Lee Contractors LLC ~ CP23002
CITY OF TIGARD - CONTRACT SUMMARY & ROUTING FORM
Contract Overview
Contract/Amendment Number: CP23002a1
Contract Start Date: 08/10/2022 Contract End Date: 12/31/2024
Contract Title: Kruger Creek Stabilization
Contractor Name: Lee Contractors, LLC
Contract Manager: Andrew Newbury
Department: PW-ENG
Contract Costs
Original Contract Amount: $3,138,765.00
Total All Previous Amendments: n/a
Total of this Amendment: n/a
Total Contract Amount: $3,138,765.00
Procurement Authority
Contract Type: Public Improvement
Procurement Type: Formal Public Improvement ITB >$100K
Solicitation Number: 2022-16
LCRB Date: 08/09/2022
Account String: Fund-Division-Account Work Order – Activity Type Amount
FY 23 510-8000-56005 94046-130
Contracts & Purchasing Approval
Purchasing Signature:
Comments: Extend the end date
DocuSign Routing
Route for Signature Name Email Address
Contractor Randy Lee estimating@leecontractorswa.com
City of Tigard Steve Rymer stever@tigard-or.gov
Final Distribution
Contractor Randy Lee estimating@leecontractorswa.com
Project Manager Andrew Newbury andrewn@tigard-or.gov
Project Manager Shauna Large shaunal@tigard-or.gov
Buyer Toni Riccardi tonir@tigard-or.gov