AKS Engineering & Forestry LLC ~ C210105
CITY OF TIGARD - CONTRACT SUMMARY & ROUTING FORM
Contract Overview
Contract/Amendment Number: C210105a3
Contract Start Date: 02/08/2021 Contract End Date: 03/31/2025
Contract Title: Kruger Creek Stabilization
Contractor Name: AKS Engineering & Forestry LLC
Contract Manager: Andy Newbury
Department: PW-ENG
Contract Costs
Original Contract Amount: $588,866.00
Total All Previous Amendments: $171,912.00
Total of this Amendment: $132,500.00
Total Contract Amount: $893,278.00
Procurement Authority
Contract Type: Personal Services
Procurement Type: Formal RFP >$150K
Solicitation Number: 94046-130
LCRB Date: 05/21/2024
Account String: Fund-Division-Account Work Order – Activity Type Amount
FY 25
Contracts & Purchasing Approval
Purchasing Signature:
Comments: extend end date
DocuSign Routing
Route for Signature Name Email Address
Contractor John Christiansen johnc@aks-eng.com
City of Tigard Joe Wisniewski joew@tigard-or.gov
Final Distribution
Contractor John Christiansen johnc@aks-eng.com
Project Manager Andrew Newbury andrewn@tigard-or.gov
Project Manager Shauna Large shaunal@tigard-or.gov
Buyer Toni Riccardi tonir@tigard-or.gov