitled to compensation for the performance of unauthorized work. 23. STANDARD OF CARE Contractor will perform all work under this Agreement with the care and skill used by members of Contractor’s professional practicing under similar circumstances at the same time and in the same locale (the “Standard of Care”). Should Contractor not the Standard of Care, it shall correct its work at its cost. Any intellectual property rights delivered to the City under this Agreement and Contractor’s services rendered in the performance of Contractor’s obligations under this Agreement, will be provided to the City free and clear of any and all restrictions on or conditions of use, transfer, modification, or assignment, and be free and clear of any and all liens, claims, mortgages, security interests, liabilities, charges, and encumbrances of any kind. 24. ATTORNEY'S FEES In the event an action, suit of proceeding, including appeal, is brought for failure to observe any of the terms of this Agreement, each party is responsible for that party’s own attorney fees, expenses, costs and disbursements for the action, suit, proceeding, or appeal. 25. CHOICE OF LAW, VENUE The provisions of this Agreement are governed by Oregon law. Venue will be the State of Oregon Circuit Court in Washington County or the U.S. District Court for Oregon, Portland. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 11 26. COMPLIANCE WITH STATE AND FEDERAL LAWS/RULES Contractor will comply with all applicable federal, state and local laws, rules and regulations applicable to the work in this Agreement. 27. CONFLICT BETWEEN TERMS In the event of a conflict between the terms of this Agreement and Contractor’s proposal, this Agreement will control. In the event of conflict between a provision in the main body of the Agreement and a provision in the Exhibits, the provision in the main body of the Agreement will control. In the event of an inconsistency between Exhibit A and Exhibit B, Exhibit A will control. 28. AUDIT Contractor will maintain records to assure conformance with the terms and conditions of this Agreement and to assure adequate performance and accurate expenditures within the contract period. Contractor agrees to permit City, the State of Oregon, the federal government, or their duly authorized representatives to audit all records pertaining to this Agreement to assure the accurate expenditure of funds. 29. SEVERABILITY In the event any provision or portion of this Agreement is held to be unenforceable or invalid by any court of competent jurisdiction, the validity of the remaining terms and provisions will not be impaired unless the illegal or unenforceable provision affects a significant right or responsibility, in which case the adversely affected party may request renegotiation of the Agreement and, if negotiations fail, may terminate the Agreement. 30. COMPLIANCE WITH TAX LAWS Contractor represents and warrants that Contractor is, to the best of the undersigned’s knowledge, not in violation of any Oregon tax laws including but not limited to ORS 305.620 and ORS Chapters 316, 317, and 318. Contractor’s failure to comply with the tax laws of this state or a political subdivision of this state before the Contractor executed this Agreement or during the term of this Agreement is a default for which the City may terminate this Agreement and seek damages and other relief available under the terms of this Agreement or applicable law. IN WITNESS WHEREOF, City and Contractor have caused this Agreement to be executed by their duly authorized officials. Awarded by Tigard’s Local Contract Review Board at their 12/10/2024_ meeting. CITY OF TIGARD KITTELSON & ASSOCIATES By: __________________________________ By: __________________________________ Name: _______________________________ Name: _______________________________ Title: ________________________________ Title: ________________________________ Date: ________________________________ Date: ________________________________ Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D 1/3/2025 Anthony Yi Senior Principal 1/3/2025 City Manager Steve Rymer QBS RFP McDonald Street Engineering Services 32500039 Page 12 EXHIBIT A City of Tigard PUBLIC WORKS ENGINEERING DIVISION CIP-95074 – MCDONALD STREET STATEMENT OF WORK GENERAL NOTES  Written authorization from City’s project manager is required prior to beginning work on: o any task labeled as Contingency; and o any Right of Way subtask listed as requiring its own specific notice to proceed.  The contracted services will be a phased development, consisting of: o Phase I, the Study phase – traffic analysis, alternatives analysis, conceptual design through preliminary design, determination of project delivery method; and o Phase II, the Design and Construction phases – preliminary design through final plans, specifications, and estimate (PS&E), including right-of-way acquisition (ROW), bidding assistance, construction engineering and inspection. The initial contract will be specific to those services related to Phase I. After completion of Phase I, City may, at its discretion amend the contract to add Phase II tasks, where City and Contractor will negotiate the detailed tasks, deliverables, schedule, and costs of Phase II services that are ultimately contracted.  Assume City will be afforded the opportunity to review deliverables and permit applications and its’ comments considered/addressed prior to deliverables being finalized or applications being submitted, i.e., most deliverables and permit applications will require a draft and final version even if not specifically described by the respective task language.  Alternative project delivery methods will be compared with the traditional project delivery method and a recommendation of project delivery method will be provided to the City for this project. For the purposes of this RFP, it is assumed that a design-build delivery will be selected and approved by City Council. PHASE I SERVICES Task 1 Project Management and Administration  Schedule, prepare for, conduct, and document project meetings. Meetings may be held virtually via Microsoft Teams. Anticipated meetings include: o Project kickoff meeting o Project team meetings o Design review meetings at design deliverable milestones o Miscellaneous coordination meetings o Bi-weekly 30-minute Microsoft Teams meeting with City project manager following a standard agenda.  Participate in CWS pre-application meeting to discuss stormwater requirements.  Prepare monthly schedule updates. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 13  Prepare and submit monthly invoices.  Monitor budget.  Prepare a project design schedule using the critical path method in Microsoft Project.  Prepare a quality assurance / quality control (QA/QC) plan for City review and approval. Task 2 Traffic Analysis The study area includes the following roadway segments and intersections, as outlined below: Roadway Segments  SW McDonald Street (Pacific Highway to SW Hall Boulevard) Intersections  SW McDonald Street/Pacific Highway  SW McDonald Street/SW 103rd Avenue  SW McDonald Street/SW 100th Avenue  SW McDonald Street/SW Omara Street/SW 98th Avenue  SW McDonald Street/SW 97th Avenue  SW McDonald Street/SW 93rd Avenue  SW McDonald Street/SW Hall Boulevard Contractor will conduct a traffic operations assessment at all of the study intersections. Traffic analysis must follow the Highway Capacity Manual (HCM) 6 procedures and comply with ODOT’s Analysis Procedures Manual (APM).  Collect weekday 16-hour turning movement counts  Seasonally adjust traffic volumes to reflect the 30th highest hour  Field inventory including lane configurations, traffic controls, speeds, operational issues (queuing, unique driving behaviors, etc).  Analyze the Manual on Uniform Traffic Control Devices (MUTCD) signal warrants under existing conditions for unsignalized intersections  Conduct an operational assessment of existing and future conditions (for all alternatives)  Develop future volumes with a subarea model refined from the travel demand model and post processed  Develop a traffic analysis model for the study area to determine the future needs, including operational standards and queuing. The traffic analysis will include various options for future conditions to address future traffic needs, such as traffic signals, roundabouts, roadway realignment, addition of turn lanes, restricted access, etc. These options will be analyzed using a combination of screening tables (such as in NCHRP Report 672), MUTCD Signal Warrants, a crash history review, and comparison of crash modification factors.  Safety Performance Analysis to support the selection of intersection control and layout for the study intersection. Safety analysis will be based on the current Highway Safety Manual (HSM) Methodology. Contractor will evaluate historic crash data to identify trends or patterns in type or severity of the crashes, identify the trends related to the primary contributing factors and inform the design considerations. Analysis will include: o Predicted crash frequency and severity of each intersection alternative. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 14 o Safety analysis of each intersection alternative compared to each other (including a ‘no-build’ alternative). o Summarize safety performance analysis to be incorporated into the Intersection Control Evaluation Report.  Contractor will analyze the lifecycle cost/benefit ratio as part of the intersection control evaluation. The lifecycle cost/benefit ratio will be analyzed based on the NCHRP Project 03-110 (Estimating the Life-cycle Cost for Intersection Designs) for each alternative including comparison of predicted safety using the Highway Safety Manual crash prediction models. Task 3 Alternatives Analysis Contractor will develop up to three cross-section alternatives for each study roadway segment and up to two alternatives for each intersection in coordination with Task 2. The alternatives will promote the complete street design concept and look at options to create safe, continuous bicycle and pedestrian routes. The options will include, but are not limited to: the addition of sidewalks, bike lanes, protected/separated bike lanes, multi-use paths, a roundabout corridor, and crossing improvements. Contractor shall develop an Evaluation Matrix to compare the alternatives, based on the evaluation criteria and goals. Evaluation criteria must be determined in consultation with City, but will likely include, but not be limited to: route connectivity, safety, traffic operations, right-of-way impacts, construction cost, environmental and drainage impacts, and impacts to natural resources. Contractor shall develop conceptual layouts for each alternative to quantify the impacts and costs as well as the design issues and constraints of the various alternatives. Contractor will prepare a technical memorandum documenting the conceptual layout and alternatives analysis process. Task 4 Public Involvement Program The purpose of the public involvement program is to make informed decisions that consider and reflect the needs and opportunities that may be present among the communities that the project is designed to serve. 4.1 PI Plan (PIP)  Prepare a PIP. Discuss, modify, and confirm with City the following: o Schedule for meetings and other deliverables associated with PI. o Target audience and stakeholders. o Desired outcome of PI. o Project messaging / talking points. o List of communications and outreach tools to engage and reach the desired audience. 4.2 PI Meetings  Participate in the planning of and attend up to four (4) meetings, as listed below, to provide Project information and address specific questions and concerns related to the Project. PI meetings may be conducted in-person, virtually, or in a hybrid setting: o Project open house for Alternatives Analysis and 30% Design milestone (2). o Advisory Committee meetings (2).  Document input received from the meetings by preparing a written public involvement summary. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 15 4.3 PI Materials  PI Toolkits. Contractor will provide a toolkit of content, informational graphics, and photos for City to post on various platforms. City will use this content to create mailers, flyers, and fact sheets, as well as develop social media and website posts throughout the Project’s duration. City will format, print, and mail the various informational pieces. City will maintain the stakeholder distribution/mailing list. Contractor will provide the toolkits at the following milestones: o Project kickoff o Alternatives analysis o Conceptual 10% design o Preliminary 30% design  Project website. City will use Engage Tigard! as the primary method to provide project updates, identify ways to get involved, and communicate current project status. The project website will also host informational videos and project graphics. City will create and manage this website; Contractor will provide content for the website via the PI Toolkits as well as when any significant change in the design or project schedule occurs between the planned PI Toolkit deliverables.  Social media engagement. City will use its existing social media platforms and will lead overall social media management and placement of the posts. Contractor will provide content for social media posts via the PI Toolkits prior to significant PI activities and/or to raise awareness about the Project. Contractor to provide technical content related to the engineering and permitting activities associated with the Project that can be provided between project milestones.  Informational graphics. Contractor will develop graphics throughout the Project to supplement PI activities and outreach. These graphics will include: o 30% Design milestone:  Project visualization graphic  Project plan and profile graphic  Project schedule graphic  General project information  Online survey/Q&A for Alternatives Analysis. Contractor will develop an interactive activity to gather input on the alternatives analysis for the project. This will include a survey or similar question and answer (Q&A) format using the City’s Bang the Table online portal that will provide the community an opportunity to provide input and ask questions. It will be available to the general public and will include primarily value-based questions. Contractor will draft the questions, provide graphics, and prepare a summary of the results.  Project visualization (3-D) Contractor will prepare a 3-D project visualization video using Sketchup of the conceptual 30% design. Task 5 Survey 5.1 Topographic Survey, Basemap, and Digital Terrain Model  Establish horizontal and vertical survey control for the project.  Prepare and distribute notification letters by mail to adjacent property owners within the work area. The notification letters are to include details of the project improvements. City to review notification letters before mailing.  Call for utility locates.  Topographic design survey will include, but not be limited to, visible and topographic features, such as existing trees, shrub clusterings, utilities (including recording of all utility locate markings such as ownership, quantity, and size), fences, lights, storm drainage and sanitary sewer structures (including Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 16 measure-downs to establish accurate invert elevations of all pipes), culverts, landscaping, driveways, edge of pavement, buildings, sidewalks, signs, and striping, etc., within the project area. Limits of topo survey are to be at minimum 300’ beyond project limits, or as needed for permitting needs, whichever is greater.  Survey creek cross sections upstream and downstream of culvert for hydraulic modeling purposes.  Tie wetlands and waters flags and geotechnical boring locations.  Prepare a topographic base map.  Use topographic data points to create a 3-D digital terrain model surface. Task 6 Technical Studies and Reports 6.1 Cultural Resources Reporting Provide a background review and visual pedestrian survey to investigate potential impacts to archaeological and historic resources, to be documented in a combined Cultural Resources Report that will include documentation of background research, methods and results of field investigations, preliminary evaluation of cultural resources, and recommendations for additional work, if applicable. The cultural resources study will be done under Section 106 of the National Historic Preservation Act due to US Army Corps of Engineers permitting required of the Project. No federal funds will be used on the Project.  Query state databases and existing parcel data to determine if archaeological sites and surveys have been done in the Project area previously. Review maps, aerial photographs, historical topographic maps, land maps, published and non-published records, archives, and soil maps. This information will assess the potential for prehistoric and historic archaeological resources in the Project area.  Conduct a pedestrian field survey of the Project area for archaeological resources. The area surveyed is to include areas where ground disturbances will occur by Project construction, including temporary features such as access roads, staging areas, detours, etc. Survey transect spacing to be per professional judgement to ensure that all probable resource locations are discovered. All archaeological resources observable on the surface will be identified and recorded. The pedestrian archaeological survey methods and reporting will be consisted with State Historic Preservation Office (SHPO) guidelines.  Perform archaeological shovel testing. Prepare site forms and isolate forms for archaeological resources.  Search the SHPO Historic Sites Database and the Washington County historic property inventories for previously recorded historic resources in the Project area. Washington County Tax Assessment will be searched for build dates of structures in the Project area.  Conduct a field survey of the Project area to document historic resources greater than 50 years of age that may be eligible for listing in the National Register of Historic Places (NHRP). All historic resources will be photographed and architecturally documented in the field. The Cultural Resources Report will include photographs and descriptions of historic resources, survey methods, historical background, and recommendations for eligibility and effect for historic resources.  Any additional work that is pursued as a result of being recommended in the Cultural Resources Report will be handled via a contract amendment with City. 6.2 Geotechnical Investigation and Pavement Design 6.2.1 Phase I Preliminary Geotechnical Investigation Conduct preliminary geotechnical and pavement field investigations to explore subsurface conditions that will inform type size and location of various geotechnical related design features of the Project, to be Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 17 summarized in a preliminary geotechnical memorandum that presents the results of the investigation, analyses, and recommendations.  Review available documentation and as-builts to evaluate geologic conditions and hazards along the proposed Project alignment, such as geologic units, historic land use, fill materials, and groundwater levels.  Conduct a geologic and geotechnical reconnaissance of the site to identify geologic conditions at the Project site, any geologic hazards present, and their impacts to the proposed Project elements. Observe surface conditions that may be indicative of subsurface conditions of concern, as well as past or ongoing geologic processes (e.g., areas of seeps or springs, erosion, unstable slopes, shallow groundwater, roadway settlement, offsets and depressions, existing earthwork performance, exposed soil and bedrock units). Identify site constraints, staging concerns (for exploration and construction), and environmental considerations. Identify potential exploration and/or monitoring locations. Locate geotechnical borings and stake or paint on the ground proposed boring locations.  Coordinate and manage field investigation including locating utilities and preparing access as necessary.  Prepare a work plan and traffic control plans and coordinate with City’s project manager to obtain City of Tigard Public Facilities Improvement (PFI) Permit, which serves as the right- of-way access permit for the drilling activity and associated traffic control. Any PFI Permit fees will be responsibility of City.  Complete up to two (2) geotechnical borings. One to a maximum depth of 75 feet and the other to a maximum depth of 50 feet.. Maintain a detailed log of each exploration, visually classify the soil encountered, obtain soil samples as appropriate for the soil conditions encountered, and observe groundwater conditions in each exploration. Thicknesses and conditions of existing pavement materials will be captured and noted in the boring logs. A vibrating wire piezometer and data logger will be installed in one of the borings to measure the ground water table elevation.  Conduct laboratory tests using soil and rock-core samples obtained from the exploration.  Perform preliminary analyses of the field and laboratory test data to identify geologic and seismic hazards and support type size and location efforts for project improvements.  Prepare a Preliminary Geotechnical Memorandum to document field explorations, laboratory testing, and preliminary geotechnical recommendations. Assumptions:  Phase I borings are near the existing culvert east of SW 92nd Terrace and anticipated retaining wall(s) between SW 93rd Ave and SW 95th Ave to evaluate seismic hazards and select wall type.  Explorations will be completed during daylight hours of 8am to 5pm. 6.3 Hazardous Materials Assessment 6.3.1 Phase I Hazardous Materials Assessment  Conduct a Hazardous Materials Corridor Study (HMCS) to identify potential sources of contamination that could impact property acquisition or construction. Conduct a site reconnaissance, review environmental and water resources databases and/or DEQ files, and conduct historical research to identify past uses of the Project corridor and adjacent properties. Assess if sampling is necessary to determine if soil excavated from the Project corridor will meet DEQ clean fill screen levels for contaminants-of-concern including Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 18 pesticides, herbicides, metals, polynuclear aromatic hydrocarbons, petroleum hydrocarbons, and solid waste. Report to include photo documentation of observations, conclusions regarding identifying specific sources of contamination that could impact Project construction, and recommendations for further investigation, if needed. Task 7 Hydraulic and Stormwater Studies 7.1 Hydraulic Analysis and Report Hydraulic Site Investigation:  Obtain the Flood Insurance Study (FIS) report and if available the Flood Insurance Rate Map using the Federal Emergency Management Agency (FEMA) web site. Obtain effective hydrologic and hydraulic models from FEMA or from the local Floodplain Manager.  Review local floodplain ordinances to determine if there are any applicable to this water body.  Determine if applicable stream gauge records exist, and obtain them, if possible.  Locate and obtain existing topographic maps of the tributary drainage basin.  Locate and obtain current and historic aerial photographs of the stream channel to support conclusions about the lateral channel stability.  Coordinate with Geotechnical Engineer and review geotechnical report with regard to lateral stream stability and scour potential.  Evaluate the site and determine survey data requirements for hydraulic analysis.  Observe the stream channel for the extents necessary to support hydraulic modeling and observe channel stability. The conditions will be documented with photographs and a narrative discussion in the hydraulics report. Record observations with respect to: lateral channel stability; stream channel and floodplain hydraulic roughness; apparent or observed high water marks; aggradation or degradation of bed material; bed material size by visual inspection as required for values for variables in scour prediction; evidence of debris; and existing evidence of scour and/or erosion. Hydrologic Analysis:  Develop site hydrology. Use appropriate information to develop the 2-year through 500-year flows for the hydraulic model and scour elevation. It is anticipated that peak flow rates will be obtained from the FEMA Flood Insurance Study for Pinebrook Creek.  Determine the temporary water management discharge estimates for the portion of the year when construction will take place to be used in temporary water management design recommendations and included in the technical specifications for the Project.  Determine the fish passage high flow and fish passage low flow.  In the absence of sufficient hydrologic models, analyze available stream gauge records to calculate flood frequency and flow duration values to support hydraulic analysis and design.  In the absence of stream specific data, delineate the tributary drainage basin utilizing available topographic maps and utilize the regional regression equations described in the U.S. Geological Survey (USGS) magnitude and frequency of floods in Western Oregon to predict design flows. Hydraulic Analysis:  Develop hydraulic models using the Hydrologic Engineering Centers - River Analysis System (HEC- RAS) software and survey data for existing and proposed conditions to determine water surface profiles, velocities, depths, and flow area for the various design flows.  Model: the existing culvert; the natural conditions; and the proposed culvert replacement (up to three (3) alternatives). Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 19  Determine the roadway overtopping flood and frequency where the water overtops the roadway before the 500-year flood peak.  Provide waterway opening design recommendations.  Prepare Hydraulic data table.  Perform scour analysis: o Evaluate up to 1 culvert scour alternative. o Review past culvert inspection reports that might include evidence of past scour problems. o Conduct a scour analysis using results from the hydraulic analysis including evaluation of pier scour and contraction scour. o Coordinate with the geotechnical engineers on the design of the foundation. o Provide scour countermeasure design recommendations and conduct supporting design calculations. Size riprap including horizontal and vertical extents. o Coordinate with engineer on countermeasure design details. Hydraulics Report:  Prepare a hydraulics report describing the analyses and results of the above-described tasks. Final report to reflect review comments and to include changes to hydraulic related design recommendations that need to be modified due to advancement of the overall Project design. 7.2 Floodplain Impact Analysis  Portions of the Project will be located within a mapped Special Flood Hazard Area (100-year floodplain), subjecting the Project to needing to meet City of Tigard floodplain development requirements.  Evaluate and prepare documentation concerning the anticipated Project impacts on the 100-year water surface elevation (floodway AND floodplain).  If applicable, prepare a “no-rise” certification for inclusion in the Project’s land use application.  Should the proposed structure not meet No-Rise requirements, preparation of a Letter of Map Revision (LOMR) submittal will be completed under an amendment to the contract. 7.3 Stormwater Analysis and Report Storm Sewer Conveyance:  Provide design of stormwater conveyance facilities that collect and carry roadway runoff per Clean Water Services standards.  Determine the locations of flow entering and leaving the Project right-of-way.  Review existing conditions downstream of locations where flow is leaving the Project right-of-way for deficiencies and document observations.  Delineate on-site drainage basins, calculate peak flow rates for design, model the proposed pipe network, and calculate hydraulic grade line to check that proper freeboard design requirements are being met.  Check inlet capacity and inlet spacing, calculate gutter flow to check spread, and provide design recommendations for inlet locations.  Provide design recommendations for pipe network, associated pipe sizes, pipe material recommendations, and manhole access design recommendations (i.e., spacing, location within a travel lane, etc.). Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 20  Provide manhole diameter design recommendations based upon analysis of pipe connections at each manhole.  Compare pipe network against known utilities in the Project area and provide design recommendations to minimize utility conflicts or to adjust existing utilities.  Provide stormwater outfall design and energy dissipater design recommendations in compliance with applicable Project permits. Stormwater Quality and Quantity Design:  Provide design of stormwater management facilities that provide water quality treatment and flow control / quantity management of roadway runoff per Clean Water Services standards or SLOPES V permitting requirements, whichever is most strict. Coordinate with City and CWS early in the design to determine preferred methods of treatment.  Prepare hydromodification assessment, as required by Clean Water Services.  Define Contributing Impervious Area (CIA).  Delineate on-site drainage subbasins.  Identify treatment Best Management Practice (BMP) types applicable for the site. Determine applicability of paying Fee-in-Lieu of constructing water quality, quantity, and hydromodification controls.  Identify a potential location to site a facility within or outside the existing right-of-way, including off- site locations.  Estimate facility size, type, and space needs.  Evaluate constraints to siting a stormwater facility (i.e., drainage area, adjacent grades, roadway safety, presence of existing utilities, protected resource areas, etc.).  Prepare a stormwater management strategy that combines Fee-in-Lieu and/or a potential stormwater facility into a comprehensive solution for meeting the needs of the Project (not separate from the strategies for Stormwater quality).  Provide written design recommendations in the Stormwater Management Report for: pipe network and associated pipe sizes; manhole diameter; pipe material recommendations; channel lining; stormwater outfall; and energy dissipation.  Provide documentation in the Stormwater Management Report for recommended stormwater management strategy. Temporary Water Management Design:  Prepare temporary water management design recommendations, special provisions, and plan for inclusion in the construction documents.  Identify the construction activities requiring temporary water management.  Determine the timeframe for which each temporary water management effort will need to be in place (often the in-water work period).  Summarize the requirements for temporary water management due to the chosen environmental permitting method.  Prepare a plan and special provisions for flow and sediment control of surface water and groundwater seepage during construction activities based on site conditions. Incorporate into Stormwater Management Report and into PS&E documents where appropriate. Stormwater Management Report: Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 21  Prepare a draft version of the Stormwater Management Report per Clean Water Services Design and Construction Standards guidelines containing preliminary stormwater facility design recommendations. Prepare a final Stormwater Management Report to reflect agency review comments on stormwater facility design recommendations, changes to stormwater facility design due to advancement of the overall Project design, and supporting documentation of the final stormwater facility design. Task 8 Environmental Documentation and Permits 8.1 Wetlands and Waters  Review background information relating to wetlands and waterways.  Identify the location and extent of jurisdictional wetlands and waters within the Project area, marking their boundaries with flagging. Flags will be numbered and tied by survey. Survey work is accounted for in the Survey task (Topographic Survey, Basemap, and Digital Terrain Model).  Prepare a wetland delineation report suitable for submittal to Oregon Department of State Lands (DSL) and U.S. Army Corps of Engineers (USACE). 8.2 City of Tigard Urban Forestry Plan and Arborist Support – Phase I Conduct one (1) site visit to assess the condition of existing trees and determine potential impacts based on the 30% Preliminary Design.  Visually assess individual trees identified on the survey and collect inventory data including species, size, and general conditions.  Prepare a Tree Risk Assessment spreadsheet meeting the requirements of the City of Tigard Urban Forestry Manual, Appendix 1 for the surveyed trees within the project footprint.  Meet with the project design team to review the Conceptual Design in terms of potential tree impacts, with the focus on identifying trees that may be impacted by the project, the health of these trees, best construction practices and design alternatives to protect the trees, and recommendations for tree removal where appropriate. Task 9 Right-of-Way Determination of right-of-way and easements needed for the project. 9.1 Rights of Entry  Prepare, negotiate, and obtain property owner signatures for temporary right of entry documents for the purposes of environmental and design studies. Contractor and City to coordinate on form of agreement to be used. 9.2 Right-of-Way Determination – Phase I  Review the ROW and easement needs of the project. Establish the proposed ROW and easements boundaries for review by City. Task 10 Utility Coordination 10.1 Utility Design Coordination  Obtain as-built maps from the utility companies. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 22  Field location and verification of their facilities and establishing control to prepare for potholing of utilities.  Review of the utilities to determine possible impacts with the proposed improvements. A base map will be provided to all of the utility companies in the project area. A summary of the possible utility conflicts for the project corridor to be prepared and distributed to all utilities for review and their use. Task 11 Design Engineering 11.1 Conceptual Design (10%) Prepare conceptual design consisting of the full roadway improvements per the preferred alternative selected in Task 3.  Provide plan view drawings of the proposed pavement widenings, bike lane, sidewalk, storm drainage, and driveway connections.  Prepare a 10% Construction Cost Estimate.  Provide 10% design report. 11.2 Preliminary Design (30%) Prepare construction plans generally at 1”=40’ for full size 11”x17” plans. The design will consist of the full roadway improvements. The construction plans are for the selected alternative only.  Provide plan view drawings of the proposed pavement widenings, bike lane, sidewalk, storm drainage, and driveway connections.  Provide conceptual roadway and sidewalk grading.  Provide a Cover Sheet.  Provide Existing Conditions Plans.  Provide Roadway Plans.  Prepare a 30% Construction Cost Estimate.  Prepare 30% design report. Task 12 Alternative Project Delivery Evaluation 12.1 Meetings and Workshops  Organize and attend one (1) workshop to introduce alternative project delivery methods and the processes related to each delivery method, including an Alternative Delivery Case Study.  Organize and attend one (1) workshop to summarize the evaluation results of alternative project delivery methods, interpret recommendation of delivery method for this project, discuss and decide the selected delivery method. This workshop will be scheduled prior to completion of the final Technical Memorandum recommending a project delivery method.  Attend the Public Hearing for alternative delivery method selection. The Public Hearing shall be held prior to the City Council meeting, and the notification of public hearing shall be published a minimum of 14 days in advance of the hearing.  Attend the City Council meeting for approval of the selected alternative project delivery method. 12.2 Evaluation of Alternative Project Delivery Methods Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 23  Compare three (3) alternative project delivery methods: General Contractor/Project Management (CMGC), Design-Build (DB), and Progressive Design-Build (PDB).  Evaluate the impact of each delivery method on project schedule, quality, and cash flow.  Summarize decision and discussion results from the workshops and provide recommendations for a preferred alternative delivery method in a draft Technical Memorandum.  Finalize the Technical Memorandum based on the City’s comments. 12.3 Assistance for Approval of the Selected Alternative Project Delivery Method  Assist the City with compliance of ORS 279C.335 for exemption from competitive building.  Present a draft Findings Memorandum to address the fourteen (14) items under ORS 279C.335 for the selected alternative project delivery method. This memorandum will provide criteria for measuring and/or monitoring achievement for each item for use in preparing the post- construction report required under ORS 279C.335.  Prepare a final Findings Memorandum that incorporates the City’s comments.  Assist the City in holding a public hearing to allow comments to the findings as required under ORS 279C.335. This includes posting findings for public review, preparing a presentation about the findings for the public hearing, and addressing comments received at the public hearing. Preliminary Project Milestone Schedule: Contractor Solicitation (QBS-RFP): September 2024 through October 2024 Council Award December 2024 Signed Contract: January 2024 Phase I Milestones  Traffic Analysis: February 2025 through April 2025  Field Survey Work: February 2025 through April 2025  Alternatives Analysis: May 2025 through July 2025  10% Design (Concept): August 2025 through October 2025  30% Design (Preliminary): November 2025 through February 2026 Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D Project Name: McDonald Street Engineering Services Project Manager: Nicholas Polenske KAI Project Number: RFP 2025-08/CIP-95074 Date:Dec 10, 2024 LABOR ESTIMATE - McDonald Street Engineering Services Kittelson Consor Yi, Anthony Polenske, Nicholas Harry, Keisuke Scarbrough, Wade Rhyne, Steven Razmpa, Ali Mannion, Megan Benjamin, Alicia CM X Hedberg CM VI Maxwell Principal II Machan Coordinator III Nguyen CAS II Inspector IV Principal Eng I PE V Eng Designer IV Tech IV Admin III Cost Est III Proj Coordinator IV Principal Eng III PE VI Eng Designer III Eng Designer IV PE IX PE IV Eng Designer III Eng Designer I Tech III Principal Eng V Tech IV Tech IV SR. Project Manager SR. Project Surveyor Project Surveyor Task Staff ASY NDP KDH WES SJR AXR MLM AAC McMurtrey Husk/WebsterHannan/Roberts Harjala Persans Greisinger Porter Morgan Garth Stellers Bindal Bugingo Ebbighausen Waldroop Golichnik McFaddin Alderman Chernishoff Harjala 001 Project Management and Administration Project Kickoff Meeting 2 4 2 2 2 2 2 2 Project Team Meetings 2 8 4 4 4 8 4 8 Design Review Meetings 2 4 2 2 4 10 10 Miscellaneous Coordination Meetings 2 6 3 3 2 6 2 6 Weekly City Project Management Meetings 20 20 3 3 3 3 Monthly Schedule Updates 12 6 Monthly Invoices 6 6 6 Monthly Budget Monitoring 12 6 Design Schedule 4 8 4 Quality Assurance/Quality Control (QA/QC) Plan 2 6 Reimbursable Expense Task #001 - Subtotal 10 82 45 11 0 0 0 0 15 0 0 0 0 0 45 0 0 0 6 0 11 0 0 0 0 29 0 0 0 0 0 0 0 0 0 0 002 Traffic Analysis Data Collection 2 2 4 Existing and Future Volume Development 2 2 4 10 Field Inventory Documentation 2 2 4 6 Stage 1 Screening Analysis 2 12 20 40 Safety Performance Analysis 2 20 40 80 Draft Traffic Analysis Memorandum 2 8 16 32 Final Traffic Analysis Memorandum 2 2 4 12 Reimbursable Expense Task #002 - Subtotal 0 14 0 48 0 92 180 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 003 Alternatives Analysis Concept Development (Sketch-level Concept Alternatives)12 32 24 56 12 4 8 16 4 4 Evaluation Matrix 2 8 16 32 1 3 1 1 3 3 CAD Concept Alternatives 2 12 40 8 64 40 16 16 60 16 Concept Design Technical Memorandum 2 8 16 32 4 1 4 4 1 4 4 4 Reimbursable Expense Task #003 - Subtotal 6 40 104 32 0 0 184 40 0 4 0 0 0 0 1 17 7 16 0 4 0 1 4 0 0 13 21 7 7 16 0 60 16 0 0 0 004 Public Involvement Program PI Plan (PIP)2 2 24 PI Meetings 20 20 10 10 8 8 66 PI Materials 6 36 24 240 10 60 146 Reimbursable Expense Task #004 - Subtotal 6 58 46 10 240 10 70 0 0 8 0 0 0 0 8 0 0 0 0 0 236 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 005 Survey Topographic Survey, Basemap, and Digital Terrain Model 2 4 5 20 84 Reimbursable Expense Task #005 - Subtotal 0 2 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5 20 84 006 Technical Studies and Reports Cultural Resources Reporting 2 2 Geotechnical Investigation and Pavement Design - Phase I 2 2 Hazardous Materials Assessment - Phase I 2 2 Reimbursable Expense Task #006 - Subtotal 0 6 6 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 007 Hydraulics and Stormwater Studies Hydraulic Analysis and Report 2 4 1 64 32 Floodplain Impact Analysis 2 4 1 32 16 Stormwater Analysis and Report 2 8 1 90 45 9 Reimbursable Expense Task #007 - Subtotal 0 6 16 0 0 0 0 0 0 0 0 0 0 0 3 186 93 9 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 008 Environmental Documentation and Permits Wetlands and Waters 2 4 City of Tigard Urban Forestry Plan and Arborist Support - Phase I 2 4 Reimbursable Expense Task #008 - Subtotal 0 4 8 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 009 Right-of-Way Rights of Entry 2 4 20 Right-of-Way Determination - Phase I 50 100 200 Reimbursable Expense Task #009 - Subtotal 0 52 104 0 0 0 200 0 0 0 0 0 0 0 0 0 0 0 0 20 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0010 Utility Coordination Utility Design Coordination 10 20 20 20 40 Reimbursable Expense Task #0010 - Subtotal 0 10 20 0 0 0 20 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 20 40 0 0 0 0 0 0 0 0 0 0011 Design Engineering 10% Plans 2 12 32 4 36 20 4 4 54 60 24 56 60 45 59 10% Construction Cost Estimate 1 2 6 2 8 2 2 4 8 1 2 4 16 10% Design Report 1 2 8 2 10 2 4 4 1 1 2 8 28 12 12 30% Plans 2 60 160 20 60 180 160 20 8 11 140 168 1 8 20 54 60 129 171 30% Construction Cost Estimate 1 8 24 8 8 32 2 2 8 8 1 2 4 4 10 30% Design Report 1 12 32 12 12 40 4 4 4 1 1 4 4 14 12 12 Reimbursable Expense Task #0011 - Subtotal 8 96 262 48 0 80 306 180 0 20 0 0 0 0 22 27 206 236 2 16 0 5 18 4 64 0 178 120 0 198 0 254 0 0 0 0 0012 Alternative Project Delivery Evaluation Meetings and Workshops 8 12 8 8 24 Evaluation of Alternative Project Delivery Methods 2 24 12 12 60 Assistance for Approval of the Selected Alternative Project Delivery Method 2 16 8 8 80 Reimbursable Expense Task #0012 - Subtotal 12 52 28 28 0 0 0 0 0 0 164 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 TOTAL HOURS 42 422 643 177 240 182 960 220 15 32 164 0 0 0 79 230 306 261 8 20 267 6 22 4 64 62 239 127 7 214 0 314 16 5 20 84 LABOR RATE $325.00 $215.00 $215.00 $285.00 $190.00 $185.00 $185.00 $175.00 $313.00 $248.00 $284.00 $177.00 $151.00 $177.00 $271.00 $214.00 $202.00 $194.00 $134.00 $305.00 $190.00 $300.00 $227.00 $202.00 $265.00 $195.00 $166.00 $174.00 $338.00 $194.00 $194.00 $176.00 $176.00 $245.00 $225.00 $185.00 LABOR COST $13,650 $90,730 $138,245 $50,445 $45,600 $33,670 $177,600 $38,500 $4,695 $7,936 $46,576 $0 $0 $0 $21,409 $49,220 $61,812 $50,634 $1,072 $6,100 $50,730 $1,800 $4,994 $808 $16,960 $12,090 $39,674 $22,098 $2,366 $41,516 $0 $55,264 $2,816 $1,225 $4,500 $15,540 Rates shown above are for budgeting purposes only. Additional staff may be billed at the time services are performed.TOTAL Cons. REIMBURSABLES TOTAL Cons. FEES $505,436 Project Budget Form TOTAL KAI REIMBURSABLES $1,480 TOTAL KAI FEES $589,920 $1,161 Kittelson & Associates Inc. I:\FIN\Contracts\FY 2024-25\32500039 McDonald Street Engineering Services\Contracts and Amendments\McDonald Street - BOC - Phase I Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D AKS Commonstreet AINW Greenworks Shannon & Wilson Surveyor Survey Cad Technician Two-person Survey Crew One-person Aerial Surveying Aerial Surveying Sepecialist- Office Sr. Natural Resources Manager Natural Resources Specialist Natural Resources Technician Sr. Certified Arborist Certified Arborist Sr. Land Use Planner Land Use Planner GIS Specialist Technical Editor Project Coordinator/ Clerical Project Manager Senior Right of Way Agent Senior Right of way Agent Right of Way Agent Project Control Specialist/ROW Tech Sr. PM/Senior Arch. Historian Sr. PM/Sr Archaeologist APM/Senior Historian APM/Supervisin g Archaeo. Architectural Historian Lab Manager/ Crew Leader Staff Archaeologist Graphics-GIS Research/ Proj Assist/Proj. Admin Principal LA LA 4 LD 3 LD2 Admin VP Assoc. Sr. Prof. III Sr. Prof. II Prof. IV Office Srvcs III BlaserWilliams-LarsonVan GenderenJohnson, Martinez Gordon,Seaver Loiselle Various Cowan Inman, Simpson 6 2 2 2 30 $7,128 2 20 2 66 $15,360 6 40 $9,532 6 12 48 $10,752 52 $11,507 18 $3,870 16 16 6 12 68 $12,790 18 $4,206 16 $3,664 8 $1,940 $288 0 0 0 0 0 24 0 0 0 0 22 0 0 0 16 0 0 0 0 0 0 0 0 0 0 0 0 0 0 14 22 0 0 12 0 0 0 0 0 0 364 $81,037 8 $1,740 18 $3,590 14 $2,850 74 $14,950 142 $28,330 58 $11,590 20 $3,960 $1,400 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 334 $68,410 10 60 80 322 $61,550 4 4 1 8 87 $17,802 274 $52,534 8 6 1 8 107 $22,386 $0 0 0 0 0 0 12 0 0 0 0 0 10 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 12 76 0 80 0 0 0 0 0 0 0 790 $154,272 28 $5,420 142 $29,992 2 40 40 604 $114,970 $1,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 40 0 40 0 0 0 0 0 0 0 774 $151,382 40 334 192 20 10 711 $136,935 $15,629 40 334 192 20 10 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 711 $152,564 23 24 84 72 314 32 48 35 25 661 $91,349 10 52 8 60 6 140 $27,280 5 56 2 67 $13,010 $20,864 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 23 24 84 72 314 32 48 35 25 0 0 0 0 0 15 52 8 56 60 8 868 $152,502 103 $21,721 55 $11,641 155 $32,517 $20 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 313 $65,899 8 24 60 4 2 1 105 $16,190 8 54 68 $11,720 $214 0 0 0 0 0 8 24 60 8 54 0 0 4 2 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 173 $28,124 50 100 50 50 276 $41,990 350 $69,250 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 50 100 0 50 50 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 626 $111,240 110 $20,690 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 110 $20,690 472 $91,108 58 $12,783 6 103 $20,605 10 40 40 40 1573 $302,641 2 8 8 144 $30,203 6 1 8 8 196 $39,942 $40 0 0 0 0 0 12 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 13 56 56 40 0 0 0 0 0 0 0 2546 $497,322 60 $15,996 110 $28,850 114 $30,810 $0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 284 $75,656 40 334 192 20 10 56 24 60 8 54 22 10 4 2 17 50 100 0 50 50 23 24 84 72 314 32 48 35 25 41 194 56 160 12 15 52 8 56 60 8 $165.00 $145.00 $275.00 $245.00 $165.00 $240.00 $170.00 $130.00 $190.00 $165.00 $220.00 $175.00 $165.00 $155.00 $130.00 $188.00 $155.00 $155.00 $125.00 $115.00 $204.00 $204.00 $145.00 $145.00 $126.00 $117.60 $100.80 $204.00 $119.00 $215.00 $185.00 $165.00 $150.00 $155.00 $310.00 $230.00 $205.00 $185.00 $150.00 $120.00 $6,600 $48,430 $52,800 $4,900 $1,650 $13,440 $4,080 $7,800 $1,520 $8,910 $4,840 $1,750 $660 $310 $2,210 $9,400 $15,500 $0 $6,250 $5,750 $4,692 $4,896 $12,180 $10,440 $39,564 $3,763 $4,838 $7,140 $2,975 $8,815 $35,890 $9,240 $24,000 $1,860 $4,650 $11,960 $1,640 $10,360 $9,000 $960 7,893 $1,519,644 $79,805 $59,223$197,116 $36,900 TOTAL AINW REIMBURSABLES TOTAL AINW FEES TOTAL CS REIMBURSABLES TOTAL CS FEES TOTAL AKS REIMBURSABLES TOTAL AKS FEES TOTAL S&W REIMBURSABLES TOTAL S&W FEES TOTAL GW REIMBURSABLES TOTAL GW FEES $20,653$0 $1,559,099 TOTAL PROJECT BUDGET TOTAL HOURS TOTAL LABOR TOTAL REIMBURSABLES $39,456 Project Budget Form WORK TASK/ TASK HOURS WORK TASK/ TASK COST $211 $90,700 $0$15,951 Kittelson & Associates Inc. I:\FIN\Contracts\FY 2024-25\32500039 McDonald Street Engineering Services\Contracts and Amendments\McDonald Street - BOC - Phase I Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D QBS RFP McDonald Street Engineering Services 32500039 Page 24 EXHIBIT B CONTRACTOR’S PROPOSAL See next page Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D 1. TRANSMITTAL PAGE October 7, 2024 Toni Riccardi City of Tigard ContractsPurchasing@tigard-or.gov RE: RFP 2025-08 McDonald Street Engineering Services Dear Ms. Furman and Evaluation Committee: The City of Tigard (Tigard) has made commendable strides towards its vision of becoming “an equitable community that is walkable, healthy, and accessible for everyone.” As the City transforms McDonald Street into a complete street, the City will move even closer to this vision. This transformation will make McDonald Street into a truly multimodal street that safely integrates bicycle and pedestrian facilities while calming traffic. This project is a milestone that will enhance Tigard’s transportation network, but will require solving several challenges, like minimizing environmental and construction impacts, identifying feasible and fundable improvements, and creating context-appropriate streetscapes. Based on the research conducted by the Kittelson team in preparation for this proposal, we are ready to work alongside the City to transition McDonald Street into a safe, connected, accessible multimodal corridor. The Kittelson team, consisting of Kittelson (Prime), Consor, AKS Engineering & Forestry (AKS), Shannon & Wilson (S&W), GreenWorks, Commonstreet, and Archaeological Investigations Northwest, Inc. (AINW), can successfully deliver this project because we can: ƒStreamline project execution by leveraging our expertise across planning, design, and environmental consulting. Our experience with McDonald Street, including conceptual design studies and Safe Routes to School crossings, enables us to efficiently implement the project from planning through to construction. ƒDevelop context-sensitive designs using performance-based design and context-classifications. Kittelson developed NCHRP Research Report 1036: Roadway Cross Sections Reallocation; A Guide and the decision-making framework in the report to evaluate trade-offs based on transportation, social, environmental, and economic outcomes. ƒConduct community-focused engagement informed by our history of working in Tigard, dating back over 30 years. We excel at facilitating outreach and engagement activities that resonate with the community, encourage active participation, and gains useful feedback. ƒDesign feasible and effective traffic calming measures, including roundabouts, based on our knowledge of national best practices in alternative intersection designs and safety improvements. Kittelson’s leadership in national guidance, including NCHRP 1043: Roundabout Guide and NCHRP Research Report 926: Pedestrian and Bicycle Safety at Intersections, positions us as experts in integrating innovative safety measures. ƒDraw upon our project management expertise, demonstrated by our record of delivering projects on time, within budget, and in alignment with community and stakeholder needs. Project Manager, Nick Polenske, PE, and Principal Engineer, Anthony Yi, PE, will lead this effort, seamlessly coordinating the multidisciplinary teams and maintaining clear communication with the City throughout all project phases. Our experience in Tigard and across Oregon reinforces our ability to meet and exceed the City’s expectations. We have successfully collaborated on numerous transportation projects, fostering a partnership built on trust, shared expertise, and a commitment to delivering innovative, contextually appropriate solutions. 851 SW 6th Avenue, Suite 600 Portland, OR 97204 P. 503-228-5230 As local residents and professionals who have worked on transformative projects in Tigard, we are eager to blend public infrastructure improvements with the unique context of the community. Our approach will prioritize neighborhood engagement, allowing us to fully understand local issues and develop cost-effective, implementable alternatives that improve safety, connectivity, and accessibility for all. Kittelson acknowledges the full project schedule is not defined and is prepared to support this project through the anticipated construction phase between 2029 and 2030. With a personal and professional interest in seeing the conversion of McDonald Street into a complete street, we are committed to servicing this project through all phases, including Phase II. We understand the timing of Phase II is uncertain and we will be ready and available to work on Phase II when the City is ready. As Principal Engineer and an authorized representative of Kittelson, I, Anthony Yi, PE, am fully committed to the success of this project. Alongside Nick, we will make sure the City is provided with the resources, expertise, and innovative approaches necessary to transform McDonald Street for the Tigard community. Sincerely, Kittelson & Associates, Inc. Anthony Yi, PE Principal Engineer Proposer Contact: Nick Polenske, PE, Project Manager 851 SW 6th Avenue, Suite 600 Portland, OR 97204 P. 503-535-7407 / E. npolenske@kittelson.com SUBMITTED BY: Kittelson & Associates Inc. Omara Street/McDonald StreetOR99W/McDonald Street CITY OF TIGARDMCDONALD STREET ENGINEERING SERVICES Hall Boulevard/McDonald StreetDocusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D City of Tigard / McDonald Street Engineering Services RFP 2025-08 i Kittelson & Associates, Inc. / October 7, 2024TABLE OF CONTENTS1. Transmittal Page2. Firm Qualifi cations & Project Team ..................................................................12.1 Firm Overview ..............................................................................................................12.2 Resources & Ongoing Projects ...............................................................................12.3 Project Experience .....................................................................................................12.4 Work Quality & Cost Control ..................................................................................22.5 Management & Organizational Capabilities ......................................................32.6 Alternative Project Delivery Experience ............................................................32.7 Team Responsibilities & Subconsultant Capabilities .....................................33. Understanding & Approach ...............................................................................43.1 Project Management & Coordination ..................................................................53.2 Project Work Tasks ....................................................................................................53.3 Schedule ........................................................................................................................84. Project Management ..........................................................................................94.1 Principal Member Involvement ..............................................................................94.2 Key Personnel .............................................................................................................9AppendicesAppendix A Team Capabilities Matrix & ResumesAppendix B Project Profi lesAppendix C Required FormsDocusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D City of Tigard / McDonald Street Engineering Services RFP 2025-08 1 Kittelson & Associates, Inc. / October 7, 20242. FIRM QUALIFICATIONS & PROJECT TEAMThe Kittelson team includes leading public works practitioners who are knowledgeable of the City’s expectations, understand McDonald Street, and can leverage their expertise to convert McDonald Street into an “equitable and walkable” roadway that benefi ts all users. 2.1 FIRM OVERVIEWKittelson is a transportation planning and engineering fi rm that is changing how people move around. Through safety performance, operations, and best-practices, Kittelson has contributed to constructing complete streets that safely and comfortably accommodate pedestrians, bicyclists, transit users, and cars. We are nationally recognized leaders in creating people-centric streets that balance the needs of all users. Our approach integrates safety, accessibility, and mobility. With expertise in urban design, transportation engineering, and community engagement, we transform streets into dynamic public spaces that foster healthy, sustainable communities. Kittelson consistently delivers streets that positively impact the communities that rely upon them.“They (Kittelson) have delivered outstanding results on complex roadway projects, ensuring that all elements of design and execution meet the highest standards of quality and effi ciency.” Russell Knoebel, PE, Capital Project Services Manager, Washington County2.2 RESOURCES &ONGOING PROJECTSThe Kittelson team, including our subconsultant partners, have applied their expertise in active transportation, geometric design, alternative intersections, safety, operations, emerging trends and technologies, access management, planning, and public engagement to make roadways safer, more connected, and accessible. The Kittelson team can adjust existing facilities to integrate non-motorized users, consider the mobility goals for motorized users, and identify solutions for various communities and contexts.Kittelson and our teaming partners have discussed the anticipated level of eff ort for this project and have confi rmed we have the capacity and resources to successfully deliver this project. Our combined resources provide the City with abundant resources and capabilities to make sure this project is completed on schedule and within budget, while building upon the momentum from each phase.2.3 PROJECT EXPERIENCE72nd Avenue Preliminary Design; Tigard, OR / Kittelson PrimeContact: Courtney Furman PE, Principal Engineer, City of Tigard, 13125 SW Hall Boulevard, Tigard, OR 97223; P. 503.718.2442Building upon the completed 72nd Avenue Corridor Study (2020), Kittelson is developing preliminary designs for the 72nd Avenue from OR217 to OR99W. This will position the City to be competitive for federal grants for fi nal design and construction, and coordinate with development frontage improvements and the future Red Rock Creek Trail. The preliminary design includes a complete street with continuous bicycle and pedestrian routes with sidewalks, cycle tracks, on-street parking and bus pull-outs.Kittelson is developing the 30% design for the OR99W to Dartmouth section of 72nd Avenue and 10% design for the Dartmouth Street to OR217 section. The 10% design will support refi ning the cross section and alignment between Dartmouth Street and OR217. Further design elements will be determined once additional funding is available. The team started implementing the public involvement process to keep the people aware of the project developments.Tiedeman Avenue Multimodal Study; Tigard, OR / Kittelson Prime Contact: Courtney Furman PE, Principal Engineer, City of Tigard, 13125 SW Hall Boulevard, Tigard, OR 97223; P. 503.718.2442Tiedeman Avenue connects pedestrians and bicyclists to schools, parks, regional trails, bus stops, and residential and commercial areas. It also provides freeway access. Kittelson studied the Tiedeman Avenue corridor from SW Walnut Street to SW Greenburg Road to advance the City’s goal of addressing operational, safety and connectivity defi ciencies. This involved analyzing traffi c conditions, identifying key issues and community priorities for the corridor, developing cross section and sketch-level alternatives, and preparing a 10% concept plans. To engage public input and buy-in, Kittelson created fact sheets, fl yers, survey questions, and online open-house content. These outreach activities communicated the project’s intent, guided selecting a preferred alternative, and assisted with concept design. Based on the selected alternative, Kittelson prepared 30% plans, cost estimates, a project visualization, and a stormwater plan.Field visit along Tiedeman AvenueKey intersection along 72nd AvenueAvailable Resources• 60 Engineers & Planners• 9 CAD Drafters• 11 Administrative & Creative Partner Staff Legal Structure• S-CorporationHome & Managing Offi ceKittelson851 SW 6th Ave., # 600Portland, OR, 97204370 Employees26 Offi ces39 Years in BusinessDocusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D City of Tigard / McDonald Street Engineering Services RFP 2025-08 2 Kittelson & Associates, Inc. / October 7, 2024 US97: Lower Bridge Way – NW 10th Street; Terrebonne, OR / Kittelson Prime Contact: Cari Charlton PE, Project Manager, ODOT. 63055 N Hwy 97, Bend, OR 97003; P. 541.815.6831 Kittelson led planning and design services to improve safety and access at US 97/Lower Bridge Way and through Terrebonne. The preferred alternative is a grade separated interchange with a dog bone roundabout ramp terminal. This will provide easier access to the community for bicycles and pedestrians and improve pedestrian crossings along US97 in town with a shared-use path. Kittelson led preparation of the Terrebonne Refinement Plan and then preparation of PS&E documents. The final design includes over 100 compliant ADA ramps (on system and off). The project was delivered on time and budget in August 2023 and construction started earlier in 2023 and is ongoing with Kittelson providing construction support. apron. To address complex roundabout grading and utility conflicts, and develop construction sequencing, Kittelson collaborated with City and the PDB team. In addition, Kittelson led design for signing & striping, illumination and traffic control plans, which involved maintaining traffic on three legs of the intersection and detours for a road closure during bridge construction. Boeckman Road Improvements Progressive-Design-Build / Tapani/Sundt Lead Contact: Andrew Barrett, Capital Projects Manager, City of Wilsonville, 29799 Town Center Loop E, Wilsonville, OR 97070; P. 503.570.1567 Kittelson is a key subconsultant for this progressive-design-build (PDB) project, Consor is the owners representative, and GreenWorks is the landscape architect. The project includes building a new bridge, a roundabout, buffered/protected bike lanes, sidewalks, and left-turn lanes to serve a growing neighborhood and new elementary school. Kittelson conducted an Intersection Control Evaluation (ICE) to compare signalized and roundabout intersection options at Boeckman Road/Canyon Creek Road, which resulted in selecting a roundabout. Subsequently, Kittelson prepared PS&E documents, including PROWAG-compliant curb ramps, bike ramps, and an internal truck 2.4 WORK QUALITY & COST CONTROL Kittelson develops a project management plan (PMP) for each project that outlines all deliverables, task leads, quality control reviewers, and milestones. Anthony Yi, PE, will facilitate our work quality and cost control approach by providing independent practitioner-oriented reviews. Nick Polenske, PE, our Project Manager, will integrate technical expertise and work with Anthony to verify work quality through team interactions and detailed reviews. Nick has successfully led large design activities for ODOT major projects, like the US 97: Lower Bridge Way – NW 10th Street and North Bend Corridor Design/Build. Anthony and Nick will maintain the schedule and budget, but understands level of efforts sometimes need adjusting to maintain them. If adjustments are needed, we will follow the process illustrated below to determine a mutually agreeable way forward to meet the schedule without sacrificing quality and maintaining costs. US 97/Lower Bridge Way will become a dogbone roundabout Kittelson created rendering of OR 43 protected intersection West Linn Arterial Roadways & OR43/ Marylhurst Drive Protected Intersection / Consor Prime Contact: Erich Lais PE, Public Works Director/City Engineer, City of West Linn, 22500 Salamo Road, West Linn, OR 97068; P. 503.722.3434 Kittelson and Consor enhanced pedestrian and bicycle facilities along the Willamette Falls Drive and OR 43 corridors, addressing safety and comfort issues for non-motorized users. For Phase I, Kittelson led the concept development and created a 30% designs to secure funding. The concepts include bicycle and pedestrian facilities along and across the corridors and supports adjacent land uses. Using augmented reality, Kittelson provided visualizations of proposed alternatives. During Phase 2, Kittelson and Consor prepared PS&E documents for the OR 43/Marylhurst Drive intersection, one of the first protected intersections on a state highway. Construction is set for early 2025, with Kittelson and Consor offering construction support. Boeckman Road Overcrossing 1. Engage 2. Determine 3. Assign 4. Leverage Engage the City’s Project Manager to evaluate what caused the change Determine staffing needs or adjust critical path items to maintain the schedule without incurring costs Use our Project Management Dashboard to assign staff to maintain the budget and schedule Leverage our nationwide resources and our teaming partners resources 5. Report Back Report back to Courtney and Kittelson team on Resolution Each task lead will provide daily coordination among the discipline leads who will perform technical analyses and calculations related to the deliverables and documentation. Nick will provide direction on relevant standards and industry guidelines and work with Courtney to gather City comments and address them as follows: ƒFor differing opinions, set up a working session with our internal team to recommend a way forward. ƒMeet with City staff to verify our approach meets the project goals. ƒUpdate each deliverable to reflect the decision-making process the team worked through. This is a proven process that Nick and Anthony have used to maintain schedules, work quality, and cost control. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D City of Tigard / McDonald Street Engineering Services RFP 2025-08 3 Kittelson & Associates, Inc. / October 7, 2024 PROJECT MANAGER Nick Polenske, PE  2.5 MANAGEMENT & ORGANIZATIONAL CAPABILITIES Kittelson structures our teams around our project managers who are experts within our service areas. Our project managers are supported by a robust staff of engineers, planners, GIS analyst, drafters, graphic designers, technical editors, administrators, and accountants. We make sure every project has sufficient resources to prepare deliverables that are technically sound, compliant, and support the communities where we live, work, and play. This structure fosters positive working relationships among staff, bringing the greatest of capabilities and resources to the City without the barriers created by geographic locations or profit center. 2.6 ALTERNATIVE PROJECT DELIVERY EXPERIENCE Kittelson and our teaming partner Consor have been involved with several alternative project delivery methods, including PDB, general contractor/construction manager (CM/GM), and design/build. Some of the projects that we have delivered using alternative project delivery methods include the following: ƒNorth Bend Corridor Design/Build, Bend, OR ƒWilson Avenue Improvement Design/Build; Bend, OR* ƒNewport Avenue Improvements CM/GM* ƒEmpire Avenue Improvements Design/Build; Bend, OR ƒBoeckman Road Improvements PDB; Clackamas County, OR ƒ9th Street Improvements Design/Build; Redmond, OR ƒI-5/La Center Road Interchange & Local Road Improvements Design/Build; La Center, WA* *Project Profile presented in Appendix B 2.7 TEAM RESPONSIBILITIES & SUBCONSULTANT CAPABILITIES Kittelson will be the primary consultant responsible for managing the overall project and leading the roadway and traffic design elements of the project. The Team Organization chart illustrates our team, lines of communication, and areas of responsibilities. The following lists our subconsultants’ expertise, experience with Kittelson, other relevant experience, and why we selected them for this project. GreenWorks is specialized in sustainable landscape architecture and environmental design. For 30 years Kittelson and Greenworks have transformed roadways into desirable destinations. This experience includes the Boeckman Road Improvements PDB. Why Selected. With a successful 20-year partnership combined with 30 years of experience with the City, our resources and capabilities can facilitate activities beyond the concept design phase. AKS has expertise in environmental compliance, wetland sciences, urban forestry, and surveying, which will support all phases of this project. They have completed over a dozen projects throughout Washington County with Kittelson, including improvements for Blanton Street, Cornelius Pass Road, and Farmington Road/209th Avenue. Why Selected. The local experience AKS has with the Temple- Twality Safe Routes to School (SRTS) and Murdock Street Sidewalk & Stormwater Improvements will streamline the analysis and design process by building upon already available information. S&W supports public infrastructure projects by providing their expertise in geotechnical engineering and environmental consulting. They have worked alongside Kittelson on transportation projects, including US 97: Terrebonne – NW 10th Avenue in Terrebonne, OR, Willamette Falls Path/OR99W Enhancements in Oregon City, and 72nd Avenue Preliminary Design and Fanno Creek Bridge for the City. Why Selected: S&W has extensive knowledge of Tigard’s geologic and geotechnical conditions gained through completing 75 projects in Tigard, and successful history of working with Kittelson. Why Selected: With a 30-year history of working with Kittelson and extensive knowledge of Tigard, having enhanced streetscapes in Tigard for 30 years, GreenWorks will bring their talents to establish a functional and aesthetically pleasing McDonald Street. Commonstreet implements right of way (ROW) programs to support public infrastructure improvements. They have direct experience with the City, which includes the Red Rock Creek Enhancement & Stabilization, and have supported Kittelson on the Shute Road Multiuse and Huffman East Extension projects in Hillsboro. Why Selected. Commonstreet successfully integrates the ROW process into design and construction timelines, under all applicable State and Federal guidelines. AINW (WBE), offers archaeological, historical, and cultural resource services, and regularly partners with Kittelson on infrastructure projects. Their experience include supporting City with the Tigard Street Bridge Replacement, Red Rock Creek Enhancement & Stabilization, and SW Wall Street Improvements. Why Selected. Building upon their knowledge of Tigard, AINW will navigate the regulatory review process by completing a cultural resource assessment that efficiently obtains approvals. ROADWAY Keisuke Harry, PE TRAFFIC Wade Scarbrough, PE STORMWATER Nicholas McMurtrey, PE WATERLINE Fulgence Bugingo, PEPRINCIPAL ENGINEER Anthony Yi, PE  STRUCTURAL ENGINEER Stuart Garth, PE GEOTECHNICAL ENGINEER James Walters, PE ENVIRONMENTAL SCIENTIST Alia Hubbard LANDSCAPE ARCHITECT Mike Faha, PLA, RIGHT OF WAY Kari Lowe, SR/WACITY OF TIGARDCourtney Furman, PEKittelson Consor AKS S&W GreenWorks Commonstreet AINW ENVIRONMENTAL SPECIALIST Julie Wirth-McGee, PWS ARBORIST Bruce Baldwin, ISA ARCHAEOLOGICAL HISTORIAN Andrea Blaser SURVEYOR Nick White, PLS UTILITY COORDINATION Fulgence Bugingo, PE PROJECT LEADS TECHNICAL SUPPORT CONSTRUCTION MANAGER Chad Maxwell, PE ADVISOR Ian Machan, PE Alternative Delivery Team Organization Subconsultants Consor specializes in public works infrastructure and will provide their engineering expertise in stormwater, structures, waterlines, support public involvement efforts, lead construction management activities, and advise on alternative delivery processes. Their experience with Kittelson spans over 20 years, which includes OR141/OR217 Curb Ramps in Tigard; Main Street Improvements in Gold Beach; and Boeckman Road Improvements PDB in Wilsonville. PUBLIC INVOLVEMENT Kimi Sloop Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D Omara St.103rd Ave.97th Ave.100th Ave.93rd Ave.89th Ave.Hall Blvd.OR99W (Pacific Hwy.)A B CC F E D Pinebrook CreekGA D E A B C F G A City of Tigard / McDonald Street Engineering Services RFP 2025-08 4 Kittelson & Associates, Inc. / October 7, 2024 3. UNDERSTANDING & APPROACH The vision for McDonald Street is to become a complete street, safely integrating all travel modes. To achieve this, the corridor’s planned cross sections and intersections must be refined to balance vehicular congestion relief with safe, connected pedestrian and bicycle facilities. These refinements will fill gaps in walking and biking infrastructure, linking key destinations like James Templeton Elementary, Twality Middle School, East Butte Heritage Park, and the Fanno Creek Trail. Additionally, traffic operations, including peak hour left turns, must be addressed to reduce risks for all users. The following illustration and table presents the project constraints, needs, and opportunities we will consider while refining the concepts. CHALLENGE APPROACH RELEVANT EXPERIENCE A. Pedestrian & Bicycle Safety | Construct comfortable, consistent pedestrian and bicycle facilities along McDonald Street and identify safe and convenient crossing locations while also controlling vehicle speeds. Prioritize continuous facilities with enhanced crossings at key locations (likely 100th Avenue, Omara Street, 97th Avenue, and 98th Avenue) to provide safe multimodal connections to schools, churches, and recreation areas. 72nd Avenue Preliminary Design / Tiedeman Avenue Multimodal Study / West Linn Arterial Roadways / Boeckman Road Improvements / Templeton-Twality SRTS / Murdock Street Sidewalk & Stormwater Improvements / Elliott Road Complete Street B. Constrained ROW | The two-lane cross section, topography, and lack of pedestrian and bicycle facilities creates a setback challenge to maintain existing land uses. Review and update traffic analysis, consider alternative intersection treatments, like roundabouts to reduce the necessary cross section width in constrained areas, specifically 103rd Avenue to 93rd Avenue. 72nd Avenue Preliminary Design / Tiedeman Avenue Multimodal Study / West Linn Arterial Roadways / Boeckman Road Improvements / Red Rock Creek Stabilization & Enhancement C. Left Turns | Left turns to and from McDonald Street create a significant queuing issue during peak hours and a safety risk as users wait for a gap. Using results from our traffic analysis and ICE we will identify which intersections warrant left turn lanes or roundabout treatments. Tiedeman Avenue Multimodal Study / West Linn Arterial Roadways / US97: Lower Bridge Way-NW 10th Avenue / Boeckman Road Improvements D. Construction Staging & Access Management | Identify construction sequencing plans that reduce disruption for the public, especially for residents on dead-end routes, while also optimizing construction activities. Review the 2D and 3D impacts associated with construction to maintain resident access points at all times and create detailed staging plans to sequence the utility undergrounding and waterline replacement. The traffic control plan will maintain safe routes for students getting to and from schools in the area. OR43 Protected Intersection / US97: Terrebonne – NW 10th Avenue / US20 Tumalo Multilane Roundabout / Boeckman Road Improvements E. Utility Undergrounding & Stormwater Infrastructure | The additional cross-sectional elements will require relocating private utilities and adding impervious area will require stormwater treatment and quantity management. Available ROW and funding to determining the length of private utilities that can be undergrounded and identifying stormwater treatment locations. Providing consistent connection while replacing the waterlines will be needed to provide residents access to water. OR43 Protected Intersection / US97: Lower Bridge Way-NW 10th Avenue / I-5 at Beltline Interchange Storm Drainage & Water Quality Design F. Pinebrook Creek Crossing | Potential improvements to the existing culvert and stormwater infrastructure at this crossing. Our team has confirmed with ODFW that the proposed roadway improvements will not trigger fish passage and require replacing the culvert. There could be benefits to a culvert replacement for additional grant funding or future fish passage mitigation at more challenging sites. 72nd Avenue Preliminary Design / US97: Lower Bridge Way-NW 10th Avenue / Hayesdale Drive Bicycle & Pedestrian Improvements G. McDonald Street/Hall Boulevard Intersection | Heavy congestion and long vehicle queues during peak hours, and lack of pedestrian facilities along McDonald Street approaching Hall Boulevard. Evaluate intersection treatment alternatives from additional turn lanes, to a protected intersection, as well as feasibility of a roundabout with future capacity and pedestrian/bicycle safety in mind. We will build upon our existing survey data collected for our work on the OR141/OR217 Curb Ramps project. OR141/OR217 Curb Ramps / 72nd Avenue Preliminary Design / Tiedeman Avenue Multimodal Study / West Linn Arterial Roadways / OR43 Protected Intersection / Boeckman Road Improvements McDonald Street Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D City of Tigard / McDonald Street Engineering Services RFP 2025-08 5 Kittelson & Associates, Inc. / October 7, 2024 3.1 PROJECT MANAGEMENT & COORDINATION Our management approach is based on proactive communication, identifying issues and risks early, and course correcting. We will prepare a PMP to stay on schedule, within budget, and proactively communicate. This approach will incorporate these guiding principles: ƒBuild a decision-making framework guided by the City’s goals, respectful of equitable and community-focused planning. ƒRight-size the analytical methods and tools to screen and refine concepts. This allows us to rapidly screen concepts and define modeling activities. ƒIntegrate design, operations, and safety throughout all project phases to develop feasible concepts that support project goals, inform design decisions, and documentation in deliverables. ƒDedicate storytellers to empower decision-making. Graphics and storytelling will be used to highlight big picture decisions and empower stakeholders. 3.2 PROJECT WORK TASKS Carrying out this project will appropriately sequence tasks so that each element is building upon the other. The schedule on page 8 displays how we will sequence the phases, timeframe for each task, and the City’s expected participation. PHASE I SERVICES Task 1 Project Management & Administration / Team Members: Nick Polenske, PE; Anthony Yi, PE To keep everyone informed, on schedule, and within budget, while fostering innovation, our project management activities will include: ƒPreparing a PMP with monthly updates to identify risks and solutions before they impact the project; ƒConducting brief, weekly meetings with Courtney to discuss progress, deadlines, questions, and strategize for risks; and ƒBi-weekly Consultant Team meetings to address schedule, work in progress, upcoming priorities, and budget updates. Task 2 Traffic Analysis Team Members: Nick Polenske, PE, Keisuke, PE, Wade Scarbrough, PE The traffic analysis will be conducted by following these steps: 1. Obtain traffic operations insights through field visits and local knowledge. We will supplement our drone images of McDonald Street with a field review and inventory to observe existing traffic operations and safety issues, unique driver behavior, and other roadway characteristics to inform the alternatives analysis. 2. Streamlined two-stage traffic/safety analysis. Stage 1 will use lower complexity tools, like NCHRP Report 672, HCM level-of- service analysis, MUTCD Signal Warrants, Synchro 11, crash history, and crash modification factors to rapidly evaluate and screen concepts. During Stage 2 we will develop a VISSIM model to capture the multimodal operations. We will consider using tools, like an expected crash reduction analysis or the 20 Flags Method in NCHRP Report 948: Guide for Pedestrian and Bicyclist Safety at Alternative and Other Intersections and Interchanges. Kittelson led development of NCHRP Report 948 and the 20 Flag Method, a qualitative analysis built around 20 design flags to highlight safety impacts for pedestrians and bicyclist at intersections. Task 3 Alternatives Analysis Team Members: Nick Polenske, PE; Keisuke, PE; Wade Scarbrough, Nick McMurtrey, PE; Mike Faha, PE Building upon Task 2 findings, we will develop the preliminary design footprint for the project. We will develop and analyze alternatives that best fit the context of McDonald Street and address the issues by: ƒDeveloping an equitable multimodal decision framework to achieve the project goals and represent them in the design. We will balance cost with bicycle and pedestrian solutions, consider stakeholders’ input, and reflect the City and residents objectives. Evaluation factors could include route connectivity, safety, traffic operations, and ROW, environmental, drainage and natural resources impacts, and construction cost. We’ll use visualizations to help people provide their opinions on different alternatives. 93rd Avenue Roundabout Alternative 100th Avenue Roundabout Alternative ƒPreparing conceptual designs and cost estimates will be informed by applying NCHRP Report 785: Performance Based Analysis of Geometric Design of Highways and Streets approach to develop concepts based on context and integrating design, operations, and safety into the overall performance the project. Also, we will apply our lessons learned from other City projects. ƒEvaluating roundabouts will be a large focus of our alternatives analysis. The preferred cross section will drive solutions for connection along the corridor, but balancing these goals with the needed ROW and public perception will be essential for moving forward. We have evaluated and sketched potential roundabout sizes at 100th Avenue/McDonald Street and 93rd Avenue/McDonald Street to begin understanding the impacts associated with this intersection treatment. (See sketches below) ƒWaterline Analysis. To replace the three waterlines located in the corridor, Fulgence Bugingo, PE, will conduct a waterline alternatives analysis to develop a strategy to maintain water and fire protection services during construction and minimize shutdowns during tie-in activities. ƒCompleting a memorandum that compiles the alternative analysis; outlines their strengths and weaknesses associated with the evaluation criteria; and helps to select a preferred alternative that will progress to design and into construction. Task 4 Public Involvement Program Team Members: Nick Polenske, PE; Kimi Sloop Kimi Sloop will prepare the public involvement plan (PIP), which will have a stakeholder engagement strategy describing the decision- making framework. This plan will be a updated throughout the project with input from the City’s communication staff to align the materials and approaches with the City’s communication approach. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D City of Tigard / McDonald Street Engineering Services RFP 2025-08 6 Kittelson & Associates, Inc. / October 7, 2024 The PIP will outline the communication goals and purpose, target audiences, key messages, and engagement strategies; identify the schedule, topics, roles, and responsibilities for the City and Kittelson team members; and describe how input will be incorporated. Other public involvement support will include: ƒAssisting the City with open houses, which includes creating graphics, gathering input, and sharing information with the community via Engage Tigard ƒConducting a community survey during the alternatives analysis phase to identity community priorities and assess tradeoffs between alternatives ƒPreparing a public involvement toolkit and updating it at each project phase to reflect changes in the design process ƒCreate a 3-D visualization with fly-through video, like the one created for the Tiedeman Avenue Multimodal Study With 3-D visualization, augmented, and virtual reality, Kittelson has successfully conveyed alternatives in a way that people are familiar with and in an interactive way to view improvements from the perspective of pedestrians and bicyclists. Task 5 Survey Team Members: Nick White, PLS AKS will lead the survey activities, which will include: ƒMapping utility locations and public ROW ƒProviding basemap of the existing roadway features ƒUsing aerial surveying and terrestrial laser scanning, in addition to conventional surveying, to improve efficiencies for the project and increase crew safety AKS is the surveyor for the Murdock Street Sidewalks & Stormwater Improvement and Templeton-Twality SRTS projects, which are adjacent to McDonald Street. Task 6 – Technical Studies & Reports Task 6.1 – Cultural Resources Planning Team Member: Andrea Blaser If a permit is needed from the US Army Corps of Engineers (USACE), AINW will complete a cultural resources survey to assist in complying with Section 106 of the National Historic Preservation Act. Once the Area of Potential Effect (APE) is delineated, AINW will direct surveys of the APE to identify historic built environment resources and archaeological sites with potential to be affected by the project. At this time, we understand there are no previously documented cultural resources within the project area. If FHWA funding is obtained, additional cultural resources services will likely be needed. ODOT has agency-specific reporting standards because of USDOT Act Section 4(f) requires analysis to avoid or minimize harm to significant historic sites, parks, recreation areas, and refuges for projects funded or authorized by an agency of the USDOT. Task 6.2 – Geotechnical Investigation & Pavement Design Team Members: James Walters, PE S&W will conduct additional explorations, supplementing their six existing boring, to better define subsurface conditions, evaluate seismic hazards, and support embankment and retaining structures. We will assess compressible soils in the creek channel for static settlement concerns and collaborate with the design team on cost- effective mitigation strategies. Fieldwork will include geotechnical borings, pavement cores, dynamic cone penetration tests, and infiltration testing, providing data for geotechnical, pavement, and stormwater design. Pavement review will guide rehabilitation and new pavement section design and provide subgrade modulus for new pavement sections. We will schedule the field investigation immediately upon notice of selection to make sure we secure a contractor with within four to six weeks of the notice to proceed. Task 6.3 – Hazardous Materials Assessment Team Members: Alia Hubbard To assess the presence of environmental impacted properties or areas, S&W will complete a Hazardous Materials Corridor Study (HMCS). Additionally, we recommend contingency tasks for a shoulder material investigation, Phase 2 Environmental Site Assessment, and geophysics surveying to identify potential underground storage tanks and any other anomalies that may impact construction. The scopes of these contingency tasks will be informed by the HMCS results. Task 7 – Hydraulic & Stormwater Studies Team Members: Keisuke Harry, PE; Nick McMurtrey, PE Pinebrook Creek has an Active Channel Width (ACW) of about 4 feet and, per ODFW, is not habitat for migratory species. Since the existing 36-inch culvert can handle runoff from the 102-acre upstream area and does not require fish-passage standards, it likely won’t need replacing. If culvert enhancements are made, Consor will perform a hydraulic analysis to check for scour, stream bed composition, roadway over topping, and impacts on the Special Flood Hazard Area. Consor will also evaluate fill within the 100-year floodplain and document impacts per the City’s floodplain development requirements, as the area is not FEMA-designated. Early selection of a stormwater management approach is crucial. West of SW 100th Avenue, Low Impact Development Approach (LIDA) or proprietary systems may integrate with traffic calming measures in landscaped strips. East of SW 100th Avenue, a regional stormwater approach could reduce ROW impacts, or a fee-in-lieu of constructing detention systems could be pursued given Pinebrook Creek’s moderate hydromodification risk level. Concepts, roadway sections, impervious surface types, and preliminary costs should be defined early to confirm applicable stormwater codes. At the 93rd Street intersection, retaining walls may help avoid wetland impacts, making SLOPES V inapplicable and reducing detention requirements. Task 8 – Environmental Documentation & Permits Team Members: Julie Wirth-McGee, PWS Our approach integrates environmental specialists into the design process to avoid triggering permits, such as using non-notifying Nationwide permits. We’ll coordinate early with USACE to secure a no-effect determination, avoiding SLOPES V requirements and keeping the project on schedule while protecting natural resources. Wetlands near the site will be considered, but Clean Water Services’ vegetated corridor impacts should be minimal due to the fill prism. AKS will seek to avoid or minimize wetland impacts in Phase I, confirming permit conditions early for smooth navigation through the process. We’ll also engage ODFW to identify potential triggers, but since Pinebrook Creek has no native fish, fish passage requirements won’t apply. Task 9 – Right of Way Team Members: Kari Lowe, SR/WA; Nick White, PLS Commonstreet will facilitate access to impacted properties through Right of Entry and manage title reviews concurrently. They will order and review title reports, addressing any issues to ensure smooth property transactions. At 60% design, the City will issue a Board Resolution of Need and a Notice to Proceed, after which Commonstreet will send General Information Notices (GIN) to landowners and occupants via certified mail. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D City of Tigard / McDonald Street Engineering Services RFP 2025-08 7 Kittelson & Associates, Inc. / October 7, 2024 Commonstreet will facilitate the appraisal process. Deliverables will include an appraisal report, appraisal review, and Just Compensation Memo, which the City will review and sign before offers are made. For simpler cases, Commonstreet will negotiate and prepare temporary easement documents, submitting offer packets to the City for approval before presenting them to landowners. Complex acquisitions will be handled by senior agents, with all documentation reviewed by the City before being presented to landowners for execution. In cases of impasse, Commonstreet will return the file to the City and assist with mediation or condemnation, providing detailed summaries of negotiations and relevant documents. Throughout this ROW process, Commonstreet will verify compliance, transparency, and alignment with City, Uniform Act, and ODOT ROW requirements. Task 10 – Utility Coordination Team Members: Keisuke Harry, PE; Fulgence Bugingo, PE To compile a preliminary list of existing utilities and potential impacts, we will use multiple data sources, including City GIS to provide a baseline of all anticipated utilities within the project area; survey locates as a second point for all utilities and the most up to date data regarding subsurface utilities; and mapping from utility companies for early coordination to give the team an opportunity to fill gaps and validate where facilities could be. Once an existing utilities map is created, the design team will use it to compare design elements and understand what utility impacts can be assumed and what, if any, relocations are required. Our team will identify opportunities for subsurface explorations and identify costs associated with potholing. This will build an understanding of key areas that may require more thorough coordination with utilities and if there are additional design alternatives to help avoid any major relocation efforts. Task 11 – Design Engineering Team Members: Nick Polenske, PE; Anthony Yi, PE; Keisuke Harry, PE; Wade Scarbrough, PE; Nick McMurtrey, PE; Stuart Garth, PE; James Walters, PE; Julie Wirth-McGee, PWS; Bruce Baldwin, ISA; Mike Faha, PLA This task will memorialize and build upon the 10% concept to develop 30% designs, which will include the project footprint and allow us to assess impacts to utilities, driveways, and ROW. In addition, we will develop a 3D visualization to establish the project’s impact area. This will be presented to the public in an easy to understand format. We will prepare a cost estimate for the City to updated this project within the Capital Improvement Program based on similar, recent work from state and local agency projects. Everything will be summarized in an 11” x 17” set of construction plans showing the horizontal and vertical design for improvements overlaid on the survey base map. Tiedeman Avenue Multimodal Study visualization The PS&E work (Roadway & Traffic) will be completed in-house by Kittelson. Support from out teaming partners will include: ƒ Consor for structures, stormwater, waterline, and utility coordination. The waterlines will be designed to bring them to current standards. ƒGreenWorks will provide LIDA landscape facilities for impacted properties. ƒS&W will complete any borings and infiltration testing to support the walls, stormwater design, and pavement section recommendations. With approved plans and secured ROW, we’ll move into construction with Consor leading Construction Management and Inspection and Kittelson supporting as the Engineer of Record. Task 13 – Bidding Assistance Team Members: Nick Polenske, PE; Ian Machan, PE; Chad Maxwell, PE Our team will work with the City through the advertisement period and will help facilitate any questions or provide clarifications necessary with the construction documents. The design team will provide the City thorough, efficient, and thoughtful responses and updates when needed to construct the improvements. Task 14 – Construction Engineering & Inspection Team Members: Nick Polenske, PE; Keisuke Harry, PE; Wade Scarbrough, PE; Nick McMurtrey, PE; Stuart Garth, PE; Chad Maxwell, PE; Kim Sloop; Mike Faha; Bruce Baldwin; Nick White, PLS Our approach to construction oversight emphasizes active management and collaboration. With one of Oregon’s largest Construction Management and Inspection teams, we prioritize proactive risk identification, effective change management, and fostering teamwork between the City, designer, and contractor. Key elements include focused community outreach to keep stakeholders informed and a rigorous documentation program to track quality and quantities in real-time. For the McDonald Street project, we propose a highly engaged construction management team, complemented by our engineering staff to address design details and handle complex field conditions efficiently. Task 12 – Alternative Project Delivery Evaluation Team Members: Nick Polenske, PE; Ian Machan, PE In collaboration with Consor’s alternative delivery and construction management specialists, Ian Machan, PE, we will analyze delivery methods, like PDB, CM/GC, and design/build, focusing on best value and qualitative procurement. The evaluation will produce a matrix summarizing the strengths, weaknesses, costs, and schedule impacts of each method. We’ll also assess risk allocation, funding opportunities, quality, and stakeholder collaboration. With input from the City, we will weigh criteria and develop a formula to rank delivery methods. For the Boeckman Road Improvements PDB, Ian Machan, PE with Consor served as Owner’s Representative and developed the PDB delivery method. PHASE II SERVICES Task 11 – Design Engineering Team Members: Nick Polenske, PE; Anthony Yi, PE; Keisuke Harry, PE, Wade Scarbrough, PE; Nick McMurtrey, PE; Fulgence Bugingo, PE; Chad Maxwell, PE; Stuart Garth, PE; James Walters, PE; Mike Faha, PLA Phase II will advance the preferred alternative through the 60%, 90%, and 100% construction documents. Specifications will follow the ODOT/ APWA standards and use the City’s special provision templates for the general conditions of the contract. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D Survey timeframe includes topography, basemap, DTM, ROW mapping, and centerline description Includes geotechnical, HCMS, Cultural Studies & Stormwater Analysis Includes Wetlands & Waters, Fish Passage Plan, Tigard Urban Forestry Plan & Arborist Support Right of Entry ROW Determination - Phase I 10% Concept 30% Preliminary 60% Design 90% Design 100% Design Construction Engineering, Inspection & Observations Close Out Includes Joint Permit Application, Tigard Land Use Permitting, Urban Forestry Plan and Arborist Support-Phase II, Clean Water Services Site Assessment and Service Provider Letter, Public Facilities Improvement Permit Support Includes Stormwater Analysis & Report PIP Public Outreach Events Public Outreach Event City Involvement WorkshopMeeting Work in Progress City of Tigard / McDonald Street Engineering Services RFP 2025-08 8 Kittelson & Associates, Inc. / October 7, 2024 3.3 SCHEDULE Phase I Study Phase 2025 2026 Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb 1 Project Management & Administration 2 Traffic Analysis 3 Alternative Analysis 4 Public Involvement 5 Survey 6 Technical Studies & Reports 7 Hydraulic & Stormwater Studies 8 Environmental Documentation & Permits 9 Right of Way 10 Utility Coordination 11 Design Engineering 12 Alternative Project Delivery Evaluation 12.1 Meetings & Workshops 12.2 Evaluation of Alternative Project Delivery 12.3 Assistance for Approval of the Selected Alternative Project Delivery Method Phase II Construction 2026 2027 2028 2029 Mar to Aug.SepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJan to Jun 1 Project Management & Administration 4 Public Involvement 5 Survey 5.4 Legal Descriptions 5.5 Appraisal Staking 5.6 Utility Coordination Support 5.7 Preconstruction Survey 7 Hydraulic & Stormwater Studies 8 Environmental Documentation & Permits 9 Right of Way 9.3 Right of Way Determination Phase II 9.4 Acquisition Services 9.5 Appraisal & Appraisal Reviews 9.6 Condemnation Process Assistance 10 Utility Coordination 11 Design Engineering 13 Bidding Assistance 14 Construction Engineering & Inspection Strategic pause to evaluate funding, delivery method, and project goals. We understand the construction schedule is flexible, but we anticipate 12 to 18 months, depending on the start date Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D City of Tigard / McDonald Street Engineering Services RFP 2025-08 9 Kittelson & Associates, Inc. / October 7, 2024 4. PROJECT MANAGEMENT Kittelson understands that the role of a Project Manager is to execute the work by assigning and monitoring the right mix of technical personnel, and earning the trust of stakeholders, staying on schedule and within budget, and meeting project goals. Project Manager Experience Nick Polenske, PE, Project Manager Nick will oversee the project daily and be the primary point of contact. Nick excels at coordinating multi- agency, multidisciplinary teams, keeping schedules on track, and controlling costs. His experience includes managing City projects and large transportation initiatives, like the NE 46th Avenue and Bryant Street Local Improvement District (LID) – one of the largest LIDs implemented by the Portland Bureau of Transportation. “Kittelson served as the lead planning and design consultant for the US97 Terrebonne dogbone interchange and modernization project. ... The project design team involved multiple competing priorities, necessitating collaboration led by Nick Polenske ... to identify solutions that worked for everyone.” – Cari Charlton, PE, Oregon Department of Transportation Region 4 Project Management Approach Nick will keep all team members properly informed through monitoring and tracking the scope, schedule, and budget; providing status updates to the City; and having regular team check-in meetings. He makes every effort to accommodate unforeseen changes to scope, schedule, and budget, allocating these amongst existing tasks within the context of a time-and-materials contract and documents these in a decision log. Each month, Nick asks: ƒAre changes to the scope needed? If yes, consider impacts to schedule and budget. ƒAre the project and related deliverables on schedule? If no, communicate the issue and mitigate. ƒWhat issues are there with the schedule that warrant changes? If yes, consider impacts to scope/budget. ƒIs the project on budget? If no, communicate and mitigate. ƒDoes the budget status imply any potential issues? If yes, consider impacts to scope/schedule. Similar Project Experience ƒ72nd Avenue Preliminary Design; Tigard, OR; Deputy Project Manager ƒ79th Avenue Corridor Plan; Tigard, OR; Project Manager ƒTempleton-Twality SRTS Grant Application; Tigard, OR; Project Manager ƒOR99W Streetlighting Design; Tigard, OR; Project Manager ƒWest Linn Arterial Roadways; West Linn, OR; Project Manager ƒTiedeman Avenue Multimodal Study; Tigard, OR; Roadway Quality Control Lead ƒUS97: Lower Bridge Way – NW 10th Street; Terrebonne, OR; Roadway Design Manager ƒWillamette Falls Path/OR99E Enhancements; Oregon City, OR; Roadway Lead 4.1 PRINCIPAL MEMBER INVOLVEMENT As Principal Engineer, Anthony Yi, PE, will be involved throughout the project by leading the quality assurance/control process. Periodically, he will check in with the City to gain feedback about our services and the team’s performance. As a long-time resident of Tigard and experienced transportation engineer, he can provide insights about the City’s expectations and requirements, and knowledge gained through regularly using McDonald Street. 4.2 KEY PERSONNEL Nicholas Polenske, PE Project Manager Nick is an experienced project manager who has led multidisciplinary teams on major roadway improvements. His experience with alternative delivery projects will guide the preliminary design phase and align concepts with the local context. Current Assignments & Locations ƒ72nd Avenue Preliminary Design; Tigard, OR ƒODOT All Roads Transportation Safety Program Grant Application Support; Tigard, OR ƒWest Linn Arterial Roadways and OR 43/Marylhurst Drive Protected Intersection, West Linn, OR Relevant Experience ƒSee projects listed above Similar Project Experience. Anthony Yi, PE Principal Engineer Specialized in traffic engineering with capabilities in integrating public input with technical analysis to develop innovative, feasible concepts that establish safe, connected, accessible multimodal corridors. Current Assignments & Locations ƒOR 141/OR 217 Curb Ramps; Tigard, OR ƒTigard Signal Support Services; Tigard, OR ƒ72nd Avenue Preliminary Design; Tigard, OR ƒExit 21 Interchange Improvements; Woodland, WA ƒS Hillsboro Traffic Design; Hillsboro, OR Relevant Experience ƒTigard On-Call Services – 15 Task Orders; Contract Manager ƒOak/Baseline/10th Avenue Study; Hillsboro, OR; Project Manager ƒMain Street Improvements; Gold Beach, OR; Traffic Engineer Keisuke Harry, PE Roadway Engineer Specialized in roadway design with experience designing roundabouts, developing and analyzing alternatives, and creating feasible concepts that integrate all travel modes. Current Assignments & Locations ƒOR99W/OR 18 Curb Ramps; McMinnville, OR ƒAirport Road & Main Street; Billings, MT Relevant Experience ƒOR 99W Streetlight Design; Tigard, OR; Roadway Engineer ƒBoeckman Road Improvements PDB; Wilsonville, OR; Roadway Engineer ƒUS 97: Bend North Corridor Design/Build; Bend, OR; Roadway Engineer ƒUS 97: Lower Bridge Way-NW 10th Street; Roadway Engineer ƒShute Road Multiuse Path; Hillsboro, OR; Roadway Engineer Wade Scarbrough, PE Traffic Engineer Over 20 years of experience assisting Tigard resolve transportation challenges and establishing a safer, more comfortable transportation network by providing his expertise in roundabout analysis and design, traffic operations and safety, and geometric design. Availability 50% 50% 45% 40% Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D City of Tigard / McDonald Street Engineering Services RFP 2025-08 10 Kittelson & Associates, Inc. / October 7, 2024 Current Assignments & Locations ƒBoeckman Road Improvements PDB; Wilsonville, OR ƒCornville at Tissaw Roundabout; Yavapai, AZ ƒGresham Fairview Trail Phase IV; Gresham, OR ƒPedestrian Crossing Enhancements; Washington County, OR ƒStafford Road/65th Avenue/Elligsen Road Roundabout; Clackamas County, OR Relevant Experience ƒDurham Road/Upper Boones Ferry Road: OR99W to I-5; Tigard, OR; Traffic & Signal Design Engineer ƒTiedeman Avenue Multimodal Study; Tigard, OR; Traffic Engineer ƒCrestview Drive Roundabout; Newberg, OR; Traffic Engineer ƒWalnut Street: 116th to Tiedeman; Tigard, OR; Traffic Engineer ƒRiver Terrace Development; Tigard, OR; Traffic Engineer N Nicholas McMurtrey, PE Stormwater Engineer Aligns stormwater design with all project elements, with a focus on fish passage, stormwater management, utilities, environmental permitting, and multimodal improvements. Is skilled in conveying a project’s purpose and need clearly and concisely to varied audiences. Current Assignments & Locations ƒNW Springfield Road Improvements: Joss to Kaiser; Washington County, OR; Project Manager ƒThompson Road: Saltzman to Marcotte, Washington County, OR ƒWashington/Monroe Greenway: 37th to Linwood, Milwaukie, OR ƒJennings Avenue: OR99E to Oatfield; Clackamas County, OR Relevant Experience ƒD Avenue Improvements; Lake Oswego, OR; Project Manager ƒVilla Road Improvements; Newberg OR; Project Manager Fulgence Bugingo, PE Waterline Engineer/ Utility Coordinator Public works professional with a background in designing water, wastewater, and roadway facilities. This combined experienced, along with being a subsurface utility engineering (SUE) specialist, provides insights into how these facilities are interrelated. Current Assignments & Locations ƒ2024 Water Line Replacement;, West Linn, OR ƒUmatilla County Curb Ramps; Pendleton OR ƒWestside Trail Segment 1; King City, OR Relevant Experience ƒSW Ridgewood Avenue & SW Grace Lane Water Facilities; Washington County, OR; Project/Construction Administrator ƒSE Division Street; Portland, OR; SUE ƒWillamette Water Supply Pipeline; Washington County, OR; SUE Chad Maxwell, PE Construction Manager Construction manager who works alongside design teams to navigate innovative concepts, advise on constructability, avoid utility conflicts, and minimize construction impacts in a fiscally responsible manner. Current Assignments & Locations ƒUS101 Curb Ramps; Lincoln City / Lincoln Beach, OR ƒGroundwater Development Project - Glendover Pressure Zone Transmission Main; Gresham, OR ƒGroundwater Development Project - Cascade Reservoir Improvements and Well No. 7; Gresham, OR Relevant Experience ƒBoones Ferry Road Improvements; Lake Oswego, OR; Construction Manager ƒJefferson Parkway Pavement Rehabilitation; Construction Manager ƒOR47 & Main Street Sidewalks Improvements; Gaston, OR; Construction Manager Kimi Sloop Public Involvement Lead Kimi is an expert at integrating the public on transportation projects. She will bring her toolbox of community engagement strategies to identify, connect with, and engage people during the public decision- making process for this project. Current Assignments ƒWillamette Water Supply Program; Washington County, OR ƒKing City Westside Trail Project; King City, OR ƒEastern Oregon Curb Ramps; Pendleton, OR Relevant Experience ƒOn-Call Transportation - Public Outreach; Tigard, OR ƒWestside Trail Segment; King City, OR ƒRural Transportation Equity Project, Department of Land Conservation and Development; Grand Ronde, OR ƒCape Kiwanda Corridor Project; Pacific City, OR Technical Support Staff Ian Machan, PE, Alternative Delivery Advisor. With a background in alternative delivery methods, engineering, and construction management, Ian will provides guidance on constructability and advises on selecting a project delivery method. Stuart Garth, PE, Structural Engineer. Stuart integrates structural designs into infrastructure projects construct structures in a fiscally responsible manner, while meeting safety standards and providing environmental protections. James Walters, PE, Geotechnical Engineer. James’ knowledge about Tigard’s geological conditions will streamline the design process by building upon readily available data gained through working in Tigard. Alia Hubbard, Environmental Scientist. Alia’s expertise in hazardous materials assessment will make sure hazardous materials are identified and addressed. Mike Faha, PLA, Landscape Architect. Mike creates streetscapes with sustainable, nature-based planning and design approaches. He effectively engages the community to align concepts with the local context and desires. Julie Wirth-McGee, PWS, Environmental Specialist. Julie contributes to developing alternatives that protect natural resources while improving roadways. Her regulatory knowledge will obtain compliance with regulatory agencies. Bruce Baldwin, ISA, Arborist. Bruce can align project improvements with preservation of natural resources by applying forestry engineering. He will guide decisions related to stormwater, waterlines, and utility undergrounding. Nick White, PLS, Surveyor. Surveyor with direct experience in Tigard, who will provide accurate surveys to support developing concepts, designs, and ROW. Kari Lowe, SR/WA, Right of Way Agent. Kari will integrate ROW services to streamline analyses and designs tasks, minimize impacts to adjacent property owners, and facilitate a smooth acquisition phase. Andrea Blaser, Architectural Historian. Andrea minimize agency reviews of cultural resource studies by providing documentation that can be easily reviewed and approved. 40% 40% 40% 50% Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D Appendix A TEAM CAPABILITIES MATRIX & RESUMES Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D Kittelson Team Capabilities CAPABILITIES Project Management & AdministrationTraffic AnalysisAlternatives AnalysesPublic InvolvementSurveyTechnical StudiesHydraulic & Stormwater AnalysisEnvironmental PermittingFish PassageLand Use PermittingRight-of-Way Utility CoordinationUtility UndergroundingRetaining Wall DesignLandscape ArchitectureGeotechnical EngineeringDesign Engineering (Final PS&E)Alternative Project Delivery EvaluationConstruction Engineering Constructability/ BiddabilityOwner’s RepresentationClaims SupportWaterline DesignSTAFF Nick Polenske, PE, Project Manager  O O O O O O O O O O O O O Anthony Yi, PE, Principal Engineer O O O O O O O O O O O  Keisuke Harry, PE, Roadway Engineer  Wade Scarbrough, PE, Traffic Engineer  Nicholas McMurtrey, PE, Stormwater EngineerO O O O  Fulgence Bugingo, PE, Waterline Engineer/ Utility Coordinator Chad Maxwell, PE, Construction ManagerO  Kimi Sloop, Public Involvement Lead Ian Machan, PE, Alternative Delivery Advisor Stuart Garth, PE, Structural Engineer James Walters, PE, Geotechnical Engineer Alia Hubbard, Environmental Scientist Mike Faha, PLA, Landscape Architect Julie Wirth-McGee, PWS, Environmental Specialist Bruce Baldwin, ISA, Arborist Nick White, PLS, Surveyor Kari Lowe, SR/WA, Right of Way Agent Andrea Blaser, Archeological Historian Skilled In O Managed Kittelson Consor AKS Shannon & Wilson GreenWorks Commonstreet AINW Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Project Manager EDUCATION • BS, Civil Engineering, Portland State University YEARS OF EXPERIENCE • 10 LICENSE • Professional Engineer: OR (#88867) AFFILIATIONS • American Public Works Association ABOUT Nick specializes in roadway design. Having led preliminary and final design processes, Nick has demonstrated an exceptional ability to coordinate multidisciplinary teams, making sure tasks are completed in the appropriate sequence to maintain schedules and control costs. His experience includes leading roadway and traffic disciplines on pavement preservation projects, establishing bicycle and pedestrian facilities, designing ADA compliant ramps, implementing safety improvements, developing stormwater conveyance and treatment systems, and providing bidding and construction support services. Nick approaches design efforts with a holistic perspective, understanding a transportation facility has multiple purposes and can provide beneficial outcomes, like improved safety and congestion, enhanced accessibility, increased transportation choices, encouragement of active transportation, and incentivize economic development. NICK POLENSKE | PE PROJECT EXPERIENCE Tiedeman Avenue Multimodal Study; Tigard, OR. Nick led the roadway design elements for the Teideman Avenue Multimodal Study. The project involved completing a traffic analysis, developing and analyzing alternatives, and creating concepts to address operational, safety, and connectivity deficiencies in the corridor. Nick led efforts to complete the 30% design plans, cost estimates, visualizations, and stormwater plan. Templeton-Twality Safe Route to School Grant Application; Tigard. OR. Nick managed the team that prepared conceptual designs to help the City of Tigard prepare a Safe Routes to School (SRTS) grant application. The work involves five specific project sites all varying from illumination upgrades to roadway widening to aid with pedestrian and bicycle upgrades. These improvement will provide critical connections for the SRTS program. 79th Avenue Corridor Plan; Tigard, OR. Nick is leading the conceptual design efforts to improve bicycle and pedestrian safety along 79th Avenue in Tigard. Phase I is a short-term conceptual design phase using the existing roadway cross section and a pavement rehabilitation project and Phase II preparing a longer- term conceptual design to support a future capital improvement project to provide a more uniform cross section through the corridor. OR99W Street Lighting Design; Tigard, OR. Nick seamlessly transitioned this project from a previous project manager and successfully led the multidisciplinary team that designed illumination upgrades at eight intersections along OR 99W with specific pedestrian and bicycle improvements at the OR 99W/Bull Mountain Road intersection. Nick led the roadway design efforts, utility coordination, and specification writing. Willamette Falls Path/OR99E Enhancements; Oregon City, OR. Nick is the roadway design lead for this conceptual design of pedestrian and bicycle improvements through Oregon City along OR99E. This project team investigated a shared-use path to provide access to the future Willamette Falls Riverwalk and the Tumwata Village development. This shared-use path is intended to contribute to the sense of place and community identity while providing recreational access and closing a critical gap in the region’s active transportation network for people walking, biking, and rolling. West Linn Arterial Roadway & OR43/Marylhurst Protected Intersection; West Linn, OR. Nick was the roadway design lead for the conceptual design of new bicycle and pedestrian improvements along Willamette Falls Drive from the Tualatin River to I-205 in West Linn. Improvements include adding continuous sidewalks, separated bike facilities along Willamette Falls Drive, and protected intersections at all major intersections along the corridor. Nick was responsible for leading the West Linn Transportation System Plan update to incorporate this conceptual design. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Principal Engineer EDUCATION • BS, Civil Engineering, University of Portland YEARS OF EXPERIENCE • 25 LICENSE • Professional Engineer: OR (#59948) AFFILIATIONS • American Council of Engineering Companies • American Public Works Association • Institute of Transportation Engineers ABOUT As a Tigard resident, Anthony understands and experiences many of the City’s key issues, while also enjoying the many amenities in the community. He is an experienced transportation engineer with expertise in traffic engineering and transportation planning. His expertise are used to carry out collaborative planning and design processes that establish transportation facilities that optimize operations, improve safety, and relieve congestion. Anthony has worked on traffic operations and safety assessments, multimodal planning and design, parking assessments, conceptual designs, corridor analyses, transportation impact analyses, and traffic design plans (traffic control, traffic signals, roadway illumination, signing & striping). His project experience also includes community involvement aspects such as planning and facilitating public workshops and presentations, and leading stakeholder discussions with interested parties and public officials. ANTHONY YI | PE PROJECT EXPERIENCE Tigard On-Call Planning & Engineering Services; Tigard, OR. Anthony has served as the contract manager, quality assurance/control lead, project manager, and task leader on transportation planning and traffic engineering projects throughout Tigard. His recent projects include: • 79th Avenue Corridor Improvements • Traffic Signal & ITS Support • Templeton-Twality Safe Routes to School Grant Application OR 8: Oak/Baseline/10th Avenue Couplet Conceptual Plan; Hillsboro, OR. A partnership between ODOT, Washington County, and City of Hillsboro worked on identifying ways to improve the OR 8 couplet through downtown Hillsboro. Anthony provided his expertise in traffic operations and design to assist with preparing the concept plan. This plan will guide incremental improvements through private development investments to reduce the access barriers and increase the comfort and utility of the corridor, particularly for pedestrians, bicyclists, and transit users. The City of Hillsboro has adopted the plan. US 101 & US 126 Streetscape; Florence, OR. Kittelson supported Consor on improving mobility and safety, with an emphasis on bicyclists and pedestrians, through Florence along US 101 between US 126 and the Siuslaw River Bridge and US 126 between US 101 and Quince St. Anthony led the traffic design elements, which included traffic signal improvements, upgrades to the pedestrian signal equipment, and new ADA ramps at the US 101/US 126 and US 101/Rhododendron Drive intersections. The improvements are constructed and Kittelson provided engineering support services during construction. NE 28th Avenue Complete Street; Hillsboro, OR. The City of Hillsboro converted NE 28th Avenue into a complete street. Anthony led all the traffic analyses to define the roadway improvements. During the design phase he prepared PS&E documents for a new traffic signal, fiber interconnect, rectangular rapid flashing beacons, LED illumination, signing & striping, and traffic control. Anthony also provided construction engineering services for all traffic elements. NE Cornell Road Corridor Improvements; Hillsboro, OR. Kittelson completed a transportation study of Cornell Road between Main Street and 25th Avenue to evaluate safety and capacity improvements. Anthony led a team that evaluated the near- and long-term transportation conditions, developed a set of recommendations and concept plans, and presented key findings and recommendations to the City of Hillsboro and Washington County. The array of potential safety and capacity improvements included roundabouts and signalized intersections. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Roadway Engineer EDUCATION • BS, Civil Engineering, Oregon State University YEARS OF EXPERIENCE • 8 LICENSE • Professional Engineer: OR (#91539) AFFILIATIONS • American Public Works Association ABOUT Keisuke has experience leading the preparation of PS&E documents to convert roadways into complete streets. He works with multidisciplinary teams to design roadways, prepare traffic control plans, and make curb ramps ADA compliant. His traffic analysis capabilities are used to inform developing and analyzing alternatives and then creating feasible concepts that can easily transition into the final design and construction phases. He is driven to continuously learn and find ways to improve design approaches that enhance safety and accessibility for all people. KEISUKE HARRY | PE PROJECT EXPERIENCE Boeckman Road Improvements Progressive-Design-Build; Wilsonville, OR. Kittelson is a major subconsultant for this progressive-design-build roadway improvement project. The improvements include a new bridge, new roundabout, and bicycle and pedestrian enhancements to upgrade this rural road to an urban context. Keisuke worked on completing an intersection control evaluation that compared signalized and roundabout alternatives, led preparation of PS&E documents for the roundabout, and assisted in staging and sequencing construction activities in a way that maintains traffic on three legs of the intersection. During construction, he coordinated with the construction team, and Consor (Owners Representative) to verify adequate drainage, resolve utility conflicts, and be the main point of contact for Kittelson. OR99W/OR18 Curb Ramps; McMinnville, OR. Kittelson is designing over 300 new curb ramps along OR99W and OR18 through McMinnville. Keisuke is leading roadway engineering tasks and serving as the deputy project manager. He is coordinating a team of civil designers to improve over 100 ramps along OR99W to current ADA standards. Shute Road Multi-Use Path; Hillsboro, OR. Keisuke led roadway design activities to support constructing a new multi-use path along Shute Road adjacent to Intel’s Ronler Acres Campus. The project includes a new traffic signal, new ADA ramps, roadway narrowing, an enhanced pedestrian crossing with a rectangular rapid flashing beacon, new street lighting, two additional signal modifications, and a regional stormwater quality facility. Arndt Road Extension (Barlow Road to Canby); Clackamas County, OR. Kittelson supported Clackamas County with studying the roadway network in the Barlow community east of the Molalla River to improve connectivity between I-5 and OR99E through Canby. The project was conducted in two phases to identify lower-cost improvements that could be constructed in the short term and evaluated a series of long-term higher-cost solutions. Keisuke designed and evaluated long-term alternatives, like extending Arndt Road to a new terminus at three possible locations along OR99E. These alternatives included a new Molalla River bridge crossing, a roundabout, signalized intersections, and extensive considerations for the railroad parallel to OR99E. Bend North Corridor Design-Build; Bend, OR. Keisuke supported the traffic analysis and design for the design-build team delivering the Bend North Corridor project. He supported refining the US20 roundabouts concepts, traffic analysis for both permanent and construction conditions, all traffic design elements, and documenting construction traffic control strategies through transportation management plans. OR99W Streetlight Design; Tigard, OR. To improve safety and operations at eight intersections in Tigard, Keisuke led the road design tasks with a Kittelson led multidisciplinary team. The overall project involved upgrading illumination at the eight intersections along OR99W with specific pedestrian and bicycle improvements at OR 99W/Bull Mountain Road. Keisuke prepared the constructable PS&E documents on time and within budget. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Traffic Engineer EDUCATION • BS, Civil Engineering, University of Idaho YEARS OF EXPERIENCE • 28 LICENSE • Professional Engineer: OR (#65552) AFFILIATIONS • Institute of Transportation Engineers ABOUT Wade routinely performs transportation studies and develops geometric plans for transportation . He is particularly adept at generating and refining conceptual transportation solutions that safely and seamlessly accommodate all modes, contribute to the quality of a place, and are responsive to design standards and budget realities. His experience includes preparing PS&E documents for traffic design elements including roundabouts, traffic signals, intelligent transportation system (ITS) applications, signing & striping, street lighting, and traffic control and detour plans. Throughout his career, Wade has worked collaboratively with agencies to evaluate and implement multimodal transportation enhancements. WADE SCARBROUGH | PE PROJECT EXPERIENCE Tiedeman Avenue Multimodal Study; Tigard, OR. Kittelson studied the Tiedeman Avenue corridor between Walnut Street and Greenburg Road. This project provides the City of Tigard with a preferred alternative design and cost estimate to support its inclusion in the capital improvement projects list. Wade provided his expertise in traffic operations, intersection design concepts, and preliminary design to assist with creating feasible concepts. 72nd Avenue/Dartmouth Road Intersection Improvement; Tigard, OR. Wade worked on developing preliminary geometric plans for intersection improvements, which involved preparing final signing & striping and illumination designs. He reviewed and coordinated with the development team that prepared the signal design. Walnut Street Improvements; Tigard, OR. Wade led the traffic analysis and final traffic design to reduced lane widths along Walnut Street, which provided capacity for pedestrian and bicycle facilities while minimizing costs and right- of-way acquisitions. For Walnut Street/135th Avenue, he prepared conceptual geometric layouts and a life cycle analysis of roundabout and signalized alternatives. This enabled the City of Tigard to identify a preferred solution. Upper Boones Ferry Road/SW Durham Road Advanced Traffic Management System; Tigard, OR. Wade worked with the City of Tigard and Washington County to develop and implement advanced signal timing and coordination strategies for the corridor from I-5 to OR99W. He led the pathway analysis to review the costs and benefits of alternatives for communications infrastructure. He also led creating alternatives for improving conditions at the Tigard High School pedestrian crossing. OR 99W/Hall Boulevard & Greenburg Road Improvements; Tigard, OR. Wade provided traffic studies and design services that led to constructing additional turn lanes at the side street approaches and auxiliary through lanes on the highway. He also prepared the traffic signal modification plans, along with signing & striping, and lighting plans. Boeckman Road Improvements Progressive-Design-Build; Wilsonville, OR. Kittelson is providing traffic and roadway design services for this progressive- design-build project. Wade developed solutions for complex roundabout grading, resolved utility conflicts, and identified strategies to maintain traffic on three legs of an intersection. In addition, Wade managed traffic design activities, which included preparing detour plans for a road closure during construction of a bridge. Roundabout Experience. Wade is an expert in analyzing and designing roundabouts. He has worked on over 100 intersections worldwide and developed guidance for FHWA Roundabouts: An Informational Guide, First Edition (reviewed the Second Edition) and FHWA Technical Summaries on Roundabouts and Mini-Roundabouts. Recently he has provided analysis and design services for roundabouts at OR219/Butteville Road in Woodburn, Stafford Road: Rosemont to Pattulo in Clackamas County (with Consor), and Campus Drive/Daggett Avenue in Klamath Falls. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Stormwater Engineer EDUCATION • BS, Civil Engineering, Oregon State University YEARS OF EXPERIENCE • 21 LICENSE/ CERTIFICATIONS • Professional Engineer: OR (#72710PE) • US Green Building Council, LEED AP BD+C • Institute for Sustainable Infrastructure, ENV SP AFFILIATIONS • American Society of Civil Engineers • American Council of Engineering Companies • Returned Peace Corps Volunteer AWARDS • APWA 2019 Project of the Year, D Avenue Improvements ABOUT Nick is experienced in the planning, design, and construction of various types of stormwater projects, including conveyances, detention systems, low- impact development, fish passage, and regional stormwater management systems. Over the course of his career, he has worked on numerous drainage- focused projects, incorporating design considerations for permit compliance, constructibility, and ongoing maintenance. He brings a practical approach toward design, seeking to balance the cost of improvements while meeting regulatory agency requirements and providing water quality protections. NICK MCMURTREY | PE, ENV SP, LEED AP PROJECT EXPERIENCE NW Springville Road: Joss to Kaiser; Washington County, OR. Nick managed design, permitting, and construction support to Washington County for upgrading NW Springville Road to arterial standards between NW Joss Avenue to NW Kaiser Road. Improvements included new bike lanes, sidewalks, utility relocations, right-of-way acquisition, illumination, and intersection signal upgrades designed by Kittelson. Impervious surface discharges to Bethany Creek’s primary outfall were intercepted with five new Low Impact Development Approach (LIDA) sales meeting Clean Water Services (CWS) Design & Construction Standards, including hydromodification requirements. Nick evaluated and documented stormwater management to a secondary off- site outfall managed by CWS. This extended dry basin was planned by CWS to operate using real time data and weather forecasts into an automatically controlled regional detention system along Bethany Creek. D Avenue Improvements; Lake Oswego, OR. Nick led this project to address pavement rehabilitation and pedestrian accessibility under the City of Lake Oswego’s new Stormwater Management Manual (SWMM) standards, where multimodal uses, mature trees, and available space vary. An alternatives evaluation assessed the roadway’s impacts to competing project elements such as private landscaping encroachments (fences, paths, parking, vegetation, etc.), mature trees, and LIDA areas. The project was further challenged with the neighborhood’s unique character, forcing a delicate balance between stormwater, pedestrian, and pavement objectives using a curbless design. The solution included traffic calming through extensive landscaping, 43 LIDA stormwater management facilities, and a meandering alignment over 10 blocks. Villa Road Improvements; Newberg, OR. Nick managed this project from design through construction to upgrade 1,500 feet of Villa Road to collector street standards. He led a robust alternatives analysis to optimize horizontal and vertical alignment and reconstruction through previously hazardous reversing curves under a railroad crossing trestle. The roadway improvements triggered Oregon fish passage law for replacing two existing culverts along Hess Creek. Upgrades also required a complex Oregon Department of States Land and US Army Corp of Engineers permits, including wetland mitigation, LIDA, floodplain infill, wetland mitigation and post-construction monitoring. Nick planned traffic control and closure phasing with the City of Newberg and communicated impacts with the public on this critical north-south transportation route. Other relevant work included extensive utility relocation and undergrounding, retaining walls, landslide repair, right-of-way acquisition, and phased project delivery to meet the City of Tigard’s budget. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Waterline Engineer/ Utility Coordinator EDUCATION • BS Civil Engineering National School of Public Works Algeria YEARS OF EXPERIENCE • 27 LICENSES • Professional Engineer: OR (#74324) AFFILIATIONS • American Society of Civil Engineers (ASCE) AWARDS • APWA Oregon Chapter Transportation, Project of the year 2023, Boones Ferry Road Improvement Project • ACEC Award, ODOT Newberg-Dundee Bypass project ABOUT Fulgence is an experienced design engineer with practical field experience on municipal drinking water storage and supply systems, stormwater and street projects. He is also a subsurface utility engineering (SUE) specialist. As Consor’s lead SUE engineer, Fulgence brings valuable experience with utility conflict identification and analysis, utility relocation assessments, coordination, and relocations. For over two decades, he has successfully managed a wide range of complex utility coordination and relocation services for counties, cities, and ODOT. His work spans roadway and interchange projects, as well as water transmission and sewer pipeline systems, across the Pacific Northwest. FULGENCE BUGINGO | PE ABOUT Willamette Water Supply Pipeline; Hillsboro, OR. Fulgence served as SUE and utility coordinator for a 48-inch, 4-mile-long water transmission pipeline. He located and documented utilities along SW 209th Avenue and SE Cornelius Pass Road, maintained a Utility Base CAD file, and developed base mapping for pipeline design. He also led utility field verification, conflict analysis, and resolution, and reviewed relocation plans. Fulgence’s leadership ensured effective utility coordination throughout the design and construction phases of this critical water supply project. I-5 at Beltline Interchange Storm Drainage & Water Quality Design; Eugene, OR. Fulgence assisted with stormwater, water quality, and utility coordination for the I-5 Beltline Interchange project. He completed final plans, specifications, and relocation of a one-mile flood channel, along with designing water quality facilities like detention ponds and bioswales. Fulgence coordinated utility relocations totaling over $5 million and representing ODOT in notifications, negotiations, and field inspections. He also applied Utility Verified Vertical and Horizontal SUE techniques to resolve conflicts and review utility reimbursement. SW Ridgewood Avenue & SW Grace Lane Water Facilities Improvement; West Slope Water District, OR. Fulgence served as Consor’s project engineer, assisting with construction administration for this water facilities improvement project. The project involved replacing one mile of 6- to 12-inch water distribution mains and coordinating permits with Washington County. Fulgence worked on obtaining easements from the Beaverton School District to facilitate smooth project execution. He contributed to the successful completion of this essential water infrastructure upgrade, benefiting the local community. OR 18: Newberg-Dundee Bypass Phase I & II; Yamhill County, OR. Fulgence is leading utility coordination and relocation for this multi-phase highway modernization project, creating a bypass around Newberg and Dundee. The project includes 4-miles of highway, 63 structures, 25 stormwater facilities, local street connections, and 4 interchanges, all requiring extensive utility coordination. Fulgence applied SUE techniques to create a detailed utility base map and lead efforts in conflict identification, relocation plan review, utility special provisions, and construction observation. His leadership provides seamless utility coordination, supporting the project’s overall success. SE Division Street Reconstruction Project; Portland, OR. Fulgence provided SUE and utility coordination services for the SE Division Street Reconstruction project in Portland. He was involved with records research, survey, mapping, conflict analysis, development of test hole recommendations, and coordination of potholing. Work also included review and approval of utility relocation plans, and review of reimbursable utility relocations. The Division Street project provided roadway infrastructure, streetscape, traffic safety, sanitary sewer and stormwater management improvements to support the City of Portland Green Street/Main Street Plan. The effort relieved the sewer backup and deficient pipes within the project limits. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Construction Manager EDUCATION • BS, Civil Engineering Portland State University YEARS OF EXPERIENCE • 19 LICENSE/ CERTIFICATIONS • Professional Engineer: OR (#76500) • ODOT Certified General Construction Inspector (#44321) AFFILIATIONS • American Public Works Association AWARDS • APWA 2024 Project of the Year Award Boones Ferry Road Improvements Project ABOUT Chad is a Construction Project Manager who is highly knowledgeable about construction materials, quality documentation, and Oregon Standard Specifications, holding several ODOT inspection certifications. With a strong background in design, utility coordination, and constructibility, Chad excels at identifying and resolving potential issues early. Focused on building strong client and contractor relationships, he ensures high-quality construction while managing costs and schedules. His diverse experience as a designer, inspector, and project manager makes him a leader in handling complex projects. CHAD MAXWELL | PE PROJECT EXPERIENCE Boones Ferry Road Improvements Construction Management - Phase 1; Lake Oswego, OR. Chad was the Construction Manager for a $23M project improving pedestrian, bicycle, and vehicular safety on Boones Ferry Road. This modernization included new storm and water systems, stormwater treatment, landscaped medians, bike lanes, sidewalks, five signalized intersections, rectangular rapid flashing beacons, 53 ADA- compliant ramps, and undergrounding 1 mile of utilities. Chad managed pre-construction tasks, such as reviewing PS&E, constructibility, and staging, and led contractor procurement. During construction, he provided continuous construction management, contract administration, and inspection services, verifying traffic, pedestrian flow, and business access were maintained throughout this high-traffic corridor. Jefferson Parkway Pavement Rehabilitation Project; Lake Oswego, OR. Consor provided professional design and construction management services for the pavement rehabilitation of Jefferson Parkway. The construction included full depth reclamation for the three-lane road, ADA ramp and intersection improvements, and stormwater inlet replacement for approximately one mile of Jefferson Parkway. Chad worked with the contractor and the inspectors to verify ADA compliance for several ramps replaced with the street reconstruction. OR47/E Main Street Sidewalk Improvements; Gaston, OR. Chad led this $2M road widening and pedestrian improvement project for the City of Gaston and ODOT. The work included several new Low Impact Development Approach stormwater treatment facilities, water and storm upgrades, a new retaining wall, ADA compliant curb ramps, a rapid flashing beacon, and sidewalk infill to increase connectivity for pedestrian access at one of the busiest intersections in town. Chad drafted contract change orders, assembled monthly progress estimates, and led weekly team meetings as part of his overall project coordination and management. SE Lake Road; Milwaukie, OR. Chad led the $5M construction phase of this ODOT/FHWA-funded project in Milwaukie, which included road widening, water and storm system upgrades, stormwater treatment, retaining walls, bike lanes, and ADA ramps. He coordinated with the Engineer of Record, ODOT, City of Milwaukie, and Contractor, resolving utility delays and negotiating change orders to maintain the project schedule and budget. Lancaster Drive: Center Street - Monroe Avenue; Marion County, OR. This was a $1.6M Marion County project to rehabilitate the pavement, replace curbs and sidewalks, reconstruct 14 ADA curb ramps, improve the drainage system, and upgrade a traffic signal to improve pedestrian connectivity in this busy corridor. Chad and his team led the construction efforts for this ODOT certified local agency project to make sure all documentation met ODOT standards. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Public Involvement Lead EDUCATION • Master of Public Administration, Portland State University • BA, Political Science, Willamette University YEARS OF EXPERIENCE • 25 AFFILIATIONS • Westside Economic Alliance ABOUT Kimi is a public involvement specialist with a background in planning, facilitation, public engagement, and project management. She specializes in engaging and educating the public about public infrastructure, land use, and transportation. Her experience includes developing and implementing community engagement strategies to involve the public from project conception through construction. With a goal of building community support and ownership of public projects, Kimi has designed hundreds of public involvement processes including stakeholder interest groups, interviews, public workshops, and open houses. KIMI SLOOP PROJECT EXPERIENCE Main Street - Green Street Phase 1; Tigard, OR. Kimi was part of the communications team that worked with the businesses in downtown Tigard during construction to promote the “Open for Business” campaign. She talked with business owners, wrote business owner profiles, and provided project updates via the City of Tigard’s website. 72nd Avenue Improvements; Tigard, OR. Kimi was part of the communications team that provided construction updates to property owners along 72nd Avenue during a full road closure to facilitate necessary street improvements. The outreach activities included providing information to businesses and residents near 72nd Avenue about the road closure schedule and alternative access during construction. Tigard-Metzger North South Improvement Project, Tigard, OR. Kimi provided property owner communications during design and construction of a Tualatin Valley Water District water pipeline in the Tigard-Metzger area. This assignment includes providing notification to property owners of pending work in the neighborhood, construction communications, and meet the contractor open house. New Burnham Street; Tigard, OR. Kimi supported development of a communications plan that provided necessary outreach to business and property owners affected by the two-year Burnham Street construction. The firm also assisted the City of Tigard with ongoing communications – arranging public meetings and preparing news releases, fact sheets, and website materials – to keep the public informed about the project. New Burnham Street was awarded the national Project of the Year Award by the American Public Works Association. Willamette Water Supply Program; Washington County, OR. As part of the communications team, Kimi is leading the public outreach for the segment of the Willamette Water Supply pipeline being constructed in the South Hillsboro area and in the Cooper Mountain/Scholls Ferry area. Outreach efforts have included: • Public Opinion Polling • Message Development • Website Development & Maintenance • Educational Materials • Community & Elected Official Briefings • Surveys • Open Houses • Video Production • Social Media Postings • Newsletters • Mailings • Property Owner Communications Before and During Construction Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Alternative Delivery Advisor EDUCATION • MS, Construction Management, Oregon State University YEARS OF EXPERIENCE • 23 LICENSE • Professional Engineer: OR (#81009) AFFILIATIONS • American Public Works Association • American Council of Engineering Companies • Construction Management Association of America AWARDS • APWA 2024 Project of the Year Award Boones Ferry Road Improvements Project ABOUT Ian has extensive experience in construction project management for both local agency and state/federal construction projects. He has a strong background in alternative delivery, contract administration, change management, and dispute resolution. Ian has served in an Owner’s Advisory role for numerous projects in Oregon and Washington, assisting with selection of alternative delivery methods, contractor procurement, and risk management throughout the life of the project. IAN MACHAN | PE PROJECT EXPERIENCE Boones Ferry Road Improvements; Lake Oswego, OR. Ian advised the City of Lake Oswego on developing a Best Value contractor procurement process and oversaw construction for this $23M project to improve pedestrian, bicycle, and vehicular safety on Boones Ferry Road. The project included new stormwater and water systems, landscaped medians, bike lanes, expanded sidewalks, new signage, traffic signals, and 43 ADA-compliant ramps. Nearly a mile of utilities was undergrounded, and complex Temporary Pedestrian Access Routes and staging provided uninterrupted traffic and pedestrian flow. Ian’s leadership contributed to the project’s success, enhancing safety and aesthetics in this high-traffic business corridor. Boeckman Road Owner’s Representative Services; Wilsonville, OR. Ian helped develop the progressive-design-build procurement process and contractor selection for this four-part project. The project includes a bridge over Boeckman Creek, urbanizing a rural road with multimodal improvements, installing sanitary sewer trunk mains, building a joint-utility trench, and constructing a roundabout. Ian’s team advised on best practices, reviewed deliverables, assisted with public outreach and cost analysis, and negotiated three guaranteed maximum price (GMP) agreements. Two early work packages, including the bridge, were completed successfully, and Ian’s team continued providing full-service construction management, inspection, and administration for the final phase. Murphy Corridor Improvements; Bend, OR. Ian, as Principal-in-Charge, collaborated with the City of Bend and the PDB team to deliver this award- winning project, improving vital east-west connectivity in Bend. Consor provided construction management, document control, public outreach, and quantity verification. Ian’s team negotiated several GMPs with the contractor, controlling cost. Consor also conducted a bridge inspection during the final phase, confirming construction adhered to City of Tigard standards. The project enhanced transportation infrastructure and won accolades for its execution and design. Awbrey Butte Distribution Improvements; Bend, OR. Ian coordinated with the City of Bend and the PDB contractor team to deliver this critical water infrastructure project. Consor provided Owner’s Representative and Construction Management services, overseeing the upsizing of 14,000 feet of aging water pipe and installing 9,000 feet of new pipe to improve capacity, fire flow, and hydraulic performance. Ian’s team facilitated communication, assisted with pre-construction phases, and successfully negotiated several GMPs. Over the estimated three-year construction, his team made sure the project stayed aligned with PDB best practices. Steigerwald Floodplain Restoration Project; Lower Columbia Estuary Partnership, OR. Ian was Principal-in-Charge for this $21M project to restore 965 acres of floodplain at Steigerwald Lake National Wildlife Refuge. The project reconnected Gibbons Creek to the Columbia River floodplain, reduced flood risk for nearby cities, improved fish and wildlife habitats, and enhanced the Refuge’s trail system. The project moved 1.7 million cubic yards of earth and raised SR-14 by three feet to improve upland habitats and flood resilience. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Structural Engineer EDUCATION • MS, Civil Engineering, Portland State University • BS, Civil Engineering, Portland State University YEARS OF EXPERIENCE • 10 LICENSE • Professional Engineer: OR (#86033) ABOUT Stuart is a skilled structural engineer specializing in bridge engineering. His expertise includes load rating existing bridges, performing independent checks on bridge widenings and seismic retrofits, assisting in seismic retrofit design, and retaining wall layout and design. Stuart also has experience designing new precast slab bridges and calculating and verifying bridge and roadway quantities. STUART GARTH | PE PROJECT EXPERIENCE ADA Path & Retaining Wall; Tillamook, OR. Stuart designed an ADA- compliant pedestrian path leading to a basement entrance of City Hall. He worked with City of Tillamook staff to develop the most practical path layout, using survey data, a site visit, and building as-constructed drawings. He also consulted with the City of Tillamook’s chosen contractor responsible for construction. Stuart designed the path, a retaining wall and wall footings, and handrails to conform with ADA and OSHA standards. I-205 Widening; Oregon City, OR. As part of the Consor bridge design team, Stuart completed the independent check for the I-205 bridge over Main Street in Oregon City, which is being widened and seismically retrofitted as part of the project. Stuart’s work included determining design loads (dead, live, and seismic), and performing structural analysis on the retrofitted bridge. He also assisted with design of the 2,717-foot long 15-span Abernethy Bridge and quantity calculations. He also designed the concrete masonry unit retaining wall with reinforced concrete footing adjacent to the Abernethy Elm Stump historical landmark. US97:OR58 – California Border; OR. Stuart assisted with the 1,179-foot long 16-span Link River Bridge seismic retrofit design by designing infill shear walls, footings, and piles. He also completed an independent check for the Green Springs Bridge seismic retrofit that included determining design loads (dead, live, and seismic), generating a three-dimensional bridge model to determine forces in the various design components being checked. He also determined the capacities of those same components. Foothill Road Widening: Corey Road to East Vilas Road; Jackson County, OR. This project involved widening and realigning a county road, replacing two 48-inch diameter pipes with a new 14-foot-9-inch open- bottom concrete culvert with wingwalls, and adding a gravity concrete retaining wall to avoid right-of-way impacts on adjacent properties. Stuart completed the bridge design, coordinating closely with roadway, geotechnical, and hydraulics engineers to establish the appropriate design parameters and project staging. He also prepared the structural special provisions, calculated quantities, and developed the project estimate. Murphy Corridor Design/Build Construction Support; Bend, OR. Stuart performed third-party quantity verification for this project that widened a roadway and added walkways and landscaping. He generated independent quantities for excavation, backfill, roadway structural sections, concrete sidewalks and walkways, new underground utilities, and landscaping. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Geotechnical Engineer EDUCATION • MS, Geotechnical Engineering, Oregon State University - 2013 • BS, Civil Engineering, Oregon State University - 2012 YEARS OF EXPERIENCE • 11 LICENSE • Professional Engineer: OR (#86021) AFFILIATIONS • American Society of Civil Engineers • American Public Works Association ABOUT James is a geotechnical engineer with a strong background in subsurface field explorations, including drilling and soil sampling, pavement design, geotechnical report writing, and geotechnical engineering design and analysis, including slope stability, seepage analysis, settlement, deep foundations, and earthquake engineering. His experience includes working on high-volume major interstate widenings to low-volume residential streets and roundabout projects for clients throughout the Pacific Northwest and specifically in the City of Tigard. James has collaborated with numerous agencies to successfully deliver these projects. JAMES WALTERS | PE PROJECT EXPERIENCE US20 at Tumalo Roundabout; Tumalo, OR. James supported the Kittelson led team as geotechnical engineer. This project constructed safety improvements to US20, including a roundabout, roadway widening, new retaining walls, cut slopes, sidewalks, and bike and pedestrian facilities. As a subconsultant to Kittelson, Shannon & Wilson performed geologic site characterizations and developed geotechnical parameters for the design of the roundabout and associated features. In addition, Shannnon & Wilson performed site reconnaissance, geotechnical explorations, and laboratory testing. The geotechnical analyses included, seismic site class and geo-seismic hazards, lateral load and sliding resistance for retaining walls and culvert foundations, earth pressures on retaining walls and culvert, and embankment settlement. US97: Lower Bridge Way - 10th Avenue; Terrebonne, OR. ODOT is planning improvements at US97/Lower Bridge Way in Terrebonne due to safety concerns because of the increased traffic volume on US 97. James is the geotechnical engineer who supported the Kittelson led team that prepared design document for a new interchange overcrossing, highway retaining walls, and the local roadway improvement. Shannon & Wilson provided geotechnical engineering services, including geotechnical fieldwork and explorations consisting of 17 borings, soil sampling, laboratory testing, geotechnical design evaluations and recommendations, and construction considerations for the proposed project. The geotechnical project features include driven pile foundations, spread footing foundations, MSE retaining walls, embankment slope stability, and soft ground settlement evaluations. Tigard Street-Fanno Creek Bridge Replacement; Tigard, OR. The City of Tigard intends to replace the North Dakota Street: Fanno Creek Bridge with a new wider bridge on the same alignment. The original wooden bridge was constructed in 1962 and often overtops during flood events and has sub-standard pedestrian facilities. James is providing geotechnical services for the project, including field explorations and geotechnical engineering services to support the proposed bridge replacement. Our current scope of services includes site reconnaissance, field explorations, and engineering recommendations for walls, bridges, and pavement. Additionally, Shannon & Wilson provided hazmat services for the project. 72nd Avenue Improvements | Tigard, OR. James is providing geotechnical services to support transforming 72nd Avenue into a complete street with pedestrian and bicycle crossings, enhanced streetscape, and new lane configurations. As a subconsultant to Kittelson, James is leading site reconnaissance, subsurface explorations, collection of samples for laboratory testing, performance of geotechnical engineering evaluations, and development of geotechnical design recommendations. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Environmental Scientist EDUCATION • BS, Environmental Sciences, Geography, GIS, Oregon State University YEARS OF EXPERIENCE • 15 ABOUT Alia has 15 years of experience in environmental field work, including soil sampling, groundwater sampling, and natural resource field surveying. She has developed a number of All Appropriate Inquiry Phase I Environmental Site Assessments, including real property transactions, corridor assessments, and railroad improvements. She has also performed more than a dozen Hazardous Material Corridor Studies (HMCS) for government agencies. In addition, Alia has aided in authoring Phase II Environmental Site Assessment (Phase II ESA) reports, including soil and groundwater sampling/monitoring, utilizing analytics, and developing conclusions and mitigation/remediation recommendations. ALIA HUBBARD PROJECT EXPERIENCE US97: NW Lower Bridge Way - 10th Avenue; Terrebonne, OR. ODOT is planning improvements at US97/Lower Bridge Way in Terrebonne due to safety concerns because of the increased traffic volume on US 97. The project includes a new interchange overcrossing, highway retaining walls, and local roadway improvements. Alia supported the Kittelson led team by completing a HMCS, shoulder soil sampling, and Phase II ESA sampling of agricultural lands. Tigard Street-Fanno Creek Bridge Replacement; Tigard, OR. The City of Tigard is replacing a roadway bridge carrying Tigard Street over Fanno Creek. The project plans to widen the roadway by approximately 10 feet in each direction to accommodate a bike lane and sidewalk. Alia completed the HMCS, conducted a hazardous building material survey, sampled shoulder soil and groundwater. Red Rock Creek Stabilization & Enhancement; Tigard, OR. Shannon & Wilson is providing geotechnical services to support the design, stabilization, restoration, and prevention of further erosion along Red Rock Creek. Shannon & Wilson prepared a comprehensive assessment of subsurface conditions and geotechnical hazards, beginning with a desktop study followed by a geologic reconnaissance of the site. A detailed geotechnical field exploration program was conducted, including laboratory testing on soil samples from borings and engineering analyses to evaluate soil properties. Key recommendations were developed for slope stability at the SW 72nd Avenue culvert outfall, stabilization of the sanitary sewer line along Red Rock Creek, and analyses for a new culvert at SW 74th Avenue, culminating in the preparation of a thorough geotechnical report. Alia was part of the Shannon & Wilson team. Wall Street Phase I Environmental Site Assessment; Tigard, OR. Alia was a part of the staff team that completed a Phase I ESA on 13045 and 13225 SW Wall Street. The project involved a comprehensive review of the current and historical uses of the property and its surroundings, including data from tax assessor records, City of Tigard directories, historical maps, and aerial photographs. State and federal databases of known and suspected contaminated sites were reviewed, along with regulatory agency file records for selected sites. A site reconnaissance was conducted and additional information on the property’s physical setting was gathered through interviews with individuals knowledgeable about the property. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Landscape Architect EDUCATION • BS, Oregon State University YEARS OF EXPERIENCE • 39 LICENSE/ CERTIFICATION • Professional Landscape Architect: OR (#0242) • LEED Accredited Professional AFFILIATIONS • Fellow of the American Society of Landscape Architects • American Society of Civil Landscape Architects, Oregon Chapter Former President • Urban Greenspace Institute AWARDS • City of Tigard - Main Street Green Street, Honor Award, ACEC OR, 2024 • Oregon City - Molalla Avenue: Beavercreek Road to OR 213, Honor Award, ACEC OR, 2024 ABOUT Mike is the founding Principal of GreenWorks. He believes that good design addresses economic, ecological, and social needs to create livable communities. With nearly four decades of experience leading multidisciplinary teams to design complex projects, Mike knows how to anticipate problems before they arise, saving his clients time, money, and resources. MIKE FAHA | PLA, LEED AP, FASLA PROJECT EXPERIENCE Boeckman Road Improvements Progressive-Design-Build; Wilsonville, OR. Mike is the Principal landscape architect for four interrelated public works projects on Boeckman Road in northeast Wilsonville. The projects address roadway safety with upgrades to traffic infrastructure and multi- modal improvements to pedestrian and bicycle facilities. OR99W Pedestrian Bridge; Sherwood, OR. Principal landscape architect on the development of a pedestrian crossing over OR99W and Elwert Road in Sherwood. The design includes irrigation and planting plans, vegetated stormwater facilities, and restoration of disturbed natural areas. Molalla Avenue Streetscape; Oregon City, OR. Principal landscape architect on a project to upgrade a key corridor of Molalla Avenue to include multimodal transportation and public transit in addition to vehicular traffic. A gateway feature was designed for the southeast end of Molalla Avenue to introduce visitors to the district. Cascade Avenue (US 20) Streetscape; Sisters, OR. Principal landscape architect on a project to increase roadway safety and pedestrian access while improving streetscape features, including trees, furniture, and paving. Kittelson worked alongside GreenWorks to integrate the traffic improvement and streetscape. Main Streets on Halsey; Fairview, Wood Village, and Troutdale, OR. As a subconsultant to Kittelson, Mike is working on improvements to a five-mile corridor of Halsey Street spanning Fairview, Wood Village, and Troutdale in east Multnomah County. The project will link these communities with pedestrian and bicycle friendly facilities that create a cohesive corridor while allowing each community to develop its own character and amenities. GreenWorks developed a toolkit of design elements and contributed to conceptual designs that address roadway safety, green infrastructure improvements, recreational opportunities, community connections, and special opportunity areas. Basalt Creek Extension; Tualatin, OR. Principal landscape architect working on the extension of the Basalt Creek Parkway eastward from SW Grahams Ferry Road to a new intersection at SW Boones Ferry Road. The new roadway will offer safe, multimodal access while addressing capacity, safety, and pedestrian and bicycle connectivity. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Environmental Specialist EDUCATION • BS, Environmental Studies, University of Oregon • MS, Forest Resources/ Natural Resources Policy and Law, Oregon State University • MS, Public Policy In Environmental Policy, Oregon State University YEARS OF EXPERIENCE • 20 CERTIFICATIONS • Professional Wetland Scientist (PWS #2279) • ODOT Certified Environmental Construction Inspector (#48815) • ODOT Qualified Endangered Species Act Biologist for ESA Documentation ABOUT Julie is a certified Professional Wetland Scientist with 20 years of experience specializing in transportation projects. She provides expertise in wetland delineations, functional assessments, wildlife habitat assessments, and local, state, and federal permitting, including Endangered Species Act (ESA) compliance. Julie’s strong relationships with regulatory personnel help streamline environmental permitting. Previously, she worked as an Engineering Technician 3 at Clean Water Services, reviewing applications and issuing Service Provider Letters as both an employee and consultant. JULIE WIRTH-MCGEE | PWS PROJECT EXPERIENCE Main Street Improvements; Banks, OR. Julie was the Senior Environmental Specialist leading the fieldwork and permitting effort for this project along OR 47. The West Fork Dairy Creek, three wetlands, and several ditches were identified within the project area and were documented in a Wetland and Water Delineation Report. The construction of a new stormwater outfall below the ordinary high water mark of the West Fork Dairy Creek required pre- and post-construction Stream Function Assessment Method (SFAM) assessments, and a wetland functional assessment was prepared to document functions and values provided by the impacted wetlands. Impacts within the West Fork Dairy Creek were determined to be “self- mitigating” and resulted in no long-term functional loss, as evidenced by the predicted conditions SFAM results. I-5: Roberts Creek Road-South Umpqua River; Douglas County, OR. As Senior Environmental Specialist, Julie completed all required wetland and waters delineation fieldwork and permitting for this ODOT Region 3 project. The project included northbound and southbound auxiliary lanes along I-5 to allow truck traffic to safely traverse the Roberts Mountain pass without slowing down through traffic. Two wetlands, one unnamed tributary, five drainages, and several ditches were delineated within the 121-acres study area. Julie prepared a Wetland and Waters Delineation Report, Joint Permit Application, FAHP documentation, wetland functional assessment, and existing and predicted state stream functional assessments using SFAM. Hayesville Drive Bicycle & Pedestrian Improvements; Marion County, OR. Julie was the Senior Environmental Specialist leading the fieldwork and ESA documentation effort for this transportation project that included the construction of sidewalks, bike lanes, and signal improvements along the highly-traveled Hayesville Drive corridor between Portland Road and Fuhrer Street. Empire Boulevard Sidewalk Project; Coos Bay, OR. Julie was the Senior Environmental Specialist leading the fieldwork and permitting effort for this roadway widening project that included the construction of bicycle lanes, sidewalks, and on-street parking along the highly traveled Empire Boulevard corridor from Newmark Avenue to Wisconsin Avenue along the Oregon Coast. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Senior Certified Arborist EDUCATION • BS, Forest Engineering, Oregon State University YEARS OF EXPERIENCE • 20 CERTIFICATIONS • LEED® Accredited Professional • Certified Professional in Erosion and Sediment Control (#3374) • International Society of Arboriculture (ISA) Certified Arborist (PN- 6666A) • ISA Tree Risk Assessment Qualification AFFILIATIONS • International Society Of Arboriculture ABOUT Bruce is an ISA Certified Arborist with over 20 years of experience in project management, forestry, forest engineering, and tree risk assessment. His expertise spans road layout, timber appraisals, fish passage culvert design, small bridge design, hydrology analysis, and construction contract supervision. Bruce excels in hazard tree evaluation, tree protection plans, and tree root zone inspections during construction. He is skilled in cost estimation, bid preparation, contractor scheduling, and inspection coordination. As a liaison between contractors and engineers, Bruce verifies compliance with local government standards during site inspections. BRUCE BALDWIN, ISA, CPESC, LEED AP PROJECT EXPERIENCE Murdock Street Sidewalk & Stormwater Improvements; Tigard, OR. As Senior Certified Arborist, Bruce supported design efforts for a new sidewalk, bike lanes, and minor roadway widening to provide a safer route to and from local schools. Bruce inspected every tree along the project corridor and evaluated the impact of the proposed improvements to the trees. He recommend design modifications to better protect trees and coordinated and facilitated air spading to explore subsurface roots on critical trees to better determine potential impacts to them. 22nd Avenue/River Road SAFE Project; Milwaukie, OR . Bruce provided arborist services for this project making sidewalk and bike lane improvements to two primary arterials. The SAFE project is working to improve pedestrian and bicycle safety with a variety of improvements on and along the Island Station neighborhood’s two primary arterials, SE 22nd Avenue, and SE River Road. The project also featured new road sections, ADA-accessible curb ramps, signing & striping, new sidewalks, additional bike lanes, new crosswalk markings, and bike symbols in bike lanes. Willamette Way/Wilsonville Road Intersection ADA Improvements;Wilsonville, OR. Bruce served as a senior certified arborist assessing potential impacts to trees from planned road improvements, including new sidewalk, ADA ramps, and signage. Bruce conducted a tree inventory and made tree preservation and removal recommendations to the City of Wilsonville. Willamette River Stormwater Outfalls; Wilsonville, OR. As Senior Certified Arborist, Bruce served as the senior certified arborist for this project to mitigate erosion at three stormwater outfalls in residential areas on the north bank of the Willamette River. Bruce worked with project stakeholders to design solutions that will address homeowner concerns over losing specific trees. He developed design alternatives to protect the trees and authored a tree protection plan for tree preservation in the project area. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Surveyor EDUCATION • BS, Forest Engineering, Oregon State University YEARS OF EXPERIENCE • 22 LICENSE • Professional Land Surveyor: OR (#70652PLS), AFFILIATIONS • Professional Land Surveyors Of Oregon • Land Surveyors’ Association of Washington ABOUT As an AKS principal and survey manager, Nick oversees all survey work by AKS crews and manages over 40 on-call survey contracts for local agencies. With 22 years of experience, he specializes in boundary, ALTA/ NSPS, right-of-way, topographic, utility, and construction staking surveys. Nick is highly experienced in managing utility project surveys, including stormwater and sewer improvements. He ensures quality control in the field and office, guaranteeing that all deliverables are accurate, complete, and meet federal, state, and local standards. His attention to detail supports delivering projects to the highest specifications. NICK WHITE | PLS PROJECT EXPERIENCE Banks Main Street Improvements; Banks, OR. As survey manager, Nick oversaw the surveying services to support intersection improvements on OR 47 in Banks. AKS prepared a traffic management plan and temporary pedestrian-accessible route plan; completed stormwater and roadway design; provided curb ramp design to bring curbs up to current ADA standards as well as construction plans and a cost estimate; coordinated and submitted design documents to ODOT for review; and prepared public involvement documents and coordinated a public open house. Washington Street Area SAFE Improvements | Milwaukie, OR. As survey manager, Nick oversaw the topographic surveying services along 2 miles of arterial and residential roadways to support the design and construction of street and utility improvements. This included drone flights over the span of the project, each of which generated orthorectified aerial images and lidar-based surfaces. Drone data were utilized for easement presentation and to identify improvements compared to legacy data. AKS designed ADA-compliant sidewalks and curb ramps, pavement reconstruction and rehabilitation, and pedestrian safety and Safe Routes to School pedestrian improvements, including infill sidewalk, rectangular rapid flashing beacons, and utility improvements. Keizer River Road Improvements | Keizer, OR. AKS is currently the City of Keizer’s engineer-of-record and under this role AKS was tasked with a resurfacing project for River Road North; the City’s main arterial and lifeline but rapidly deteriorating each year. Because the resurfacing work triggered ADA improvements, the project scope included signal improvements at 11 intersections, upgrading more than 90 curb ramps, and resurfacing 2.75 miles of a 5-lane major arterial. As survey manager, Nick oversaw field surveying, survey coordination, meeting coordination with City of Keizer staff, existing conditions plan preparation and review, boundary calculations, and updating locates. SW Century Boulevard Study | Hillsboro, OR. Nick oversaw the surveying services for a preliminary plan and study to address SE Century Boulevard’s (formerly SW 229th Avenue) narrow roadway. The deficient roadway required bringing it up to current City of Hillsboro standards, which included realignment, widening, pedestrian and bike paths, and a bridge replacement. The first study involved an alternatives analysis to determine the ultimate alignment and profile for the replacement of the Butternut Creek Bridge and bridge approaches. Boeckman Road Improvements Progressive-Design-Build; Wilsonville, OR. Nick served as project surveyor and performed right-of-way/boundary surveying, site/topographic surveying, legal description preparation, survey control networking, and construction staking to widen Boeckman Road and provide a sidewalk and marked bicycle lanes that allow for safer vehicular, pedestrian, and bicycle movements. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE ROW Agent EDUCATION • BA, English Technical Writing, University of Oregon YEARS OF EXPERIENCE • 23 LICENSES/ CERTIFICATIONS • SR/WA – International Right of Way Association, (#6317) • Real Estate Principal License: OR (#201233922) • Notary Public: OR (#421252) AFFILIATIONS • International Right of Way Association - Beaver Chapter 3, Board of Directors, Advisory Board, 2019 to 2020 • American Council of Engineering Companies - Liaison Steering Committee Co-Chair, 2023 ABOUT Kari Lowe, CEO of Commonstreet and Oregon Right of Way (ROW) Program Manager, is an expert in complex acquisitions for public agencies. With over 23 years of public and private real estate experience, including 18 years on ROW projects, she excels at navigating the Uniform Relocation Act and ROW procedures. Skilled in communication, Kari works effectively with clients, property owners, and legal representatives. Her service- oriented management style delivers projects on time and within budget, while her expertise in process improvement enhances project outcomes. KARI LOWE | SR/WA PROJECT EXPERIENCE Red Rock Creek Stabilization & Enhancement; Tigard, OR. This project, funded with Sanitary Sewer, Stormwater, and Urban Renewal funds, provides stream enhancements and long-term stabilization to Red Rock Creek. Kari collaborates with the City of Tigard’s project team to manage scope, schedule, and budget; quality assurance/control; risk management; and the acquisition team’s tasks. Tualatin Sherwood Road Project; Tualatin, OR. Kari led efforts for this acquisition and relocation project. With an aggressive schedule, the project required 3 complex acquisitions and 38 PPO relocations with prominent businesses. Acquisitions encompassed a large storage unit facility, a local business, and a Les Schwab Tire Store. Located in an area of significant private and public development, Kari also guided the ROW team in successfully overcoming initial property owner resistance by conducting early outreach strategies, which directly helped to complete all relocations on-time for construction deadlines. Willamette Drive/10th Street Improvements; West Linn, OR. This project consisted of constructing bike and pedestrian facilities consistent with the West Linn Transportation System Plan (led by Kittelson). The project met ODOT design requirements and improved overall safety of the corridor by adding new roundabouts. Kari was responsible for risk management, quality assurance/control, and managing the ROW acquisition team. The project was completed under budget and on-schedule for 9 files. 257th Drive Corridor Safety Project; Troutdale, OR. Kari developed scope, schedule, and budget for 16 complex files. She is responsible for quality assurance/control, risk management, programmatic estimates, facilitating appraisal, and appraisal review, and managing the acquisition team’s on- time delivery. This project applied the alternative acquisition process to save time and costs. City of Wilsonville & Cable Houston - Kinsman Road Partnership Program; Wilsonville, OR. This large program required a suite of ROW improvements to enable transportation improvements for motorized and non-motorized traffic; ADA curb ramps; conduit installation for future fiber optic lines; streetlighting; and pavement. Kari developed scope, schedule, and budget; facilitated valuations; and led risk management and quality assurance/control. She also managed the ROW team to acquire fee acquisitions and permanent and temporary easements from 19 prominent businesses (local and national) to include Fred Meyer (Kroger), Pacific Foods, PGE, Schnitzer Properties, Prologis, and more. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D PROJECT ROLE Architectural Historian EDUCATION • MS, Historic Preservation, University of Oregon • BA, Art History, University of Oregon YEARS OF EXPERIENCE • 19 CERTIFICATIONS • Meets the Secretary of the Interior’s Professional Qualifications Standards for Architectural History and History • ODOT Qualified Consultant for Built Environment Studies AFFILIATIONS • American Cultural Resources Association ABOUT Andrea has 19 years of experience documenting the built environment of the Pacific Northwest. She assists clients in navigating their projects through review for compliance with Section 106 of the National Historic Preservation Act (NHPA), Section 4(f) of the Department of Transportation Act, and local preservation ordinances. Andrea excels at working with consultant teams to deliver transportation projects of all sizes and has a wealth of experience working on projects that require permits from the US Army Corps of Engineers (USACE) and regularly manages cultural resource studies that are done for the review and concurrence of the Oregon State Historic Preservation Office (SHPO). ANDREA BLASER | M.S. PROJECT EXPERIENCE OR99W: I-5 to McDonald Street; Tigard, OR. Andrea is the Cultural Resources Lead for a project to complete road improvements on OR99W. Cultural studies were completed to comply with Section 106 of the NHPA and Section 4(f) of the US Department of Transportation Act. Tigard Street Bridge Replacement, Tigard, OR. Andrea is the Cultural Resources Lead for cultural studies done in support of bridge replacement. Cultural studies comply with Section 106 of the NHPA and will be reviewed by USACE and SHPO. OR141/OR217 Curb Ramps; Tigard, OR. Andrea is the Cultural Resources Lead for improving curb ramps between OR99W and SW Durham Road and at locations along SE 72nd Avenue in Tigard. Cultural studies were completed to comply with Section 106 of the NHPA. SW Wall Street Improvements, Tigard, OR. Andrea was the Architectural Historian Lead for cultural resource studies done in support of improving SW Wall Street between SW Hunziker Street and the Portland & Western Railroad. Cultural studies were done to comply with Section 106 of the NHPA and were reviewed by USACE. Southwest Corridor Light Rail; Multnomah & Washington Counties, OR. Andrea is the Lead Architectural Historian for studies done to comply with Section 106 of the NHPA and Section 4(f) of the US Department of Transportation Act. AINW documented dozens of buildings in Tigard in support of the project’s Environmental Impact Statement. SW Millikan Way Extension; Beaverton, OR. Andrea is leading the reconnaissance cultural resource studies to support analysis of alternatives for a locally funded transportation improvement project. Tigard Water Partnership Project; Clackamas & Washington Counties, OR. Andrea is providing cultural resource and historical architectural services for a new water pipelines and associated intake and treatment facilities in Gladstone, West Linn, Lake Oswego, and Tigard. The project included archaeological testing, evaluation, and monitoring done under SHPO archaeological permits and in coordination with USACE. The documentation of historic resources along the project alignment was done to meet requirements of ORS 358.653 and Section 106 of the NHPA. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D Appendix B PROJECT PROFILES Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D RELEVANCE: 3 Design/Build project for freeway interchange and local road improvements to increase capacity and improve safety 3 Multi-year effort which involved traffic studies, preliminary design, environmental approvals, and public involvement 3 Navigated public engagement efforts to build understanding and support for the project 3 Established improved bicycle and pedestrians facilities and responded to long term traffic demands I-5/LA CENTER INTERCHANGE Improving the I-5/La Center Road interchange provided a new interchange bridge with modified ramps, roundabout-controlled terminals, and bicycle/ pedestrian improvements and multi-use pathways. Approximately two miles of local roadways were re-aligned to improve safety and circulation and meet Washington State DOT access management requirements for crossroads. Kittelson led the multidisciplinary/multi-agency team that prepared the planning and construction documents for the design/build contract. Specific tasks included: • Managing the overall project for improvements within the public right of way • Preparing an interchange justification report and traffic impact analysis to meet local, state, and federal requirements, including National Environmental Protection Act compliance • Designing an interchange bridge with modified ramps and roundabout controlled terminals along with bicycle and pedestrian improvements and multi-use pathways • Realigning roadway network to improve safety, circulation, and access management • Developing transportation management plan and traffic control plans Public Involvement. Kittelson navigated the public engagement process with sensitivity and skill, discussing with neighbors the new roadway alignments through private properties absent the presence of the power of eminent domain. Kittelson engaged people to help them understand the issues, develop and evaluate alternatives, and support an alternative. These engagements included in-person meetings with agencies and property owners and presenting alternatives in ways people could understand. Constructed Improved Transportation Network. Kittelson successfully managed a multidisciplinary team and coordinated the legal team and local agencies to deliver a new $40 million interchange, three roundabouts, and multi-use paths introduced to the interchange area, resulting in lower maintenance costs, and improved safety. APWA Washington Project of the Year Transportation - 2018 Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D NEWPORT AVENUE - COMPLETE STREET The Newport Avenue public infrastructure improvements project is a great example of how to simultaneously improve a roadway along with sewer, water, and stormwater facilities. On June 9, 2023, Newport Avenue was reopened to the public and: • Demonstrated how the City efficiently planned, designed and constructed the improvements; • Is leading the way on using roundabouts to solve congestion and safety issues; and • Applying the CM/GC project delivery method to efficiently deliver public infrastructure projects. Traffic Analysis. Kittelson, as part of a multidisciplinary team, analyzed traffic operations along Newport Avenue and identified improvements to address the safety and functionality of the corridor. The recommended improvements included sidewalks, striped bike lanes, enhanced pedestrian crossings, accessible ramps, and illumination. Traffic Calming with Driver Behavior Study. The segment of the corridor at 11th Street and 12th Street experienced high speeds causing left turn and pedestrian conflicts. Kittelson used driver behavior studies to conclude drivers increase their speeds in this area because a driver’s viewshed opens abruptly when a grocery store, Newport Avenue Market, came into view. The sudden expansion of the viewshed was causing drivers to unconsciously speed up in response to the open space and made it difficult to see potential conflicts.  Dogbone Roundabout. Kittelson developed a dogbone roundabout concept to improve safety at the 11th and 12th Streets. The dogbone roundabout, uniquely shaped to fit the constrained site, streamlines the viewshed, causing drivers to slow down and focus on navigating the roundabouts. This alternative makes the corridor safer while also adding capacity. After two years of being closed, Newport Avenue was reopened to the public with secure stormwater infrastructure below ground and various above-ground improvements to make the corridor safer for all travel modes. In addition, improved stormwater infrastructure protects the Deschutes River by treating the runoff before entering the river. ACEC OREGON Engineering Excellence Grand Award - 2024 RELEVANCE: 3 Combined roadway, water, sewer, and stormwater improvements using CM/GC delivery 3 Multi-year effort which involved traffic analysis, conceptual design, and driver behavior study 3 Established improved bicycle and pedestrians facilities and responded to long term traffic demands Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D WILSON AVENUE - COMPLETE STREET Wilson Avenue is a Key Route that links neighborhoods in Bend, OR (East of 3rd Street to the 2nd Street Neighborhoods Greenway and Old Town/ Downtown Districts). This project was selected to be implemented as part of the GO Bond initiative. Application of Performance Based Design. Kittelson used performance-based design to align the alternatives with the local context. Specific project elements Kittelson led include: • Preparing a traffic study which informed the design for roundabouts at 9th Street and 15th Street • Connecting to trails, implementing low-stress bicycle network, and installing auxiliary lanes • Developing cross-section to incorporate bicycle lanes and widen multi-use paths • Addressing Burlington North Santa Fe Rail requirements and expectations • Determining a stormwater management methodology • Preparing PS&E documents that consider accessibility • Conducting public outreach during design and construction phases Innovative Traffic Calming & Safety Solution • Redesigned signalized intersection to include protected bicycle safety corners and detection • Roundabout with integrated protected bicycle lanes (first of its kind in Bend); required design approvals beyond the standard criteria • Addressed steep and varied grade of driveways and constrained right of way with acceptable design deviations while achieving ADA compliance Installation of Key Route from Bend Transportation System Plan. This multi-year initiative resulted in developing a context- appropriate, feasible alternative and successfully coordinating multidisciplinary team through several phases. RELEVANCE: 3 Application of performance-based design to develop context- appropriate alternatives 3 Multi-year effort which involved public involvement, traffic analysis, conceptual design, final PS&E preparation, and advising on delivery method 3 Established improved bicycle and pedestrian facilities, along with traffic calming measures using design/build alternative delivery method VISUALIZATION CREATED BY KITTELSON OF PROTECTED INTERSECTION AT 5TH STREET/WILSON AVENUE Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D Appendix C FORMS Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D ATTACHMENT B PROPOSAL FORM ATTACHMENT 1 RFP 2025-08 McDonald Street Engineering Services / Contract Exceptions Kittelson prefers language that limits it liability should the City revise the Contractor’s work product with- out its consent or use said work for another purpose other than that contemplated under any awarded agreement. Is the City amenable to modifying Section 4 of its agreement as follows: 4. OWNERSHIP OF WORK PRODUCT City is the owner of and is entitled to possession of any and all work products of Contractor which result from this Agreement, in- cluding any computations, plans, correspondence, or pertinent data and information gathered by or computed by Contractor prior to termination of this Agreement by Contractor or upon completion of the work pursuant to this Agreement. Contractor shall have no liability should its work product be revised by others without its consent or utilized for any other purpose than that contemplat- ed under this Agreement. The recently passed SB 1575 becomes effective January 1, 2025, and will render any contractual upfront duty to defend obligations by design professionals unenforceable. See link to adopted legislation: SB1575 (oregonlegislature.gov) What steps is the City taking to ensure its indemnification provision is revised to reflect this new legislation as of January 1, 2025? Given the timing of the award and anticipated start date; would the City be amendable to modifying Section 8 of its agreement as follows to ensure compliance with this new legislation: 8. INDEMNIFICATION City has relied upon the professional ability and training of Contractor as a material inducement to with generally accepted pro- fessional practices and standards as well as the requirements of applicable federal, state, and local laws, it being understood that acceptance of a Contractor’s work by City will not operate as a waiver or release. To the extent allowed by law, Contractor agrees to indemnify and defend the City, its officers, employees, agents, and representa- tives and hold them harmless from any and all liability, causes of action, claims, losses, and damages, judgments, or other costs or expenses, including attorney’s fees and witness costs (at both trial and appeal level, whether or not a trial or appeal ever takes place including any hearing before federal or state administrative agencies), that may be asserted by any person or entity to the extent which in any way such liability, claims, losses and damages arise from the fault of Contractor, during, or in connection with the performance of the work described in this contract, except liability arising out of the sole negligence of the City and its employees. Relative to professional services, Contractor’s duty to defend is limited to reimbursement of reasonable legal costs should Contractor be found liable by adjudication or alternative dispute resolution or otherwise resolve by settlement agreement. In no event shall defense costs charged to the Contractor exceed Contractor’s proportionate percentage of fault. Such indemni- fication will also cover claims brought against the City under state or federal worker’s compensation laws. If any aspect of this indemnity is found to be illegal or invalid for any reason whatsoever, such illegality or invalidity does not affect the validity of the remainder of this indemnification. As a design professional, Contractor can make no warranty, expressed or implied, relative to the services it would provide under this or any other agreement. Contractor can only agree to perform the work in ac- cordance with the common law standard of care for design professionals. Would the City be amenable to modifying Section 23 of its agreement as follows upon any contract award which serves to make this clear: 23. WARRANTIES STANDARD OF CARE Contractor will perform all work under this Agreement with the care and skill used by members of Contractor’s professional practicing under similar circumstances at the same time and in the same locale (the “Standard of Care”). Should Contractor not the Standard of Care, it shall correct its work at its cost. meet guarantee work for a period of one year after the date of final ac- ceptance of the work by the owner. Contractor warrants that all practices and procedures, workmanship and materials are the best available unless otherwise specified in the profession. Neither acceptance of the work nor payment therefore relieves Contractor from liability under warranties contained in or implied by this Agreement. Any intellectual property rights delivered to the City under this Agreement and Contractor’s services rendered in the perfor- mance of Contractor’s obligations under this Agreement, will be provided to the City free and clear of any and all restrictions on or conditions of use, transfer, modification, or assignment, and be free and clear of any and all liens, claims, mortgages, security interests, liabilities, charges, and encumbrances of any kind. Docusign Envelope ID: 96BE4ADF-7C08-4866-9F22-2C35B5114A0D